1 beam pipe and vxd mockup status at kek s.tanaka (kek) svd/pxd meeting

63
1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

Upload: paul-brown

Post on 29-Jan-2016

222 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

1

Beam pipe and VXD mockup status at KEK

S.Tanaka (KEK)SVD/PXD meeting

Page 2: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

2

Beam pipe preparation status

Items Study

Beam pipe design Almost done (minor change is still acceptable)

Beryllium part production done

Titanium part production Design has done

IP Cooling OK

Mechanical tolerance estimation OK (by weight, temperature stress)

Crotched part production procedure OK

Cost estimation of materials OK (1 set has ordered)

Connectivity test (Be-Ti) OK (should be validate before this March)

Connectivity test (Ti-Ta) OK(should be validate before this March)

Ridge shape optimization To be finished soon

PXD mount To be solved (space for sensor)

Au plating inside IP chamber Start discussing with company

Page 3: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

3

2011 Optimizing production procedure(writing rough sketch note for each procedure) for first prototype.– Service space allocation will be decided– Validate the technology of connectivity for each materials.2012From the end of 2012– Starting VXD mock-up assembly

Mechanics check -> installation test , Cooling test

Beam pipe production(for BEASTII)Freezing the mechanics design (including cooling system, cabling, monitors)2013 SVD Ladder mount start (SVD) (2013 Sep.) Beam pipe production 2014 End of 2014 -> BEAST Beam pipe production2015 Starting VXD assembly(Aug-Sep) (CR test ) and installation

3

Schedule (IR mechanics)

When is the time limit to produce of IR subparts?

Page 4: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

IR mechanics schedule

• We have still spare time to modify beam pipe design

4

Page 5: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

Beam pipe production

5

Page 6: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

How to optimize the IR mechanics design?

Subject Requirement to optimize

IP chamber Be part lowest atomic number metal

Ti part coefficient of linear thermal expansion difference with Be (similar number is better)

Au coating Protect SR from final focus magnet

Crotch part Material (Tantalum)

Cost, heavy material as shield , experience using as vacuum chamber, BG simulation

Outer shape Production procedure, Space requirement from PXD,SVD

Inner shape Beam optics, SR shielding, HOM power

Shield Heavy metal Cost, upper limit from CDC weight request, BG simulation, Space request from PXD, SVD

Page 7: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

Technology choice of connectivity on each part

HIP = Hot Isostatic Pressing

•A test for Be-Ti brazing and Ti-Ta HIP is now undergoing.•They are not special technologies.•Ti is adopted instead of stainless steel to reduce the stress (see the following slides).

WL: 210W (Ta) WL: 140 W (Ta)

WL: 190 W (Ta)SRQ: ~ 50 WSRB: 100 W

WL: 70 W (Au)SRQ: few W

WL: 270 W (Ta)SRQ: ? WSRB: 130 W

10~20 m

Page 8: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

VXD design

Otherwise BG shower reach PXD directly

Add heavy metal here

Add more if not too heavy

6mm gap for cabling

gap for Cooling pipe/BPM cable

2011/10/17ver.Base design are not changed

Request by BG simulation

PXD request

Page 9: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

Latest space request(Dec.) from PXD:PXD group requested to make a space for Kapton flex and Omega.We may cut the beam pipe for Kapton flex, however those region is critical toshield BG for PXD or SVD. We have enough time to discuss before production

Page 10: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

10

Design work has been done.The mock-ups are in KEK and MPI.

Page 11: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

Beam pipe and QCS mock-up

11

Page 12: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

Au coating inside of IP chamber

• The company, which performed Au coating, changed their policy not to use Be. Then we ask another company to produce dedicated sputtering system.

• Next fiscal year, we will try Au sputtering study using SUS pipe with CLEOII data.

12Pipe diameter was 4cm

Page 13: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

Beam pipe (Crotch part)

13

The crotch part (Tantalum) is divided into three pieces.The inner pipe structure has made by drilling with 5-axis stage.After then, those three pieces are joined by welding. Drilling test : finished Material for 1st version has ordered

Ridge shape to protect SR(x-ray) from final focus magnet

Page 14: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

Beam pipe production

14

Ti small pipe is connected with HIP (Ti-Ta)

IP chamber(inner) is connected with welding (Ti-Ti)

Outer pipe of IP chamber and inner pipe are connected by EBW

Page 15: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

Vertex detector Assembly and installation

Koike(BP,SVD design, install jigs)Kohriki(BP,CDC,SVD design)Kanazawa(BP,KEKB machine)Sato(SVD mounting)

Page 16: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

Simple Installation test

• Almost all mock-up components will be produced before the end of Mar.(including CDC inner cylinder and CDC inner structure mock-up)

16

We will start from this April

Page 17: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

End flange

• SVD flange should take care for SVD cables and pipes.• BP flange should take care for BP, PXD and shield support• This two components will be assembles, independently.

Page 18: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

18

Beam pipe is keep by this shield structureSUS mock up will be produced in a few weeks.The cost of HM ver, is around 6000$.

The shield is fixed by the end-flange

Page 19: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

19

Beam pipe endflange

Page 20: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

SVD outer structure mock-up

20

Page 21: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

SVD end flange

21

The holes for cabling are just implementation of SVD2

Page 22: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

22

Beam pipe is connected at here PXD PP space is not optimized on this ver.

Page 23: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

SVD support flange

23

Page 24: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

VXD installation jigs

24

Page 25: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

Assembly at KEK

Combined with QCS at Tsukuba hall

SVD support ring

Vertex detector installation

Page 26: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

The sled guide is fixed on backward side

Vertex detector installation

Page 27: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

How to connect with backward sled

27

Adapting support ring Connected with sled

Page 28: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

Vertex detector installation

Guide pin to fix the VXD angle

Page 29: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

Vertex detector installation

Temporal support guide

The VXD weight is keep by support guide and QCS

Page 30: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

Vertex detector installation

This guide ring keep weight

Page 31: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

Vertex detector installation

The backward weight is shift to this guide

SVD cover should not attach to another structure on installation at every time

Page 32: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

Vertex detector installation

Remove backward sled

Page 33: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

33

Page 34: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

How to fix at SVD backward

34VXD detector is fixed at backward endfor x, y, z axis

Remove sled

Remove support ring and adopt a bracketconnecting with CDC inner structure

Page 35: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

SVD support ring at forward region

Guide roller to keep weight of SVD

Positioning guide pin(CDC side)

Release control rod after install(QC cryostat side)

The VXD center position is arranged by those rollers.Forward region is fixed only for x and y axis

Page 36: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

Vertex detector installation

Page 37: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

Vertex detector installation

Page 38: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

Summary of KEK group statusKEK group are preparing mock ups for simple installation test.

Beam pipe (+PXD mount): done (KEK and MPI) QCS structure: done Heavy metal shield:

SVD end flange (for SVD and beam pipe each): SVD support ring: done SVD outer cover: CDC inner structure(between QCS and CDC):

CDC inner cylinder: All of parts will be produced before the end of this March.Then we will start studying installation procedure. After checking each parts, we will produce

one more set of Heavy metal shield(by Al) and beam pipe end flange, then send those to MPI.

(PXD assemble test (cables or cooling?) can be started from around this May or June at MPI.)• After our installation test, those parts may use for mechanics check or cooling test(Where

and how?).• The final mock up (the target is the end of this year) will be produced including feedback o

r requirements from cooling or mechanics community.

Page 39: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

cont'd

• We will produce one beam pipe for BEASTII to validate whole production procedure in next fiscal year.

• After installation test, KEK mechanics group should concentrate into mainly SVD mechanics (Ladder mounting table or assembly jigs).

(Of course, Mechanics request from PXD is always welcome.)

Page 40: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

Belle rotation

40

Page 41: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

41

Belle Rotation

Machine group decided to rotateBelle detector.This work will be on next fiscal year.

Page 42: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

42

Interference

Interference

Exchange piping

What we should take care?

Belle alignment pin position should be shift

Page 43: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

Belle Rotation• Organizer: I.Nakamura, J.Haba• There are two candidate companies

interested in Belle rotation work.• One option is exchanging rail with

rotated angle at interaction region.• Another option is exchange all trucks

with shifted position.

43

Page 44: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

Discussion and requested items

4444

Page 45: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

SVD/PXD dock position

• Please prepare the space request for Dock (SVD and PXD for each).– Also list of cables connectors with dimension for inlet and outlet

• On next B2GM well discuss about space allocation. 45

Page 46: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

Service space allocation on QC cryostat

46

I propose to have a special meeting about allocation of each service on next B2GM( Nov). -> summarize the list of parts in next B2GM

Related subjects:CO2 cooling tubes(SVD, PXD)SVD cablesPXD air cooling tubePXD cablesBP cooling tubesMonitor cables

Space:250cm2

Page 47: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

Space requirement from QCS •Ouchi-san (QCS group leader) propose to put iron shield between QCS and Belle structure (Blue region) PXD/SVD dock space seems to be still free for this requirement

Page 48: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

SVD mechanics discussion

Page 49: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

Conflict region• The structure is cut at the center and a projection is made.

– Hatched region is the cut surface.– Regions with a blue circle is interfering.

• 1, 4, 5: Layer3 ladder and PXD.• 2, 6: Layer 3 ladder support and PXD• 3: Layer 3 hybrid and Layer 4 ribs.• 7, 8, 9 : The gap between CFRP cone and Beam pipe is narrow for the PXD cables. (The

top-view is narrowest… though).• 8: CFRP cone is interfering with the PXD patch panel. (we do not know the patch panel

shape is optimized or not.) • 7-9: The CFRP shape has been changed. The previous shape (shown in yellow) was

compatible with PXD design.

1 Feb. 2012 Toru Tsuboyama49

Page 50: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

Discussion (Tanaka)There are two important milestones: 1, VXD mechanics mock-up production(end of this year)2, SVD ladder mounting (starting the end of next year)Then I asked Tsuboyama-san to set more detail schedule (also time of no return). i.e (including my questions, but some items may already be solved) A, when the design and production of mounting table should be finalized? B, Ladder mount test for each layer (+ thermal stress test?) should be finished before mo

ck-up productionC, Cooling test of hybrid with endring(+CO2 system?)How to manage to thermal connection between hybrid and endring?D, Until when, we should solve the interference between SVD(3rd) andPXD, or SVD(3) and SVD(4)etc.

Page 51: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

SVD Milestone(Tsuboyama)

• Many subjects seem to be jammed on second quarter of 2012• To encourage those study effectively, man power should be concentrated

in one or two places to discuss in detail.

Page 52: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

First step to solve the issues• The main subject of KEK IR group shift the stage of beam pipe design into helping S

VD mechanics work.– Mockup production– Some test to select materials– Ladder mount table design– Final SVD structure production

• In order to encourage sharing work with KEK group or other groups, SVD group prepare "Problem note" which describes (like weekly report):– Name of issue– responsible person– requirements to solve the issue– The time limit– concerning with other subjects (i.e. physics impact on ladder position) etc.

• We start discussion with SVD EVO meeting about this project and will discuss in detail at next B2GM (dedicated session concerning mechanics problems)

Page 53: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

VXD assembly procedure

BKUP

Page 54: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

Beam pipe have been already produced(KEK and MPI)

Page 55: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

Heavy metal shield

SVD end flange

Page 56: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

Beam pipe is connected with this bracket

Page 57: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

Small Heavy metal shield(which keep by beam pipe)

Page 58: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting
Page 59: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

SVD structure

Page 60: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting
Page 61: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting
Page 62: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting
Page 63: 1 Beam pipe and VXD mockup status at KEK S.Tanaka (KEK) SVD/PXD meeting

Connection bracket of SVD halves