1 a fundamental principle of tps produce to demand 1.make only what is needed when it is needed....

12
1 A Fundamental Principle of TPS Produce to Demand 1. Make only what is needed when it is needed. 2. Base production and planning on Takt Time. 3. Develop flexible production lines. When demand changes, the line changes. Usually, labor changes to maintain labor efficiency.

Upload: cameron-boyd

Post on 13-Jan-2016

213 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: 1 A Fundamental Principle of TPS Produce to Demand 1.Make only what is needed when it is needed. 2.Base production and planning on Takt Time. 3.Develop

1

A Fundamental Principle of TPS

Produce to Demand

1. Make only what is needed when it is needed.

2. Base production and planning on Takt Time.

3. Develop flexible production lines. When demand changes, the line changes. Usually, labor changes to maintain labor efficiency.

Page 2: 1 A Fundamental Principle of TPS Produce to Demand 1.Make only what is needed when it is needed. 2.Base production and planning on Takt Time. 3.Develop

2

Produce to Demand…Takt Time

1. Takt Time is the pace at which the customer is buying a particular product.

2. Takt time is not how long it takes to perform a task. It is customer demand, not cycle time.

3. Takt time is calculated by taking the available time to work and dividing it by the demand for that period of time

4. Takt time cannot be reduced or increased except by a change in sales or the available time to work

Page 3: 1 A Fundamental Principle of TPS Produce to Demand 1.Make only what is needed when it is needed. 2.Base production and planning on Takt Time. 3.Develop

3

Takt Time Formula

Productive Time Available per period

Number of Required Units per period

Time available per Shift (8 hours)

Breaks (2 at 10 minutes each)

Lunch

Productive Time Available =

480 minutes

-20 minutes

-20 minutes

440 minutes or 26,400 seconds

Example: Productive Time Available Calculation

Page 4: 1 A Fundamental Principle of TPS Produce to Demand 1.Make only what is needed when it is needed. 2.Base production and planning on Takt Time. 3.Develop

4

Takt Time Formula

Productive Time Available per period

Number of Required Units per period

Units = 72,000 units ordered per month = 1,200 Units Required per Shift

60 shifts per month (3 shifts x 20 days)

Example: Number of Required Units Calculation

Page 5: 1 A Fundamental Principle of TPS Produce to Demand 1.Make only what is needed when it is needed. 2.Base production and planning on Takt Time. 3.Develop

5

Takt Time Formula

Productive Time Available per period

Number of Required Units per period

Takt Time = 26,400 seconds available per shift = 22 seconds / unit

1,200 units required per shift

So…the line should make one unit every 22 seconds to meet customer demand.

Example: Takt Time Calculation

Page 6: 1 A Fundamental Principle of TPS Produce to Demand 1.Make only what is needed when it is needed. 2.Base production and planning on Takt Time. 3.Develop

6

123 seconds = 5.59 or 6 operators required

22 seconds

Example: Operators Required Calculation

Number of Operators Required Formula

Sum of Manual Cycle Time

Takt Time

Page 7: 1 A Fundamental Principle of TPS Produce to Demand 1.Make only what is needed when it is needed. 2.Base production and planning on Takt Time. 3.Develop

7

Labor Efficiency Formula

(Sum of Manual Cycle Time / 3600seconds per hour) x Demand per Shift x100

Current Manning x Available Hours per Shift

Total manual time to make one unit

Demand per shift

Current Manning

Available hours per shift

123 seconds

1,200 units

7 direct operators

7.3 hours (440 minutes)

Example: Variables

Page 8: 1 A Fundamental Principle of TPS Produce to Demand 1.Make only what is needed when it is needed. 2.Base production and planning on Takt Time. 3.Develop

8

(123 seconds / 3600 seconds) x 1,200 units per shift x100 = 70% labor efficiency 7 operators x 7.3 hours per shift

Example: Labor Efficiency Calculation

Labor Efficiency Formula

(Sum of Manual Cycle Time / 3600 seconds per hour) x Demand per Shift x100

Current Manning x Available Hours per Shift

Page 9: 1 A Fundamental Principle of TPS Produce to Demand 1.Make only what is needed when it is needed. 2.Base production and planning on Takt Time. 3.Develop

9

26,400 seconds per shift = 1,553 unit capacity per shift

17 second cycle time bottleneck station*

Example: Capacity Calculation

Line Capacity Formula

Productive Time Available (seconds)

Bottleneck Station Cycle Time* (seconds)

*Bottleneck Station Cycle Time = Machine C/T + Manual Load / Unload C/T

Page 10: 1 A Fundamental Principle of TPS Produce to Demand 1.Make only what is needed when it is needed. 2.Base production and planning on Takt Time. 3.Develop

10

1,200 units per shift x 100 = 77%

1,553 units per shift

Example: Performance to Capacity Calculation

Performance to Capacity Formula

Actual Line Output (units) x100

Line Capacity (units)

Page 11: 1 A Fundamental Principle of TPS Produce to Demand 1.Make only what is needed when it is needed. 2.Base production and planning on Takt Time. 3.Develop

11

Examples: Operational Availability Calculation

Operational Availability (Formal TPS Definition)

Actual Output (units) x100

Demand (units)

1,080 units per shift x100 = 90%

1,200 units per shift

1450 units per shift x100 = 120%

1200 units per shift

under-production over-production

Page 12: 1 A Fundamental Principle of TPS Produce to Demand 1.Make only what is needed when it is needed. 2.Base production and planning on Takt Time. 3.Develop

12

Examples: Rate of Operation Calculation

Rate of Operation Formula

Demand (units) x100

Capacity (units)

1,200 units per shift x100 = 77%

1,553 units per shift