02 oliver nenadovic
DESCRIPTION
TractionTRANSCRIPT
-
/Railway Electrification Programme - The System Design Challenge
24-July-2014 1
Railway Electrification Programme
- The System Design Challenge
-
/24-July-2014
Railway Electrification Programme - The System Design Challenge
2
Agenda
1. IntroductionChallenge 1
2. Rail Electrification SystemsChallenge 2
3. System DesignChallenge 3
4. Summary
-
/Railway Electrification Programme - The System Design Challenge
24-July-2014 3
Introduction
-
/Railway Electrification Programme - The System Design Challenge
24-July-2014 4
Network Rail Who we are
Britain relies on rail
We own and operate Britains railway infrastructure
We are constantly maintaining and improving the railway for customers
We aim to provide a safe, reliable and efficient railway
-
/Railway Electrification Programme - The System Design Challenge
24-July-2014 5
Why Electrify the Railway?
Reduce long term costs Rolling stock is cheaper to run and maintain Lighter rolling stock so less damage to the track
Improve reliability Simpler rolling stock Fewer moving parts to go wrong
Greener Less CO2 emissions and less noise pollution Regenerative breaking benefit
Better journeys More seats and faster journeys
-
/Railway Electrification Programme - The System Design Challenge
24-July-2014 6
Railway Electrification Programme
Great Western
North West & Trans-Pennine
Welsh Valleys
Edinburgh to Glasgow
Electric Spine
Infill schemes
-
/Railway Electrification Programme - The System Design Challenge
24-July-2014 7
Challenge 1
-
/Railway Electrification Programme - The System Design Challenge
24-July-2014 8
Volume of Work
Biggest programme for a generation
Electrification Investment
CP4 CP5
260 Million
4 Billion
-
/Railway Electrification Programme - The System Design Challenge
24-July-2014 9
Enablers
Rail electrification development group
Addressing skills, resources and other issues
Sharing good practice and building a collaborative electrification community
-
/Railway Electrification Programme - The System Design Challenge
24-July-2014 10
Rail ElectrificationSystems
-
/Railway Electrification Programme - The System Design Challenge
24-July-2014 11
Why AC?
Better efficiency
Supports faster and high density traffic
Lower capital, operating and renewal costs
-
/Railway Electrification Programme - The System Design Challenge
24-July-2014 12
Booster Transformer System
BOOSTER TRANSFORMER
FEEDERSTATION
RETURN CONDUCTOR
CONTACT WIRE
RAIL
-
/Railway Electrification Programme - The System Design Challenge
24-July-2014 13
Booster Transformer System
-
/Railway Electrification Programme - The System Design Challenge
24-July-2014 14
Autotransformer System
AUTOTRANSFORMER
FEEDERSTATION
CONTACT WIRE
RAIL
AUXILIARY FEEDER
2 I
I
I
0.5 I
0.5 I
I
0.5 I
I0.5 I
0.5 I
0.5 I
1.5 I
-
/Railway Electrification Programme - The System Design Challenge
24-July-2014 15
Autotransformer System
-
/Railway Electrification Programme - The System Design Challenge
24-July-2014 16
AT / BT Impedance ProfileM
P
T
S
C
T
S
C
F
S
T
S
C
M
P
T
S
C
T
S
C
A
T
F
S
/
F
S
T
S
C
M
P
T
S
C
T
S
C
F
S
M
P
T
S
C
T
S
C
M
P
A
T
S
A
T
S
A
T
S
S
A
T
S
A
T
S
A
T
S
A
T
S
A
T
S
S
A
T
S
A
T
S
A
T
S
M
P
A
T
S
0
2
4
6
8
10
12
-60 -50 -40 -30 -20 -10 0 10 20 30 40 50 60Distance [km]
I
m
p
e
d
a
n
c
e
[
o
h
m
s
]
-
/Railway Electrification Programme - The System Design Challenge
24-July-2014 17
Challenge 2
-
/Railway Electrification Programme - The System Design Challenge
24-July-2014 18
Energy Risk
Supply shortage leading to BrownoutsElectricity price rise
-
/Railway Electrification Programme - The System Design Challenge
24-July-2014 19
Enablers
Largest single consumer of electricity in UK
Asset portfolio comparable to DNO
Opportunities in new technology and utilisation of our networks
-
/Railway Electrification Programme - The System Design Challenge
24-July-2014 20
System Design
-
/Railway Electrification Programme - The System Design Challenge
24-July-2014 21
Traction Power Modelling
Assessment of the impact of future services on existing and proposed infrastructure
Propose and analyse electrification enhancements
Strategic view
-
/Railway Electrification Programme - The System Design Challenge
24-July-2014 22
Technical Requirements
Technical Specifications for Interoperability
Bulk supply point assessment
Negative Phase Sequence
Equipment loading assessment
Voltage regulation
Rail potentials and induced voltages
Energy loss
-
/Railway Electrification Programme - The System Design Challenge
24-July-2014 23
Example Compliance Outputs From Western Route Traction Power System Strategy
-
/Railway Electrification Programme - The System Design Challenge
24-July-2014 24
Didcot GSP Feeding Area- Simplified to support slides which follow
-
/Railway Electrification Programme - The System Design Challenge
24-July-2014 25
Demand Analysis Didcot Morning Peak - GSP transformer naturally cooled ONAN rating 80 MVA
Transformer utilisation compliant.
Analysis supports capacity headroom definition.
-
/Railway Electrification Programme - The System Design Challenge
24-July-2014 26
Voltage Analysis Train Scatter Plot- Minimum voltage compliance limit 19 kV [EN 50119:2009]
Train pantograph voltages compliant.
Voltage decays away from supply point, with the largest voltage drop at extremities of feeding area. This places a limit on how far a supply point can feed since train performance deteriorates at lower voltages.
-
/Railway Electrification Programme - The System Design Challenge
24-July-2014 27
Earth Potential Analysis- Load conditions compliance limit 60 V [EN 50122-1]
Safe touch potentials on rails compliant.
Jump in rail voltages is because Didcot is the point where the railway changes from four tracks to two tracks, hence larger rail impedance.
-
/Railway Electrification Programme - The System Design Challenge
24-July-2014 28
Electromagnetic Induction Analysis- Fault conditions compliance limit 645 V [EN 50122-1] for safe touch potentials
Safe touch potentials on lineside cables compliant.
Again jump in voltages is because Didcot is the point where the railway changes from four tracks to two tracks, hence larger rail impedance.
-
/Railway Electrification Programme - The System Design Challenge
24-July-2014 29
Fault Analysis - Nominal fault level is 300 MVA (12 kA) [Network Rail Policy]
washing line appearance is a result of lower impedance at intermediate autotransformer sites due to paralleling.
-
/Railway Electrification Programme - The System Design Challenge
24-July-2014 30
Energy Loss - Portion of active power provided by GSP not transferred to train pantographs
Supports whole life cost assessment of system.
-
/Railway Electrification Programme - The System Design Challenge
24-July-2014 31
Electromagnetic Induction
-
/Railway Electrification Programme - The System Design Challenge
24-July-2014 32
Return Screen Conductor
-
/Railway Electrification Programme - The System Design Challenge
24-July-2014 33
Challenge 3
-
/Railway Electrification Programme - The System Design Challenge
24-July-2014 34
Technical Complexity Whilst Delivering Efficiencies
Distributed demand and power generation that is constantly moving around network
Modelling is detailed and takes time
-
/Railway Electrification Programme - The System Design Challenge
24-July-2014 35
Enablers
Need tools that well suited to future planning and option analysis
Traction Power Supply Strategies
Technological innovation
-
/Railway Electrification Programme - The System Design Challenge
24-July-2014 36
Why are we moving to TPSS approach?
To identify better whole life cost options that may span multiple control periods.
To move away from project by project timetable specific TP enhancements.
To demonstrate to the regulator that our power projects are aligned to the future needs of the railway.
To allow the Energy industry to have a better understanding of our future energy needs.
To develop the fundamental system design early to allow projects to focus on delivering and implementing the detailed design.
-
/Railway Electrification Programme - The System Design Challenge
24-July-2014 37
Integrated Protection & Control (IPC)
Intelligent Electronic Device (IED) A typical device is shown which uses a microprocessor to perform protection and control functions .
IEC 61850A standard architecture for communication networks and systems in substations.
Rugged Ethernet Switch A typical device (harden for use within a railway substation environment) is shown which directs Ethernet network traffic.
Communication
Marshalling
Hardware
-
/Railway Electrification Programme - The System Design Challenge
24-July-2014 38
IPC Development Suite
-
/Railway Electrification Programme - The System Design Challenge
24-July-2014 39
Summary
1. Biggest rail electrification programme for a generation
2. Challenges ahead
3. Exciting opportunities to make a difference in system design