Page 1: 1 Control procedures: EC Audits European Commission RTD.M.1 External audits Maurizio Dal Toso Horizon 2020 Tallinn 1/12/2011

1

Control procedures: EC Audits

European CommissionRTD.M.1 External audits

Maurizio Dal Toso

Horizon 2020Tallinn 1/12/2011

Page 2: 1 Control procedures: EC Audits European Commission RTD.M.1 External audits Maurizio Dal Toso Horizon 2020 Tallinn 1/12/2011

2

Topics

EC Audit in FP71. When?

2. Who can carry out an audit

3. What is verified in an audit?

4. How is it verified? Audit Procedures

5. Which are the supporting documents for the audit?

6. Which are the obligations of the beneficiaries?

7. Audit Reports, implementation & follow-up

Page 3: 1 Control procedures: EC Audits European Commission RTD.M.1 External audits Maurizio Dal Toso Horizon 2020 Tallinn 1/12/2011

3

1-Audit : when?

Article II.23 of ECGA - Technical audits and reviews: “The Commission may initiate a technical audit or review at any time during the implementation of the project and up to up to five years after the end of the project.”

Article II.23 of ECGA - Technical audits and reviews: “The Commission may initiate a technical audit or review at any time during the implementation of the project and up to up to five years after the end of the project.”

Article II.22 of ECGA – Financial audits and controls: “The Commission may, at any time during the implementation of the project, and up to five years after the end of the project, arrange for financial audits to be carried out”.

Article II.22 of ECGA – Financial audits and controls: “The Commission may, at any time during the implementation of the project, and up to five years after the end of the project, arrange for financial audits to be carried out”.

Page 4: 1 Control procedures: EC Audits European Commission RTD.M.1 External audits Maurizio Dal Toso Horizon 2020 Tallinn 1/12/2011

4DG RTD-A.4

2-Audits: Who?

Audits by EC auditors (RTD-M.01)

• Approx. 1/3 of audits • Specific audits (follow-up, requests, …)

Audits by Contracted firms (RTD-M.02)

• Approx. 2/3 of audits • Supervision of the audit by EC services

Clashes

Article II.22 of ECGA – Financial audits and controls

3. Audits may be carried out by:

• The Commission (its own departments – including OLAF – or by any of its duly authorised representatives (including external auditors appointed by the Commission).

• The European Court of Auditors (by its own departments or by any of its duly authorised representatives).

Article II.22 of ECGA – Financial audits and controls

3. Audits may be carried out by:

• The Commission (its own departments – including OLAF – or by any of its duly authorised representatives (including external auditors appointed by the Commission).

• The European Court of Auditors (by its own departments or by any of its duly authorised representatives).

Page 5: 1 Control procedures: EC Audits European Commission RTD.M.1 External audits Maurizio Dal Toso Horizon 2020 Tallinn 1/12/2011

7

Topics

EC Audit in FP71. When?2. Who can carry out an audit3. What is verified in an audit?4. How is it verified? Audit Procedures5. Supporting documents for the audit6. Obligations of the beneficiaries 7. Internal strategy concerning audits8. Audit Reports

Page 6: 1 Control procedures: EC Audits European Commission RTD.M.1 External audits Maurizio Dal Toso Horizon 2020 Tallinn 1/12/2011

8

Technical audits – what is verified?• Technical review is performed at the project level

by Project Officers and/or external experts to give external advice to the Commission

Article II.23 of ECGA - Technical audits and reviews

…The aim of a technical audit or review shall be to assess the work carried out under the project over a certain period, inter alia by evaluating the project reports and deliverables relevant to the period in question. Such audits and reviews may cover scientific, technological and other aspects relating to the proper execution of the project and the grant agreement.

Page 7: 1 Control procedures: EC Audits European Commission RTD.M.1 External audits Maurizio Dal Toso Horizon 2020 Tallinn 1/12/2011

9

Financial audits – what is verified?

• Article II.22 of ECGA – Financial audits and controls: … “Such audits may cover financial, systemic and other aspects (such as accounting and management principles) relating to the proper execution of the grant agreement.”

• Article II.22 of ECGA – Financial audits and controls: … “Such audits may cover financial, systemic and other aspects (such as accounting and management principles) relating to the proper execution of the grant agreement.”

Page 8: 1 Control procedures: EC Audits European Commission RTD.M.1 External audits Maurizio Dal Toso Horizon 2020 Tallinn 1/12/2011

10

Topics

EC Audit in FP71. When?2. Who can carry out an audit3. What is verified in an audit?4. How is it verified? Audit Procedures5. Supporting documents for the audit6. Obligations of the beneficiaries 7. Internal strategy concerning audits8. Audit Reports

Page 9: 1 Control procedures: EC Audits European Commission RTD.M.1 External audits Maurizio Dal Toso Horizon 2020 Tallinn 1/12/2011

11

Audit CycleAudit Strategy & Selection

Planning & Preparation

Examination on site

Reporting &Audit Closure

Implementationof Audit Results

Page 10: 1 Control procedures: EC Audits European Commission RTD.M.1 External audits Maurizio Dal Toso Horizon 2020 Tallinn 1/12/2011

12

Audit Cycle - Timeline

Audit Strategy & Selection

Planning & Preparation

Examination on site

Reporting &Audit Closure

Implementationof Audit Results

3 months 3-4 months

Page 11: 1 Control procedures: EC Audits European Commission RTD.M.1 External audits Maurizio Dal Toso Horizon 2020 Tallinn 1/12/2011

1313

Audit on-the-spot – Preparation

• Selection of Agreements• Initial contact by the responsible auditor approx. 2 month

before examination on site to agree on dates and logistics

• Collection of audit information (internal and external) • Formal Announcement including detailed annex on

information and documentation to be provided:– prior to the audit examination on site– at the time of the audit examination

Page 12: 1 Control procedures: EC Audits European Commission RTD.M.1 External audits Maurizio Dal Toso Horizon 2020 Tallinn 1/12/2011

14

Examination on site

Openingmeeting

Analysis of Systems in place

Test of systemsand substantive

evidence

Closuremeeting

Assessmentafter on site

visit

Usually within 4-5 working days (one week) (…)

General info on:

• organisation

• projects

• financial administration

• internal control system

Clarification on audit agenda for further days

Analysis of documents and explanation received and collection of audit evidence

Discussion ofpreliminary findings andobservations

Indication of further audit procedure

Audit Process Handbook

Different legislationDifferences in administrative culture

Page 13: 1 Control procedures: EC Audits European Commission RTD.M.1 External audits Maurizio Dal Toso Horizon 2020 Tallinn 1/12/2011

15

Article II.22 of ECGA – Financial audits and controls

In order to permit a complete, true and fair verification that the project and the grant are (have been) properly managed and performed, beneficiaries are required to:

• keep the originals, or in exceptional cases, where the national legislation accepts or contemplates this possibility, duly authenticated copies – including electronic copies – of all documents relating to the grant agreement for up to five years from the end of the project.

• ensure that the Commission's services, and/or any external body(ies) authorised by it, have

• on-the-spot access at all reasonable times, notably to the beneficiary's offices where the project is being carried out, to its computer data, to its accounting data and to all the information needed to carry out those audits, including information on individual salaries of persons involved in the project. They shall ensure that the information is readily available on the spot at the moment of the audit and, if so requested, that data be handed over in an appropriate form.

• make available directly to the Commission all the detailed data that it may request,

• ensure that the rights of the Commission and the European Court of Auditors to carry out audits are extended to the right to carry out any such audit or control on any third party whose costs are reimbursed in full or in part by the EC contribution, on the same terms and conditions.

Article II.22 of ECGA – Financial audits and controls

In order to permit a complete, true and fair verification that the project and the grant are (have been) properly managed and performed, beneficiaries are required to:

• keep the originals, or in exceptional cases, where the national legislation accepts or contemplates this possibility, duly authenticated copies – including electronic copies – of all documents relating to the grant agreement for up to five years from the end of the project.

• ensure that the Commission's services, and/or any external body(ies) authorised by it, have

• on-the-spot access at all reasonable times, notably to the beneficiary's offices where the project is being carried out, to its computer data, to its accounting data and to all the information needed to carry out those audits, including information on individual salaries of persons involved in the project. They shall ensure that the information is readily available on the spot at the moment of the audit and, if so requested, that data be handed over in an appropriate form.

• make available directly to the Commission all the detailed data that it may request,

• ensure that the rights of the Commission and the European Court of Auditors to carry out audits are extended to the right to carry out any such audit or control on any third party whose costs are reimbursed in full or in part by the EC contribution, on the same terms and conditions.

5-Supporting documents for the audit

Page 14: 1 Control procedures: EC Audits European Commission RTD.M.1 External audits Maurizio Dal Toso Horizon 2020 Tallinn 1/12/2011

16

6-Beneficiaries' obligationsArticle II.22 of ECGA – Financial audits and controls

In order to permit a complete, true and fair verification that the project and the grant are (have been) properly managed and performed, beneficiaries are required to:

• keep the originals, or in exceptional cases, where the national legislation accepts or contemplates this possibility, duly authenticated copies – including electronic copies – of all documents relating to the grant agreement for up to five years from the end of the project.

• ensure that the Commission's services, and/or any external body(ies) authorised by it, have on-the-spot access at all reasonable times, notably to the beneficiary's offices where the project is being carried out, to its computer data, to its accounting data and to all the information needed to carry out those audits, including information on individual salaries of persons involved in the project. They shall ensure that the information is readily available on the spot at the moment of the audit and, if so requested, that data be handed over in an appropriate form.

• make available directly to the Commission all the detailed data that it may request,• ensure that the rights of the Commission and the European Court of Auditors to

carry out audits are extended to the right to carry out any such audit or control on any third party whose costs are reimbursed in full or in part by the EC contribution, on the same terms and conditions.

Article II.22 of ECGA – Financial audits and controls

In order to permit a complete, true and fair verification that the project and the grant are (have been) properly managed and performed, beneficiaries are required to:

• keep the originals, or in exceptional cases, where the national legislation accepts or contemplates this possibility, duly authenticated copies – including electronic copies – of all documents relating to the grant agreement for up to five years from the end of the project.

• ensure that the Commission's services, and/or any external body(ies) authorised by it, have on-the-spot access at all reasonable times, notably to the beneficiary's offices where the project is being carried out, to its computer data, to its accounting data and to all the information needed to carry out those audits, including information on individual salaries of persons involved in the project. They shall ensure that the information is readily available on the spot at the moment of the audit and, if so requested, that data be handed over in an appropriate form.

• make available directly to the Commission all the detailed data that it may request,• ensure that the rights of the Commission and the European Court of Auditors to

carry out audits are extended to the right to carry out any such audit or control on any third party whose costs are reimbursed in full or in part by the EC contribution, on the same terms and conditions.

Page 15: 1 Control procedures: EC Audits European Commission RTD.M.1 External audits Maurizio Dal Toso Horizon 2020 Tallinn 1/12/2011

17

Topics

EC Audit in FP71. When?2. Who can carry out an audit3. What is verified in an audit?4. How is it verified? Audit Procedures5. Supporting documents for the audit6. Obligations of the beneficiaries 7. Audit Reports, implementation & follow-up8. Audit strategy

Page 16: 1 Control procedures: EC Audits European Commission RTD.M.1 External audits Maurizio Dal Toso Horizon 2020 Tallinn 1/12/2011

18

Quality control

• Quality check on audit report for– Coherence– Completeness– Correctness– Compliance with the Audit Handbook

• Audit Steering Committee

Page 17: 1 Control procedures: EC Audits European Commission RTD.M.1 External audits Maurizio Dal Toso Horizon 2020 Tallinn 1/12/2011

19

Reporting and Closure of the Audit

• Transmission of Draft audit report (after internal consultations) for comments by the audited organisation– Usually based on the preliminary conclusions– Delay (30 days) to provide comments to the draft– Letter of representation

• Consideration of comments and finalisation of the audit report• Closure of the audit by formal letter indicating the further

procedures on the implementation of audit results

END OF THE AUDIT

Page 18: 1 Control procedures: EC Audits European Commission RTD.M.1 External audits Maurizio Dal Toso Horizon 2020 Tallinn 1/12/2011

20

Implementation of Audit Results

Page 19: 1 Control procedures: EC Audits European Commission RTD.M.1 External audits Maurizio Dal Toso Horizon 2020 Tallinn 1/12/2011

21

General

• Financial adjustments administred by the operational EC service in charge of the project management (decentralised)

• Besides adjustments, possibility of liquidated damages

• Consideration of serious audit findings (i.e. high adjustments) in future project and agreement negotiations

Page 20: 1 Control procedures: EC Audits European Commission RTD.M.1 External audits Maurizio Dal Toso Horizon 2020 Tallinn 1/12/2011

22

Implementation of Results: Cases

No findings

Financial Adjustment

(Only) qualified recommendation

Non-systematicfinding identified

Systematicfinding identified

Implementation finalised

Correction of future payments or recovery by the responsible financial services

Extrapolationof audit results

Follow-up Audit

Page 21: 1 Control procedures: EC Audits European Commission RTD.M.1 External audits Maurizio Dal Toso Horizon 2020 Tallinn 1/12/2011

23

Implementation of Results – Systematic Finding

• The implication of this type of error is that the beneficiary is not complying in a systematic way with his agreement obligation .

• Assumption:– Can imply that all currently open and closed agreements under

the same framework program (FP) are affected and might need to be (retrospectively) adjusted

• Impact:– Beneficiaries will be asked to reconsider all financial statements

handed in under the same FP and where necessary recalculate and revise the statements

Page 22: 1 Control procedures: EC Audits European Commission RTD.M.1 External audits Maurizio Dal Toso Horizon 2020 Tallinn 1/12/2011

26

Audit tools: extrapolationSystematic errors

Extrapolation Steering Committee

RDG common decision

Joint RDG projects list

Audit closure

Extrapolation process start

Implementation by operational directorates

NON Systematic errors

Audit closure

Implementation by operational directorates

FP7 Audit Strategy

Page 23: 1 Control procedures: EC Audits European Commission RTD.M.1 External audits Maurizio Dal Toso Horizon 2020 Tallinn 1/12/2011

28

ADDITIONAL INFORMATION

FP6 / FP7 Audit certification policy websitehttp://cordis.europa.eu/audit-certification/home_en.html

FP7 Certification FAQs

ftp://ftp.cordis.europa.eu/pub/fp7/docs/faq-certification_en.pdf

http://ec.europa.eu/research/enquiries

And in case of doubts, don't forget:

RESEARCH HELPDESK

Guidance notes on FP7 audit certificationhttp://cordis.europa.eu/fp7/find-doc_en.html#guidance

Page 24: 1 Control procedures: EC Audits European Commission RTD.M.1 External audits Maurizio Dal Toso Horizon 2020 Tallinn 1/12/2011

29

Questions?

Page 25: 1 Control procedures: EC Audits European Commission RTD.M.1 External audits Maurizio Dal Toso Horizon 2020 Tallinn 1/12/2011

30

The End

DG RTD-A.4