09 03 25 transprotation safety presentation 2
TRANSCRIPT
-
8/8/2019 09 03 25 Transprotation Safety Presentation 2
1/21
NJ Transit
ALP45DP ProjectStatus
March 2009
Dual-Powered Locomotive(Artist Rendition)
-
8/8/2019 09 03 25 Transprotation Safety Presentation 2
2/21
Dual-Powered Locomotive
2003 Dual-Power feasibility Study
Considerations: Service Expansion - New Routes
Ridership Growth
Replacement of aging Diesel Locomotives
High Density Multilevel Fleet
Seven of Twelve Lines Non-Electrified but >50% ExistingCatenary Infrastructure
Conclusion:
Dual-Powered Locomotives are feasible with todaystechnology for system wide operation
March 2009
Background
-
8/8/2019 09 03 25 Transprotation Safety Presentation 2
3/21
Dual-Powered Locomotive
Exceeds ALP-44 and approaches ALP-46 (ALP-45) performance inelectric mode
Matches PL42-AC performance in diesel mode
2 high speed engines
Provide a fast load rate for acceleration
Space & weight reduction
High capacity - 1000 kW HEP (Twelve Multi-level capable)
AC propulsion & adhesive weight increases traction
FRA 238 & EPA Tier III compliance
Will meet the ARC tunnel fuel tank requirement for compartmentalizationof 400 gallons or less. Total capacity 1600 gallons.
Equipped with an on-board fire suppression system.
March 2009
Overview
-
8/8/2019 09 03 25 Transprotation Safety Presentation 2
4/21
Dual-Powered Locomotive
Base Order is 26 ALP45DP
Contract has options for 63 Additional ALP45DPs
NJT partnered with Agence Metropolitaine de Transport (AMT) to sharethe engineering costs. AMT is purchasing 20 ALP45DPs
First 3 ALP45DPs (1 AMT and 2 NJT) scheduled for delivery for testing inthe 1st quarter of 2011. 1 NJT to Pueblo for testing.
First revenue train is contemplated for end of 2011 on the M&E.
March 2009
Overview - Continued
-
8/8/2019 09 03 25 Transprotation Safety Presentation 2
5/21
Dual-Powered Locomotive
Maximum design speeds: 125 mph in electric mode
100 mph in diesel mode
Maximum power at wheels: 5,360 HP in electric mode
3,600 HP in diesel mode
Starting tractive effort: 71,000 lbs
Length over couplers: 72 0
Width: 9 8
Height: 14 6.4
March 2009
Major Characteristics
-
8/8/2019 09 03 25 Transprotation Safety Presentation 2
6/21
Dual-Powered Locomotive
Improved acceleration over existing diesel locomotives
High speed Caterpillar engines offer improved performance for passengeroperations as opposed to our current medium speed EMD engines
March 2009
Diesel Mode Performance
Distance vs. Time
0
1
2
3
4
5
6
7
0 50 100 150 200 250 300 350 400 450
Time (s)
Distance(miles
)
Dual Pow er - Diesel w ith 8 MultiLevel
PL-42AC w ith 8 MultiLevel
GP40PH w ith 6 MultiLevel
-
8/8/2019 09 03 25 Transprotation Safety Presentation 2
7/21
Dual-Powered Locomotive
Dual Powered Locomotive acceleration will fall between that of the ALP44and the ALP46 Locomotives
March 2009
Distance vs. Time
0
1
2
3
4
5
6
7
0 50 100 150 200 250 300 350 400
Time (s)
Distance(miles)
Dual Pow er - Electric w ith 8 MultiLevel
ALP-46 w ith 8 MultiLevel
ALP-44 w ith 8 MultiLevel
Electric Mode Performance
*ALP44 shown for reference only. The ALP44cannot support HEP for 8 Multilevel.
*
-
8/8/2019 09 03 25 Transprotation Safety Presentation 2
8/21
Dual-Powered Locomotive
Operational flexibility (can operate over the entire NJ TRANSIT system)
Fuel savings by taking full advantage of the catenary system Twin-engines offer redundancy, low noise & fuel savings
110-125 mph NEC operation - Pending
Can self-rescue an Electric mode failure by utilizing Diesel mode
Each axle individually powered allows for wheel differential on same truck
Diesel engine starting system requires no starting motors
Drive units are interchangeable with the ALP46
March 2009
Operating Advantages
-
8/8/2019 09 03 25 Transprotation Safety Presentation 2
9/21
Dual-Powered Locomotive
Will be used to replace aging existing diesel locomotives
Allows NJ TRANSIT to develop operational experience with the DualPower capability in advance of opening ARC
March 2009
Conclusions
-
8/8/2019 09 03 25 Transprotation Safety Presentation 2
10/21
Dual-Powered Locomotive
March 2009
Time-Line
Warranty completion32014
Warranty2013
Production completion32012
Revenue service start4
Prototypes scheduled for Pueblo testing12011
Final Design Complete12010
Preliminary Design Complete2
12009
Board approval - NTP (Notice To Proceed)32008
Bombardier Selected as the Builder4
Advertised RFP22007
Industry Review3
Specification Development1
2006
EVENTQTRYEAR
-
8/8/2019 09 03 25 Transprotation Safety Presentation 2
11/21
-
8/8/2019 09 03 25 Transprotation Safety Presentation 2
12/21
ALP45DPPreliminary Layout
-
8/8/2019 09 03 25 Transprotation Safety Presentation 2
13/21
Clean Cab Radio
-
8/8/2019 09 03 25 Transprotation Safety Presentation 2
14/21
Fire Suppression System
-
8/8/2019 09 03 25 Transprotation Safety Presentation 2
15/21
Fire Suppression System
-
8/8/2019 09 03 25 Transprotation Safety Presentation 2
16/21
Fire Suppression System
-
8/8/2019 09 03 25 Transprotation Safety Presentation 2
17/21
Remote Mode Change (from Cab Car)
-
8/8/2019 09 03 25 Transprotation Safety Presentation 2
18/21
Remote Mode Change (from Cab Car)
-
8/8/2019 09 03 25 Transprotation Safety Presentation 2
19/21
Remote Mode Change (from Cab Car)Remote Mode Change Operation Active When Stopped
-
8/8/2019 09 03 25 Transprotation Safety Presentation 2
20/21
Remote Mode Change (from Cab Car)Mutlilevel - Comet IV
-
8/8/2019 09 03 25 Transprotation Safety Presentation 2
21/21