05 - 1 nasa’s goddard space flight center systems engineering mike pryzby swales aerospace august...

11
05 - 1 NASA’s Goddard Space Flight Center Systems Engineering Mike Pryzby Swales Aerospace August 16-17, 2005

Upload: patrick-rice

Post on 30-Dec-2015

216 views

Category:

Documents


0 download

TRANSCRIPT

05 - 1NASA’s Goddard Space Flight Center

Systems Engineering

Mike Pryzby

Swales Aerospace

August 16-17, 2005

05 - 2NASA’s Goddard Space Flight Center

LRO Systems TeamMartin Houghton

Mission Systems Engineer

Michael PryzbyOrbiter Systems Engineer

Charles Wilderman

HW / SW Systems

Eric HolmesGN&C Systems

Giulio RosanovaMechanical

Systems

Phil LuersElectrical Systems

Rich SaylorGround Systems

Mike XapsosRadiation Engineer

Chris LorentsonContamination

Engineer

Nick VirmaniMfgr Engineer

Pilar JoyMaterials Engineer

Subsystem Leads

Lydia LeeSystems Reliability

Engineer

J. Simpson - ACS

C. Zakrzwski - Prop

Q. Nguyen - C&DH

J. Soloff - Comm.

M. Blau - Flight S/W

T. Spitzer - Power

C. Baker - Thermal R. Kinder - Harness

R. Saylor - Ground System

G. Casto - Structures

M. Hersh - Mechanisms

M. Beckman - Flight Dynamics

Ken DeilyMission Success

Systems Engineer

Mission Requirements Document (MRD)Systems ConceptRequirements Management

Concept of Operations

Reliability Analysis(FTA,FMEA, RBD, etc.)

Radiation Environment Assessment

Contamination Control Plan

Level 3 RequirementsSubsystem Spec & Verification PlansComponent SpecsICDs

Software ArchitectureS/W ResourcesSoftware ICDs

GN&C ArchitectureMechanismsDeployment Sys

Mechanical ICDs

Parts ReviewParts Use / Applicability

Database

Material ReviewMaterials Use /

Applicability Database

T. AjluniJ. Brannen

Arlin BartelsPayload Systems Manager

Joanne BakerI&T Engineer

I&T Plan Electrical Sys. SpecElectrical ICDs

R. Kinder

J. BakerL.HartzM. Reden

Tom JonesLaunch Vehicle Manager

LV ICD

05 - 3NASA’s Goddard Space Flight Center

LRO Systems Engineering Implementation Approach

• SE is integrated into project as defined in our SEMP in accordance with GPR 7120.5 and tailored to reflect the successful approach taken by the core LRO team on past missions

• Key SE documents include; SEMP, Golden Rules, MRD & Siblings including Electrical, Mechanical, Thermal, and Pointing specifications, Allocations and Con Ops documents

Requirements ID & Mgmt- Level 1 Reqs, Min Mission Reqs

-Mostly Driven by Science- Top Down Hierarchy

- Reqs Flow, Doc Tree, WBS, Product Structure, Team Org

-Database utilized to track reqs flow, owner, verification

Architecture & Design- What the End Item looks like

- Flight and Ground Elements, Hardware, Software Block Diagrams, Operations Team

-Special Accommodations for Verification & Test

- Design for testability

Operations Concept Development- How the End Item is used

-Flight and Ground Elements, Hardware, Software, Operations Team

- How the End Item can be verified & tested on the ground- Test Points, GSE impacts on Architecture and Design

The Three Major Functions Must Lead to a Balanced Design that isConsistent with Project Cost, Schedule and Risk

Project Objectives Met,Ready for Operations

• SE activities defined by phase in our SEMP, phase A&B presented today• Evidence of our SE process is the content of this SRR

- Gold used by subsystems as requirements at L2/L3. Compliance matrix in process, due at PDR

05 - 4NASA’s Goddard Space Flight Center

Phase A Plans and ActivitiesLRO SEMP (431-PLAN-000005) System Engineering Lifecycle Activities Matrix

All Completed Preliminary Analysis - Phase A

Understanding the Objectives

- Understand and define Level 1 science requirements; Identify full and minimum mission reqs- 1st draft of Level 1 reqs for review at MDR- Validate Level 1 requirement and show flowdown to Level 2 requirements at MD

Operations Concept Development

- Identify and define LRO Mission Phases- Complete preliminary draft version of LRO Operation Concept Document

Architecture & Design Development

- Review LRO ORDT Report & previous concept studies- Identify key LRO design drivers & perform trade studies of various implementation design concepts- Define architecture design concept and balance with reqs and ops concept

Requirements Identification & Management

- Define draft Level 2 MRD reqs & demonstrate flowdown & traceability to Level 1 reqs at MDR- Detailed walkthrough of MRD Level 2 reqs traceability and assignment at SRR- Initial entry of MRD Level 2 reqs into DOORS database for mgmt and tracking- Define initial LRO Doc Tree, detailing subsystem reqs documentation structure & responsibility

Validation & Verification

- Perform initial trade studies and fold into initial system architecture design concept- Demonstrate MRD Level 2 reqs traceability to Level 1 reqs and to implementation design concept at SRR

Interfaces & ICDs - Begin initial discussions across instrument and subsystem lines on interface design concepts as part of initial architecture design baseline effort- Identify proposed ICD documents within LRO Document Tree

Mission Environments

- Complete initial radiation environment assessment and document in draft radiation white paper- Distribute contamination questionnaire to Instr, establish contamination working group, and complete draft contamination assessment- Define initial flight operational & test environments in Systems Verif & Envi Def document

Technical Resource Budget Tracking

- Establish formulation resource allocations as part of architecture design concept investigations- Baseline resource allocations at end of Phase A within SCR allocation margins- Bring resource allocations under CM at beginning of Phase B

Risk Management - Establish Risk Management Plan & Procedures & identify, classify, & report initial risk items- Begin initial fault tree analysis and reliability block diagrams and use to optimize design concept

System Milestone Reviews

- Hold Mission Design Retreat (MDR) to review Level 1 reqs and initial design concept- Hold System Reqs retreat (SRR) for detailed walkthrough of Level 2 MRD reqs and demonstrate flowdown & traceability to Level 1 reqs- Hold SRR/SCR for external review team- acts as review milestone for progression Phase B

Configuration Management &

Documentation

- Define LRO document tree and define subject, when due, and who responsible for each document

System Engineering Management Plan

- Complete draft SEMP and plans for Phase A definition of “single system design” concept- Update SEMP for Phase B activity plans to “design the right system”

05 - 5NASA’s Goddard Space Flight Center

Phase B Plans and Activities

LRO SEMP (431-PLAN-000005) System Engineering Lifecycle Activities Matrix Black –done, ◘Green – In progress

System Definition - Phase B

Understanding the Objectives

- Level 1 Science Reqs competed & signed off by NASA HQ; Includes minimum mission reqs- Track any changes to Level 1 reqs (changes req NASA HQ approval)

- Refine LRO Mission Phases definitions and LRO Operation Concept DocumentOperations Concept

Development

Architecture & Design

Development ◘- CM block diagram of LRO architecture design concept - Begin preliminary system and subsystem design process- Begin conceptual breadboard design process; use breadboards as testbeds and for interface testing across ss for risk reduction

Requirements Identification & Management

- Define draft Level 2 MRD reqs & demonstrate flowdown & traceability to Level 1 reqs at MDR- Detailed walkthrough of MRD Level 2 reqs traceability and assignment at SRR- Initial entry of MRD Level 2 reqs into DOORS database for mgmt and tracking- Define initial LRO Doc Tree, detailing subsystem reqs documentation structure & responsibility

Validation &

Verification ◘- Update MRD Level 2 reqs with verification information and use process to check validity of reqs

Interfaces & ICDs - Baseline and release initial documents and ICDs on LRO Document Tree

Mission

Environments◘- Update contamination assessment and complete draft Contamination Control Plan- Begin evaluation and tracking of parts and materials for use in identified flight environment- Update flight operational & test environments in Systems Verif & Envi Def document

Technical Resource Budget Tracking

- Bring resource allocations under CM at beginning of Phase B within appropriate margins- Track and control resource allocations to complete Phase B within PDR margin allocations

Risk Management ◘ - Complete initial FMEA of preliminary design concept and fold results back into design- Update fault tree analysis and reliability block diagrams & use to further optimize design concept- Ongoing identification, classification, & reporting of risk items per Risk Mgmt Plan & Procedures

System Milestone

Reviews ◘- Hold subsystem peer reviews and PDRs to review Level 3 reqs and initial design concepts- Hold Mission PDR for external review team- acts as review milestone for progression Phase C

Configuration Management &

Documentation

- Initiate CCB process to address changes to configured documents- Bring Level 1 Reqs, MRD Level 2 Reqs, and Level 3 Subsystem spec under CM

System Engineering

Management Plan ◘- Update SEMP for Phase C Design activity plans to ensure system is “implemented right”

05 - 6NASA’s Goddard Space Flight Center

Requirement Capture and Control Process

L1 RequirementsControlled at NASA HQ

L2 RequirementsControlled at LRO Project

L3 Requirements forSpacecraft, Ground Elements

Controlled at LRO Project

L3 Requirementsfor Instruments

Controlled at PI Institution

L4, L5, L6 RequirementsDeveloper Controlled at LRO or PI Institution as Rqd

LRO Project LevelTracking Verification Database

In DOORS

Updated Documents in

CM*

*CM Plan is Document431-PLAN-0000xx

05 - 7NASA’s Goddard Space Flight Center

Review Process• Peer Reviews discipline driven, ingrained as an

institutional process at GSFC and our PI institutions• Project mandated peer reviews by SE and

management as deemed necessary– Examples include; FPGA’s, LROC Optical Design,

PDE Architecture

• Peer Review Process in accordance with GPR 8700.6A and LRO Peer Review Plan.

– SE attends and assigns actions as warranted– Project mandated/schedules as necessary, part of GSFC

process across all project elements– Team comprised of technical experts, internal and external as

required– Desire to keep review team through project lifecycle– Contested RFAs tracked in Project Action Item database

• PDR, CDR, PER, PSR etc content defined in our SE plan and controlled by LRO IIRT Review Plan (431-PLAN-000007)

TOPIC

Spacecraft & Ground System

Subsystem Peer Reviews

Phase

A/B

Phase

C/D

S/C Mechanical Sy stems 8/5/05 9/21/05

Thermal Sy stem 9/15/05

GN&C 8/5/05 9/15/05

Propulsion Module 5/5/05 3/22/06

Propulsion Tank 3/10/06

Pow er 8/5/05 9/13/05

C&DH 9/5/05 9/22/05

FLT S/W 11/5/05 11/4/05

Communication

Ground netw orks

Ground Data Sy stem/MOC

Div iner 8/25/05

LROC 8/1/05

LOLA

CRaTER

LAMP 6/17/05

LEND

PDE detail design options and

reliability assessment

38569

FPGA Implementations (all

subsy stems using FPGAs)

A/R A/R

SSR implementation options

preliminary design decision rev iew &

assessment. (C&DH, Flight Softw are)

38600 N/A

High Accuracy Tracking

implementation options and decision

rev iew . (Comm., GDS, LOLA)

38569 N/A

DATE/TIMEFRAME

Instrument Peer Reviews

Focused Technical Peer Reviews

???

05 - 8NASA’s Goddard Space Flight Center

Validation and Verification

• Validation process includes use of DOORS to insure no orphan requirements and proper traceability and flow down

• Verification is part our CM process and a mandatory section of each requirements document

• Verification matrix using DOORS database will include the following fields– Ownership to identify which individual is responsible for verifying this

requirement, as well as those others with a significant effort in the verification activities.

– Verification method; Inspection / Analysis / Demonstration / Test– Description of type of test, if needed– Verification Documentation to show where the requirement is verified– Verification Result Summary

• Mission Verification Plan will define overall process and plan for completion.

05 - 9NASA’s Goddard Space Flight Center

Risk Management Intertwines with Mission Success & Reliability to Minimize Risk

• Mission Success Engineering, Reliability Engineering, and Risk Management coordinating an integrated process

– Capture spacecraft concept/design using Advanced Functional Schematic (AFS)

– Identify Mission Success and Degraded Mission performance of spacecraft concept.

• Criticality & Degraded Mode Analyses• Critical Items List, FMEAs, RBDs,

FTAs, & PRA• Safety & Reliability Analyses

– Mission Success vs. Implementation Decisions

• Risks to Mission Success assessed• Trades Space (Requirements vs.

Implementation Considerations)• Recommend changes to level 2, 3 and 4

requirements that improve mission success

• Risk inputs provided to Systems Engineering & Project Management

Level 2 Req.

DegradedMission Criteria

SafetyReq.

Mission SuccessCriteria

Identify Mission Success & Degraded Mission

Performance

Risks TradesReq.Chg

Level 3Req.

AdvancedFunctionalSchematics(concept)

Risks TradesReq.Chg

……

AdvancedFunctionalSchematics(concept)

Identify Mission Success & Degraded Mission

Performance

05 - 10NASA’s Goddard Space Flight Center

LRO - PSE Reliability Prediction WorksheetOutput Module A

Designator Part Description & Type Part Number Manufacturer QualityBase Failure Notes

Critical Total Rate (FR)Critical CktBeing UsedCrit. Ckt Being

Ckt (N1)Used (N2) (Q) FRxN1xQ FRxN2xQ Used

C3, C5, C7, C10, C700, C1000, C4, C6, C8, C12, C13, C23, C34, C35, C43, C51, C53, C54, C55, C56, C14, C15, C16, C17, C18, C19, C20, C21, C22, C24, C25, C26, C27, C28, C29, C30, C31, C32, C33, C62, C63, C64, C65, C66, C67, C68, C69, C70, C71, C72, C73, C74

Cap, Ceramic, Chip, 0.010 uF, 25V, SR0805X7R103Presidio Components

56 60 1 6.3400E-13 3.5504E-11 3.8040E-11 ##### #####Obtained FR from the Manufacturer.

npC37, C38 Cap, Ceramic, Chip, 10 uF, 50V, 10% SR0405BX106K2S2Presidio Components

2 2 1 6.3400E-13 1.2680E-12 1.2680E-12 ##### 0.0001%Obtained FR from the Manufacturer.

C44, C45, C46, C47, C48, C49, C52, C50, C84

Cap, Ceramic, Chip, 0.10 uF, 50V, 10% SR0805X7R104Presidio Components

9 9 1 6.3400E-13 5.7060E-12 5.7060E-12 ##### #####Obtained FR from the Manufacturer.

C59 Cap., Fixed, Tantalum, Solid, ER, 22 uF, 20V, 10% CWR06J C226KCA 1 1 0.01 7.0000E-10 7.0000E-12 7.0000E-12 0.0010% 0.0007% Grade-1

C81Cap., Fixed, Tantalum, Solid, Low ESR, 100 uF, 16V, 10%

T495X107K016AS (562)

1 1 0.03 7.0000E-10 2.1000E-11 2.1000E-11 ##### #####Commercial. Goddard screening to FR Level: S

C82 Cap., Fixed, Cer. Dielectric, 1.0 UF, 50V, 10%M123A02BXB105KC

1 1 0.1 8.6000E-10 8.6000E-11 8.6000E-11 0.0117% ##### Grade-2, FR Level: C

C83Cap., Fixed, Tantalum, Solid, Low ESR, 220 uF, 6.3V, 10%

T495X227K006AS (562)

1 1 0.03 7.0000E-10 2.1000E-11 2.1000E-11 ##### #####Commercial. Goddard screening to FR Level: S

C200, C201, C202, C204, C205, C206, C208, C209, C210, C212, C213, C214, C220, C221, C222, C224, C225, C226, C228, C229, C230, C232, C233, C234, C236, C237, C238, C240, C241, C242, C244, C245, C246, C248, C249, C250, C252, C253, C254

Cap, Multi Layer, Fixed, Unencap, Ceramic Dielectric, 0.1 uF, 100V, 10%

CDR35BX104BKUS 27 39 0.03 1.8000E-09 1.4580E-09 2.1060E-09 0.1980% ##### Grade-1, FR Level: S

C203, C207, C211 Cap, Tantalum, Non-Solid, 6.8 uF, 75V, 10% M39006/30-0826 3 3 0.3 1.1000E-09 9.9000E-10 9.9000E-10 0.1344% 0.1035% Grade-2, FR Level: P

C215, C223, C227, C231, C235, C239, C243, C247, C251, C255

Cap, Tantalum, Non-Solid, 3.3 uF, 75V, 10% M39006/30-0823 6 10 0.3 1.1000E-09 1.9800E-09 ####### ##### 0.3451% Grade-2, FR Level: P

C216, C217, C218, C219

Cap, Tantalum, Non-Solid, 110 uF, 75V, 93026-46KS 4 4 0.1 1.1000E-09 4.4000E-10 4.4000E-10 0.0597% #####Commercial. Goddard screening to FR Level: R

Quantity Total Failure % of Assembly

Architecture Optimization from Single String to Selective Redundancy

• Mission Success requirements flow top down to individual subsystems/elements

• Advanced Functional Schematics (AFS) capture big picture; end to end view of spacecraft systems and architecture.

• Spacecraft operations, mission modes & phases, timing, event durations and criticality considered.

• Criticality of risk factors to mission success and residual risks considered

• Apportionment of requirements to improve mission success

– Hardware Requirements, Independence, Fault Tolerance, Reliability Apportionment

LRO Spacecraft

R = 0.90

Power GN&C C&DH Propulsion Communications Deployment Instrument

R = 0.98506 R = 0.98506 R = 0.98506 R = 0.98506 R = 0.98506 R = 0.98506 R = 0.98506

Including 1 Instrument

LRO SPACECRAFT RELIABILITY BLOCK DIAGRAMReliability Allocation

LRO Spacecraft

R = 0.90

Power GN&C C&DH Propulsion Communications Deployment Instrument

R = 0.99126 R = 0.99126 R = 0.99126 R = 0.99126 R = 0.99126 R = 0.99126 R = 0.99126

Reliability AllocationIncluding 6 Instruments

LRO SPACECRAFT RELIABILITY BLOCK DIAGRAM

LRO Spacecraft

R = 0.90

Power GN&C C&DH Propulsion Communications Deployment

R = 0.98529 R = 0.98529 R = 0.98529 R = 0.98529 R = 0.98529 R = 0.98529

LRO SPACECRAFT RELIABILITY BLOCK DIAGRAMReliability Allocation

System Reliability Goalor Aggregate Failure Rate

Missionor Ops

Criticality

Subsystemor ElementComplexity

Operational Profile.Function Criticality

Complexity

System Architecture Options:Single String, Redundancy

(Block or Functional), or SelectedRedundancy

Equal Apportionment

for Functions orSubsystem

Redundancy:Functional,

Block, orSel.

Single String

Apportionmentfor Functions or

Subsystem Redundancy

Apportionmentfor Functions or

Subsystem Criticality

Missionor Operational

Profile

Residual RiskTrades

Requirement Change

Apportionmentfor Functions or

Subsystem Complexity

Apportionmentfor Functions orOperation Time

& Duration

Design ToAggr.

FailureRate

Mission Success & Reliability Assessment

Mission & SystemRequirements &

Constraints

05 - 11NASA’s Goddard Space Flight Center

Driving System Trades

TOPIC TRADE OUTCOMELV 2 Stage vs 3 Stage 7925H-9.5 ELVProp Mono Prop vs Bi Prop vs Hybrid Mono Prop

Primary StructureMaterial, configuration and tank accomodation

Honeycomb with Al facesheets for bus, composite face sheets for instrument deck, Configuration J

Solar Array Configuration Structure, shape and materialsSingle circular Ultra Flex array

Data Bus Architecture 1553, SpaceWire, CAN, Wireless, etc.

1553 for low speed, Spacewire for high speed interfaces

Data Storage SRR or Hard Drive Ongoing, due at PDRTiming USO in bus or LOLA instrument USO part of bus C&DHTracking S Band vs Other Ongoing, due at PDRComm System Ka vs X-Band Ka