043 integrating risk management
TRANSCRIPT
INTEGRATINGINTEGRATINGRISK MANAGEMENTRISK MANAGEMENTWITH COST WITH COST CONTROL& CONTROL& COMMUNICATIONCOMMUNICATION
[email protected]://www.construction-productivity.co.uk
RISK MANAGEMENT Risks have a significant impact on a
construction project’s performance in terms of:
cost Time quality Size and complexity of the projects
have increased over the past 30 years. The ability to manage risks throughout
the construction process has become a major factor for preventing risk.
RISK MANAGEMENTSupply chain must share the risk.Risk to a large extent is governed
by the procurement option and the content of the related contract documents.
Selecting an appropriate project procurement option is a key issue for risk reduction.
RISK MANAGEMENTA systematic process of: identifying assessing and responding to
project risk The aims and objectives of the
risk management process is to maximize the opportunities and minimize the consequences of a risk event.
A variety of risk management models with different numbers of stages can be obtained.
RISK MANAGEMENT The international standard “Project risk
management – Application guidelines” (IEC 2001) is a good source for risk management.
IEC suggest a model with 5 steps: 1.risk identification 2.risk assessment 3.risk treatment 4.risk review5.monitoring
RISK MANAGEMENT PMBOK’s model (PMI 2000) is
similar but divides risk assessment into two processes. They are:
1. qualitative risk analysis2. quantitative risk analysis Baloi and Price (2003) include an
additional step of risk management process it is:
communication.
RISK MANAGEMENT
Risk Transfer & Indemnification
Two most problematic areas for construction management teams are:
1.contractual risks2.the insurability of projects.
RISK MANAGEMENT Risk management can reduce risk in
the different procurement options. Design and build contracts and
collaborative form of partnering. Better understanding is expected to
contribute to a more effective risk management.
Therefore, a better project output and better value for both clients and contractors.
RISK MANAGEMENT
A clear link between the procurement option and risk management
Design-build projects offer better cooperative work by the architects and contractors in early phases
Therefore, more thorough risk management.
RISK MANAGEMENT
effective communication; information exchange;open attitudes and good relationship;
all have open discussion of project risk and a strong determinant for project success.
RISK MANAGEMENTRISK ASSESSMENT-SUPPLY CHAIN1. identify risks2. evaluated risks3. ranked risks4. use both qualitative and quantitative
methods for assessment5. based on fuzzy estimates of risk
components or a better option 6. Identify risk to cover all KPI’s (TIME-
COST-QUALITY-CUSTOMER SATIFACTION-SAFTEY)
RISK MANAGEMENT
RISK MANAGEMENT
PredictiveMetrics
DiagnosticMetrics
RetrospectiveMetrics
RISKIDENTIFYASSESS
TREATMENTREVIEW
MONITOREtc.
RISK MANAGEMENT
Y
ResourcesLabour
MaterialsMachinery
Etc
N
Microin UK-Public
orPrivate
Civil EngineeringBuildingHousingschools
hospitalsother
Level of Risk with:
Projects in EUProjects in UAE
Projects elsewhere
Is itMacro
Identifyrisk
DemandFluctuationFinance
Weather
Use ofnew construction
methods
Designcomplexity
RISK MANAGEMENT
RiskMetrics
Predictivemetrics
Retrospectivemetrics
y Diagnosticmetrics
yes
yes
Forward-looking,based on
expectations.Y
Drawn fromcurrent project
status-throughoutthe work
Y
Backward-lookingderived from
resultsY
RISK METRICS:RELATES TO DISCOVERY ANDMINIMIZATION OF RISK
COST CONTROLCost control is a key factor and an
important determinant during construction for achieving project’s KPIs.
Construction costs control includes:performing an adequate constructability
review to minimize unexpected costs;establishing a construction cost cash flow
plan;monitoring cost performance to detect
and understand variances from plan;
COST CONTROLensuring that all appropriate
changes are recorded;preventing incorrect, inappropriate,
or unauthorized changes from being included in the project;
Informing appropriate stakeholders of authorized changes;
Acting to bring expected costs within acceptable cost limits.
COST CONTROLCost control must be thoroughly integrated with the other control processes such as:
scope change control; schedule control and quality control.
Any inappropriate responses to cost variations can cause quality or schedule problems.
COST CONTROLRemoving gang members from one job to another can increase the contract duration.
Decreasing gang members can also increase the cost.
It also can produce an unacceptable level of risk later in the project.
COST CONTROL
construction costs include:contractor costs; the client cost;consultant costs;Any other hidden cost such as in case of any major dispute between contractor and the client.
COST CONTROLRESPONSIBILITIESProject Manager (PM): The PM is responsiblefor overall project cost control, running of theproject. The PM should work closely with the
Construction Site Manager, Site Engineers to ensure that changes are minimized.
Make sure the project is completed within budget.
COST CONTROLConstruction Manager (CM)-Project
manager (PM)-Site Manager (SM) Once the construction work starts on
site, the management team on site will be responsible for day-to-day cost control as well as other responsibilities.
The CM,PM, must not only know the project’s costs to date, but also be able to project costs For any additional work.
The CM, PM,.. is responsible for controlling costs to ensure that construction is completed within budget.
COST CONTROL If any changes are anticipated during
the construction process, immediate steps must be taken and they are:
1. the CM must notify the senior management as soon as possible;
2. an informed decision can be made on whether or not to proceed with the change;
3. Once the decision is made can the necessary funding be obtained?
COST CONTROL
Step 1-pull information from bill of quantity
Productivity measurement table -related to case no.1
CRAFT/LABOUR
PRODUCTIVITY
CASE NO.1 POOR
Total MD =Cost of material
Waste Waste Craft Optve
Craft Optve
Labour Labour
Productivity Loss or Gain £
Total loss/Gain =PR x TQ
Unit
3x3 Bed House -2 Story level
Quantity (TQ)
Delivered to site
(Estimate)
(Actual)
Hrs Hrs Hrs Hrs- PR=MD[A-X]+HC(EC-AC) +HL(EL-AL)
LOSS £
Description -Activities
(Act-) % % (EC) (AC) (E L) (AL)
SUPERSTRUCTURE
Facing Brick P.C £350 PER 1000 /Common Block
156 31.14 5% 6.50% 2.55 2.58 1.95 1.97 -0.9 -140 M2
Common Brick/Block
264 18.88 5% 6.50% 2.25 2.26 1.75 1.76 -0.47 -124 M2
Internal Walls -LWC Block
282 8 5% 7.00% 1.45 1.47 1.1 1.12 -0.38 -107 M2
Internal Walls -Plastering -13mm thick
708 1.71 5% 6.50% 0.45 0.45 0.23 0.23 -0.03 -24 M2
Internal Finish-Ceiling finish -set
504 0.47 5% 6.50% 0.25 0.25 0.13 0.13 0.47x (-0.02) 4 M2
Wall Tiling-152x152
75 14.5 5% 6.50% 1 1 0.6 0.6 1.71x (-0.02) 22 M2
carry outcalculations-useformulas (ACTUAL)
Informationfrom bill of quantity(ESTIMATION)
Net Rate
Gross Total Total Total Total Total Time
Total Time
Total Cost
Total Cost
Total Time
Total Time
Total Cost
Total Cost
Unit
(£) Rate Quant-
Quant-
Cost Cost Est- Est- Est- Est- Act.- Act.- Act- Act-
(Est-) (Act-) (Est-) (Act-) Craft Labour
Craft Labour Craft Labour Craft Labour
(£) (£) (£) (Hrs) (Hrs) (Hrs) (Hrs) (Hrs) (Hrs) (Hrs) (Hrs) 64.5
5 72.94 160 - 1167
0 - 464 688 3257.3 3969.7
5 - - - - M2
57.29
64.73 130 - 8414.9
- 63.75 315.9 447.15 1822.75
- - - - M2
40.81
46.12 225 - 10377
- 506.25
393.75
3553.9 2271.95
- - - - M2
35.24
39.82 410 16326
- 922.5 451 6475.95
2602.25
- - - - M2
13.91
15.98 440 - 7031.2
- 638 484 4478.75
2792.7 - - - - M2
5.04 5.69 1125 - 6401.3
506.25
258.75
3553.9 1492.95
- - - - M2
3.99 4.5 785 - 3532.5
196.25
102 1377.7 588.55 - - - - M2
26.88
30.37 90 - 2733.3
- 90 54 631.8 311.6 - - - - M2
Net Rate
Gross Total Total Total Total Total Time
Total Time
Total Cost
Total Cost
Total Time
Total Time
Total Cost
Total Cost
Unit
(£) Rate Quantity
Quantity
Cost Cost (Est-) (Est-) (Est-) (Est-) (Act.-)
(Act.-) (Act-) (Act-)
(Est-) (Act-) (Est-) (Act-) Craft Labour
Craft Labour Craft Labour Craft Labour
(£) (£) (£) (Hrs) (Hrs) (Hrs) (Hrs) (Hrs) (Hrs) (Hrs) (Hrs)
64.5 72.94 114 - 8315. - 330.6 490.2 2320.8 2828.4 - - - - M2
1 3 82 11 15
12
0
0
14
14
40
40
4
55
43
43
47
47
55
55
61
61DU=14 DU= DU= DU= DU=54
44
58
9
44
47
7
55
59
14
45
45
6
55
55
13
70
70
17
43
46
5
45
59
10
59
66
16
26
DU=4
DU=1
DU=1
3
DU=2
DU=1
DU=1
DU=1 8
DU=1
DU=4
DU=3
DU=2
DU=2
Network Programming(AOA)-ESTIMATION
GanttChart-ACTUAL
GanttChart-ESTIMATION
1 3 82 11 15
12
0
0
14
14
40
40
4
55
43
43
47
47
55
55
61
61DU=14 DU= DU= DU= DU=54
44
58
9
44
47
7
55
59
14
45
45
6
55
55
13
70
70
17
43
46
5
45
59
10
59
66
16
26
DU=4
DU=1
DU=1
3
DU=2
DU=1
DU=1
DU=1 8
DU=1
DU=4
DU=3
DU=2
DU=2
Network Programming(AOA)-ACTUAL
LABOURYESNOMATERIALS(wastage)
YESNO
MACHINERYYESNO
COST OVERRUN(YES)
COSTOVERRUN(NO)
COST OVERRUN(NO)
YES A
A
Carry outcalculationsuse formula(ACTUAL)
Productivi ty measurement table-rela ted to case no.1
CRAFT/LABOUR
PRODUCTIVITY
CASE NO.1 POOR
Total MD =Cost of material
Waste Waste Craft Optve
Craft Optve
Labour Labour
Productivity Loss or Gain £
Total loss/Gain =PR x TQ
Unit
3x3 Bed House-2 Story level
Quantity (TQ)
Delivered to site
(Estimate)
(Actual)
Hrs Hrs Hrs Hrs- PR=MD[A-X]+HC(EC-AC) +HL(EL-AL)
LOSS £
Descr iption-Activities
(Act-) % % (EC) (AC) (EL) (AL)
SUPERSTRUCTURE
Facing Brick P.C £350 PER 1000 /Common Block
156 31.14 5% 6.50% 2.55 2.58 1.95 1.97 -0.9 -140 M2
Common Brick/B lock
264 18.88 5% 6.50% 2.25 2.26 1.75 1.76 -0.47 -124 M2
Internal Wal ls-LWC Block
282 8 5% 7.00% 1.45 1.47 1.1 1.12 -0.38 -107 M2
Internal Wal ls-Plastering-13mm thick
708 1.71 5% 6.50% 0.45 0.45 0.23 0.23 -0.03 -24 M2
Internal Finish-Ceiling finish -set
504 0.47 5% 6.50% 0.25 0.25 0.13 0.13 0.47x (-0.02) 4 M2
Wall Tiling -152x152
75 14.5 5% 6.50% 1 1 0.6 0.6 1.71x (-0.02) 22 M2
SITE ENGINEERS
MANAGEMENT
CHIEF EXECUTIVE
LOWPRODUCTIVITYCOST OVERRUN
HIGHPRODUCTIVITY
COST CONTROLCost Control
CostEstimate
(CE)Actual cost
(AC)
Stored dataprice book(Spons,
Laxton, etc.
SuppliersManufacturers
etcprice list
Stored data frompast experience
/projects
IsCE>AC Yes
HighProductivity
No
IsAC>CE
Data Base
No
Productivityloss
Yes
Send reportto managers
COST CONTROLCost
controlInput
DataProcessing
Output
ContractDocuments
Stored DataPrice book
etc
DataBase
DisplayCost
Overrun
LabourActivities
1-2,2-3,...
15-16
Materials
Machinery
FormulasAC = a EC (1+? xi) and similarly AL = a EL
(1+? xi)
FormulaPR (Loss/Gain)=MD [A-X] + {(EC . HC)+ (EL
. HL)}-{(AC . HC)+ (AL . HL)}
Labour Productivity (Pi) for time periodi=WHi / Qi
Total MD =Cost of material
Waste Waste
Quantity (TQ)
Delivered to site
(Estimate)
(Actual)
(Act-) % %
156 31.14 5% 6.50%
264 18.88 5% 6.50%
282 8 5% 7.00%
708 1.71 5% 6.50%
Costoverrun?
c
Yes
No
Highproductivity
DATA MODEL-ESTIMATED COST COMPARED TO ACTUAL COST
Labour(Actual)
1-2
2-3
3-5
4-6
1-12
3-4
5-7
4-6
n activities
Labour(Estimates)
1-2
2-3
3-5
4-6
1-12
3-4
5-7
4-6
n activities
Materials(Actual)
1-2
2-3
3-5
4-6
1-12
3-4
5-7
4-6
n activities
Machinery(Actual)
1-2
2-3
3-5
4-6
1-12
3-4
5-7
4-6
n activities
Materials(Estimate)
1-2
2-3
3-5
4-6
1-12
3-4
5-7
4-6
n activities
Machinery(Estimate)
1-2
2-3
3-5
4-6
1-12
3-4
5-7
4-6
n activities
Controlcost
overrun
Controlcost
overrun
Controlcost
overrun
No Yes
Database
c
c
c
c
c c c
No
Yes
NoYes
DATA MODEL FOR LABOUR, MATERIAL AND MACHINERY COST OVERRUN
Labour(Actual)
with cost overrunactivities
4-6
1-12
3-4
Labour(Estimates)
4-6
1-12
3-4
5-7
Materials(Actual)
with wasteincrease
4-6
1-12
4-6
Machinery(Actual)
Lossof
efficiency(%)
1-2
2-3
Materials(Estimate)
4-6
1-12
4-6
Machinery(Estimate)
1-2
2-3
3-5 Database
5-7
PR (Loss/Gain)=MD [A-X] +HC(EC- AC)+HL(EL- AL)
AC = a EC (1+? xi) and similarlyAL = a EL (1+? xi)
xi = % of influential factorssuch as weather, crew size,
absenteeism, machinery,accidents on site, etc.
c
Cost overrun documentLabour
MaterialsMachinery
send tomanagement team
COMMUNICATION
Every year defects in the UK construction industry cost at least £20 billion to repair or rebuild
Some of the defects are as the result issues such as:
Poor communication; Poorly detailed drawing; Incorrect instructions or technical
information not being available on time;
COMMUNICATIONMeeting types and frequencies;Method's of drawing transfer;Use and control of revised
drawings, or unconfirmed drawings;
Reporting and tracking of defects;Lack of knowledge in detecting
defects on time.
COMMUNICATION
Single points of contactConsideration should be given to appointing defined, single points of contact at suppliers, design offices and contractors.
This should help to avoid delays, confusion and duplication of effort.
COMMUNICATION
Upwards feedback Establish means by which
information can be effectively fed back up through the formal management structure.
Two key areas where this can be particularly important are as follows:
COMMUNICATION
1. operatives to site office (e.g. reporting on an incorrect drawing);
2. Site office to head office (e.g. where an incorrect detail is discovered;
3. this should be reported back to the design office and the drawings corrected).
COMMUNICATIONThere are different communication
instruments, suchas: e-mail document telephone meeting contracts specifications reports manuals schedules calculations
COMMUNICATION drawings computer files Disks print-outs photographs agenda’s and minutes of meetings The management of documentation
and communication used in a project is used by a number of subcontractors, the storage and retrieval thereof for further use.
Communicationon site
Contractorsub-contractor
site engineers,clerk of work,..
communicationresponsibilitiesand methods
Suppliers1-2-3
Suppliers4-5-..
Single points ofcontact
Head Office
Subcontractor BSubcontractor A
Web Browser
General Contractor
Web Browser
Web Browser
XML XML
XML
Message Agent
Message Agent
Message Agent
Platform: IBM PCOS: Window 2000 ProfessionalFTP server: IIS 5.0
Platform: IBM PCOS: LinuxFTP server: WuFTP
Platform: IBM PCOS: Window 2000 ProfessionalFTP server: IIS 5.0
DataSynchronization
Subcontractor BSubcontractor A
Web Browser
General Contractor
Web Browser
Web Browser
XML XML
XML
Message Agent
Message Agent
Message Agent
Message Agent
Message Agent
Message Agent
Platform: IBM PCOS: Window 2000 ProfessionalFTP server: IIS 5.0
Platform: IBM PCOS: LinuxFTP server: WuFTP
Platform: IBM PCOS: Window 2000 ProfessionalFTP server: IIS 5.0
DataSynchronization
External communication
Indirect
Direct
Client