08 cmgt 360 lesson plan 8 tqm - bldg commissioning - safety

Upload: shams78600

Post on 07-Jul-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/18/2019 08 CMGT 360 Lesson Plan 8 TQM - Bldg Commissioning - Safety

    1/12

    3/6/16

    1

    Lesson Plan No. 8TQM – Safety - Building Commissioning 

    Project ManagementInstructor: David Shirah

    CMGT 360  California State University, Chico

    TQM & Safety

    TQM (Total Quality Management)

    •  Relatively new concept in construction, but has madesignificant impacts during the past two decades inmanufacturing

    •  The entire concept can be summed up as:

    1. Customer satisfaction

    2. Never ending, continuous, incremental improvement

    process

    TQM & Safety

    TQM (Total Quality Management)

    •  Customers are considered to be everyone involved inthe building process from designers to subcontractorsand employees

    •  Does away with hierarchical barriers with input from allthe parties encouraged to be part of the process( ideasflow more freely)

    •  TQM is everyone’s responsibility and everyone’srewarded

  • 8/18/2019 08 CMGT 360 Lesson Plan 8 TQM - Bldg Commissioning - Safety

    2/12

    3/6/16

    2

    TQM & Safety

    When it comes to quality and safety, attitude is everything.To achieve quality results and safety performance,

    Construction Managers must:•  Ensure they have good quality plans andspecification

    •  Provide experienced and adequate supervision on all jobs

    •  Ensure all workers are qualified to do the job they

    are hired to do

    •  Never accept inferior work

    •  Instill an attitude toward high quality and safetythroughout the project team

    TQM & Safety

    !  Quality & Safety (Continued)

    •  Project Manager and Superintendent are accountable fordevelopment and implementing quality and safety plans

    •  Must have the support and participation from the field

    •  Quality and safety are ultimately achieved at the laborforce level

    •  Employees and subcontractors alike must embrace the

     plans and be acknowledged for their efforts to producequality work and a safe working environment

    •  Quality Management Plan should be in place beforemobilizing work at the site

    TQM & Safety

    Quality & Safety (Continued)

    •  Defining Quality:

    • 

    The quality of a project is set through the plans andspecifications by the architect ad engineers

    •  “Quality” is meeting or exceeding the requirementsof the plans and specification

    •  “Construction is not a perfect science, and it would be

    impossible to produce a project without some defects,failures, or complaints. After all, you are working with

    imperfect materials and imperfect people.”

  • 8/18/2019 08 CMGT 360 Lesson Plan 8 TQM - Bldg Commissioning - Safety

    3/12

    3/6/16

    3

    TQM & Safety

    Quality & Safety (Continued)

    • 

    Defining Quality:•  Quality is one of those factors we discussed that

    would impact cost and/or the project schedule

    •  Example of how quality can impact price:

     – RS Means has a cost calculator atwww.rsmeans.com for various types of buildings

    with three distinct levels: low, medium and high 

    TQM & SafetyQuality & Safety (Continued)

    •  Defining Quality: Four examples of price differences are given for anapartment, high school, warehouse and parking garage projects

    Problem arises when the quality of design is not communicated to

    the owner by the designer and the owner take exceptions with the

    contractor

    TQM & Safety

    Quality & Safety (Continued)

    •  So how do you work towards achieving quality?

    •  Do things right the first time

     –  Project team needs to know the quality standards and the best wayto achieve them communicated

    •  Prevent things from going wrong

     –  Project team must be one step ahead of the work in terms ofoversight and supervision through preparatory inspections andcatching things before it becomes and issue

     –  Responsibility of the entire team not just the superintendent

    •  Continually improve the process (TQM)

     –  Never ending

     –  Small steps

  • 8/18/2019 08 CMGT 360 Lesson Plan 8 TQM - Bldg Commissioning - Safety

    4/12

    3/6/16

    4

    TQM & Safety

    Quality Assurance and Quality Control 

    Quality Assurance•

      Long-range view toward developing systems that produce high- quality work consistently

    •  Practices that affect quality for better or worse:

     –  Hiring: have high quality standards (skills, attitude, pride & safe practices

     – 

    Training Programs: employees must be consistently trained intechnical skills and techniques

     –  Safety: establishment of rules, regulations and standards

     –  Hiring subcontractors: low bid not always good ! pre-qualifysubcontractors in advance of bidding

     –  Procurement methods: pre-qualify

     –  Employee incentives: recognition awards and incentives

  • 8/18/2019 08 CMGT 360 Lesson Plan 8 TQM - Bldg Commissioning - Safety

    5/12

    3/6/16

    5

    TQM & Safety

    Quality Assurance and Quality Control 

    Quality Control•

     

    Quality at the project level and is implemented on the jobsite•  Quality Control Practices:

     –  Submittals

     –  Mock-ups: building small models utilizing specified materials

     –  Shop Drawings

     –  Testing Standards: in accordance with industry and testingstandards spelled out in the specifications (ASTM, UL)

     –  Independent Testing and Inspections: Soil, concrete, bolt torque

     –  Building Code Requirements: ensures work conforms with code

     –  Supervisory Inspections: contractor/subcontractors supervise theirwork throughout the process

    TQM & Safety

    Safety (Component of Quality Management)•  Project Managers and Superintendents are responsible

    for the safety of their workers on the jobsite.

    •  Must set standards for safety up front and be forever

    diligent regarding adherence safety plans and OSHA

    •  In 1970, the federal government established an agencycharged with developing safety standards for

    construction and all other industries in the U.S.

    Occupational Safety and Health Administration (OSHA)

    •  OSHA plays big role in construction safety and has theauthority to issue citations and assess fines for

    violation of OSHA standards

    TQM & Safety

    Safety (Component of Quality Management)•  Construction is dangerous work

    •  Accounts for more than 20% of all occupational fatalities

    •  6,000 die from workplace industries yearly in U.S.

    •  50,000 die from chemical exposure

    •  6 million suffer non-fatal injuries

    • 

    Safety is an attitude. It starts with topmanagement and is reflected on the jobsite in many

    ways through training, tailgate meetings, housekeepingand intolerance of violations

  • 8/18/2019 08 CMGT 360 Lesson Plan 8 TQM - Bldg Commissioning - Safety

    6/12

    3/6/16

    6

    TQM & SafetySafety (Component of Quality Management)

    • 

    All contractors/companies must have safety plans for theiremployees. Typical Table of Contents:

    •  Your responsibility

    • 

    Safe Work Rules•  Personal Protective Equipment•  Machinery and Equipment•  Elevated Work•  Excavation and Trenches•  Hand and Portable Electric Tools•  Fire and Flammable Material•  First Aid•  Housekeeping•  Weekly Safety Meetings•  Medical Treatment and Injury Report•  Hazardous Substances•  Facts about Workers’ Compensation•  Drug-Free Workplace Policy

    TQM & SafetySafety  All contractors/ 

    companies must have

    safety plans for theiremployees.

    TQM & Safety

    Safety (Component of Quality Management)

    •  Weekly Tailgate Safety Meeting (OSHA Requirement)•

      Reinforces safety as a high priority on the jobsite

    •  Conducted weekly with workers

    •  Choose a topic weekly and discuss

    •  Employees sign and meeting filed

    •  Safety Officer – Designate and workers must know

    •  MSDS Sheets - Material Safety Data Sheets (OSHA Requirement)

    • 

    Every Safety Management Plan must have a system forcompiling and documenting chemical information on various products used on the sites called MSDS sheets

    •  For chemicals obtained from vendors and manufacturers(provide upon request/request when purchasing)

    •  Contains information about chemical exposure, protection, andfirst aid

  • 8/18/2019 08 CMGT 360 Lesson Plan 8 TQM - Bldg Commissioning - Safety

    7/12

    3/6/16

    7

    TQM & Safety

    Safety (Component of Quality Management)

    •  Lost Time Frequency Rate: Man Hours ÷Incident Rate

    •  Total Reportable Incident Rate (TRIR): An incidence rate

    of injuries and illnesses may be computed from the

    following formula -

    •  (Number of injuries and illnesses X 200,000) / Employee hoursworked = Incidence rate) 

    •  Experience Modifier Incident Rate (EMR): computation

    that compares a company's annual losses in insurance

    claims against its policy premiums over a three-year

    period, excluding the most current year

    •  Near Misses 

    TQM & SafetySafety (Component of Quality Management)

    Experience Modifier Incident Rate (EMR): The average experience modification rate is1.00 and simply means that a company has average workers’ compensation lossesfor their industry and will pay 100 percent of the manual premium that is set by theirstate. A higher than average experience modifier would be any number greater than1.00. A company with a 1.43 experience modifier will pay 143 percent of their manual

     premium. The 43 percent surcharge reflects the higher than average claims thecompany has experienced. The experience modifier can also be lower than 1.00. If acompany has an experience modifier of .73, they will pay only 73 percent of theirmanual premium. This effectively gives the company a 27 percent discount forhaving lower than average losses, claims, and injuries. The following chartcompares different experience modifiers with varying results.

    Manual Premium - $62,106

    Experience Modifier - .73Discount/Surcharge - $16,769 discountModified Premium - $45,337

    Experience Modifier - 1.00Discount/Surcharge - NeitherModified Premium - $62,106

    Experience Modifier - 1.43

    Discount/Surcharge - $26,706 SurchargeModified Premium - $88,812

    Building Commissioning

    Why is it so hard for the design

    and construction team to

    produce exactly the building an

    owner wants, so that once

    finished, all the owner needs to

    do is open the door and turn onthe lights?

  • 8/18/2019 08 CMGT 360 Lesson Plan 8 TQM - Bldg Commissioning - Safety

    8/12

    3/6/16

    8

    1994 study of 60 commercial buildings found: !

      More than 50% suffered temperature control problems

    !  40% had problems with HVAC equipment

    !  33% had sensors that were not operating properly

    !   And 15% were missing specified equipment

    !  20-30% of building suffer from indoor air quality problems

    (sick building syndrome)

    “This is a pervasive absence of quality in the finished

    product. Owners think they have already paid for and are

    getting quality are engaging in denial. In far too manyprojects, cutting out quality has been the business norm,

    not the exception.” (1998 Building Commissioning article by Paul C. Tseng)

    Building Commissioning

    What is building Commissioning?

    !  Principal goal of Commissioning

    is the assurance the building

    systems meet the design intent

    and the building owners andoccupants are comfortable

    !  Commissioning helps prevent

    problems that lead to

    uncomfortable conditions

    Building Commissioning

    !  We know three elements in theconstruction project triad (quality, cost

    and schedule) are so closely related that

    changes in one result in changes to the

    others

    !  But, do you need to pay more and take

    longer to produce a higher quality

    building?

    !  Commissioning can actually reduce

    costs and help meet aggressive

    deadlines

  • 8/18/2019 08 CMGT 360 Lesson Plan 8 TQM - Bldg Commissioning - Safety

    9/12

    3/6/16

    9

    Commissioning is a systematic approach

    Integrates & enhances the traditionally

    separate functions of:

    •  design review

    •  equipment operation and maintenancedocumentation and facility staff training tooperate equipment

    •  and building systems functional testing and performance verification

    Commissioning is a quality assurance process

    Spans from pre-design to construction and

    start-up and increases the likelihood that a new

    building will meet the owner’s expectations

    !  Commissioning enables a building to begin its lifecycle at optimal productivity and assists in maintainingthis high level of performance

    !  Commissioning brings back the missing ingredientnecessary for all great buildings! not fancy curbappeal, but an infusion of quality

    Building Commissioning is documentation

    Commissioning provides documentedconfirmation that building systems functionaccording to criteria set forth in the projectdocuments to satisfy the owner’s operationalneeds.

  • 8/18/2019 08 CMGT 360 Lesson Plan 8 TQM - Bldg Commissioning - Safety

    10/12

    3/6/16

    10

    Key Elements of Building Commissioning 

    !  Thorough documentation of system designintent and operating systems

    Verification of system performance based ondocumented functional testing andmeasurement (example: air balancing)

    !  Preparing and submitting O&M manuals(videos) and the training of buildingoperations staff on systems operations andmaintenance procedures

    !  Ongoing monitoring of system performance

    Project Closeout & Turnover 

    !  Project moves from physical building toadministrative

    •  Close-out

    •  Punch Lists

    •  Commissioning

    •  Turning project over to the owner

    !  Closeout begins when contractor turns overCertificate of Substantial Completion (alsocalled Certificate of Completion which isrecorded) 

    Project Closeout & Turnover 

    The start of Warranty periods are generallyestablished by the filing/issuance of theCertificate of Substantial Completion 

  • 8/18/2019 08 CMGT 360 Lesson Plan 8 TQM - Bldg Commissioning - Safety

    11/12

    3/6/16

    11

    Project Closeout & Turnover 

    Planning the closeout happens at the beginning and

    is part of the specifications

    • 

    Specifications for closeout include:•  What constitutes substantial completion

    •  Responsibilities of the owner, contractor anddesigner

    •  Schedule of owner-furnished equipment andfurniture

    •  Confirmation of warranty start and duration

    •  Review of turnover procedures

    Project Closeout & Turnover 

    Closeout includes turning over documents toowner

    •  Guarantees and warranties

    •  Certificates of Completion (requires final inspection)

    •  Operation and Maintenance Manuals (O&Ms)

    •  Keying schedule

    •  Maintenance materials, spare parts, special tools(extra paint, carpet, tiles)

    •  Certificates of code compliance

    •  Lien Waivers

    •  Consent of surety for final payment

    Project Closeout & Turnover 

    Closeout of construction and subcontracts:•  Preparing closeout schedule

    • 

    Demobilize subcontractor trailers, equipment and supplies

    •  Terminating temporary utilities

    •  Issuing contractors’ certificates of completion

    •  Conducting pre-punch list inspections

    • 

    Preparing punch list with architect or CM•  Final inspection

    • 

    Receiving Certificate of Substantial Completion and/or

    Certificate of Completion

    •  Requesting Final Payment

    • 

    Issuing lien waivers and consent of surety of payment

    •  Receiving final payment

  • 8/18/2019 08 CMGT 360 Lesson Plan 8 TQM - Bldg Commissioning - Safety

    12/12

    3/6/16

    12

    Project Closeout & Turnover 

    Closeout construction office:•

     

    Inventory office equipment, furniture & supplies

    •  Change field office address

    •  Terminate phones

    •  Terminate office rentals and leases

    •  Demobilize office and remove from site

    •  Reassign field office staff

    Final Closeout & Turnover 

    !  Closeout could be as long as a yearrequiring the contractor to operatebuilding systems during the warranty period (depends on specification)

    Final thought !.closeout is where acompany’s profit margin can be easilylost if attention to detail and compliancewith plans and specification are not practiced

    End Lesson Plan No. 8TQM – Safety - Building Commissioning

    Project Management  

    Instructor: David Shirah CMGT 360  California State University, Chico