  • Pearl GTL Project

    LINDE ENGINEERING

    Shell Project No: HP-3000-QAT Contractor Project No: 5887

    Project Document Number: T- 4.234.557 Project Rev.: O Page 2 of 17

    Purchase Order Number:

    2MH127

    Tag/Item Number(s): N/A

    Unit(s): ASU

    PCWBS: Z

  • QATAR SHELL GTL PROJECT (PEARL) C2 AIR SEPARATION UNITS CONSTRUCTION

    D O 11.02.09 Company Comments Incorporated SK EO AG CCI

    C O 27.01.09 Issued for Company Comments SK EO AG IFR

    B 27.01.09 Issued for Review SK EO AG IFR

    A 12.01.09 Issued for Internal Review SK EO AG IIR

    GAMA Rev.

    Project Rev Date Description

    Prepared By

    Checked By

    Approved By

    Status

    No. No. ORIGINATOR

    LINDEGINEERING AG

    Document Title:

    INSPECTION TEST PLAN FOR INSTALLATION OF MAC/BAC/ST MACHINERY UNIT

    Contractor

    Gama Qatar Co. W. L. L.

    Document No. LOC470

    GAM ITP QAC GTL 046 D

    Org. Code

    Doc. Type

    Disc. Code

    Geogr. Area

    Seq. No

    Rev. No Vendor Code

    Project Document Number: T-4.234.557

    Rev No: O

  • QSGTL PEARL PROJECT C2 ASU Construction Works

    ITP NO: GAM-ITP-QAC-GTL-046

    ITP FOR INSTALLATION OF MAC/BAC/ST MACHINERY UNIT

    DATE: 11.02.09-REV. D

    S. GAMA QATAR X. CONTRACTOR QC C. COMPANY A. VENDOR (MAN)

    I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS (Notification Required but Presence not Mandatory)

    Item Activity Test Frequency Reference Document Acceptance Criteria Responsible

    Party Verifying Documents S A X C

    T-4.234-557 REV-O Page 4 of 17

    1.0

    DOCUMENTATION

    1.1 Contractor drawings, project specifications, manuals, codes 100% - -

    TECHINICAL OFFICE - H R R

    1.2 Lifting studies (For Heavy Equipments) 100%

    T.4.234.084,T.4.129.859 - HSSE - H R R

    2.0 EQUIPMENTS

    2.1

    Receiving inspection (Including nameplate verification) & Open Box Inspection during unpacking

    100% T-4.250.945;T.4.250.927 Packing list

    DEP 31.29.00.10 DEP 31.10.03.10

    STORE

    INCHARGE

    GAM-QCR-QAC-GTL-080

    I S I S

    2.2 Storage, preservation and documentation(FSI) 100% T.13.377.360E;T.4.250.932

    Approved drawing, DEP 31.29.00.10;DEP

    70.10.70.11 T.13.377.454E; Vendor instruction,

    FSI GAM-QCR-QAC-GTL-069

    I R S S

    2.3 Inspection measuring and test equipment calibration 100% T.4.250.915 - QCI Calibration certificates H R R R

    3.0 INSTALLATION

    3.1 Foundation complete and accepted 100% T-4.095.567, T-4.250.945

    MC documents, DEP 34.19.20.31;

    T.13.376.358 DEP 31.29.00.10,

    QCI Ref. ITP 023; MC certificates H R R R

  • QSGTL PEARL PROJECT C2 ASU Construction Works

    ITP NO: GAM-ITP-QAC-GTL-046

    ITP FOR INSTALLATION OF MAC/BAC/ST MACHINERY UNIT

    DATE: 11.02.09-REV. D

    S. GAMA QATAR X. CONTRACTOR QC C. COMPANY A. VENDOR (MAN)

    I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS (Notification Required but Presence not Mandatory)

    Item Activity Test Frequency Reference Document Acceptance Criteria Responsible

    Party Verifying Documents S A X C

    T-4.234-557 REV-O Page 5 of 17

    3.2 Sole plates and spindles/wedges or shims Installation

    100% T-4.095.805, T-4.250.945 Approved drawings,

    T-4.260.824 DEP 31.29.00.10,

    QCI GAM-QCR-QAC-GTL-169

    Surveyor report I I S S

    3.3 Erection of pre alignment of coolers/wash water unit/steel structure of skid/ oil system

    100% T-4.095.567, T-4.250.945, Approved drawings,

    T-4.260.824 DEP 31.29.00.10,

    QCI GAM-QCR-QAC-GTL-169 Surveyor report I I S S

    3.4 Installation/levelling of steel struts for base frame 100%

    T-4.095.567, T-4.250.945, T-4.233.680

    Approved drawings, T-4.260.824

    DEP 31.29.00.10, QCI GAM-QCR-QAC-GTL-038 H I S S

    3.5 Installation & alignment of skid on steel structure 100%

    T-4.095.567, T-4.250.945, T-4.233.680

    Approved drawings, T-4.260.824

    DEP 31.29.00.10, QCI

    GAM-QCR-QAC-GTL-169

    H I I I

    3.6 Check alignment of gear box (soft foot, coupling, slope etc.) 100%

    T-4.095.567, T-4.250.945, T-4.233.680

    Approved drawings, T-4.260.824

    DEP 31.29.00.10, QCI

    GAM-QCR-QAC-GTL-170

    H I I S

    3.7 Steam Turbine alignment / coupling check 100%

    T-4.095.567, T-4.250.945, T-4.233.680

    Approved drawings, T-4.260.824

    DEP 31.29.00.10, QCI Linde/MAN Report H I I S

    3.8 MAC Alignment to steam turbine 100%

    T-4.095.805, T-4.250.945, T-4.233.680

    Approved drawings, T-4.260.824

    DEP 31.29.00.10, QCI Linde/MAN Report H I I S

    3.9 BAC Alignment to gear box 100% T-4.095.805, T-4.250.945, T-4.233.680

    Approved drawings, T-4.260.824

    DEP 31.29.00.10, QCI Linde/MAN Report H I I S

  • QSGTL PEARL PROJECT C2 ASU Construction Works

    ITP NO: GAM-ITP-QAC-GTL-046

    ITP FOR INSTALLATION OF MAC/BAC/ST MACHINERY UNIT

    DATE: 11.02.09-REV. D

    S. GAMA QATAR X. CONTRACTOR QC C. COMPANY A. VENDOR (MAN)

    I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS (Notification Required but Presence not Mandatory)

    Item Activity Test Frequency Reference Document Acceptance Criteria Responsible

    Party Verifying Documents S A X C

    T-4.234-557 REV-O Page 6 of 17

    3.10

    Pre alignment of coolers MAC/BAC to machine skid and ACC Condensate Piping to steam turbine

    100% T-4.095.805, T-4.250.945, T-4.233.680

    Approved drawings, T-4.260.824

    DEP 31.29.00.10, QCI Linde/MAN Report H I I S

    3.11 Oil Unit Alignment on foundation 100%

    T-4.095.451, T-4.209.390, T-4.250.945

    Approved drawings, T-4.285.227

    DEP 31.29.00.10, QCI

    GAM-QCR-QAC-GTL-115

    H I I S

    3.12 Alignment of Motor Pump for oil unit 100%

    T-4.250.927, T-4.209.390, T-4.248.567

    Approved drawings, T-4.285.227

    DEP 31.29.00.10, QCI Linde/MAN Report H I I S

    3.13 Grouting Release for all unit contents 100%

    T-4.095.567, T-4.250.945, T-4.233.680

    Approved drawings, T-4.260.824

    DEP 31.29.00.10, QCI Ref. ITP 024

    3.14 Recheck Alignment after grouting 100%

    T-4.095.805, T-4.250.945, T-4.233.680

    Approved drawings, T-4.260.824

    DEP 31.29.00.10, QCI

    GAM-QCR-QAC-GTL-115

    H I I S

    3.15 All piping installation, alignment, & connection without any objectionable load

    Ref. ITP 033 (T-4.250.918 Rev. A)

    3.16 Verification of piping pressure test acceptance Prior to final alignment

    Ref. ITP 033 (T-4.250.918 Rev. A)

    3.17 Erection Damage(Equipments) 100% T.4.251.035 - QCI GAM-QCR-QAC-GTL-127 I I I R

  • QSGTL PEARL PROJECT C2 ASU Construction Works

    ITP NO: GAM-ITP-QAC-GTL-046

    ITP FOR INSTALLATION OF MAC/BAC/ST MACHINERY UNIT

    DATE: 11.02.09-REV. D

    S. GAMA QATAR X. CONTRACTOR QC C. COMPANY A. VENDOR (MAN)

    I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS (Notification Required but Presence not Mandatory)

    Item Activity Test Frequency Reference Document Acceptance Criteria Responsible

    Party Verifying Documents S A X C

    T-4.234-557 REV-O Page 7 of 17

    4.0 FINAL INSPECTION

    4.1 Final alignment checks 100% T-4.095.805, T-4.250.945, T-4.233.680

    Approved drawings, T-4.260.824

    DEP 31.29.00.10, QCI

    GAM-QCR-QAC-GTL-117

    I I S S

    4.2 FSI Checks (cleaning, preservation) 100%

    T-4.095.805, T-4.250.945, T-4.233.680

    Approved drawings, T-4.260.824

    DEP 31.29.00.10 FSI GAM-QCR-QAC-GTL-069 I I S S

    4.3 MC Inspections 100% T-4.095.805, T-4.250.945, T-4.233.680

    Approved drawings, T-4.260.824

    DEP 31.29.00.10 QCI Linde MC Records I S I S

    4.4 Installation Completion , sign-off quality records and hand over to Linde MC Dept

    100% T-4.250.945 T.13.377.555G QCI All Reports H R R R

  • GAM-QCR-QAC-GTL-038 Rev. O

    C2 ASU PEARL GTL PROJECT

    RASLAFFAN INDUSTRIAL CITY

    STEEL STRUCTURES ELEVATION REPORT

    ( BASED ON SURVEY REPORT)

    Subcontract Ref.: Report No.:

    Item Description: Inspection Date:

    Item Location / Area: Test Code No.:

    Subsystem: ITP No.:

    Ref. DWG / Documents:

    Used Measuring and test equipment ref. (if applicable):

    INSPECTIONS

    Column No Planned Level Actual Level Level/Difference Plumb

    0 Degree 90 Degree

    ORGANIZATIONS DATE NAME SIGNATURE

    Acce

    pted

    By THIRD PARTY REP.

    GAMA REP.

    LINDE REP.

    QSGTL OR its PMC REP.

  • PROJECT: C2 ASU PEARL GTL PROJECT, RAS LAFFAN INDUSTRIAL CITY

    EQUIP. TAG.NO.: DESCRIPTION: LOCATION:

    MANUFACTURER: DRG.NO.: RFI NO:

    MONTH

    1 2

    3 4 5 6

    7

    8

    9

    10

    11

    12

    ACTIVITY Month

    Date Checked

    Check all internal and accessories storage is acceptable

    Visual Check : Is there any damage

    Check for protective covers on all the openings

    Check all warning labels,like N2 warning plate are existent

    Actual Pressure level

    Required Pressure Level

    GAMA SIGN WITH DATE

    LINDE SIGN WITH DATE

    QSGTL or its PMC

    NOTE:

    GAM-QCR-QAC-GTL-069 Rev. O

    STORAGE, PRESERVATION AND NITROGEN PURGING REPORT

    FORM NO:

    SHT:

  • C2 ASU PEARL GTL PROJECT

    RAS LAFFAN INDUSTRIAL CITY

    GAM-QCR-QAC-GTL-080 Rev. O

    EQUIPMENT RECEIPT CHECK SHEET

    ITEM No: PO No: REQ No:

    UNIT No: MANUFACTURER :

    ITEMS TO BE CHECKED INSPECTOR

    INITIAL REMARKS

    1 Name Plate

    2 Preparation and painting

    3 Desiccant installed

    4 Moisture present

    5 Nozzle flange faces acceptable

    6 Temporary nozzle protection acceptable

    7 Internals and accessories complete and storage acceptable

    8 Purge - pressure:

    Purge monitoring date: Pressure

    Date of initial inspection:

    Name and signature of Inspector:

  • GAM-QCR-QAC-GTL-115 Rev. O PAGE 1 OF 2

    EQUIPMENT LEVELLING & ALIGNMENT REPORT

    Report No:

    Date:

    PROJECT: C2 ASU PEARL GTL PROJECT-RAS LAFFAN INDUSTRIAL CITY

    Tag No: Manufacturer: Drg. No:

    Equip. Description

    No. of reading Orientation Elevation Plumpness Tolerance Remarks

    ORIENTATION : ACCEPTED REJECTED

    LEVELLING REQUIRED ACTUAL ACC REJECTED

    GRADIENT / SLOPE REQUIRED

    ACTUAL ACC REJECTED

  • GAM-QCR-QAC-GTL-115 Rev. O PAGE 2 OF 2

    REMARKS: ..

    GAMA LINDE QSGTL or its PMC

    Name

    Sign

    Date

  • C2 ASU PEARL GTL PROJECT RAS LAFFAN INDUSTRIAL CITY

    TURBINE INSTALLATION PROCESS SHEET

    Item No: Report No: Item Description: Date: Drawing No: Area:

    Item No

    Description

    Signature & Date Gama Linde QSGTL

    1. Foundation complete, Level & Accepted. 2. Sole plates level 3. Align base 4. Align casing 5. Align rotor 6. Anchor bolts tight 7. Piping complete & connected with no objectionable loads or

    strains on the flanges

    8. Verify pressure test accepted 9. Coupling face gap checked & acceptable 10. Final alignment checked 11. Coupling set screws tight 12. Accessories Installed & Ready for service

    (i.e,Vents,Drains,strainers,etc)

    13. Auxiliary System Complete(i.e. lube system, Water cooling etc) 14. Lubrication system flushed & recharged with appropriate lubricant 15. Turbine rolls freely, By hand 16. Governor Mechanism: Linkages checked Manual Trip Level Free 17. Relief valves checked & installed 18. Expansion bellows for condensing turbines installed properly Remarks:

    The Installation of the above compressor has been satisfactorily completed in accordance with the Drawings & Specifications ORGANIZATIONS DATE NAME SIGNATURE GAMA QATAR REP

    LINDE REP

    QSGTL REP

    GAM-QCR-QAC-GTL-117 Rev. O

    QQQ AAA TTT AAA RRR

  • PROJECT: C2 ASU PEARL GTL PROJECT RAS LAFFAN INDUSTRIAL CITY

    Originator Date of observation:

    Discipline:

    Location / Area:

    Unit No :

    SYSTEM NUMBER:

    Drawing / Specification Numbers Description of Discrepancy/Observation (Be specific, events, time, date, location, etc :)

    Corrective Action:

    Originator: Name: _____________________________Signature: _____________________Date: ________________ NCR Required YES NO (Circle one) CTQ to Contractor Required YES NO (Circle one) Remarks if any: Site Engineer: Name: _______________________ Signature: ________________ Date: ______________ QA/QC Manager: Name: _________________________ Signature: _______________ Date: ______________ Discrepancy Corrected/Remarks: GAMA Representative: Name: ____________________ Signature: ______________ Date: ________________ Close-out of Corrective Action - Remarks: NCR No.: ___________________ CTQ No: ______________ Site Engineer: Name: ___________________ Signature: __________________ Date: ___________ DISTRIBUTION (Original QA/QC file)

    QA/QC Manager Site Manager

    Site Engineer Project Manager

    Construction Manager Originator GAM-QCR-QAC-GTL-127 Rev. O

    SITE INSPECTION REPORT

    REPORT NO.:

    DATE:

  • C2 ASU PEARL GTL PROJECT RAS LAFFAN INDUSTRIAL CITY

    MAC/BAC/ST MACHINERY UNIT INSTALLATION PROCESS SHEET

    Item/Tag No: Report No: Item Description: Date: Drawing No: Area: System No: Subsystem No:

    Item No

    Description

    Signature & Date Gama Linde QSGTL

    1. Foundation complete, Level & Accepted. 2. Sole plates and spindles/wedges or shims installation accepted 3. Erection of pre alignment of coolers/wash water unit/steel

    structure of skid/oil system

    4. Skid alignment accepted 5. Alignment of all equipment accepted 6. Piping complete & connected with no objectionable loads or

    strains on the flanges

    7. Verify pressure test accepted 8. Coupling Installation (face gap checked & acceptable) 9. Final alignment checked 10. Accessories Installed & Ready for service (i.e. Vents, Drains,

    strainers, etc)

    11. Auxiliary System Complete(i.e. lube oil system, Water cooling etc) 12. Turbine rolls freely, By hand 13. Governor Mechanism 13.1 Linkages checked 13.2 Manual Trip Level Free 14. Expansion bellows for condensing turbines installed properly Remarks:

    The Installation of the above Machinery Unit has been satisfactorily completed in accordance with the Drawings & Specifications ORGANIZATIONS DATE NAME SIGNATURE GAMA QATAR REP

    LINDE REP

    QSGTL REP

    GAM-QCR-QAC-GTL-169 Rev. O

    QQQ AAA TTT AAA RRR

  • GAM-QCR-QAC-GTL-170 Rev. O PAGE 1 OF 2

    GEAR BOX LEVELLING & ALIGNMENT REPORT

    Report No: Date:

    System No:

    PROJECT: C2 ASU PEARL GTL PROJECT-RAS LAFFAN INDUSTRIAL CITY

    Tag No: Manufacturer: Drg. No:

    Equip. Description:

    No. of reading Orientation Elevation Plumpness Tolerance Remarks

    ORIENTATION : ACCEPTED REJECTED

    LEVELLING REQUIRED ACTUAL ACC REJECTED

    GRADIENT / SLOPE REQUIRED

    ACTUAL ACC REJECTED

    SOFT FOOT : ACCEPTED REJECTED

  • GAM-QCR-QAC-GTL-170 Rev. O PAGE 2 OF 2

    REMARKS: ..

    GAMA LINDE QSGTL or its PMC

    Name

    Sign

    Date