1 fims conference, 2008 ed weideman. 2 location of nrel sites in the denver metro area

Download 1 FIMS Conference, 2008 Ed Weideman. 2 Location of NREL Sites in the Denver Metro Area

If you can't read please download the document

Upload: itzel-ginyard

Post on 15-Dec-2015

216 views

Category:

Documents


0 download

TRANSCRIPT

  • Slide 1

1 FIMS Conference, 2008 Ed Weideman Slide 2 2 Location of NREL Sites in the Denver Metro Area Slide 3 3 NREL Owned vs. Leased Occupants (9/30/07) NREL Owned vs. Leased GSF (9/30/07) Owned 573 49% Owned 460,326 63% Leased 274,608 37% Slide 4 4 NREL Sites (as of 09/30/07) AcresTotal GSFOwnershipOccupants (as of 9/30/07) Distance from STM site South Table Mountain*327404,242Owned482--- National Wind Technology Center 30556,084Owned9120 miles Denver West Office ParkN/A207,247Leased5731.2 miles Joyce Street FacilityN/A56,000Leased08 miles ReFuel FacilityN/A4,576Leased615 miles Washington, D.C.N/A6,785Leased10--- Total632734,9341162 * Approximately 136 acres of site can be developed; the balance is in easements. Slide 5 5 South Table Mountain Site (looking from the east) Slide 6 6 South Table Mountain Site (looking from the west) Slide 7 7 NREL Laboratory Utilization (as of 09/30/07) Total Labs Available= 297 Slide 8 8 NREL Workstation Utilization (as of 09/30/07) Slide 9 9 Denver West Office Park Bldg 15, 16,17 NREL STM Site Denver West Office Park Bldg 15, 16,17 NREL STM Site Denver West Office Park Bldg 15, 16,17 NREL STM Site Denver West Lease Facilities and South Table Mountain Site Slide 10 10 National Wind Technology Center Slide 11 11 Solar Research Facility (SERF) and Science and Technology Facility (S&TF) Slide 12 12 Science & Technology Facility Funding TEC$22,690,000 TPC$29,190,000 by CD-2/3 authorization Year 1$800,000 Year 2$769,958 Year 3$3,924,707 Year 4$6,626,568 Year 5$10,409,850 $22,531,083 Note: -$158,917 unfunded Slide 13 13 Science & Technology Facility Milestone datesScheduled Actual 1 CD-1 6/14/2002 6/10/2002 2 Preliminary Design 12/28/2002 12/27/2002 3 Final Design 7/30/2003 9/30/2003 4 Substantial Completion 12/1/2006 6/21/2006 5 Construction Complete 12/1/2006 11/16/2006 Parameters Sq. Ft. Office & Office Support10,425 Lab22,933 Lab Support11,442 Building Support26,547 71,347 No. Staff 55 (72 as configured) LEED Funded = Silver; Designed = Gold, Constructed = Platinum Pwr Consumption 42% less energy than ASHARE std office bldg~$96,000/yr savings Summary:Under budget, ahead of schedule, Platinum LEED Slide 14 14 South Table Mountain Campus Slide 15 15 STM Build-out Site Plan with Utilities Slide 16 16 FY07 Construction Line Item Research Support Facility $73 MillionFY06-$10,000,000 / FY07-$63,000,000 220,000 SF 800 Occupants (NREL/GO) LEED Platinum 25,000 BTU/Sq Ft/Year Move out of Leased Buildings Design-Build Project Stipends for Two Unsuccessful Bidders Incentives for Safety, Design, Workmanship, Timelines of Completion, Responsiveness, Cooperation, Partnering, Social Economic Commitment. Construction Start October 2008 Construction Complete June 2010 Slide 17 17 FY07 Construction Line Item Integrated Bio-Refinery Facility $20 Million TEC $6 Essential Equipment 16,400 SF 30 Occupants Design Build Project Expand Feedstock Input Capability to Existing Ethanol Plant Construction Start November 2008 Construction Complete November 2009 Slide 18 18 Energy Savings Performance Contract (ESPC) Renewable Fuels Heating Plant (RFHP) Ameresco 2,000SF Pad $3,200,000 24yr payback Wood chips, One trailer per day (Heating season) Construction Start September 2007 Construction Complete August 2008 1 st Performance Year 2008-2009 Heating Season Slide 19 19 RFHP May 1, 2008 Slide 20 20 FY08 Construction Line Item Energy Systems Integration Facility (ESIF) Funding TEC$93,000,000 TPC$98,300,000 Year 1$54,500,000 Year 2$4,000,000 Year 3$34,500,000 Equipment$34,000,000 Supercomputer$12,000,000 130,000 SF 150 Occupants Construction Start September 2009 Construction Complete September 2011 Slide 21 21 Challenge: Address integration issues unique to renewable and efficiency technologies. Critical at this stage of their development to accelerate large-scale deployment Function: Unique DOE capability for conducting integrated research, testing, and analysis to enable economic, reliable integration of renewable electricity generation, fuel production, storage, and building efficiency technologies with the U.S. fuels and electricity delivery infrastructures. 130,000 sq ft. multi-story space building with high-bay and low-bay laboratories User facility for collaborative research and testing High-speed computational science capability. Office and support space researchers and partners. Energy Systems Integration Facility (ESIF) Slide 22 22 Take me to your LEEDer