1 conceptual framework for ppps presentation to the planning board may 2007 pv ravi infrastructure...
TRANSCRIPT
1
Conceptual Framework for PPPsConceptual Framework for PPPs
Presentation to the Planning Board
May 2007
PV RaviInfrastructure Development Corporation (Karnataka) Limited
2
Definition
A Public Private Partnership is an arrangement between a public (government) entity & a private (non-government) entity by which services that have traditionally been delivered by the public entity are provided by the private entity under a set of terms and conditions that are defined at the outset
3
Characteristics
The public entity should have the enabling authority to transfer its responsibility – enabling legislative & policy framework, administrative order – the instrument of transfer is through a contract
There is usually a significant transfer of responsibility to the private entity – and usually includes financial investment obligations
For a payment to the private entity – directly by users or by the public entity such that - a significant portion of project revenues and/ or the payments, are conditional on achieving pre-specified levels of performance
The nature of the relationship is usually long-term
4
Risk Sharing
A risk is defined as any factor, event or influence that could threaten the successful completion of a project in terms of time, cost or quality
In a conventional BOQ based implementation : risks – planning, design, construction, environmental & social, physical damage and financing are evaluated
Commercial risks – revenue or maintenance costs, quality, safety of users and general regulatory risks – not critically evaluated – this is critical though to a private investor
PPP involves sharing of risks – risk allocated to the party best suited to manage them
5
Why PPPs?
Fiscal reasons - Inadequacy of resources – leveraging on lower government funding
Optimal transfer of risks – to the entity best suited to manage the risks Design, Financing, Construction, Operations and
Maintenance – all are commercially understood and manageable
Change of scope, defective designs, time overrun, cost overruns, leakage of revenues, high maintenance costs
Transfer of responsibilities – efficiency gain Appropriate technology, innovative design solutions,
project management, better collection practices, life cycle costing
6
Other Reasons Enhanced bankability – more rigorous project
preparation Incentive to deliver whole life solution – not
just asset creation Focus shifts to service delivery – integrated
with construction, measurement of quality & payment linked to service delivery
Acceleration of programme – time-bound implementation
Better overall management of public services – transparency in prioritisation, selection and ongoing implementation
7
PPP Options
Full Privatization
Works & Services
Contracts
Management &
Maintenance Contracts
Operation & Maintenance Concessions
Build Operate Transfer
Concessions
Low High
Extent of private sector participation
8
Concessions
BOT - Build Operate Transfer
BOOT - Build Own Operate Transfer
BOO - Build Own Operate
BOOST - Build Own Operate Share Transfer
BOLT - Build Own Lease Transfer
DBFO - Design Build Finance Operate
OMT - Operate Maintain Transfer
9
Types of PPPs
Financially free standing projects Role of public sector - planning, licensing & statutory
procedures; no financial support/ payment by government Revenues through levy of user charges by private sector Toll Roads and Bridges, Telecom services, Port projects
Projects where Government procures services Private Sector paid a fee (tipping fee), tariff (shadow toll) or
periodical charge (annuity) by Government for providing services; payment against performance – no/partial demand risk transfer
Risks associated with asset creation (including design) and O&M transferred to private sector
Accountability to users for service - retained by Government Roads - annuity/ shadow tolls, power - under PPAs. In the UK -
prisons, education, health services, defence related services
Other Types - Joint ventures, Not-for-Profit vehicles
10
Features of PPPs - 1 Genuine risk transfer
All risks pertaining to design, building, financing and operation transferred to the private entity
Transfer of demand risk depends on the extent to which the private sector can influence usage
Output based Specifications Contracts specify the service outputs required rather
than asset configuration/mode of service delivery Emphasis on type of service & performance standards Private entity incentivised to deliver outputs using
innovation in design, construction, operation and financing
11
Features of PPPs - 2
Whole life asset performance Private entity takes responsibility &
assumes risk for the performance of the asset and delivery of service over a long term
Payment for Performance Revenue/ Payment to private entity is
subject to performance in relation to specific & quantified criteria enshrined in the contract
12
Value for Money
Transfer of risks/ responsibilities under a PPP structure should result in better value for money for the user Telecom sector – mobile phone tariffs from
Rs. 16/- per minute to Re.1/- or 50 paise per minute
Tolls paid – offset by savings in direct & indirect costs and value of time
Annuity payments – public sector comparator – value for money
Efficiency gain Savings in cost of project versus overrun Savings in operating costs Revenue maximization - leakages
13
Basic Issues
Striking a balance between differing concerns & objectives of parties
Legislative Back upRights and obligations of partiesIdentification and allocation of risksPenalties and rewards which would
ensure performance
14
Broad Roles & Responsibilities Government Agency
Providing Project Site/ Assets Environmental Clearances Supporting Infrastructure and Utilities Specific Obligations (e.g. dredging) Regulatory Functions
Concessionaire Designing, Engineering, Financing Construction/ augmentation / upgradation Operation and Maintenance Payment and other obligations Transfer of assets at expiry of concession period
In exchange the concessionaire has the right to receive revenue – tolls or annuity or any other mechanism
15
Other Key Elements Bankability Issues
Concessionaire’s ability to assign rights Lenders’ step-in rights Charge on project assets and enforceability Critical Events and consequences
Force MajeureEvents of Default
Remedial process incase of default/ events leading to termination
Protection of debt in the event of termination
Supporting Provisions Dispute Resolution Mechanism Re-negotiation in good faith Termination as a last resort Preferential treatment in re-bidding
16
What a PPP is not & what it is
PPP is not privatisation or disinvestment PPP is not about borrowing money from the private
sector. PPP is more about creating a structure
in which greater value for money is achieved for services through private sector innovation and management skills delivering significant improvement in service efficiency levels
This means that the public sector no longer builds roads, it purchases miles of maintained
highway no longer builds prisons, it buys custodial services no longer operates ports but provides port services through
world class operators No longer builds power plants but purchases power
17
Partnership in Practice
Partners not adversaries – background of mistrust
Project should be the focus – “win-win” for both
the parties
Independent agencies – Independent Engineer -
useful during both implementation and operations
Government retains ultimate responsibility – uses
the private sector to deliver infrastructure
services of specified standard
Private Financing – can significantly leverage
public funds
18
Basic Features Conventional financing is asset based – debt provided is
usually a percentage of project cost linked to the value of asset cover
Project Financing is cash flow based - on the estimated cash flows that are generated by the project “A financing structure that relies on future cash flows of a
project as the primary source of its servicing & repayment, with only the project assets, rights and interests being the security”
There is little or no recourse to the sponsors Usually large projects - investments are huge & costs of
non-completion/ unsuccessful operations - affect many Little tangible security All stakeholders would, therefore, like to see it succeed
19
Project Appraisal
An elaborate project appraisal process – analysis of risks and specification of return expectations (pricing) from investing in the project
Cash flow projections based on technical, market and financial analysis
Risk mitigated through project contracts and financing agreements or consciously taken after evaluation
Structured financing – to meet the characteristics of the project
Security and documentation - elaborate
Project monitoring and compliance
20
Typical Funding Sources Equity Capital
Core capital provided by the promoters (developers / contractors) Minority stakes may be taken by financial investors / funds
Preference Capital Can be used if suitable changes made to the CA
Senior Secured Debt Normally in the form of rupee term loans/ debentures from Indian
banks/ institutions Capital market instruments – may be possible after CoD; not too
popular yet A variant could be debt with 2nd charge
Subordinated Debt Typically with far lesser rights May even be unsecured
Challenge is to evaluate how additional resources can be channelised into the sector - insurance funds, pension funds
21
Key Project Contracts
Concession Agreement Project Site Licence Agreement Shareholder/ JV Agreement Substitution Agreement / Direct
Agreement State Support Agreement EPC Contract O&M Contract Trust and Retention Agreement
22
Main Provisions Concession Agreement
Terms and conditions of undertaking the project Obligations of the parties Tenor of the contract Default provisions and remedies Provision for substitution Force Majeure provisions and remedies Termination and compensation payments
State Support Agreement Support during implementation Protection from a competing facility
23
Other Key Contracts EPC Contract
Price Overrun Time Overrun LDs and Bonus provisions Performance security Standards and Specifications
O&M Contract Operating Standards Costs Quality of Service Penal provisions
TRA Agreement Trapping of all the project cashflows Prioritization of Cash flows
24
Financial Analysis Elaborate Financial Model capturing these risks – base case
analysis Establishes breakeven levels of traffic/ tariffs Assessment under various scenarios – sensitivity analysis
Demand / Traffic Tariff / Tolls Inflation Maintenance Costs
Financial Ratios
Debt Equity Ratio – cash flow impact & level of promoters’
funds
Internal Rate of Return (project/ equity)
Debt Service Coverage Ratio
Loan Life Ratio
Project Life Ratio
25
Financing Documents
Facility Agreement Financial Terms Project Risk Mitigating
Conditionalities General Conditions
Inter-Creditor Agreements Security Documentation
26
Basic Structure
Project SPV
NHAI
Lenders
Contractor
JV Partner
Main Sponsor
Indep EngLE
Debt
Financing Agreements
Equity
EPC Agmnt
O&M Agmnt
Annuity
Shhldr’s Agmnt
Concession
Agreement
27
Transaction Structure
Government
Project SPV
Invt. Bankers,Technical & Legal
Advisers
Advisers
Invt. Bankers,Technical & Legal
Advisers
Advisers
UsersOff-take Contracts
InsuranceCompanies
Insurance Policies
EPC Contractor
EPC ContractTRA
Agent
TRA/Escrow Agreement
Concession / Licence Agreement
O&M Operator
O&M Contract
Sponsors
Equity
FinancialInvestors
Equity /Sub-Debt
Lenders
Debt SubstitutionAgreement
28
Implementation Structures
Existing Assets Full Divestiture – UK – Telecom, Steel, Electricity, Ports,
Water, Airlines, Airports; so far in India – Modern Foods, BALCO, Hotels
Asset Sales/ Leases – airports in Australia BOT/ ROMT Concessions – roads, tourism facilities, berths in
ports Management contracts – water assets, ports in Philippines
New Assets Implementation by government – followed by OMT
concessions – Mumbai-Pune expressway, Ports in Rotterdam, hospitals
Implementation through SPVs – Moradabad bypass or port connectivity projects or dedicated freight corridor for railways
BOT Concessions – commonest form – roads, ports,
29
Isn’t Private Infrastructure Expensive?
30
Isn’t Private Infrastructure Expensive?
Additions to Cost BenefitsRisk Premium Lower Cost From Efficiency
Example
Public Entity Private Entity
ROI 8% WACC 13.7% (Debt @ 11% 70: 30 Equity @
20%)
Cost 105.3 Cost 100
Required RequiredReturn 113.7 Return 113.7
A 5.3% cost overrun (increase in actual project cost) in the public sector is enough to overcome the private sector disadvantage of higher financing cost!
31
Isn’t Private Infrastructure Expensive?
Additions to Cost BenefitsRisk Premium Lower Cost From Efficiency
Example
Public Entity Private Entity
ROI 8% WACC 13.7% (Debt @ 11% 70: 30 Equity
@ 20%)
Cost 100 Cost 95
Required RequiredReturn 108 Return 108
A 5% reduction in project cost (efficiency) by the private sector is enough to overcome the higher financing cost!
32
Key question What should be the framework to induce the
private entity make the investments needed to provide efficient service to the end user? Investments decided by the investor or driven by
the market, i.e. the consumer Private entity has a stronger case for state support
if it makes investments determined by the State Demand risk – how much passed on?
Extricate the public entity from making commercial decisions on individual projects, wherever possible
Public entity’s role from being a planner, financier & manager to facilitator & regulator
33
The Right BalanceThe Investor wants
Monopoly rights
Full pricing freedom
State support for social obligations/ viability considerations
The Investor needs
Initial risk mitigation support - can be pre-defined
Stable environment -
regulatory and policy framework
State support for social obligations/ viability considerations – can be transparently determined
34
Some Indian Examples - 1 Roads
BOT Concessions for toll roads and bridges (NHAI, state governments) (OMT Concessions in future)
Annuity payment based concessions – highways, urban roads (NHAI/ state governments)
Solid Waste Management Engineered landfills – tipping fee linked payments
(Bangalore, Trivandrum) SW Collection and Transportation (MCD/ NDMC)
Port Concessions Major Ports – container berths (JNPT, Chennai, Kochi,
Tuticorin, Vizag, Kandla); bulk cargo berths (Marmagao, Haldia, Ennore, New Mangalore)
Minor Ports –Pipavav, Mundra, Kakinada
35
Some Indian Examples - 2
Water Supply and Sanitation – Bulk water supply systems in Tirupur and Vizag
Tourism Facilities – hotels, tourist facilities, PWD rest houses – Karnataka & Kerala
Bus Terminals/ Parking Facilities Bus terminals – Dehra Dun, Amritsar, Jullundur Parking + commercial complexes – NDMC/
DDA/ MCD/ Bangalore
36
International Experience - 1
Toll Roads (Chile, Mexico, Hungary, Poland); Ports (Argentina, Philippines, Sri Lanka)
Airports (Australia, Greece, Germany) Roads in UK under DBFO program Private Finance Initiative of UK – diverse areas
Dorset Police Service - $ 40 million contract for refurbishment of police stations, construction of a divisional headquarters building, maintenance, janitorial & waste management services
Nottinghamshire, Police Fleet Management Contract - ($ 180 million over 25 years) – driver slots - usage of a vehicle for a 24 hour period
Durham & Dunstead Hospital Project, Durham – 30 year, $ 155 million hospital services contract – to construct and operate health care facilities + ancillary services
Stoke-On-Trent Grouped Schools Project – a $ 250 million project involving 122 schools – refurbishment and maintenance contract
37
International Experience - 2
Louis Trichardt Maximum Security Prison Project, South Africa – a $ 270 million project – largest prison facility (also UK and Australia)
Full fledged water concessions in Argentina (Buenos Aires) and Philippines (Manila); Management contract for water supply & sanitation in Johannesburg, South Africa
Rural Pay Phones, Peru – against payment of a subsidy – based on a system of monitoring of service standards
38
On the Table in Karnataka
Airport Rail Link Core Ring Road Airport Expressway BMRDA Townships Minor airports Tourism Properties IMTC (Kempegowda) Mega Convention Center, Bangalore Bypass roads Truck terminals …