1 design and construction of bnct irradiation facility at tehran research reactor 1 nuclear science...
TRANSCRIPT
1
Design and construction of BNCT irradiation
facility at Tehran research reactor
1Nuclear Science and Technology Research Institute (NSTRI), Iran2Department of Physics, K.N.T University, Iran
Yaser Kasesaz
Isfahan
2
Contents
BNCT project at Iran
Introduction to TRR
Structure of thermal column
Epithermal neutron beam design
Main challenges in construction process
Thermal neutron beam design
New challenges
Measurements of the neutron beam parameters
Conclusions
3
BNCT project at Iran
Yazd
4
~ 1990: The first attempt was conducted by Dr. Marashi & Dr. Pazirandeh
2009- Continue: A new Project has been defined at NSTRI:
in 5 International Symposium on Neutron Capture Therapy (1992)
The results showed that the neutron flux at none of the beam exits is not sufficient
Construction of BNCT facility at TRR
5
Boron Drug
Phantom
TPS
ShieldingBoron Measur.
Dosimetrysystem
Simulatorroom
Medical room
Neutron Beam
The project has different sub-projects
6
Introduction to TRR
Kashan
7
8
Seven Beam Tubes
TRR is a 5 MW MTR, pool type research reactor
fuel assemblies : LEU, plates ,U3O8 Al alloy
Reactor pool has two major parts, stall-end and open pool
Irradiation facilities:
In-core irradiation boxes
Two rabbit systems
Medical room
Gamma room
Main application: radioisotopes production
9
it has been shown that the thermal column is the best facility which can be adapted for BNCT
Appl. Radiat. Isot, 90, 132-137 (2014).
10
Structure of Thermal column
Shiraz
11
Is it possible to remove all graphite blocks?
12
13
14
All parts placed in their position for routine TRR activity
15
Epithermal Neutron Beam Design
Shiraz
16
Core
Lead Graphite
Reactor pool
Concrete
Concrete
Reflector
Reflector
Moderator
Collimator
17
Moderator: Al (30 cm)
Reflector : Pb (35 cm)
Gamma filte: Two Bi Layers (5 cm)
Thermal neutron filter: Cd (2 mm)
Ann. Nucl. Energy (2014) 234–238
18
19
20
Main Challenges in construction process
Shiraz
21
high gamma dose caused by activated materials in the reactor structure
Access to 3th and 4th graphite layers
a new project is defined to design the thermal beam instead of epithermal beam
22
Thermal Neutron Beam Design
Ramsar
23
the 3Th and 4Th graphite layers are fixed
From the first layer only 9 special blocks are removed
For the 2Th layer three different configurations have been studied
24
three different configurations
25
26
27
28
Thermal neutron Flux: 2.6E7 (n/cm2.s)
Cadmium Ratio: 112
Measurement of neutron beam parameters: at 90 kW
Gamma Dose Rate: failed
29
New Challenges
Isfahan
30
The new challenge : Gas and particle contamination at the reactor hall
Air
31
Solution 1: using wood blocks
Not effective
32
Solution 2: re- arranging the blocks in the second layer
It is effective
33
Designed Neutron Beam Parameters
Isfahan
34
Gamma Dose Rate: 0.19 mSv/Min (at 100 kW)
Neutron beam parameters:
Thermal neutron Flux: 1.7E8 (n/cm2.s) at 1.5 MW
Cadmium Ratio: 186
35
Conclusions
Shiraz
36
Conclusions
The designed beam has two major advantages:
We impose minimal changes in the thermal column structure
A sample or phantom can be irradiated outside of the thermal column
thermal neutron beam has been constructed based on the use of thermal column.
The arrangement of graphite blocks has been modified to provide a thermal neutron beam.
The final results have been shown that the thermal neutron flux at the beam port is 1.7E8 (n/cm2.s) at 1.5 MW which is appropriate for BNCT.
37
Thank you ….
Isfahan