04802275

Upload: brockwell496

Post on 14-Apr-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/30/2019 04802275

    1/6

    IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 45, NO. 2, MARCH/APRIL 2009 569

    Arc Flash and Coordination Study Conflictin an Older Industrial Plant

    Peter E. Sutherland, Fellow, IEEE

    AbstractOnce arc flash hazard analysis became a requirementfor many industrial power system studies, the reduction of arcflash hazards has become an important concern. Inevitably, thefactors that lead to reductions in arc flash hazards do not alwayslead to an improvement in other areas, i.e., in particular, protectivedevice coordination. This paper will examine several particularcases where an arc flash hazard analysis of an older industrialplant yielded several cases of buses where the hazard level wasextreme danger above category 4. By changing protective devicesettings and, if necessary, the devices themselves, the hazard levelcan be reduced. Methods to maintain coordination, if possible, arediscussed.

    Index TermsArc flash hazard analysis, protective devicecoordination.

    I. INTRODUCTION

    AN ARC FLASH hazard analysis usually begins with a

    study of a facility based upon the procedures and method-

    ology of the National Fire Protection Association (NFPA) 70E

    [1] and IEEE 1584 [2]. However, an arc flash hazard analysis

    is usually performed in conjunction with a suite of other power

    system studies [3], such as the following:

    1) load flow;

    2) short circuit;3) protective device coordination.

    The results of an arc flash hazard analysis are labels to

    be placed on equipment, which give, among other things, the

    following:

    a) the flash protection boundary, the distance within which a

    person must wear personal protective equipment (PPE);

    b) the hazard/risk category, a number from 0 to 4 indicating

    which classification of PPE that the person must wear.

    The arc flash protection boundary must be reasonable, such

    that people who are not working on the equipment can still

    perform their functions. For example, it should not extend

    outside the fence of an outdoor substation or prohibit opening

    the door of an indoor substation. If the hazard/risk category

    is above level 4 (40 cal/cm2), no approach is possible with-

    out deenergization of the equipment. This is usually called

    Paper ICPSD-MT09-5, presented at the 2007 Industry Applications SocietyAnnual Meeting, New Orleans, LA, September 2327, and approved forpublication in the IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS bythe Power Systems Engineering Committee of the IEEE Industry ApplicationsSociety. Manuscript submitted for review October 31, 2007 and released forpublication September 2, 2008. Current version published March 18, 2009.

    The author is with GE Energy Services, Schenectady, NY 12306 USA(e-mail: [email protected]).

    Color versions of one or more of the figures in this paper are available onlineat http://ieeexplore.ieee.org.

    Digital Object Identifier 10.1109/TIA.2009.2013597

    danger or extreme danger on arc flash labels. It is de-

    sirable that the risk category be standardized so that all per-

    sonnel working on a single project, or piece of equipment,

    can wear the same gear. Table 130.7(C)(9)(a) in NFPA 70E

    gives recommended clothing for various tasks on different

    equipment if a study has not been performed. For example, in

    600-V class Switchgear, there are tasks at levels 03. Many

    plants, however, standardize on level-2 and level-4 PPE. A

    typical hazard/risk reduction task would be to reduce a cal-

    culated extreme danger to level 3, or a level 4 to a level 2.

    Thus, a reduction to a level 3 would mean that the personnelwould wear level-4 PPE.

    Arc flash hazard levels depend upon fault current magnitude

    and duration, I2t. The power going into the arc resistance

    is a function of I2R, where R is the arc resistance. This

    is multiplied by time, which is the arc duration. Since arcs,

    currents, and resistances are in constant variation, this is really a

    time-varying integral whose units are energy (calories). When

    this energy is radiated to a persons skin, they experience an

    incident energy (in calories per square centimeter), which is

    what causes the burn.

    The factors that can be controlled are in the timecurrent

    characteristics of the system protective devices, reducing I2t

    by reducing t for any given I. These factors include thefollowing.

    1) Pickup: The minimum current at which a device actuates.

    Lower pickup provides arc fault protection for a greater

    range of fault currents.

    2) Time delay: Shorter time delay reduces time to trip and

    lowers I2t.

    3) Instantaneous pickup: Operating time is typically the

    minimum possible for the circuit breaker being used.

    Lower instantaneous pickup settings reduce arc flash

    hazard.

    A more extensive list of six design changes and six overcur-rent upgrades is given in [4].

    Protective devices in a power system are coordinated in

    time and in current pickup in order to provide for an orderly

    shutdown in case of a fault and to prevent blackouts. Changes

    in protective device settings to solely reduce arc flash hazards

    will inevitably result in a loss of coordination, resulting in

    misoperation during faults and unnecessary blackouts.

    This is slightly different than the problem of the design of

    limited arc energy distribution systems [5], although many of

    the same principles can be used.

    It is the purpose of this paper to give some examples of these

    coordination problems and how they may be resolved.

    0093-9994/$25.00 2009 IEEE

  • 7/30/2019 04802275

    2/6

    570 IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 45, NO. 2, MARCH/APRIL 2009

    Fig. 1. Example 600-V substation.

    Fig. 2. Coordination curves for substation of Fig. 1 (before).

    II. EXAMPLES OF ARC FLASH VERSUS COORDINATION

    A. Correcting an Arc Flash Problem When a Coordination

    Problem Requires Trip-Unit Replacement

    In this older substation (Fig. 1), the low-voltage circuit break-

    ers use electromechanical dashpot-type trip units with wide

    characteristics (Fig. 2). The main breaker has an instantaneous-

    only characteristic (vertical bar on the timecurrent curve). The

    transformer protection is from an older inverse-time overcurrent

    relay, with nearly definite time characteristics. The relay and

    low-voltage circuit breakers do not coordinate in this situation,

    such that the only practical solution is an upgrade to modernelectronic equipment. The 600-V transformer secondary and

    Fig. 3. Coordination curves for substation of Fig. 1 (after). Relay IAC 11 timedial reduced from 1.5 to 0.5.

    TABLE IARC FLASH RESULTS AT BUS-4 VERSUS TIM E DIA L

    SETTING FOR RELAY 50/51-1 FO R FIG. 1

    bus both have high levels of incident energy, exceeding level 4.

    Arc flash hazard risks can be reduced to level 3 on the trans-

    former secondary and 600-V bus by reducing the time dial

    of the relay from 1.5 to 0.5, as shown in Fig. 3 and Table I.

    This does not change the coordination, or lack thereof, signif-

    icantly, because the actual tie breaker characteristics, defined

    by a dashpot-type trip unit, are probably not very close to the

    published curve. Dashpots of these old-type circuit breakers

    tend to suffer from drying out of oil and lack of the correctdashpot oil for maintenance. The main breaker is instanta-

    neous only.

    The main breaker is set at the same value as the instantaneous

    unit of the tie breaker. Therefore, no changes of primary relay

    setting or relay curve shape will alleviate the coordination

    problem.

    The only practical solution is to update the low-voltage

    circuit breakers with solid-state trip units. However, the arc

    flash problem needs to be corrected now, while the circuit

    breakers might not be updated or replaced for some time. The

    arc flash hazard can be reduced, while the coordination problem

    should be addressed separately. When this occurs, the fact that

    the relay setting has been lowered to reduce arc flash hazardshould not be forgotten.

  • 7/30/2019 04802275

    3/6

    SUTHERLAND: ARC FLASH AND COORDINATION STUDY CONFLICT IN AN OLDER INDUSTRIAL PLANT 571

    Fig. 4. Original configuration of 600-V substations on a 13.8-kV feeder withnormal inverse relays.

    TABLE IIARC FLASH RESULTS AT BUS-16 VERSUS TIM E DIA L

    SETTING FOR RELAY R1

    B. Correcting a Coordination Problem Without

    Introducing an Arc Flash Problem

    In the existing configuration of this feeder (Fig. 4), there

    is initially a severe arc flash problem, as shown in line 1 of

    Table II, as well as a coordination problem (Fig. 5). This relay

    does not protect the 500-kVA transformer because the pickup is

    too high. It also does not coordinate with the main breakers on

    the 1500-kVA substation.

    It was decided to upgrade the feeder with a relay having a

    very inverse timecurrent curve for better coordination char-

    acteristics (Fig. 6). If the relay is set to protect the 500-kVA

    transformer (Fig. 7 and line 2 of Table II), there is a coordina-

    tion problem, in that the relay no longer coordinates with the

    protection for the 1500-kVA transformer (Fig. 8).

    The other alternative of setting the relay for the 1500-kVA(Figs. 9 and 10 and line 3 of Table II) transformer leaves the

    Fig. 5. Original coordination of 600-V substations on a 13.8-kV feeder.

    Fig. 6. Two 600-V substations on a 13.8-kV feeder with very inverse relays(protection of 500-kVA transformer).

    500-kVA unit unprotected (Fig. 11) and raises the incident

    energy to unacceptable levels.

    One solution to this dilemma is the use of a transformerprimary fuse on the 500-kVA transformer, such that the incident

  • 7/30/2019 04802275

    4/6

    572 IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 45, NO. 2, MARCH/APRIL 2009

    Fig. 7. Protection of 500-kVA transformer.

    Fig. 8. Protection of 1500-kVA transformer with 500-kVA settings.

    energy is within acceptable limits on the 600-V bus. This will

    allow the primary relay R1 to be set to protect the 1500-kVAtransformer.

    Fig. 9. Two 600-V substations on a 13.8-kV feeder with very inverse relays(protection of 1500-kVA transformer).

    Fig. 10. Protection of 1500-kVA transformer with settings for arc flashreduction.

    It is important to select the proper fuse when remediating

    arc flash hazards. Two different fuses of the same rating andmanufacturer, even if both are current-limiting fuses, may have

  • 7/30/2019 04802275

    5/6

    SUTHERLAND: ARC FLASH AND COORDINATION STUDY CONFLICT IN AN OLDER INDUSTRIAL PLANT 573

    Fig. 11. Protection of 500-kVA transformer with 1500-kVA settings.

    Fig. 12. Two 600-V substations on a 13.8-kV feeder, with fast fuses onsmaller substation.

    TABLE IIIARC FLASH RESULTS AT BUS-16 VERSUS FUS E TYPE

    (R1 AT 6.0 AT, 0.5 TD)

    Fig. 13. Two 600-V substations on a 13.8-kV feeder, with slow fuses onsmaller substation.

    completely different arc flash limitation characteristics. This is

    shown in Fig. 12 and Table III, where, for this situation, the

    fuse in line 1 has an incident energy of 6.6 cal/cm2, while that

    in Fig. 13 and in Table III (line 2) has 44.9 cal/cm2

    , which is inthe extreme danger category.

    Looking at the timecurrent curves (Fig. 14), the fuse-1 curve

    sweeps down and to the left, providing short clearing times

    across the range of high available fault currents. However, the

    fuse-2 curve is steep, providing long clearing times at all but the

    highest fault currents. An example of changing a slow fuse for

    a fast fuse can also be found in [6]. However, the fast fuse may

    trip on transformer inrush, making that option unworkable.

    III. CONCLUSION

    Resolution of combined arc flash and coordination problems

    requires evaluation of multiple options. Solution of one prob-lem may cause the other problem to reappear in another place.

  • 7/30/2019 04802275

    6/6

    574 IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 45, NO. 2, MARCH/APRIL 2009

    Fig. 14. Comparison of fuse timecurrent curves.

    The presence of old equipment with unreliable characteristics

    complicates the assessment. Published timecurrent curves

    and breaker opening times should not always be relied upon.

    Proposed solutions may not always be implemented, and the

    engineer should be prepared for a long drawn-out process

    before all problems are resolved. Proposed solutions which

    reduce arc flash hazards may create other protection problems

    which render the solution unusable.

    REFERENCES

    [1] Standard for Electrical Safety in the Workplace, NFPA 70E, 2004.[2] IEEE Guide for Performing Arc-Flash Hazard Calculations,

    IEEE Std. 1584-2002.[3] IEEE Recommended Practice for Industrial and Commercial Power System

    Analysis, IEEE Std. 399-1997.[4] M. Hodder, W. Vilcheck, F. Croyle, and D. McCue, Practical arc-flash

    reduction, IEEE Ind. Appl. Mag., vol. 12, no. 3, pp. 2229, May/Jun. 2006.[5] J. C. Das, Design aspects of industrial distribution systems to limit arc

    flash hazard, IEEE Trans. Ind. Appl., vol. 41, no. 6, pp. 14671475,Nov./Dec. 2005.

    [6] R. Doan and R. Sweigart, A summary of arc-flash energy calculations,IEEE Trans. Ind. Appl., vol. 39, no. 4, pp. 12001204, Jul./Aug. 2003.

    Peter E. Sutherland (M77F07) received the B.S.degree in electrical engineering from the University

    of Maine, Orono, and the Ph.D. degree in elec-tric power engineering from Rensselaer PolytechnicInstitute, Troy, NY.

    In 1987, he joined General Electric (GE)Company, Schenectady, NY, and held a variety of po-sitions, becoming a Senior Engineer in the GE PowerSystems Energy Consulting Department. In 2001,he joined SuperPower, Inc., Schenectady, where heworked on applications of superconductivity to elec-

    tric power systems. He was then with EPRI PEAC Corporation (currentlyEPRI Solutions, Inc.), Schenectady, as a Consulting Engineer. He is currentlya Lead Consultant with GE Energy Services, Schenectady. He is the author ofnumerous technical papers.

    Dr. Sutherland is a Registered Professional Engineer in the States ofPennsylvania, Maine, and New York. He is active in the IEEE IndustryApplications Society and in the IEEE Schenectady Section.