1 9. SEQUENCING CONSTRUCTION TASKS Objective: To understand the problem of sequencing tasks in a manufacturing system, and the methods of finding optimal solutions to this problem. Summary: 9.1 Introduction 9.2 A Number of Jobs, Two Processes 9.3 Two Jobs, A Number of Processes 9.4 A Number of Jobs, A Number of Processes

Upload: joy-holland

Post on 16-Dec-2015

214 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: 1 9. S EQUENCING C ONSTRUCTION T ASKS Objective: To understand the problem of sequencing tasks in a manufacturing system, and the methods of finding optimal

1

9. SEQUENCING CONSTRUCTION TASKS

Objective: To understand the problem of sequencing tasks in a

manufacturing system, and the methods of finding optimal solutions to this problem.

Summary:9.1 Introduction9.2 A Number of Jobs, Two Processes 9.3 Two Jobs, A Number of Processes9.4 A Number of Jobs, A Number of Processes

Page 2: 1 9. S EQUENCING C ONSTRUCTION T ASKS Objective: To understand the problem of sequencing tasks in a manufacturing system, and the methods of finding optimal

2

9.1 INTRODUCTION

Sequencing and scheduling are different problems, both essential to the effective planning of a project:

– Sequencing: arranging the order of tasks/events (where there is a choice) so that some measure of performance (time, cost, etc...) is optimized;

– Scheduling: timing the occurrence of tasks/events (the order of tasks/events is largely determined by other factors and is not normally a choice);

Page 3: 1 9. S EQUENCING C ONSTRUCTION T ASKS Objective: To understand the problem of sequencing tasks in a manufacturing system, and the methods of finding optimal

3

Sequencing problems in their most general definition comprise the following components:

Fig. 9-1: Components of a Sequencing Problem

ProcessA

ProcessB

ProcessC

ProcessD

There are a number of jobs to be performed (for example, manufacture ‘n’ prefabricated RC beams and columns).

Each job must go through several processes (for example, fabricate forms, fix steel, pour conc…)

There are limited resources available to perform each process (for example, one carpenter, one steel fixer, etc..)

There may be other constraints such as a predefined order in which the processes must be performed for a job, but not for the order of jobs at a process.

The duration at each process may vary for each job.

The objective may be to complete work as quickly as possible.

Job 1Job 1

Job 1Job 1

Job 1Job 6

Page 4: 1 9. S EQUENCING C ONSTRUCTION T ASKS Objective: To understand the problem of sequencing tasks in a manufacturing system, and the methods of finding optimal

4

9.2 A Number of Jobs, Two Processes

Solving sequencing problems is not usually that easy. However, there are a number of special cases where there is a simple method of solution:

– the first of these is the two-process job-shop problem, which comprises the following:• two processes;• any number of jobs;• one crew at each process;• the order in which a job must pass through the processes is predetermined;• the order of jobs must be the same at each process, but is not pre-specified;• the project must be completed as soon as possible.

– This problem can be solved using Johnson’ Algorithm:

Page 5: 1 9. S EQUENCING C ONSTRUCTION T ASKS Objective: To understand the problem of sequencing tasks in a manufacturing system, and the methods of finding optimal

5

Consider the problem of manufacturing a number of prefabricated RC components (beams and columns):

– the two processes are:• set-up forms; and• pour concrete into forms and let cure.

– the components and the amount of time at each process are:

Component Set-up (hrs) Conc+Cure (hrs)

A 15 9B 10 4C 8 2D 10 11E 10 8F 4 4G 9 3

- what order should process the jobs to minimize project duration?- draw the schedule for the above arbitrary sequence, determine

total duration, and suggest improvements:

Page 6: 1 9. S EQUENCING C ONSTRUCTION T ASKS Objective: To understand the problem of sequencing tasks in a manufacturing system, and the methods of finding optimal

6

A

B

C

D

E

F

0 15 24 25 33 43 53 54 62 69

G

66

15 9

10 4

8

10 11

10 8

4 4

9 3

Page 7: 1 9. S EQUENCING C ONSTRUCTION T ASKS Objective: To understand the problem of sequencing tasks in a manufacturing system, and the methods of finding optimal

7

– Step 1: select the shortest time which appears in either list (if two values are the same, the choice is arbitrary) .

Component Set-up (hrs) Con+Cure (hrs) Order

A 15 9B 10 4C 8 2D 10 11E 10 8F 4 4G 9 3

Johnson’s algorithm:

– Step 2: if shortest time is first process, do the job first, otherwise do it last.

– Step 3: repeat steps 1 and 2, until all jobs have ben sequenced.

CG

EB

ADF

Page 8: 1 9. S EQUENCING C ONSTRUCTION T ASKS Objective: To understand the problem of sequencing tasks in a manufacturing system, and the methods of finding optimal

8

A 15 9

B 10 4

C 8

D 10 11

E 10 8

F 4 4

G 9 3

0 4 14 25 29 38 47 49 53 6858 61- draw the new schedule

- the new schedule reduces the overall duration by one day;- more complicated projects may have even bigger savings.

Page 9: 1 9. S EQUENCING C ONSTRUCTION T ASKS Objective: To understand the problem of sequencing tasks in a manufacturing system, and the methods of finding optimal

9

9.3 Two Jobs, A Number of Processes

This section describes another special case of sequencing problems:– the problem is characterized by:

• any number of processes;• two jobs;• one crew at each process;• the order in which a job must pass through the processes is predetermined;• the order of jobs does NOT have to be the same at each process;• the project must be completed as soon as possible.

– This problem can be solved using a graphical approach, but unlike Johnson’s algorithm, it does not guarantee finding the optimal solution:

Page 10: 1 9. S EQUENCING C ONSTRUCTION T ASKS Objective: To understand the problem of sequencing tasks in a manufacturing system, and the methods of finding optimal

10

Consider the following example problem:– two different houses are to be built;– there are different crews for each task (task A to task G) but

only one crew for each type of task;– the following specifies the order in which the tasks must be

completed for each house, and the corresponding durations:

Order House 1 House 2

1 A 2 C 32 C 3 D 53 D 1 B 24 B 4 A 15 F 2 G 36 E 1 F 47 G 3 E 2

– determine the optimum sequence of the houses at each task, in terms of minimizing the project duration.

Page 11: 1 9. S EQUENCING C ONSTRUCTION T ASKS Objective: To understand the problem of sequencing tasks in a manufacturing system, and the methods of finding optimal

11Fig. 9-2: An Example House Construction Project

• Each axis represents progress for one of the houses.

• Block out regions where there is a common demand for a crew.

HOUSE 1A C D B F E G

HO

US

E 2

C

D

B

A

G

F

E

• Draw a progress line, noting:– it cannot pass diagonally through

the blocked out regions;– a vertical or horizontal line

through a blocked region implies one of the tasks has been interrupted (not always good).

– where the progress line is diagonal, progress is being made on both activities;

– where the progress line is horizontal or vertical, only one job is being worked upon;

– the progress line should be as short as possible (count 1 time unit for every box traversed);

– draw the line with the objective of reducing project duration

Idle time forHouse 1

ProjectDuration = 22

Try other routesto see if they are

better.

Page 12: 1 9. S EQUENCING C ONSTRUCTION T ASKS Objective: To understand the problem of sequencing tasks in a manufacturing system, and the methods of finding optimal

12

9.4 A NUMBER OF JOBS, A NUMBER OF PROCESSES

There is no direct method of finding an optimal solution to this category of problems.

– Computer software is available that will search for a near optimal solution. Common examples of such algorithms are:

• heuristic search methods;• simulated annealing;• genetic algorithms;• neural networks.

Page 13: 1 9. S EQUENCING C ONSTRUCTION T ASKS Objective: To understand the problem of sequencing tasks in a manufacturing system, and the methods of finding optimal

13

Consider genetic algorithms (simulated evolution).

– Emulates the theory of evolution through natural selection:

1 generate a number of solutions (sequences for construction);2 test each solution to see which are the most optimal (apply

the objective function);3 cross breed the most optimal solutions (and introduce some

random mutations) to generate another set of solutions;4 with the new set of solutions, return to step 1 and repeat.

Page 14: 1 9. S EQUENCING C ONSTRUCTION T ASKS Objective: To understand the problem of sequencing tasks in a manufacturing system, and the methods of finding optimal

14

The algorithm should operate in a way that satisfies the following requirements

– Cross breeding should be subtle enough to ensure that the offspring solutions are not a complete jumble of their parents:

• if they are a complete jumble, the approach is no better than testing different solutions totally at random;

– Cross breeding employed on its own will cause solutions in successive generations to become increasingly similar (genetic convergence):

• this is unlikely, therefore, to find a solution that is nearly optimal;• we get around this problem by introducing some random mutations in each

offspring;• the mutation should be small otherwise we might as well just search at random

for optimal solutions.

Page 15: 1 9. S EQUENCING C ONSTRUCTION T ASKS Objective: To understand the problem of sequencing tasks in a manufacturing system, and the methods of finding optimal

15

– Care needs to be taken to make sure that offspring solutions are legal:• for example, consider the following method of cross breeding sequences of jobs in a job shop problem;• we have to sequences (solutions) to be cross bred:

Sequence X’ = J4 J1 J8 J7 J3 J5 J2 J9 J6

Sequence X” = J2 J1 J8 J7 J3 J5 J9 J4 J6

The resultant offspring from the above would be:

Sequence Y’ = J4 J1 J8 J7 J3 J5 J9 J4 J6

• The resultant sequence, Y’, is illegal since it implies job J4 is fabricated twice, whilst job J2 is not fabricated at all.

Page 16: 1 9. S EQUENCING C ONSTRUCTION T ASKS Objective: To understand the problem of sequencing tasks in a manufacturing system, and the methods of finding optimal

16

– There are proposed methods of cross breeding that guarantee that the resultant solutions are legal, but:• many of these also restrict the possible legal solutions that may be generated:• this could limit the optimality of the solution that can be found.

– A method that guarantees the production of legal solutions, and does NOT restrict the solutions that may be found:• assign real numbers to the list of jobs

J1 J2 J3 J4 J5 J6 J7 J8 J9String X’ = 0.23 0.62 0.36 0.01 0.48 0.91 0.35 0.29 0.87

Strin X” = 0.23 0.02 0.36 0.88 0.63 0.91 0.35 0.28 0.87

The resultant offspring from the above would be:

String Y’ = 0.23 0.62 0.36 0.01 0.63 0.91 0.35 0.28 0.87Deciphered sequence = J4 J1 J8 J7 J3 J2 J5 J9 J6