PRE - FEASIBILITY REPORT
for
PROPOSED EXPANSION OF SPECIALTY
CHEMICALS & AGROCHEMICAL INTERMEDIATES
MANUFACTURING PLANT
of
M/s. ANUPAM RASAYAN INDIA LTD. (UNIT- 4)
PLOT NO. 907/3 & 907/4, JHAGADIA INDUSTRIAL
ESTATE, JHAGADIA, DIST: BHARUCH – 393 110,
GUJARAT
2
CONTENTS
Sr.
No.
Description Page No.
1. Executive Summary 3
2. Introduction of the Project/Background information 9
3. Project Description 11
4. Site Analysis 17
5. Planning Brief 20
6. Proposed Infrastructure 24
7. Rehabilitation and resettlement (R & R) Plan 24
8. Project Schedule & Cost Estimates 25
9. Analysis of Proposal (Final Recommendations) 26
3
1.0 Executive Summary
1.1 Company Profile
Introduction History of Anupam Rasayan India Ltd.
Anupam Rasayan India Limited was started in 1976 and we are 36 years old ISO 9000:2000 and ISO 14000:1994 certified chemical company with sound technology, environment consciousness, a rich history of innovation through research, and a total commitment to excellence in quality and customer satisfaction. ARIL is a manufacturer of Specialty Chemicals, with products catering to a plethora of market segments such as Pharmaceuticals, Agrochemicals, Pigments, Dyestuff, Material Sciences and Human Care. Our vision is to exploit to the maximum the potential of our extensive infrastructure and knowledge base, and then go beyond these to explore new horizons. Our objective is to grow exponentially in a multi-faceted manner through our chemistry, our technology and most importantly, through our customer support. ARIL thrives on its strong Research & Development and we have introduced numerous products for the first time in India. Many products have been introduced on an exclusive basis for our customers, for which we have entered into exclusivity agreements.
Vision:
"ARIL strives to be a globally reputed organization with respect to Research, Technology,
Quality and Ethical Values".
Mission:
Attaining business growth by:
• Delivering Customer Satisfaction.
• Attaining a globally competitive / sustainable business model.
• Enhancing the values we deliver to stakeholders.
• Establishing preferred vendor viewpoint.
• Maximizing competitiveness and gaining market share.
• Enhancing the portfolio of new products, services and business model.
• Developing the internal innovation champions and competencies.
• Establishing innovation as disciplined "process" in the DNA of company for
continuous innovations.
• Achieving higher growth and larger than average profits.
• Commitment to our CSR values.
4
Objective:
"The objective of the company is to be a leading player in specialty chemical industry and
service our customer demand".
Employee Strength
� Anupam banks on total employee strength of 275 people, out of which skilled
employees are 100, which includes Ph.D.s, Chemical, Mechanical and Electrical
engineers, Science Graduates with Masters and Bachelors, qualified safety officers.
Total unskilled employees are 175.
� Anupam has 20 people working full time in Research & Development.
� Anupam has a fantastic strength of employee retention, as rarely human capital leaves
Anupam, examples of the same are as follows:
� R&D Head – 25 Years with Anupam
� Maintenance Head – 33 Years with Anupam
� Production Head – 20 Years with Anupam
� Production Chemist – 15 Years with Anupam
� Unskilled Workers – 25 Years with Anupam
Thus “Knowledge remains within Anupam as we are able to retain people”
Capabilities:
Some products have technological barriers in terms of chemical engineering, Anupam over
comes these barriers by in-house manufacturing of key engineering equipment’s, the
examples are:
� Specific key & complex engineering instruments are designed and manufactured in
STAR ENGINEERING, which is in-house workshop.
SWOT Analysis
Strength
� Proven dependability
� Customized manufacturing that delivers
� Customer centric engagements in a spirit of partnership
� Efficient Operations
� Faster decision making
� Reach in terms of logistics
� Ability to retain people
5
Weakness
� Challenges of transformation from a family managed company to professionally
managed company
� Management depth
� Challenges to meet time-lines for up-coming production facilities
Opportunities
� New Plants & production facilities
� New Products
� Potential new customers
Threats
� Intense competition
� Market uncertainty
1.2 Project Details
Sr.
No. Name of Products
CAS No. Existing
Capacity
(MT/Month)
Additional
Capacity
(MT/Month)
Total
capacity
(MT/Month)
1.1 1,4 Dioxane 123-91-1 1000 0 1000
1.2 2- Methyl 1,3 Dioxolane 497-26-7
2.0 CHLORO BENZENE COMPOUNDS
2.1 Chloro Benzene ( MCB) 108-90-7
2500
0
2500
2.2 Para Di Chloro Benzene (PDCB) 106-46-7
2.3 Ortho Di Chloro Benzene ( ODCB) 95-50-1
2.4 1- Amino 2,4,6 Trichloro Benzene/ 2,4,6
Tri Chloro Aniline
634-93-5 0
2.5 2,6 Di Chloro Benzoxazole 3621-82-7 0
2.6 2,3,4,5,6 Penta Chloro Pyridine 2176-62-7 0
2.7 3,7 Di Chloro 8- Methyl Quinoline 84086-96-4 0
3.0 CHLORO PHENOLCOMPOUNDS
3.1 Para Chloro Phenol (PCP) 106-48-9
6
3.2 Ortho Chloro Phenol (OCP) 95-57-8
500
0
500
3.3 2,4 Di Chloro Phenol 120-83-2
3.4 2,6 Di Chloro Phenol 87-65-0
3.5 4- Bromo 2,5 Di Chloro Phenol 1940-42-7 0
4.0 Meta Di Chloro Benzene ( MDCB) 541-73-1 400 0 400
5.0 NITRO COMPOUNDS
5.1 Nitro Benzene 98-95-3 800
0 800
5.2 Meta Di Nitro Benzene ( MDNB) 99-65-0
5.3 2,4 Di Chloro 3,5 Dinitro Benzotrifluoride 29091-09-6 0
5.4 2,3,4 Tri Chloro Nitro Benzene 17700-09-3 0
5.5 4- Nitro Ortho Xylene 99-51-4 0
6.0 Calcium Chloride 10043-52-4 1800 0 1800
7.0 AMINO BENZOIC ACID / ESTERS
7.1 3-Amino-4-Chloro Benzoic Acid Methyl
Ester
40872-87-5
500
0 500
7.2 3-Amino 4-Methyl Benzoic Acid Isopropyl
Ester (AMBI)
21447-47-2
7.3 3-Amino 4-Methyl Benzoic Acid(2' -
Chloro Ethyl Ester) (AMBC)
2458-12-0
7.4 5-Amino-2-Methyl Benzene Sulphonic
Acid Phenyl Ester
1089339-15-0
7.5 Benzene Sulphonic Acid 3-Amino Phenyl
Ester
13653-12-4
7.6 2-Cyano-3,4,5,6-Tetrachloro Benzoic
Acid Methyl Ester
10276-78-2
7.7 Benzene Sulphonic Acid 2-Methyl-5-
Nitrophenyl Ester
85896-03-5
7.8 4- Methyl Benzoic Acid Methyl Ester 99-75-2
7
7.9 3,5 Di Amino 4- Chloro Benzoic Acid Iso
Butyl Ester
32961-44-7
7.10 3,4,5 Tri Methoxy Benzoic Acid 118-41-2 0
7.11 1- Methyl 3,4,5 Tri Methoxy Benzene /
3,4,5 Tri Methoxy Toluene
6443-69-2 0
7.12 5- Methyl 2,3 Pyridine Di Carboxyllic Acid 53636-65-0 0
7.13 3,4,5 Tri Methoxy Benzaldehyde 86-81-7 0
Total 7500 0 7500
List of By-Products:
Sr. No.
Name of By-Products
CAS No. Existing Capacity
(MT/Month)
Additional Capacity
(MT/Month)
Total Capacity
(MT/Month)
1. Dilute Sulphuric Acid 7664-93-9 753.3 0.0 753.3
2. 30 % HCl Solution 7647-01-0 3375.0 0.0 3375.0
3. 35 -40 % Nitrosyl Sulphuric Acid / Sodium Nitrite Solution
7780-78-7 986.0 0.0 986.0
4. POCl3 10025-87-3 265.0 0.0 255.0
5. Caustic Soda Solution (30% to 40%)
1310-73-2 470.0 0.0 470.0
6. Ammonium Chloride 12125-02-9 55.0 0.0 55.0
7. Ammonium Sulphate Salt 7783-20-2 150.0 0.0 150.0
8. 20-28 % HBr Solution 10035-10-6 0.0 10920.0 10920.0
9. Sodium Bromide Salt 7647-15-6 0.0 3570.0 3570.0
10. Sodium Sulphate 7647-15-6 0.0 6093.0 6093.0
11. 8-10 % Sodium Hypochlorite Solution
7681-52-9 00 600.0 600.0
12 2- Methyl 1,3 Dioxolane 497-26-7 0.0 25.0 25.0
8
13 MnSO4 Salt 7785-87-7 0.0 650.0 650.0
14. 30 -40 % Dilute Nitric Acid 7697-37-2 0.0 20.0 20.0
15. Sulphur Dichloride 105454-99-
0 0.0 1090.0 1090.0
Total 6054.3 11209.0 17253.3
1.3 Water Requirement, Waste Water Generation and Treatment
Total water requirement will 310 m3/day which will be met through GIDC water supply. The
wastewater generation will 78 m3/day. The wastewater generation will be 74 m3/day which
shall be treated in ETP & MEE and Treated Effluent shall go to SBT.
Domestic wastewater (4 KL/Day) shall be disposed in septic tank/sock pit.
1.4 Air Pollution Source and Control Management
There will be emission from Boiler-1, Boiler -2, Thermoapck Heater, Hot Air Generator, DG
Set & Process Vents (3 Nos.). ESP with Online Monitoring System, Two Stage Water +
Alkali Scrubber will be installed to control the emission from air pollution source.
1.5 Hazardous Waste
Hazardous waste generation will be ETP Sludge [15.83 MT/Month] which will be Collected,
Stored, Transported and Disposed at TSDF at M/s. BEIL, Ankleshwar. Spent Oil [50
Liter/Month] which will be collected, stored, transported and sold to registered recycler.
Empty Bags/ Discarded Liners [1003 Nos./Month], which will be collected, stored,
Transported and sold to GPCB authorized scrap dealer after decontamination. MEE Salt (60
MT/Month) from MEE will be Collected, Stored, Transported and Disposed at TSDF at M/s.
BEIL, Ankleshwar. Distillation Residue (85.66 MT/Month) will be Collected, Stored,
Transported and sold to Cement Industry for Co-processing or Disposal at Common
Incineration Site. Fly Ash (80MT/Month) will be Collected, Stored, and Transported and sold
to brick manufacturers or disposed in TSDF.
9
1.6 Green Belt
Total 53997 m2 land area is available at site; out of this 16467 m2 (i.e. approx 31 % of total
area) shall be developed as greenbelt and other forms of greenery.
1.7 Power & Fuel Requirements
Power required from DGVCL will 1500 KVA (Proposed)
DG Set of equivalent capacity will be kept for emergency power back up
Fuel:
Existing: Natural Gas/LDO -150 KL/Day or 9 MT/Month D.G.Set-5 MT/Month
Proposed:
Boiler (Coal/Lignite/Briquette) –Proposed: 40 MT/day
Natural Gas/LDO -200 KL/Day or 10 MT/Month D.G.Set-5 MT/Month
2.0 INTRODUCTION OF THE PROJECT/BACKGROUND INFORMATION
2.1 Identification of the project and project proponent. In case of mining project, a
copy of mining lease/letter of intent should be given.
Identification of the project
PROPOSED EXPANSION OF SPECIALTY CHEMICALS & AGROCHEMICAL INTERMEDIATES
MANUFACTURING PLANT
Identification of the project proponent
Presently following are the director of the company:
Sr. No.
Name of Director Education Nationality Address
1 Mr. Anandbhai Sureshchandra Desai
B. Sc., MBA Indian 5, Janata Nagar Society, Near Kapadia Health Club, Bhatar Road, Surat – 395007 (Guj.)
2 Mrs. Hanshaben Sureshchandra Desai
B. Com. Indian 5, Janata Nagar Society, Near Kapadia Health Club, Bhatar Road, Surat – 395007 (Guj.)
3 Mrs. Monaben Anandbhai Desai
B. Sc. Indian 5, Janata Nagar Society, Near Kapadia Health Club, Bhatar Road, Surat – 395007 (Guj.)
10
4 Mr. Akhilbhai Milanbhai Thakker
MBA Indian 7, Lowswood Close, Northwood Middlesex, HA62XE, UK
5 Mr. Apurvabhai J. Nanavati B. Com. Indian Arunodaya, Sarojini Road, Vileparle (W), Mumbai-400056, Maharashtra
2.2 Brief description of nature of the Project
PROPOSED EXPANSION OF SPECIALTY CHEMICALS & AGROCHEMICAL INTERMEDIATES
MANUFACTURING PLANT
2.3 Need for the project and its importance to the country and or region
The objective is to be achieved by:
• Consolidating Business.
• By constantly upgrading the product range.
• Continuously reducing the Costs & improving Quality.
• To generate local employment
2.4 Demands-Supply Gap
Based on our informal survey of the market with our current customers and various traders,
we have found that there is a big potential for the range of the products we are planning.
These products will be an addition to the current range of our products.
2.5 Imports vs. Indigenous production
Based on the current cost of indigenous raw materials and the non availability of some
materials, we will have to import some of the key raw materials as they are not available
indigenously. This will make us very competitive against imported finished products and we
will be able to increase the export of our finished products.
2.6 Export possibility
There is export potential of our proposed products.
2.7 Domestic/Export Markets
There is export potential as well as demand in local market.
11
2.8 Employment Generation (Direct and Indirect) due to project.
Employment would be as per prevailing norms of state government for skilled and unskilled
people for the proposed expansion project.
3.0 Project Description
3.1 Type of Project including interlinked and interdependent projects, if any.
No interlinked project has been submitted.
12
3.2 Location (map showing general location, specific location and project boundary &
project site layout) with coordinates.
• Map showing general location
PROJEC
T SITE
13
• Specific location and project boundary
14
Plot Layout
15
3.3 Details of alternate sites considered and the basis of selecting the proposed site,
particularly the environmental considerations gone into should be highlighted.
Major factors involved in the selection of site are listed below:
• Site is very well connected by road
• Proximity to Raw Material suppliers
• Availability of sufficient land free from cultivation
• Availability of power evacuation facilities
• Availability of water for industrial use
Modern infrastructure support and amenities at par with industrial estates in other global
markets, including:
� Efficient transport facilities within the industrial estate and to & fro the city area.
� Environment-friendly zone.
� Uninterrupted power supply.
3.4 Size or Magnitude of Operation
Please refer Section-1.2
3.5 Project Description with process details (a schematic diagram/flow chart showing
the project layout, components of the project, etc. should be given)
Please refer Form-I, Annexure-III.
3.6 Raw Material required along with estimated quantity, likely source, marketing area
of final product/s, mode of transport of raw material and Finished product.
For raw material required along with quantity; Please refer Form-I, Annexure-I. Majority of
the products will be used for domestic market and some products will be exported
depending on the international market.
3.7 Resource optimization/recycling and reuse envisaged in the project, if any, should
be briefly outlined.
Every effort will be put to recycle/reuse the water.
16
3.8 Availability of water its source, energy/power requirement and source should be
given.
Water Source
Total water requirement shall meet through GIDC water supply.
Power & Fuel Requirement
Power required from DGVCL will 1500 KVA (Proposed)
DG Set of equivalent capacity will be kept for emergency power back up
Fuel:
Existing: Natural Gas/LDO -150 KL/Day or 9 MT/Month D.G.Set-5 MT/Month
Proposed:
Boiler (Coal/Lignite/Briquette) –Proposed: 40 MT/day
Natural Gas/LDO -200 KL/Day or 10 MT/Month
D.G.Set-5 MT/Month
3.9 Quantity of wastes to be generated (liquid and solid) and scheme for their
management/disposal.
Please refer Form-I, Annexure-V.
3.10 Schematic representations of the feasibility drawing which give information of
EIA purpose.
RECONNAISSANCE SURVEY OF EXISTING PLANT ANNUAL REPORT
MARKET ASSESSMENT
FINANCIAL REPORT
PROJECT REPORT
INTRODUCTION
MONITORING OF AIR, WATER & SOIL QUALITY & NOISE
LEVELS. DATA ON METEOROLOGY SOCIO-ECONOMIC STATUS
& BASIC AMENITIES. SITE VISITS BY AND INTERVIEWS WITH
LOCALS
BASELINE
ENVIRONMENTAL
STATUS
ENVIRONMENTAL INFORMATION CENTRE
CENTRAL GROUND WATER BOARD
GUJARAT POLLUTION CONTROL BOARD (GPCB)
PUBLIC HEALTH ENGINEERING DEPT.
AGRICULTURE DEPARTMENT
FOREST DEPARTMENT
IRRIGATION DEPARTMENT
EMPLOYMENT EXCHANGE
HEALTH CENTER
CENSUS DEPT.
INDIAN METEOROLOGICAL DEPT.
SOCIOECONOMIC
STATUS &
INFRASTRUCTURE
EXPANSION
PLANT
FACILITY DESCRIPTION
IMPACTS
METHODOLOGY OF
IMPACT
ASSESSMENT
IDENTIFICATION & ASSESSMENT OF IMPACTS
EVALUATION OF IMPACTS BY MATRIX METHOD
SOURCE OF INFORMATION OVERVIEW OF
E. I. A. STUDIES
ACTIVITIES
ENVIRONMENTAL
MANAGEMENT PLAN
DESCRIPTION OF EFFLUENT TREATMENT PLAN, AIR
POLLUTION CONTROL, HAZARDOUS WASTE MANAGEMENT,
GREEN BELT DEVELOPMENT MONITORING PROGRAM
RISK ANALYSIS
STUDIES &
DISASTER
MANAGEMENT PLAN
SAFETY, HEALTH & ENVIRONMENTAL POLICY, GUIDELINES BY
DIRECTOR GENERAL OF FACTORY SAFETY, MINISTRY OF LABOR. CONSEQUENCE ANALYSIS
PREPARATION OF DISASTER MANAGEMENT PLAN
17
4.0 Site Analysis
4.1 Connectivity
• Site is very well connected by road
• Availability of power evacuation facilities
• Availability of water for industrial use
4.2 Land Form, Land Use and Land Ownership
(Source: Environmental Information Center, New Delhi)
18
4.3 Existing land use pattern (agriculture, non-agriculture, forest, water bodies
(including area under CRZ)), shortest distances from the periphery of the project to
periphery of the forests, national park, wild life sanctuary, eco sensitive areas, water
bodies (distance from HFL of the river), CRZ. In case of the notified industrial area, a
copy of the Gazette notification should be given.
(Source: Environmental Information Center, New Delhi)
17
AREAS UNDER DIFFERENT LANDUSE
(Source: Environmental Information Center, New Delhi)
4.4 Existing Infrastructure
The project site is located in GIDC, Jhagadia, Dist: Bharuch, which is a well developed
designated Industrial Area.
Total Plot Area = 27,178.98 m2
Green Belt =8,154 m2
Sr. No.
Landuse Classification Area (in sq.km.) Percentage Area
1 Water Body 0.46 0.15
2 Open/Barren Land 46.55 14.84
3 Agriculture 46.47 14.81
4 Fallow Land 168.64 53.74
5 Degraded Vegetation 31.94 10.18
6 Scrub 0.08 0.03
7 River 3.64 1.16
8 Settlement 5.08 1.62
9 Sand 1.14 0.36
10 Industrial Area 3.11 0.99
11 Miscellaneous 6.71 2.14
Total 313.81 100.00
18
4.5 Soil Classification
Soil Characteristics under Project Area are as below Table;
Category Area
(Sq. kms) Description Taxonomy1 Taxonomy2 Class Sub
Class
Category C 176.30
Very deep, moderately well drained, fine soils on very gently sloping basaltic
interfluves with slight erosion; associated with deep well drained,
calcareous fine soils with slight erosion
Fine, montrmorillonitic, hyperthermic Typic
Chromusterts
Fine, montmorillonitic
(calcareous) hyperthermic Vertic
Ustochrepts
Soils of west coast(soils of Gujarat plain)
Soils of interfluves
Category D 0.23
Deep, well drained, clacareous, fine soils on very gently sloping alluvial plain with slight erosion and slight salinity; associated with very deep,
imperfectly drained, calcareous, fine-loamy soils with slight erosion
Fine, mixed (calcareous),
hyperthermic Fluventic Ustochrepts
Fine-loamy, mixed (calcareous),
hyperthermic, Udic Ustochrepts
Soils of west coast (soils of gujarat plain)
Soils of alluvial plains
Category E 10.96
Very deep, well drained, calcareous, fine-loamy soils on gently sloping
alluvial plain with moderate erosion; associated with deep, well drained, calcareous, fine-loamy soils on very gently sloping lands with moderate
erosion
Fine loamy, mixed (calcareous),
hyperthermic Fluventic Ustochrepts
Fine loamy, mixed (calcareous),
hyperthermic Udic Ustochrepts
Soils of west coast(soils of Gujarat plain)
Soils of alluvial plains
Category F 42.87
Very deep, moderately well drained, fine soils on very gently sloping alluvial plain with moderate erosion; associated
with very deep, moderately well drained, fine soils on nearly level lands
with slight erosion.
Fine, montmorillonitic, hyperthermic Typic
Chromusters
Fine, montmorillonitic,
hyperthermic Vertic Ustochrepts
Soils of west coast(soils of Gujarat plain)
Soils of alluvial plains
Category G 31.21
Very deep, moderately well drained, fine soils on nearly level alluvial plain
with slight erosion; associated with very deep moderately well drained,
calcareous, fine soils on gently sloping lands with severe erosion
Fine, montmorillonitic, hyperthermic Typic
Chromusterts
Fine, montmorillonitic
(calcareous), hyperthermic Typic
Chromusterts
Soils of west coast (soils of Gujarat plain)
Soils of alluvial plains
Category H 52.31
Very deep, moderately well drained, fine soils on nearly level alluvial plain
with moderate erosion; associated with very deep, moderately well drained,
calcareous, fine soils on gently sloping lands with severe erosion
Fine, montmorillonitic, hyperthermic Typic
Chromusters
Fine, montmorillonitic
(calcareous) hyperthermic Typic
Chromusterts
Soils of west coast(soils of Gujarat plain)
Soils of alluvial plains
Category I 0.06
Very deep, moderately well drained, fine soils on very gently sloping alluvial
plain with moderate erosion and moderate salinity; associated with very
deep, moderately well drained calcareous, fine soils with moderate
erosion
Fine, montmorillonitic, isohyperthermic Typic
Chromusterts
Fine, montmorillonitic,
(calcareous), hyperthermic Udic
Chromusterts
Soils of west coast(soils of Gujarat plain)
Soils of alluvial plains
(Source: Environmental Information Centre, New Delhi)
19
SOIL CHARACTERISTICS MAP
(Source: Environmental Information Centre, New Delhi)
20
4.6 Climatic data from secondary sources.
Secondary Sources – Indian Meteorological Department, Ahmedabad and our own weather
station.
4.7 Social infrastructure available.
Depending on the growth of the company the required social infrastructure will be provided.
5.0 Planning Brief
5.1 Planning Concept (type of industries, facilities, transportation etc) Town and
Country planning/Development authority classification.
Type of Industry: PROPOSED EXPANSION OF SPECIALTY CHEMICALS & AGROCHEMICAL
INTERMEDIATES MANUFACTURING PLANT
Facility: Canteen, Administration, Transportation
5.2 Population Projection
It will be incorporated in EIA Report.
5.3 Land use planning (breakup along with green belt etc.)
Total Plot Area: 53997 m2
Total 53997 m2 land area is available at site; out of this 16467 m2 (i.e. approx 31 % of total
area) shall be developed as greenbelt and other forms of greenery.
5.4 Assessment of Infrastructure Demand (Physical & Social)
• Employment would be as per prevailing norms of state government for skilled and
unskilled people for the proposed project activity.
• Social Welfare
• Cordial relation with the industry shall be established and representation shall be made
to villagers for help for creation of facilities related to health, education, etc.
21
5.5 Amenities/Facilities
Details of amenities available in study area
Taluka Village Educational Medical Drinking Water
Post & Telegraph
Communication
Approach to Village
Nearest Town
Power Supply
Jhagadia Dumala Haripura P(2) CHW T, W, TW PO BS PR, KR Rajpipla - 30 EA
Uchedia P(4) PHS , RP W, T , HP PO, Phone BS PR, KR Ankleshwar-17 EA
Govali P(4) , H , Ac ,
O CHW , PHS ,RP , FPC
T, W , TK ,TW PO, Phone BS PR, KR Bharuch – 13 EA
Nana sanja
P(2) CHW T, W, TK , TW ,
R , N
PO, Phone BS PR, KR Bharuch-15 EA
Rainpara P(3), Ac PHS , CHW T, W ,TW PO, Phone BS PR, KR Ankleshwar-15 EA
Mota sanja P(2) CHW T, W PO , Phone BS PR, KR Ankleshwar-21 EA
Sultanpura P(3), O, H ,
PUC PHS, RP , MH
, D T, W, TK , TW PO, Phone BS PR, KR Ankleshwar-20 EA
Kunvarpara P(2) , Ac(3) -(5-10 Kms)
W -(5-10 Kms) -(5-10 Kms) KR Ankleshwar -
28 EA
Damlai P(2) CHW W -(5-10 Kms) BS , RS KR Ankleshwar-27 EA
Andharkachhala P(2) -(5 - Kms) W -(5-10 Kms) BS PR, KR Ankleshwar-24 EA
Dholakuva P(2) CHW W -(5 - Kms) BS , RS PR, KR Ankleshwar-27 EA
Malpor P(2) , Ac(8) CHW W, TK PO BS PR, KR Ankleshwar-25 EA
Vanthevad P(2) CHW W, TK -(-5 KMS) BS PR, KR Ankleshwar-21 EA
Kharia P(2) -(5 - Kms) W , S -(5 - Kms) -(5 - Kms) PR, KR Ankleshwar-21 EA
Fulwadi P(2) CHW , PHS W, TW , R PO BS PR, KR Ankleshwar-26 EA
Boriwada P(2) CHW TK , W , TW
,HP -(5 - Kms) BS , RS PR , KR Ankleshwar-12 EA
Mulad P(2) CHW , PHS T, W , TK ,
TW ,HP PO BS PR , KR Bharuch - 9 EA
Naugama P(2) CHW T, W , TK , HP
,R -(5 - Kms) BS PR, KR Bharuch-8 EA
Kharchi bhilwada P CHW T, W ,TK , HP -(-5 KMS.) BS , RS PR , KR Akleshwar-10 EA
Kharchi P(2) CHW , PHS ,
FPC TK, W, HP PO , Phone BS, RS PR, KR Ankleshwar-10 EA
Kapalsadi P(3),O CHW TK, W, TW,
HP, R PO BS PR , KR Ankleshwar-17 EA
Selod P(3) , Ac(2) CHW T, W, R PO BS PR Ankleshwar-23 EA
Padal P(6), AC(11) -(5 - Kms) T, W , R PO BS PR Ankleshwar-21 EA
Moran Ac(5) CHW W -(5 - Kms) BS PR, KR Ankleshwar-34 EA
Vasna P(4) PHS , CHW W , R , F PO BS PR, KR Ankleshwar-40 EA
Ralpore P -(5 - Kms) W , R -(5 - Kms) -(5 - Kms) Ankleshwar-38 EA
Navagam mota P CHW W -(5 - Kms) BS KR Ankleshwar-33 EA
Sardarpura P(2) CHW T , W, TK , HP -(5 - Kms) BS KR Ankleshwar-14 EA
Untia P(2) CHW T ,W ,HP -(5 - Kms) BS KR Ankleshwar-12 EA
Dadheda P(2) , O -(5 - Kms) T ,W, TK. , HP PO BS PR Ankleshwar-11 EA
Randedi P(2) CHW W -(5 - Kms) BS PR , KR Ankleshwar-15 EA
Limet P(2) PHS , CHW T, W, TK,HP,
R PTO BS PR ,KR Ankleshwar-20 EA
Talodara P(3) , H ,Ac(8) PHS ,FPC ,
CHW T, W, TK ,TW
,HP PO BS PR , KR Ankleshwar-19 EA
Panvadi P(2) CHW W , TK, HP, C -(5 - Kms) BS PR Ankleshwar-22 EA
Borjai P(6) , O(2) CHW T, W, TK ,HP
,C PO BS PR ,KR Ankleshwar-25 EA
Ankleshwar
Amrutpura P(2) -(5 – 10 Kms) W ,HP -(5 - Kms) -(-5 Kms) PR Ankleshwar-10 EA
Motali P(3) -(5-10 kms) T, W, R PO , Phone BS PR Ankleshwar-9 EA
22
Uchhali P(2) CHW W, TK , HP PO BS , RS PR, KR Ankleshwar-10 EA
Jitali
P(3) , H ,O PHC, CHW,,SMP ,
RP
T,W, HP PO, Phone BS PR, KR Ankleshwar-10 EA
Dadhal P(3) ,O CHW,PHS
,FPC T, W, HP PO, Phone BS PR, KR Ankleshwar-9 EA
Kararvel P(2) ,Ac ,O CHW T, W, HP PO BS PR,KR Ankleshwar-12 EA
Avadar P(2) ,Ac -(-5 Kms) T, W, TK PO BS PR ,KR Ankleshwar-10 EA
Piprod P(2), O PHS W PO BS PR, KR Ankleshwar-16 EA
Pardi mocha P(2), O CHW T, W -(-5 Kms) BS PR, KR Ankleshwar-16 EA
Sangpor P(3) PHS, CHW T, W PO BS PR, KR Ankleshwar-17 EA
Valia
Kondh P(4), H, O PHS, D, FPC,
RP, CHW T, W PO BS PR, KR Ankleshwar-12 EA
Vatariya P(2) CHW W PO, Phone BS PR, KR Ankleshwar-15 EA
Naldhari P(2) CHW W , TK -(-5 Kms) BS PR, KR Ankleshwar-18 EA
Hirapor P(4) CHW T ,W -(-5 Kms) BS PR, KR Ankleshwar-24 EA
Valia
P(5), H, PUC, I, Tr
H, MCW, MH, CWC, D, O, RP, CHW, FPC, TB
T , W PTO, Phone BS PR, KR Ankleshwar-22 EA
Dholgam P(6) PHS, CHW T, W PO BS PR, KR Ankleshwar-27 EA
Bhilod P(4) PHS, RP,
CHW T, W, HP, R PO BS PR Ankleshwar-30 EA
Vagadkhol P(2) CHW T, W, HP ,R PO BS PR, KR Ankleshwar-27 EA
(Courtesy: Census Dept., GOI)
23
ABBREVIATIONS
1. Education
P-Primary Elementary School
H-Matriculation or Secondary
O-Other Educational Institution
PUC-Higher Secondary/Intermediate/pre-University/junior Collage
AC – Adult literacy class
TR – Training center
2. Medical Facilities
RP-Registered Private Practitioner
PHS-Primary Health Centre
FPC-Family Planning Centre
D- Dispensary
CHW - Community Health Worker/Health Worker
H - Hospital
NH - Nursing Home
MH - Maternity Home
PHC - Public Health Centre
CWC - Child Welfare Centre
TB - T.B Clinic
O - Others
3. Drinking Water
T-Tap Water
HP-Hand Pump
TK-Tank Water
W-Well Water
R-River Water
C-Canal
N - Nallah
S - Spring
4. Post & Telegraph
PO-Post Office
PTO-Post & Telegraph
Phone-Telephone Communication
24
5. Transportation
RS- Railway Station
BS-Bus Station
NW-Navigable Waterway
6. Approach to Village
PR-Pucca Road
KR-Kuccha Road
7. Power Supply
EA-Electricity for all purposes
EAG - Electricity for Agriculture
ED - Electricity for domestic
EO - Electricity for other purpose like Industrial, Commercial etc.
6.0 Proposed Infrastructure
Total Plot Area: 53997 m2
Well developed infrastructure is already available in the area.
6.1 Green Belt
Total 53997 m2 land area is available at site; out of this 16467 m2 (i.e. approx 31 % of total
area) shall be developed as greenbelt and other forms of greenery.
6.2 Social Infrastructure
Depending on the growth of the company the required social infrastructure will be provided.
6.3 Connectivity (Traffic and Transportation Road/ Rail/Metro/ Water ways etc)
Site is very well connected by road & railway.
6.4 Drinking water Management (Source & Supply of water)
Total water requirement shall meet through GIDC supply.
25
6.5 Sewerage System
Sewage pipes would be laid in entire company for the removal and disposal of mainly non-
harmful liquid wastes from the offices, canteen and domestic waste coming from different
section of plant. These liquid wastes would be disposed by septic tank & soak pit.
6.6 Solid Waste Management
Please refer Form-I, Annexure-V.
6.7 Power Requirement & Supply/Source
Please refer Section 3.8 of this report.
7.0 Rehabilitation and Resettlement (R & R) Plan
7.1 Policy to be adopted (central/state) in respect of the project affected including
home oustees, land oustees and landless laborers (a brief outline to be given)
There is no habitation on the project land and it is existing industry which is purchased from
GIDC for development of company, so R & R policy is not applicable to this project.
There shall not be displacement of any population in project area. Any major activity that
may lead to resettlement of the people is considered as permanent impact. Hence, there is
no permanent impact on this account. The increasing industrial activity will boost the
commercial and economical status of the locality up to some extent.
8. Project Schedule & Cost Estimates
8.1 Likely date of start of construction and likely date of completion (Time schedule
for the project to be given).
This is an expansion project. Construction activity will start after getting Environmental
Clearance from SEIAA, Gandhinagar and Consent to Establish from GPCB, Gandhinagar.
8.2 Estimated Project cost along with analysis in terms of economic viability of the
project.
Total Project Cost is Rs. 40 Crores.
26
9. Analysis of Proposal (Final Recommendations)
9.1 Financial and social benefits with special emphasis on the benefit to be local
people including tribal population, if any, in the area.
• Employment would be as per prevailing norms of state government for skilled and
unskilled people for the proposed expansion project.
• Social Welfare shall be done.
• Cordial relation with the industry shall be established and representation shall be made
to villagers for help for creation of facilities related to health, education, etc.