04802275
TRANSCRIPT
-
7/30/2019 04802275
1/6
IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 45, NO. 2, MARCH/APRIL 2009 569
Arc Flash and Coordination Study Conflictin an Older Industrial Plant
Peter E. Sutherland, Fellow, IEEE
AbstractOnce arc flash hazard analysis became a requirementfor many industrial power system studies, the reduction of arcflash hazards has become an important concern. Inevitably, thefactors that lead to reductions in arc flash hazards do not alwayslead to an improvement in other areas, i.e., in particular, protectivedevice coordination. This paper will examine several particularcases where an arc flash hazard analysis of an older industrialplant yielded several cases of buses where the hazard level wasextreme danger above category 4. By changing protective devicesettings and, if necessary, the devices themselves, the hazard levelcan be reduced. Methods to maintain coordination, if possible, arediscussed.
Index TermsArc flash hazard analysis, protective devicecoordination.
I. INTRODUCTION
AN ARC FLASH hazard analysis usually begins with a
study of a facility based upon the procedures and method-
ology of the National Fire Protection Association (NFPA) 70E
[1] and IEEE 1584 [2]. However, an arc flash hazard analysis
is usually performed in conjunction with a suite of other power
system studies [3], such as the following:
1) load flow;
2) short circuit;3) protective device coordination.
The results of an arc flash hazard analysis are labels to
be placed on equipment, which give, among other things, the
following:
a) the flash protection boundary, the distance within which a
person must wear personal protective equipment (PPE);
b) the hazard/risk category, a number from 0 to 4 indicating
which classification of PPE that the person must wear.
The arc flash protection boundary must be reasonable, such
that people who are not working on the equipment can still
perform their functions. For example, it should not extend
outside the fence of an outdoor substation or prohibit opening
the door of an indoor substation. If the hazard/risk category
is above level 4 (40 cal/cm2), no approach is possible with-
out deenergization of the equipment. This is usually called
Paper ICPSD-MT09-5, presented at the 2007 Industry Applications SocietyAnnual Meeting, New Orleans, LA, September 2327, and approved forpublication in the IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS bythe Power Systems Engineering Committee of the IEEE Industry ApplicationsSociety. Manuscript submitted for review October 31, 2007 and released forpublication September 2, 2008. Current version published March 18, 2009.
The author is with GE Energy Services, Schenectady, NY 12306 USA(e-mail: [email protected]).
Color versions of one or more of the figures in this paper are available onlineat http://ieeexplore.ieee.org.
Digital Object Identifier 10.1109/TIA.2009.2013597
danger or extreme danger on arc flash labels. It is de-
sirable that the risk category be standardized so that all per-
sonnel working on a single project, or piece of equipment,
can wear the same gear. Table 130.7(C)(9)(a) in NFPA 70E
gives recommended clothing for various tasks on different
equipment if a study has not been performed. For example, in
600-V class Switchgear, there are tasks at levels 03. Many
plants, however, standardize on level-2 and level-4 PPE. A
typical hazard/risk reduction task would be to reduce a cal-
culated extreme danger to level 3, or a level 4 to a level 2.
Thus, a reduction to a level 3 would mean that the personnelwould wear level-4 PPE.
Arc flash hazard levels depend upon fault current magnitude
and duration, I2t. The power going into the arc resistance
is a function of I2R, where R is the arc resistance. This
is multiplied by time, which is the arc duration. Since arcs,
currents, and resistances are in constant variation, this is really a
time-varying integral whose units are energy (calories). When
this energy is radiated to a persons skin, they experience an
incident energy (in calories per square centimeter), which is
what causes the burn.
The factors that can be controlled are in the timecurrent
characteristics of the system protective devices, reducing I2t
by reducing t for any given I. These factors include thefollowing.
1) Pickup: The minimum current at which a device actuates.
Lower pickup provides arc fault protection for a greater
range of fault currents.
2) Time delay: Shorter time delay reduces time to trip and
lowers I2t.
3) Instantaneous pickup: Operating time is typically the
minimum possible for the circuit breaker being used.
Lower instantaneous pickup settings reduce arc flash
hazard.
A more extensive list of six design changes and six overcur-rent upgrades is given in [4].
Protective devices in a power system are coordinated in
time and in current pickup in order to provide for an orderly
shutdown in case of a fault and to prevent blackouts. Changes
in protective device settings to solely reduce arc flash hazards
will inevitably result in a loss of coordination, resulting in
misoperation during faults and unnecessary blackouts.
This is slightly different than the problem of the design of
limited arc energy distribution systems [5], although many of
the same principles can be used.
It is the purpose of this paper to give some examples of these
coordination problems and how they may be resolved.
0093-9994/$25.00 2009 IEEE
-
7/30/2019 04802275
2/6
570 IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 45, NO. 2, MARCH/APRIL 2009
Fig. 1. Example 600-V substation.
Fig. 2. Coordination curves for substation of Fig. 1 (before).
II. EXAMPLES OF ARC FLASH VERSUS COORDINATION
A. Correcting an Arc Flash Problem When a Coordination
Problem Requires Trip-Unit Replacement
In this older substation (Fig. 1), the low-voltage circuit break-
ers use electromechanical dashpot-type trip units with wide
characteristics (Fig. 2). The main breaker has an instantaneous-
only characteristic (vertical bar on the timecurrent curve). The
transformer protection is from an older inverse-time overcurrent
relay, with nearly definite time characteristics. The relay and
low-voltage circuit breakers do not coordinate in this situation,
such that the only practical solution is an upgrade to modernelectronic equipment. The 600-V transformer secondary and
Fig. 3. Coordination curves for substation of Fig. 1 (after). Relay IAC 11 timedial reduced from 1.5 to 0.5.
TABLE IARC FLASH RESULTS AT BUS-4 VERSUS TIM E DIA L
SETTING FOR RELAY 50/51-1 FO R FIG. 1
bus both have high levels of incident energy, exceeding level 4.
Arc flash hazard risks can be reduced to level 3 on the trans-
former secondary and 600-V bus by reducing the time dial
of the relay from 1.5 to 0.5, as shown in Fig. 3 and Table I.
This does not change the coordination, or lack thereof, signif-
icantly, because the actual tie breaker characteristics, defined
by a dashpot-type trip unit, are probably not very close to the
published curve. Dashpots of these old-type circuit breakers
tend to suffer from drying out of oil and lack of the correctdashpot oil for maintenance. The main breaker is instanta-
neous only.
The main breaker is set at the same value as the instantaneous
unit of the tie breaker. Therefore, no changes of primary relay
setting or relay curve shape will alleviate the coordination
problem.
The only practical solution is to update the low-voltage
circuit breakers with solid-state trip units. However, the arc
flash problem needs to be corrected now, while the circuit
breakers might not be updated or replaced for some time. The
arc flash hazard can be reduced, while the coordination problem
should be addressed separately. When this occurs, the fact that
the relay setting has been lowered to reduce arc flash hazardshould not be forgotten.
-
7/30/2019 04802275
3/6
SUTHERLAND: ARC FLASH AND COORDINATION STUDY CONFLICT IN AN OLDER INDUSTRIAL PLANT 571
Fig. 4. Original configuration of 600-V substations on a 13.8-kV feeder withnormal inverse relays.
TABLE IIARC FLASH RESULTS AT BUS-16 VERSUS TIM E DIA L
SETTING FOR RELAY R1
B. Correcting a Coordination Problem Without
Introducing an Arc Flash Problem
In the existing configuration of this feeder (Fig. 4), there
is initially a severe arc flash problem, as shown in line 1 of
Table II, as well as a coordination problem (Fig. 5). This relay
does not protect the 500-kVA transformer because the pickup is
too high. It also does not coordinate with the main breakers on
the 1500-kVA substation.
It was decided to upgrade the feeder with a relay having a
very inverse timecurrent curve for better coordination char-
acteristics (Fig. 6). If the relay is set to protect the 500-kVA
transformer (Fig. 7 and line 2 of Table II), there is a coordina-
tion problem, in that the relay no longer coordinates with the
protection for the 1500-kVA transformer (Fig. 8).
The other alternative of setting the relay for the 1500-kVA(Figs. 9 and 10 and line 3 of Table II) transformer leaves the
Fig. 5. Original coordination of 600-V substations on a 13.8-kV feeder.
Fig. 6. Two 600-V substations on a 13.8-kV feeder with very inverse relays(protection of 500-kVA transformer).
500-kVA unit unprotected (Fig. 11) and raises the incident
energy to unacceptable levels.
One solution to this dilemma is the use of a transformerprimary fuse on the 500-kVA transformer, such that the incident
-
7/30/2019 04802275
4/6
572 IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 45, NO. 2, MARCH/APRIL 2009
Fig. 7. Protection of 500-kVA transformer.
Fig. 8. Protection of 1500-kVA transformer with 500-kVA settings.
energy is within acceptable limits on the 600-V bus. This will
allow the primary relay R1 to be set to protect the 1500-kVAtransformer.
Fig. 9. Two 600-V substations on a 13.8-kV feeder with very inverse relays(protection of 1500-kVA transformer).
Fig. 10. Protection of 1500-kVA transformer with settings for arc flashreduction.
It is important to select the proper fuse when remediating
arc flash hazards. Two different fuses of the same rating andmanufacturer, even if both are current-limiting fuses, may have
-
7/30/2019 04802275
5/6
SUTHERLAND: ARC FLASH AND COORDINATION STUDY CONFLICT IN AN OLDER INDUSTRIAL PLANT 573
Fig. 11. Protection of 500-kVA transformer with 1500-kVA settings.
Fig. 12. Two 600-V substations on a 13.8-kV feeder, with fast fuses onsmaller substation.
TABLE IIIARC FLASH RESULTS AT BUS-16 VERSUS FUS E TYPE
(R1 AT 6.0 AT, 0.5 TD)
Fig. 13. Two 600-V substations on a 13.8-kV feeder, with slow fuses onsmaller substation.
completely different arc flash limitation characteristics. This is
shown in Fig. 12 and Table III, where, for this situation, the
fuse in line 1 has an incident energy of 6.6 cal/cm2, while that
in Fig. 13 and in Table III (line 2) has 44.9 cal/cm2
, which is inthe extreme danger category.
Looking at the timecurrent curves (Fig. 14), the fuse-1 curve
sweeps down and to the left, providing short clearing times
across the range of high available fault currents. However, the
fuse-2 curve is steep, providing long clearing times at all but the
highest fault currents. An example of changing a slow fuse for
a fast fuse can also be found in [6]. However, the fast fuse may
trip on transformer inrush, making that option unworkable.
III. CONCLUSION
Resolution of combined arc flash and coordination problems
requires evaluation of multiple options. Solution of one prob-lem may cause the other problem to reappear in another place.
-
7/30/2019 04802275
6/6
574 IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 45, NO. 2, MARCH/APRIL 2009
Fig. 14. Comparison of fuse timecurrent curves.
The presence of old equipment with unreliable characteristics
complicates the assessment. Published timecurrent curves
and breaker opening times should not always be relied upon.
Proposed solutions may not always be implemented, and the
engineer should be prepared for a long drawn-out process
before all problems are resolved. Proposed solutions which
reduce arc flash hazards may create other protection problems
which render the solution unusable.
REFERENCES
[1] Standard for Electrical Safety in the Workplace, NFPA 70E, 2004.[2] IEEE Guide for Performing Arc-Flash Hazard Calculations,
IEEE Std. 1584-2002.[3] IEEE Recommended Practice for Industrial and Commercial Power System
Analysis, IEEE Std. 399-1997.[4] M. Hodder, W. Vilcheck, F. Croyle, and D. McCue, Practical arc-flash
reduction, IEEE Ind. Appl. Mag., vol. 12, no. 3, pp. 2229, May/Jun. 2006.[5] J. C. Das, Design aspects of industrial distribution systems to limit arc
flash hazard, IEEE Trans. Ind. Appl., vol. 41, no. 6, pp. 14671475,Nov./Dec. 2005.
[6] R. Doan and R. Sweigart, A summary of arc-flash energy calculations,IEEE Trans. Ind. Appl., vol. 39, no. 4, pp. 12001204, Jul./Aug. 2003.
Peter E. Sutherland (M77F07) received the B.S.degree in electrical engineering from the University
of Maine, Orono, and the Ph.D. degree in elec-tric power engineering from Rensselaer PolytechnicInstitute, Troy, NY.
In 1987, he joined General Electric (GE)Company, Schenectady, NY, and held a variety of po-sitions, becoming a Senior Engineer in the GE PowerSystems Energy Consulting Department. In 2001,he joined SuperPower, Inc., Schenectady, where heworked on applications of superconductivity to elec-
tric power systems. He was then with EPRI PEAC Corporation (currentlyEPRI Solutions, Inc.), Schenectady, as a Consulting Engineer. He is currentlya Lead Consultant with GE Energy Services, Schenectady. He is the author ofnumerous technical papers.
Dr. Sutherland is a Registered Professional Engineer in the States ofPennsylvania, Maine, and New York. He is active in the IEEE IndustryApplications Society and in the IEEE Schenectady Section.