· web viewquality quality quality risk risk risk organization organization organization change...

246
Introduction and Principles 1. 1 PURPOSE OF PRINCE2 ® MANUAL The PRINCE2 ® manual aims to answer the frequently asked questions on project management and project support. PRINCE2 (Projects in a Controlled Environment) is a structured _______________________________________ method based on experience drawn from thousands of projects. 1.2 THE IMPORTANCE OF PROJECTS Projects are the means by which we introduce change. A key challenge for organizations is to succeed in balancing two parallel, competing imperatives: o To ___________________ current business operations o To ___________________ business operations in order to survive and compete in the future – business change. 1.3 WHAT MAKES PROJECTS DIFFERENT? Characteristics of a project that distinguish it from business as usual are: o Change o Temporary o Cross-functional o Unique o Uncertainty © 2010 PROJstudy.com 1 Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC. PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries. The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Upload: nguyenhuong

Post on 30-Jun-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

Page 1:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Introduction and Principles

1. 1 PURPOSE OF PRINCE2® MANUAL

The PRINCE2® manual aims to answer the frequently asked questions on project management and project support.

PRINCE2 (Projects in a Controlled Environment) is a structured _______________________________________ method based on experience drawn from thousands of projects.

1.2 THE IMPORTANCE OF PROJECTS Projects are the means by which we introduce change.

A key challenge for organizations is to succeed in balancing two parallel, competing imperatives:

o To ___________________ current business operations

o To ___________________ business operations in order to survive and compete in the future – business change.

1.3 WHAT MAKES PROJECTS DIFFERENT?

Characteristics of a project that distinguish it from business as usual are:

o Change

o Temporary

o Cross-functional

o Unique

o Uncertainty

A project is a ____________________________________ organization that is created for the purpose of delivering one or more business products according to an agreed _________________________________.

© 2010 PROJstudy.com 1Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 2:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Introduction and Principles

1.4 WHY HAVE A PROJECT MANAGEMENT METHOD? Project management is the _______________________________,

___________________________, __________________________ and ________________________________ of all aspects of the project, and the motivation of those involved.

It is the development of the project's ________________________________ (known as _________________________ in PRINCE2) that deliver the project's results.

Purpose of project management is to keep control over the _________________________________________ work required to create the project's _________________________________.

Implementing a secure, consistent, well-proven approach to project management is a valuable business investment.

1.5 INTRODUCING PRINCE2

PRINCE2 is a non-proprietary method

It is one of the most widely accepted methods for managing projects.

It is truly __________________________________: can be applied to any project

It isolates the _______________________aspects of project work from the _____________________________________________contributions.

1.5.1 What does a Project Manager do?

It is the Project Manager’s responsibility to _____________________________________ how well the work in progress matches the project ______________________________.

1.5.2 What is it we wish to control?

There are __________________________ variables involved in any project, and therefore six __________________________________ of project performance to be managed.

© 2010 PROJstudy.com 2Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 3:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Introduction and Principles

The six variables (aspects) of a project that we wish to control are:

o Time T

o Cost C

o Quality Q

o Scope S

o Risk R

o Benefit B

PRINCE2 is an integrated framework of ________________________________ and ______________________________ that addresses the planning, delegation, monitoring and control of all these six aspects of project performance.

1.5.3 The structure of PRINCE2 The principles: These are the

________________________________________________ and good practices which determine whether the project is genuinely being managed using PRINCE2.

The themes: These describe ________________________________________ of project management that must be addressed ____________________________________ and in parallel throughout the project.

The processes: Describe a ___________________________________ progression through the project lifecycle, from getting started to project __________________________________________.

Tailoring PRINCE2 to the _____________________________ environment

© 2010 PROJstudy.com 3Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 4:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Introduction and Principles

Figure 1.2, Managing Successful Projects with PRINCE2, page 6“©Crown copyright 2009 Reproduced under licence from OGC”

1.6 RELATED OGC GUIDANCE1.6.1 What PRINCE2 does not provide

Specialist aspects Detailed techniques Leadership capability

1.7 BENEFITS OF PRINCE2 The key benefits of adopting PRINCE2:

o Best practice and governance for project managemento It can be applied to any type of projecto PRINCE2 is widely recognized and understoodo It provides for the explicit recognition of project

________________________________________.o Its ______________________________ focus clarifies what a project

will delivero PRINCE2 ____________________________ are carefully designed to

meet the needs of the different levels in the management team

© 2010 PROJstudy.com 4Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 5:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Introduction and Principles

o It is based on a 'management by ______________________________’ framework that efficient and economic use of project management time

o PRINCE2 ensures that participants focus on the _________________________________ of the project in relation to its _______________________________________ objectives

o It defines a thorough but __________________________________structure of reports

o It ensures that _________________________________________ are properly represented in planning and decision making

o It promotes learning and continual improvement in organizationso It promotes consistency of project work and the ability to reuse project

assetso It facilitates the _________________________________________

and assessment of project worko There are scores of accredited training and consultancy organizations

(ATOs and ACOs) who can supply expert support for PRINCE2 projects or for organizations planning to adopt PRINCE2

© 2010 PROJstudy.com 5Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 6:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Introduction and Principles

Questions

Sl. No Question Answer1. Organizations must aim to achieve a balance

between business as usual and _______ _______.

2. According to PRINCE2, the means through which business change can be introduced by an organizations is:

Project Relocation Business operation

3. Which of the following is not a feature that distinguishes a project from business as usual?

Change Temporary Cross-functional Continuous production

4. Which of the following is NOT a project variable that one wishes to control while managing a project?

Cost Quality Scope Employee benefits

5. The seven PRINCE2 ________ explain the specific treatment required by PRINCE2 for various project management disciplines and why they are necessary.

6. Which of the following is considered to be outside the scope of the PRINCE2 method?

Specialist aspects of a project Scope of a project Organization that is carrying out the

project Product quality

© 2010 PROJstudy.com 6Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 7:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Introduction and Principles

2. PRINCE2 Principles

Principles are characterized as universal, self-validating, and empowering.

They provide a framework of good practice for those people involved in a project. If a project does not adhere to ___________________________________________, it is not considered as being managed using PRINCE2.

The seven PRINCE2 principles can be summarized as:

o Continued business justification B

o Learn from experience E

o Defined roles and responsibilities R

o Manage by stages S

o Manage by exception E

o Focus on products P

o Tailor to suit the project environment T

2.1 CONTINUED BUSINESS JUSTIFICATION

There must be a ________________________________ for a PRINCE2 project to begin. The _______________________________ must remain ____________________________ throughout the life of the project. The justification is documented and approved.

The justification is documented in _____________________________________.

Organizations that lack rigour in developing __________________________________________ may find that some projects proceed even where there are few real benefits or where a project has only tentative associations with corporate strategy.

__________________________________ and evolving _________________________________ should remain consistent.

If, for whatever reason, the project can no longer be justified, the project should be stopped.

© 2010 PROJstudy.com 7Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 8:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Introduction and Principles

2.2 LEARN FROM EXPERIENCE

PRINCE2 project teams learn from previous experience: lessons are sought, recorded and acted upon throughout the life of the project.

In PRINCE2 learning from experience permeates the method at various stages as given below:

o When a project starts, lessons learned from previous or similar projects must be analysed to see if they could be applied to the current project.

o As the project progresses, lessons should be learned from the project to see if they can be applied to achieve improvements.

o As the project closes, lessons learned from the project must be passed on for future projects.

2.3 DEFINED ROLES AND RESPONSIBILITIES

A PRINCE2 project has defined and agreed _______________________ and ___________________________ within an organization structure that engages the ________________________, __________________________ and _____________________________________ stakeholder interests.

For a project to succeed, right people should be involved in a project and they know what's expected of them or what to expect of others.

A project is typically _____________________________________. To be successful, projects must have an explicit

______________________________________________ structure. ‘_______________________________’ sponsors endorse the objectives

and ensure that the business investment provides value for money. ‘_______________________________’ use the products to gain the

intended benefits. ‘_________________________________’ provide the resources and

expertise. A defined project management team structure provides the answer to the

question, ’What is expected of me?’

2.4 MANAGE BY STAGES

A PRINCE2 project is planned, monitored and controlled on a ___________________________________________ basis.

______________________________________________ provide senior management with ____________________________________________ at major intervals throughout the project.

© 2010 PROJstudy.com 8Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 9:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Introduction and Principles

Shorter stages offer more control, while longer stages reduce the burden on senior management

PRINCE2 overcomes the planning horizon issue.

A PRINCE2 project must have a minimum of ________________ ________________________ stages: one _______________________ and one or more further management stages.

2.5 MANAGE BY EXCEPTION

A PRINCE2 project has defined _______________________________ for each project ____________________________________ to establish limits of delegated authority.

In PRINCE2, authority is delegated from one management stage to the next by setting of tolerances against the following six objectives for the respective level of the plan:

o Cost

o Timescale

o Quality

o Scope

o Risk

o Benefits

Implementation of ‘______________________________________________________’ provides for very efficient use of senior management time as it reduces senior managers’ time burden without removing their control by ensuring decisions are made at the right level in the organization.

2.6 FOCUS ON PRODUCTS

A PRINCE2 project focuses on the definition and delivery of products, in particular their __________________________________ requirements.

A successful project is ______________________________________, not activity-oriented.

© 2010 PROJstudy.com 9Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 10:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Introduction and Principles

_______________________________________________ define the purpose and quality criteria of each product.

Without a product focus, projects are exposed to several major risks such as acceptance disputes, and ‘scope creep’.

2.7 TAILOR TO SUIT THE PROJECT ENVIRONMENT

PRINCE2 is tailored to suit the project’s environment, size, complexity, importance, capability and risk.

Tailoring ensures that the project management method relates to the project’s ___________________________________________ and that __________________________________________________ are based on the project’s scale, complexity, importance, capability and risk.

© 2010 PROJstudy.com 10Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 11:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Introduction and Principles

Questions

Sl. No Question Answer1. If a project does not adhere to the PRINCE2

__________, then it is not considered as being managed using PRINCE2.

2. Which of the following is not a PRINCE2 principle?

Continued business justification Defined roles and responsibilities Tailoring the operations to suit the

PRINCE2 method3. The PRINCE2 principles are derived from:

Application of PRINCE2 processes in projects

Lessons learned from successful and unsuccessful projects

Lessons learned from successful projects4. Justification for a PRINCE2 project is

documented in: Business Case Project Brief Project Initiation Documentation

5. Who are the three primary stakeholders of a project?

6. A PRINCE2 project must have at least _____ management stages.

7. Which of the following PRINCE2 principles ensures that a PRINCE2 project has accountability within the project team?

Manage by exception Continued business justification Focus on product Learn from experience

8. Which of the following PRINCE2 principles ensures that a PRINCE2 project has an explicit project management team structure?

Manage by stages Learn from experience Focus on product Defined roles and responsibilities

9. Which of the following PRINCE2 principles ensures that a PRINCE2 project takes all the customer quality requirements into consideration?

Tailor to suit the project environment Continued business justification Focus on product

© 2010 PROJstudy.com 11Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 12:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Introduction and Principles

Defined roles and responsibilities10. Which of the following PRINCE2 principles

ensures that project management effort and approach are appropriate for the needs of the project?

Continued business justification Focus on product Tailoring PRINCE2 to suit the project

environment Defined roles and responsibilities

© 2010 PROJstudy.com 12Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 13:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Introduction and Principles

Sample TestQuestion

No Answer Comment

1

2

3

4

5

6

7

Chapter TestQuestion

No Answer Comment

1

2

3

4

5

6

7

8

9

10

11

12

© 2010 PROJstudy.com 13Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 14:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Introduction and Principles

Case Study Format Questions

1. Which two of the following are justifiable reasons for an organization to close a project prematurely?A. Viable Business Case no longer exists.B. A more profitable project is in the pipeline.C. Expected benefits of the project have decreased D. Justification for the project has changed.E. Justification for the project has changed but the project and its evolving justification are not consistent.

Correct Answer: A and E.

Justification:If, for whatever reason, the project can no longer be justified, the project should be stopped. Stopping a project in these circumstances is a positive contribution to an organization as its funds and resources can be reinvested in other more worthwhile projects.Although the justification should remain valid, it may change. It is therefore important that the project and evolving justification remain consistent.Reference: Managing Successful Project with PRINCE2, page 11

2. According to the PRINCE2 method, which two of the following are essential requirements for a project to be successful?A. Explicit project management team structure with well-defined and agreed roles and responsibilitiesB. Day-to-day line management structureC. Effective communication among project team membersD. At least two of the three primary stakeholder interests must be effectively represented in the project management team.E. Implementation of all the lessons identified from previous similar projects.

Correct Answer: A and C

Justification:Options A and C: To be successful, projects must have an explicit project management team structure consisting of defined and agreed roles and responsibilities for the people involved in the project and a means for effective communication between them.Option B: The management structures of the parties involved in the project are likely to be different – with different priorities, objectives and interests to protect. The day-to-day line management structures may not be designed for, or suited to, project work.Option D: All three stakeholder interests need to be represented effectively in the project management team – two out of three is not enough.Reference: Managing Successful Project with PRINCE2, page 12

© 2010 PROJstudy.com 14Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 15:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Introduction to PRINCE2 Themes

3.1 WHAT ARE THE THEMES?

The PRINCE2 themes describe ______________________of project management that must be addressed ____________________.

Table 3.1 The PRINCE2 themesTheme DescriptionBusiness Case This theme addresses _________________the idea is

developed into a viable _________________________for the organization and how _______________________maintains the focus on the organization’s objectives throughout the project.

Organization This theme describes the _________________ in the PRINCE2 project management team required to manage the project effectively

Quality This theme explains how the outline is developed so that all participants understand the ________________attributes of the ________________to be delivered

Plans This theme complements the ______________________theme by describing the steps required to develop plans and the PRINCE2 techniques that should be applied.PRINCE2 projects proceed on the basis of a series of approved plans.

Risk This theme addresses how project management manages the _______________________in its _____________.

Change This theme describes how project management assesses and acts upon issues which have a potential impact on any of the baseline aspects of the project.

Progress This theme addresses the on-going viability of the plans. The theme explains the decision-making process for approving plans, the monitoring of actual performance and the escalation process if events do not go according to plan.

Mnemonic to remember the Themes is “COQPRCP”

© 2010 PROJstudy.com 15Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 16:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Introduction to PRINCE2 Themes

3.2 APPLYING THE THEMES

All seven themes must be applied in a project but they should be __________________________________ according to the scale, nature and complexity of the project concerned. 3.3 FORMAT OF THE THEMES

Purpose

Theme defined

The PRINCE2 approach to the theme

Responsibilities

© 2010 PROJstudy.com 16Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 17:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Introduction to PRINCE2 Themes

Questions

Sl. No

Question

1 Plans theme complements which of the following PRINCE2 themes by describing the steps required to develop plans and the PRINCE2 techniques that should be applied?

Organization Business Case Quality Risk

2 The __________ theme describes the roles and responsibilities in the PRINCE2 project management team required to manage the project effectively.

3 PRINCE2 projects proceed on the basis of a series of approved _____.

4 PRINCE2 treats each of the seven themes specifically in order to _______ them.

5 Which PRINCE2 theme ensures that there is an escalation process in place if things do not go according to the project plan?

© 2010 PROJstudy.com 17Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 18:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Introduction to PRINCE2 Themes

Case Study Format Question

1) Which of the following statements on PRINCE2 theme/s are true?

A) PRINCE2 themes address all the aspects of project management that must be addressed throughout the life of a project.B) The Plans theme addresses the aspects of the project that enable the project management to focus on the objectives of the commissioning organization.C) The Quality theme addresses the uncertainties in a project’s plans and in the wider project environment.D) The Risk theme addresses the on-going viability of the project’s plans.E) The PRINCE2 themes can be modified or altered to suit the scale and nature of the project.

Correct Answer: A and E

Justification:

Option A: This option is correct. The PRINCE2 themes describe aspects of project management that must be addressed continually.Option B: This option is incorrect. The Business Case theme addresses the aspects of the project that enable the project management to focus on the objectives of the commissioning organization. Option C: This option is incorrect. The Risk theme addresses the uncertainties in a project’s plans and in the wider project environment.Option D: This option is incorrect. The Progress theme addresses the on-going viability of the project’s plans.Option E: This option is correct. All seven themes must be applied in a project but they should be tailored according to the scale, nature and complexity of the project concerned.Reference: Managing Successful Projects with PRINCE2, pages 17 and 18

© 2010 PROJstudy.com 18Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 19:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Introduction to Processes

11.1 The PRINCE2 processes

It takes one or more defined inputs and turns them into defined outputs.

There are _________________________ processes in PRINCE2, which provide the set of activities required to direct, manage and deliver a project successfully. The PRINCE2 processes are:

o Starting up a Project So Directing a Project Do Initiating a Project Io Controlling a Stage Co Managing Product Delivery Po Managing a Stage Boundary Bo Closing a Project C

11.2 The PRINCE2 journey

11.2.1 Pre-project The trigger for the project could be almost anything.

In PRINCE2, this trigger is called a ________________________________.

Prior to the activity to fully scope the project, it is important to verify that the project is worthwhile and viable. Such activities are covered by the process ______________________________________________ which culminates in the production of a _____________________________________ and a Stage Plan for project initiation.

The ___________________________________________ reviews the Project Brief and decides whether to initiate the project, and states the levels of authority to be delegated to the Project Manager for the initiation stage.

11.2.2 Initiation stage Once there is a decision to go ahead with the project, it needs to be planned

in detail. Funding needs to be obtained and controls should be defined to ensure that

the project proceeds in accordance with the wishes of those people paying for the project and those who will make use of what the project delivers.

The detailed planning, establishment of the project management strategies and controls, development of a robust Business Case, and a means of reviewing benefits are covered by the _______________________________________________ process

The initiation stage culminates in the production of the _______________________________________________, which is reviewed by the Project Board

© 2010 PROJstudy.com 19Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 20:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Introduction to Processes

11.2.3 Subsequent delivery stages The Project Board delegates day-to-day control to the

_________________________________ on a stage-by-stage basis. The Project Manager ensures that a set of project records are maintained to assist with progress control.

The Project Manager informs the _______________________________ of progress through regular Highlight Reports.

In the _______________________________________________ process, the Team Manager(s) or team members execute assigned Work Packages and keep the Project Manager apprised of progress via Checkpoint Reports.

Towards the end of each management stage, the Project Manager requests permission to proceed to the next stage by reporting how the stage performed, providing an update to the ____________________________________ and planning the next management stage in detail.

The activities to manage each stage boundary are covered in the ___________________________________________________ process.

11.2.4 Final delivery stage As a project is a temporary undertaking, during the final stage it is time to

decommission the project.

The project should be assessed for performance against its original plan and the resources assigned to the project need to be released.

The closure activities are planned and approved as part of the stage approval for the final stage; therefore the ____________________________________________ process takes place in the final stage.

Figure 11.1 Managing Successful Project with PRINCE2, page 113“©Crown copyright 2009 Reproduced under licence from OGC”

© 2010 PROJstudy.com 20Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 21:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Introduction to Processes

Stages in a PRINCE2 Project

The first plan prepared in a PRINCE2 project is Initiation Stage plan.

11.4 The structure of the process chapters in the PRINCE2 manual

PRINCE2 processes comprise a set of activities.

PRINCE2 activities comprise a set of recommended actions designed to achieve a particular result.

The relationship between processes, activities and actions is shown in Figure 11.3.

Figure 11.3 Managing Successful Project with PRINCE2, page 116

© 2010 PROJstudy.com 21Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 22:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Introduction to Processes

“©Crown copyright 2009 Reproduced under licence from OGC”Management Products

Management products are information sets used by the PRINCE2 processes to enable certain roles to take action and/or make decisions. Most of the baseline products evolve during pre-project and initiation stage activities. The baseline products are reviewed and (possibly) updated at the end of each stage. There are three types of management product: baselines, records and reports.

1) Baseline management products are those that define aspects of the project and, once approved, are subject to change control. These are:

Benefits Review Plan Business Case Communication Management Strategy Configuration Management Strategy Plan (covers Project, Stage and, optionally, Team Plans) Product Description Project Brief Project Initiation Documentation Project Product Description Quality Management Strategy Risk Management Strategy Work Package.

2) Records are dynamic management products that maintain information regarding project progress. These are:

Configuration Item Records Daily Log Issue Register Lessons Log Quality Register Risk Register.

3) Reports are management products providing a snapshot of the status of certain aspects of the project. These are:

Checkpoint Report End Project Report End Stage Report Exception Report Highlight Report Issue Report Lessons Report Product Status Account.

© 2010 PROJstudy.com 22Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 23:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Introduction to Processes

Section 1 – Questions

Sl. No Question1. Which process is used by both the directing and

managing levels?2. In PRINCE2, the trigger for the project is called

as _____________.3. For complex or lengthy initiations, which two

processes can be used optionally to manage the initiation stage?

4. What is the minimum number of management stages required in PRINCE2?

5. In the Managing Product Delivery process, the Team Manager(s) or team members execute assigned ______________________________ (a) and keep the Project Manager apprised of progress via ___________________________ (b).

6. Which process is used to request Project Board’s approval of the Stage Plan?

7. The Project Manager informs the Project Board of progress through regular ________________________________.

Case Study Format Question:

1. Which two of the following statements on Managing a Stage Boundary process are true?

A. It is first used at the end of the initiation stage B. It is repeated at the end of each subsequent stage C. It is used to prepare Exception PlansD. It is used to request Project Board approval to initiate the project E. It is used by both the directing and managing levels

Correct Answer: A, CJustification:

Starting up a Project is used by both the directing and managing levels Managing a Stage Boundary is first used at the end of the initiation stage and

repeated at the end of each subsequent stage except the final stage. It is also used to prepare Exception Plans, which can be done at any time including in the final stage.

At the end of the initiation stage, the Initiating a project process is used to request Project Board approval to initiate the project (with the submission of the Project Initiation Documentation) and in parallel the Managing a Stage Boundary process is used to request Project Board approval of the Stage Plan for the second management stage.

Reference: Figure 11.1 Managing Successful Project with PRINCE2, page 113 Figure 11.2 Managing Successful Project with PRINCE2, page 115

© 2010 PROJstudy.com 23Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 24:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Organization

Section 1 (5.1 to 5.3.1)

5.1 PURPOSE The purpose of the Organization theme is to define and establish the project’s

structure of __________________________ and _____________________________.

5.2 ORGANIZATION DEFINED 5.2.1 Project

PRINCE2 defines a project as ‘a __________________organization that is created for the purpose of delivering one or more business products according to an agreed __________________________________.

5.2.2 Programme A programme is a temporary flexible organizational structure created to

coordinate, direct and oversee the implementation of a set of ______________________________ and activities in order to deliver outcomes and benefits related to the organization's strategic objectives.

5.2.4 Roles and jobs PRINCE2 does not define management jobs. It defines roles, each of which is

defined by an associated set of responsibilities. Roles might be shared or combined according to the project's needs.

5.2.5 Three project interests For completeness Project Board should include representation from each of

the___________________, _________________________and ___________________________interests at all times.

Reference: Managing Successful Projects with PRINCE2, page 32“©Crown copyright 2009 Reproduced under licence from OGC”

© 2010 PROJstudy.com 24Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 25:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Organization

Businesso The products of the project should meet a business need which will

justify the investment in the project. The project should also provide______________________________________.

o The __________________________________role is defined to look after the business interests.

Usero The user viewpoint should represent those individuals or groups for

whom some or all of the following will apply: They will use the outputs of the project to realize the benefits after

the project is complete. They will operate, maintain or support the project's outputs. The outputs of the project will impact them.

o The__________________________ will represent the users’ interest on the Project Board. Supplier

o The supplier view point should represent those who will provide the necessary skills and produce the_____________________________. The project may need to use both in-house and external supplier teams to construct the project product.

o The Senior Supplier(s) will represent this stakeholder interest on the Project Board.

o The level of overlap between the interests of the business, user and supplier will change according to the type of ____________________________and__________________________.

o ‘Customer’ can usually be interpreted as a collective term for the business and user interests.

5.3 THE PRINCE2 APPROACH TO ORGANIZATION 5.3.1 Levels of organization

Reference: Managing Successful Projects with PRINCE2, page 33“©Crown copyright 2009 Reproduced under licence from OGC”

© 2010 PROJstudy.com 25Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 26:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Organization

A PRINCE2 project has defined and agreed roles and responsibilities within an organization structure that engages the business, user and supplier stakeholder interests.

To be successful, projects must have an explicit project management team structure consisting of defined and agreed roles and responsibilities for the people involved in the project and a means for effective communication between them.

The four levels of management are: Corporate or programme management: This level sits outside the project

management team but is responsible for ____________________________the project, including identifying the __________________________and defining the project-level ________________________________________.

Directing: The __________________________ is responsible for the overall direction and management of the project within the constraints set out by corporate or programme management.

Managing: The ______________________________ is responsible for the day-to-day management of the Project within the constraints set out by the Project Board.

Delivering: ________________________________ is responsible for delivering the project's products to an appropriate quality within a specified timescale and cost.

© 2010 PROJstudy.com 26Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 27:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Organization

Section 1 - Questions

Sl. No Question1. The purpose of the Organization theme is to

define and establish the project’s structure of ____________ and responsibilities.

2. Is the following statement true?Project is a permanent organization that is created for the purpose of delivering one or more business products according to an agreed Business Case.

3. Whose role is defined to take care of the business interests?

4. Who provides the necessary skills to produce the project product?

5. What are the factors that change the level of overlap between the interests of the business, user and supplier?

6. Who is responsible for the overall direction and management of the project within the constraints set out by corporate or programme management?

7. Who is responsible for the day-to-day management of the Project within the constraints set out by the Project Board?

© 2010 PROJstudy.com 27Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 28:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Organization

Section 2 (5.3.2 – 5.3.2.9)

5.3.2 The project management teamProject management team structure

The_____________________ and _____________________ roles can often be combined, e.g., in an in-house project involving creation of employee identification system, the roles of the Executive and the Senior User can be combined. In such cases, to avoid any conflict, two individuals could be appointed to carry out________________________, one looking after the user interests and the other representing the business interests.

Some of the PRINCE2 responsibilities cannot be shared or delegated if they are to be undertaken effectively. For example:

o The _______________________ and _______________________ roles cannot be shared. The Executive cannot also be the ____________________ and there cannot be more than _________________ Executive or Project Manager.

o The ___________________ and ______________________ decision-making accountability cannot be delegated.

Project Board An effective Project Board should display four key characteristics:

o Authorityo Credibilityo Ability to delegateo Availability

Size of the Project Board It is a good practice to keep the size of the Project Board as small as possible.

Executive The __________________________ is appointed by corporate or programme

management during the pre-project process of Starting up a Project. The role of the Executive is vested in one individual, so that there is a single point of accountability for the project.

Senior User

The Senior User role commits user resources and monitors products against requirements. This role may require more than ________________________ person to cover all the user interests.

Senior Supplier This role is accountable for the __________________ delivered by the

supplier(s) and is responsible for the technical integrity of the project.

© 2010 PROJstudy.com 28Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 29:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Organization

Project Assurance The ________________ is responsible, via its Project Assurance role, for

monitoring all aspects of the project's performance and products independently of the Project Manager.

If necessary, the Project Board can delegate its Project Assurance role to another group.

Change Authority It is the ______________________ responsibility to agree to each potential

change before it is implemented.

Project Manager In a PRINCE2 environment the Project Manager role ___________________

be shared. The Project Manager will normally come from the customer corporate

organization. The Project Manager is responsible for the work of all the PRINCE2

processes except for the___________________ , and appointing the Executive and the Project Manager in the pre-project process Starting up a Project.

The Project Manager manages the Team Managers and Project Support, and is responsible for liaison with Project Assurance and the Project Board.

The Executive will appoint the Project Manager if not done by the corporate or programme management.

Team Manager The Team Manager's primary responsibility is to ensure production of those

products allocated by the _________________. PRINCE2 uses Work Packages to allocate work to Team Managers or team

members. The structure of the project management team does not necessarily reflect

line function or seniority but represents roles on the project.

Project Support Project Support is the responsibility of the______________________. If required, the Project Manager can delegate some of his work to a Project

Support role: this may include providing administrative services or advice and guidance on the use of project management tools or configuration management.

Project Support can also provide specialist functions to a project such as planning or ___________________.

Project Support defaults to the Project Manager if it is not otherwise allocated. Project Support and Project Assurance roles should be kept separate in order

to maintain the independence of _________________________.

© 2010 PROJstudy.com 29Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 30:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Organization

Dealing with changes to the Project Management Team The use of ___________________ and ____________________can help to

ensure that any hand over procedure is thorough. A ________________________ provides an opportunity to hand over the role

during the project. Communication Management Strategy (For composition, refer appendix A, p.239 of the manual.)

The frequency, means and detail of communication between the project and the project’s stakeholders as required by the Project Board should be documented in the ______________________.

The Communication Management Strategy contains a description of the means and frequency of communication to parties both internal and external to the project.

The ____________________ should be responsible for documenting the Communication Management Strategy during the Initiating a Project process.

It is also important to review and possibly update the Communication Management Strategy at each ______________________in order to ensure that it still includes all the____________________.

When planning the final stage of the project it is also important to review the _________________ to ensure it includes all the parties who need to be advised that the project is closing.

Configuration Management Strategy (For composition, refer appendix A, p.241 of the manual.)

A description of how and by whom the project’s products will be controlled and protected.

The Project Board should define in the ________________________ a scale of severity ratings for requests for change. Depending on the severity the request for change could be handled by:

o Corporate or programme managemento The Project Boardo Delegating to a Change Authorityo Delegating to the Project Manager.

Working with the corporate organizationCentre of excellence

The concept of a ____________________ is that of a central standards unit, which defines standards, and provides skills, training and possibly independent assurance functions to a number of projects.

5.3.5 Working with stakeholdersTypes of Stakeholders

A stakeholder is any individual, group or organization that can affect, be affected by, or perceive itself to be affected by, an initiative (programme, project, activity, risk).

There are likely to be individuals or groups who are not part of the ________________team, but who may need to interact with the project or

© 2010 PROJstudy.com 30Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 31:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Organization

who may be affected by the project’s outcome. So, it important to identify these stakeholders and engage them for the successful completion of the project.

Stakeholder engagement It is usually carried out at the programme level. Six-step procedure for stakeholder engagement:

o Identifying stakeholders (Who?)o Creating and analysing stakeholder profiles (What?)o Defining the stakeholder engagement strategy (How?)o Planning the engagement (when?): Defining the methods and timings of

the communicationso Engaging stakeholders (Do)o Measuring effectiveness (Results)

PRINCE2 Management Levels

© 2010 PROJstudy.com 31Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 32:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Organization

Reporting Structure in PRINCE2

© 2010 PROJstudy.com 32Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 33:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Organization

Section 2 – Questions

Sl. No Question1. Which of the following statements is not true?

A. The Executive and Senior User roles can often be combined.

B. The Project Manager and Executive roles cannot be shared.

C. The Project Manager and Project Board decision-making accountability can be delegated.

2. Who appoints the Executive and when?3. Who monitors products against requirements?4. __________ role is accountable for the quality

of products delivered by the supplier and is responsible for technical integrity of the project.

5. Who is responsible for monitoring all aspects of the project’s performance and products independently of the Project Manager?

6. ‘In a PRINCE2 environment the Project Manager role can be shared’ – True or False?

7. Who is responsible for the role of Project Support?

8. Who is responsible for documenting the Communication Management Strategy during the Initiating a Project process?

© 2010 PROJstudy.com 33Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 34:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Organization

Sample TestQuestion

No Answer Comment

1

2

3

4

5

6

7

8

Chapter TestQuestion

No Answer Comment

1

2

3

4

5

6

7

8

9

10

© 2010 PROJstudy.com 34Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 35:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Organization

Case Study Format Questions:Question 1 contains an assertion statement and a reason statement. For each line identify the appropriate option from among A, B, C, D and E. Each option may be used once, more than once, or not at all.Option Assertion ReasonA True True And the reason explains the assertionB True True And the reason does not explain the assertionC True FalseD False TrueE False False

1. Assertion: The Executive cannot be the Project Manager. Because Reason: The Project Manager and Executive roles cannot be shared.

Correct Answer: A

Justification:The Project Manager and Executive roles cannot be shared. The Executive cannot also be the Project Manager and there cannot be more than one Executive or one Project Manager.Reference: Managing Successful Projects with PRINCE2, page 34

2. Which two of the following are applicable to the Project Manager in a PRINCE2 environment?

A. Accountable for the success or failure of the project in terms of the business, user and supplier interests.

B. Normally comes from the customer corporate organization.C. Responsible for the work of all the PRINCE2 processes.D. In a PRINCE2 environment the Project Manager role can be shared.E. Manages the Team Managers and Project Support, and is responsible for

liaison with Project Assurance and the Project Board

Correct Answer: B, E

Justification: In a PRINCE2 environment the Project Manager role should not be shared. The Project Manager will normally come from the customer corporate

organization. The Project Manager is responsible for the work of all the PRINCE2

processes except for the Directing a Project process, and appointing the Executive and the Project Manager in the pre-project process Starting up a Project.

The Project Manager manages the Team Managers and Project Support, and is responsible for liaison with Project Assurance and the Project Board.

Reference: Managing Successful Projects with PRINCE2, page 38

© 2010 PROJstudy.com 35Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 36:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Business Case

4.1 PURPOSE Business Case establishes ____________________to judge whether the

project is (and remains) desirable, viable and achievable as a means to support decision making in its (continued) investment.

It is a PRINCE2 ____________________that a project must have continued business justification.

The business justification is documented in a Business Case describing the _____________________for the project based on estimated ________________, _______________ and the expected _______________________.

Project justification is based on whether the project is _______________________(the cost/benefit/risk balance), ___________________(the project can deliver the products) and _____________________(the products can provide the benefits).

The __________________ is responsible for specifying the benefits and subsequent realisation of benefits.

The____________________ ensures that those benefits specified by the Senior User(s) represent value for money, are aligned to corporate objectives, and are capable of being realized, e.g. for a project involving production of cars to meet the demand of low-priced cars, the Executive would have to ensure that the investment is viable, i.e., the cars can be low-priced, meet the user requirements and accrue profits, and that the corporate objectives can be met.

The Business Case is developed at the _________________of the project and maintained throughout the life of the project.

4.2 Business Case defined4.2.1 What is a Business Case?Business Case is a management product that provides the justification for an organizational activity (project), which typically contains costs, benefits, risks and timescales, and against which continuing viability is tested. (For Composition, refer Appendix A, p.237 of the manual.)

4.2.2 Outputs, outcomes and benefits Output: project’s ______________ ______________________,

Outcome: result of the change derived from using the project’s products,

Benefit: _________________ ___________________ resulting from an __________________that is deemed an advantage by one or more________________________,

© 2010 PROJstudy.com 36Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 37:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Business Case

Figure 4.2, Managing Successful Projects with PRINCE2, page 22“©Crown copyright 2009 Reproduced under licence from OGC”

4.2.3 Types of Business Case The nature of the project will determine the objectives that will be used to

verify the desirability of the project. The various types of projects are compulsory project, not-for-profit project, evolving project, customer/supplier project, and multi-organization project.

4.3 THE PRINCE2 APPROACH TO THE BUSINESS CASE The Business Case is developed at the beginning of the project and

maintained throughout the life of the project, verified by the Project Board, and confirmed throughout the period that the benefits accrue.

___________________________ means getting the right information upon which decisions can be made.

_____________________________ means assessing whether the project is (still) worthwhile.

___________________________ means to update the Business Case with actual costs.

_______________________________ means assessing whether the intended benefits have been (or will be) realized.

© 2010 PROJstudy.com 37Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 38:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Business Case

Figure 4.3, Managing Successful Projects with PRINCE2, page 23 “©Crown copyright 2009 Reproduced under licence from OGC”

4.3.1 Developing the Business Case The _________________ is responsible for the Business Case.

Development of the Business Case may be delegated.

Whoever is given the task of developing the Business Case, it is important to ensure that they have the appropriate business skills required (for example, understanding the implications of a cash-flow forecast, a profit-and-loss account and a balance sheet).

The ___________________ Business Case is derived from the project ___________________and developed pre-project in the ______________________ process.

The detailed Business Case is derived from the____________ _______________ ______________, the ___________ _____________ and the ________________ Register.

The development of Business Case will be iterative.

4.3.2 Verifying and maintaining the Business Case The Business case should be reviewed to drive the decision making.

It is the responsibility of the________________ to assure the project’s ____________________ that the project remains desirable, viable and achievable at all times. The Executive should not rely on end stage assessments alone to make this judgement and should consult _____________ __________________ to assist.

© 2010 PROJstudy.com 38Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 39:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Business Case

The ___________ _______________ section of the Business Case provides the Project Board with the source of information to verify that the Business Case justifies the authorization or continuation of the project.

4.3.3 Confirming the benefits The approach to confirming benefits is to:

o Identify the _________________

o Select _____________ _____________ that reliably _________________ the benefits

o Collect the ______________________ measures(from which the improvements will be quantified)

o Decide how, when and by whom the ________________ measures will be collected.

The _________ __________________ specifies the benefits and is accountable for benefits realisation.

Benefits Review Plan Defines how and when a measurement of the achievement of the project’s

benefits can be made. If the project is being managed within a programme, this information may be created and maintained at the programme level. (For Composition, refer Appendix A, p.235 of the manual.)

The project’s _________ __________ Plan will use the detailed Business Case to define the scope, timing and responsibility of a number of reviews based on the timing and nature of the expected_______________.

The Benefits Review Plan is first created by the ____________ _____________ in the________________ stage and is submitted to the ___________ _________________ for approval when seeking project________________.

The Benefits Review Plan is updated towards the end of each stage.

The post-project benefits review(s) will involve ________________________ management.

© 2010 PROJstudy.com 39Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 40:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Business Case

For Practitioner Examination:

Relationship between a Programme Business Case and a Project Business Case: The distinction between projects and programmes is that projects typically

produce or change something and are then disbanded. Programmes are typically used to help transform organizations.

The business justification is the reason for the project. In PRINCE2, the business justification is documented in a Business Case describing the reasons for the project based on estimated costs, risks and the expected benefits.

In PRINCE2, the Business Case is developed at the beginning of the project and maintained throughout the life of the project, being formally verified by the Project Board at each key decision point, such as end stage assessments, and confirmed throughout the period that the benefits accrue.

The Business Case drives all decision making by ensuring that the project remains justified and that the business objectives and benefits being sought can be realized.

Projects operating in a programme environment benefit from a number of advantages, and there are a number of ways in which PRINCE2 can be tailored for use within a programme.

The programme will define the standards that the project will need to use when developing the Business Case.

The project Business Case comprises just the details of the budget, a list of benefits (and the benefits tolerance), and a statement as to how the project is contributing to the programme blueprint, with the justification aspects of the project Business Case sitting in the programme Business Case.

The Business Case might be produced and maintained by the programme and even exist in detail prior to initiating the project.

Benefits will be defined, tracked and managed by the programme management team, and the project’s Benefits Review Plan will be part of the programme’s benefits realization plan.

(End of Practitioner Section)

4.3.4 The contents of a Business Caseo A business Case typically contains: An executive summary, Reasons,

Business options, Expected benefits, Expected dis-benefits, Timescale, Costs, Investment appraisal, Major risks.

Reasons The reasons for the requirement of the project are likely to be defined in the

project ____________________.Business options

There are __________________basic business options concerning any investment.

____________________ should always be the starting option. Other options are ‘do something’ and ‘do the minimum’.

Expected benefits

© 2010 PROJstudy.com 40Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 41:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Business Case

To assess the improvements after project completion, it is necessary to define the current status of each benefit in quantifiable terms.

Benefits can be ________________ and ___________________l.

The Senior User is responsible for the set of benefits within their respective areas.

The list of expected benefits will influence the set of _________________ that the project will provide.

As much as possible benefits should be expressed in tangible ways.

The quantification of benefits enables benefit _______________ to be set. There are many ways to verify the expected benefits. For example, 1) __________________ analysis,2) Three views on the achievement of the benefits, 3) Building into the cost an allowance for estimating inaccuracies, changes and risks should be built into the costs.

Costs The costs should include details of the on-going ________________ and

___________________ costs and their funding arrangements.

Investment appraisalInvestment appraisal techniques:o Through-life costso Net benefitso Return on investment (ROI) Payback periodo Discounted cash flowo Net present valueo Sensitivity analysis

© 2010 PROJstudy.com 41Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 42:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Business Case

QuestionsSl. No Question

1. In PRINCE2, the viability of the project is determined by analyzing which of the following?

Project Plan Business Case Project Benefits Highlight Report

2. Who approves or disapproves the outline Business Case that is developed in the Starting up a Project process?

3. To whom among the following can the Project Board assign the work of assisting the development of Business Case?

Project Assurance Senior User Senior Supplier Project Support

4. What are the three basic investment options In PRINCE2?

5. Who among the following can define a benefit as intangible?

Senior User Senior Supplier Project Manager Project Assurance

6. Whom among the following can the Executive use to verify the viability of the Business Case?

Project Support Team Manager Project Assurance Senior Supplier

© 2010 PROJstudy.com 42Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 43:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Business Case

© 2010 PROJstudy.com 43Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

7. Who among the following is responsible for ensuring that benefits reviews are planned and executed?

Project Manager Executive Team Manager Senior Supplier

8. Who should report the benefits that are measurable during the life of the project?

9. Which of the following will provide information that can be documented under the ‘Reasons’ section of the Business Case?

Project Mandate End Stage Report Initiation stage plan

10. According to PRINCE2, which of the following business options is the starting option that provides basis for quantifying other options?

Do something Do nothing Do the minimum

11. A dis-benefit is an outcome that is perceived as _______ (a) by one or more ___________ (b).

Page 44:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Business Case

Sample TestQuestion

No Answer Comment

1

2

3

Chapter TestQuestion

No Answer Comment

1

2

3

4

5

6

7

8

9

© 2010 PROJstudy.com 44Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 45:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Business Case

Case Study Format Questions

Column 1 is a list of true statements. Column 2 is a selection of headings. For each statement in column 1, select from column 2 the heading under which it should be recorded. Each selection from column 2 can be used once, more than once or not at all.

Column 1 Column 21 Responsible for assuring the project

stakeholders that the project remains desirable and viable at all times.

A. Project Assurance

2 Responsible for approving the outline Business Case.

B. Project Board

3 Responsible for formally verifying the Business Case at every key decision point.

C. Executive

JUSTIFICATION 1 Correct [C] Executive – It is the responsibility of the Executive to assure

the project’s stakeholders that the project remains desirable, viable and achievable at all times.Reference: Managing Successful Projects with PRINCE2, page 23

2 Correct [B] Project Board - The outline Business Case is derived from the Project Mandate and developed pre-project in the Starting up a Project process in order to gain approval from the Project Board in the Directing a Project process to initiate the project.Reference: Managing Successful Projects with PRINCE2, page 23

3 Correct [B] Project Board - In PRINCE2, the Business Case is developed at the beginning of the project and maintained throughout the life of the project, formally verified by the Project Board at each key decision point, such as end stage assessments, and is confirmed throughout the period that the benefits accrue.Reference: Managing Successful Projects with PRINCE2, page 22

© 2010 PROJstudy.com 45Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 46:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Quality

6.1 PURPOSE The purpose of the ________________theme is to

_________________________and __________________the means by which the project will create and verify __________________ that are fit for the purpose.

The _______ ______ _______ principle provides an explicit common understanding of what the project will create. Without product focus, the project would be exposed to major risks.

6.1.1 Quality Approach and Lessons Learnt

The Quality theme covers the implementation of continuous improvement during the project, for example, looking for ways to introduce more efficiency or effectiveness into the management of the project and the project’s products. Capturing and acting on lessons contributes to the PRINCE2 quality approach, as it is a means of achieving continuous improvement.

6.2 QUALITY DEFINED The terminology with respect to _________________________used in

PRINCE2 is derived from the ISO 9000 standards.

6.2.1 Quality ___________________________ is generally defined as the

________________of features and inherent or assigned characteristics of a product that bear on its ability to show that it satisfies _______________________________ or _______________________________.

In PRINCE2, a _________________________ can also be a person, process, service and/or system.

6.2.2 Scope The scope of a plan is defined by the product breakdown structure for the plan

and its associated ____________ ________________.

6.2.3 Quality management and quality management systems: A____________ ________________ system is the complete set of quality

standards, procedures and responsibilities for a site or organization

In the context of a project, 'sites' and 'organizations' are recognised as ______________ or __________________ organization(s) sponsoring the project work.

The 'sites' and 'organizations' are __________________ to the project's temporary organization.

In case more than one permanent organization is involved in a project, each may have its own ______________ ___________ system.

© 2010 PROJstudy.com 46Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 47:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Quality

6.2.4 Quality planning: ____________________ _______________ refers to defining the products

required of the project, with their respective quality criteria, quality methods and the quality responsibilities of those involved.

6.2.5 Quality control __________ ____________ fulfils the requirements for quality and identifies

ways of eliminating causes of unsatisfactory performance by focusing on the activities and the operational techniques used by those involved in the project.

Figure 6.1: The Quality Audit Trail, Managing Successful Projects with PRINCE2, page 49 “©Crown copyright 2009 Reproduced under licence from OGC”

6.2.6 Quality Assurance: Quality __________________________ should ideally be independent of the

project management team.

© 2010 PROJstudy.com 47Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 48:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Quality

Quality Assurance ensures that the project's direction and ___________________________ are adequate for the nature of the project and that it complies with the standards and policies of the _________________________management.

Quality Assurance activities are _____________________the scope of PRINCE2 as it is the responsibility of the ________________________ organization.

Quality Assurance is about independently checking that the organization and processes are in place for quality _______________ and ____________________.

The term 'Quality Assurance' is used in two senses; in both senses of the term, Quality Assurance involves contributions that are independent of the project management team, whereas quality planning and quality control are undertaken by the project.

Quality Assurance should not be confused with _____________ _____________________. Project Assurance refers specifically to the accountability of the _______________________ _______________for assuring that the project is conducted properly. However, Project Assurance and quality assurance do overlap as shown in the following table:

© 2010 PROJstudy.com 48Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 49:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Quality

Table 6.1 Relationship between Project Assurance and Quality Assurance

Project Assurance Quality AssuranceWhat they do.

Provide assurance to the project’s stakeholders that the project is being conducted appropriately and properly.

Provide assurance to the wider corporate or programme organization that the project is being conducted appropriately, properly and complies with relevant corporate or programme management standards and policies.

How they differ Responsibility of the ________ _____, therefore undertaken from within the project.

Responsibility of the ____________management, therefore external to the project.

How they relate

Quality Assurance as a corporate or programme management function could be used by the Project Board as part of its Project Assurance regime.

Quality Assurance would look for effective Project Assurance as one of the indicators that the project is being conducted properly.

6.3 THE PRINCE2 APPROACH TO QUALITY: Identify all the project's products.

Define them in Product Descriptions.

Implement and track the quality methods employed throughout the project

Quality ______________________addresses identification and definition of all the project's products in the Product Descriptions, whereas quality _______________________and quality _______________________address implementation and tracking of quality methods employed throughout the project.

© 2010 PROJstudy.com 49Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 50:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Quality

Section 1: QuestionsSl. No Question Answer

1 Which of the following PRINCE2 principles is central to the PRINCE2 approach to quality?

Continued business justification Tailoring PRINCE2 to project environment Focus on product Management by Stages

2 To estimate project costs and timescales, it is essential to establish the _______ _________ (a) for the products and the ______ __________ (b) activities that need to be included in the project’s plans.

3 In PRINCE2, focus of quality is on the product’s ability to meet its ______________ (b).

4 _________ ________ is defined as the coordinated activities to direct and control an organization with regard to quality.

5 Which of the following best defines Project Assurance? Project Assurance refers to the responsibilities of

the Project Board to assure itself that the project is conducted properly in all respects.

Project Assurance refers to the responsibilities of the Project Board to assure itself that the organization and processes are in place for quality planning and control.

Project Assurance refers to the functions of the Project Board that establish and maintain the quality management system.

Project Assurance refers to the activities of the Project Board to assure itself that the quality requirements adhere to the policies and processes of the corporate management.

6 Identification and definition of all the project's products in the Product Descriptions are addressed by:

Quality planning Quality control Quality assurance

© 2010 PROJstudy.com 50Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 51:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Quality

Section 2 (6.3.1 – 6.4)6.3.1 Quality planning6.3.1.1 The Customer’s Quality Expectations:

The customer’s ______________________expectations are defined and agreed early in the _______________ __________ a Project process.

They are captured in discussions with the customer and then refined for inclusion in the ___________ ____________ __________________.

They should be reviewed at the end of each ___________ _______________.

6.3.1.2 Acceptance criteria: The project's __________ _______________ form a prioritized list of

measurable definitions of the attributes required for a set of products to be acceptable to key ___________________.

Acceptance criteria should be prioritized as this helps if there has to be a trade-off between some criteria.

Example of a prioritization technique – MoSCoW: Each acceptance criterion is rated as either Must have, Should have, Could have or Won't have.

Once finalized in the Project Product Description, acceptance criteria are subject to __________ ___________ and can only be changed with the approval of the ___________ __________________.

6.3.1.3 The Project Product Description

(For Composition, refer Appendix A, p.256 of the manual)

The Project Product Description is created in the _____________ process, refined during the ________________ process, and checked at ___________________.

It is used by the _________________ process as part of verification.

The Project Product Description includes: The overall purpose of the ______________ Its composition The ___________________ quality expectations _____________ criteria, method and responsibilities _______________ quality tolerances

© 2010 PROJstudy.com 51Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 52:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Quality

The approved Project Product Description is included as a component of the ____________________ _____________ and is used to help select the _____________ _______________.

The project approach defines the solution or method to be used by the ________________________ to create the project product.

6.3.1.4 The Quality Management Strategy (For Composition, refer Appendix A, p.257 of the manual.)

A strategy defining the quality techniques and standards to be applied, and the various responsibilities for achieving the required quality levels during a project.

6.3.1.5 Product Descriptions(For Composition, refer Appendix A, p.251 of the manual.)

Once detailed planning gets underway, ____________________ _________________ should be created for all of the project's _________________.

The level of detail aims at providing a secure and appropriate measure of___________________ sufficient to fulfil the customer's _______________ ___________________.

Care should be taken not to write Product Descriptions in too much detail as this can lead to an unnecessary increase in the cost of quality for the project.

Quality Criteria:o The Product Description should include the quality specifications

that the product must meet.

Quality tolerances:o Quality tolerances for a product can be specified in

_____________________by defining an acceptable range of values.

Quality methods:o The quality methods section is used to specify the

_____________ _______________ to be implemented during the development of a product, for review and approval on completion.

© 2010 PROJstudy.com 52Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 53:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Quality

Quality responsibilities:o The three categories of responsibilities related to quality are:

___________________, ______________, _____________________.

6.3.1.6 The Quality Register (For Composition, refer Appendix A, p.258 of the manual.)

A register containing summary details of all planned and complete quality activities. The Quality Register is used by the Project Manager and Project Assurance as part of reviewing progress.

The Quality _____________________ is a diary of the quality events planned and undertaken.

It is created during the ____________________ process.

The Quality register is used by the Project Manager and Project Assurance as part of reviewing progress.

6.3.2 Quality control

6.3.2.1 Quality methods: The cost of correcting flaws in products increases the longer they

remain undetected.

There are two types of quality methods:o 'ln-process’ methods : These are the means by which quality can be 'built

into' the products as they are developed. This involves the use of specialist methods or techniques including calibrated process controls, automation, and quality inspections.

o Appraisal methods : These are the means by which the finished products are assessed for completeness and fitness for purpose. There are two types of appraisal methods: ______________________and _______________________. A quality inspection is a systematic, structured assessment of a product conducted in a planned, documented and organized fashion.

The PRINCE2 Quality Review Technique

o Objectives

a) To assess conformity of the product to the agreed upon quality standardsb) To involve key interested parties in the reviewc) To provide confirmation that product is ready for final approvald) To baseline products for change control>

© 2010 PROJstudy.com 53Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 54:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Quality

o Review team rolesRoles are chair (responsible for overall conduct of the review), presenter (presents product and coordinates & tracks work after review), reviewer (reviews product and confirms corrections), and administrator (provides administrative support for the chair).

o Review preparationo Review meeting agendao Review follow-upo Hints and tips

The PRINCE2 quality review technique can yield side-benefits in terms of:

o Stakeholder engagement: encourages buy-in to the project

o Leadership: improves decision making

o Team building: members each other’s contributions and needs better.

o Developing individuals

o Quality documentation

o Quality culture: positive and familiar quality culture

6.3.2.2 Quality records: It is important that evidence is gathered to demonstrate that the

planned quality activities have been carried out.

Quality ________________ should include references to the quality inspection documentation.

6.3.2.3 Approval records: This is a record that the product has been _________________.

6.3.2.4 Acceptance records: During the _____________________ process, check that all forms of

approval have been obtained and records kept for audit and/or contractual purposes.

PRINCE2 uses the term ____________________ to describe the ultimate approval of the project’s product.

© 2010 PROJstudy.com 54Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 55:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Quality

© 2010 PROJstudy.com 55Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 56:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Quality

Section 2: QuestionsSl. No Question

1 Which of the following is not an objective of quality planning? Obtaining Project Board agreement on the overall

quality expectations Communicating Project Board agreements on quality

unambiguously to all the project stakeholders Establishing an effective baseline for the project’s

quality controls Maintaining all the approval records of the project

2 Who approves the changes to Project Product Descriptions?3 In which of the following should the customer’s quality

expectations be included? Project Product Description Quality Register Quality Management Strategy

4 Product Descriptions will include quality criteria, quality _______ (a), quality method, and quality _________ (b).

5 In PRINCE2, which of the following is not a quality review team role?

Reviewer Presenter Chair Consultant

6 In PRINCE2, the term ‘acceptance’ refers to __________ _________ of the project’s product.

7 Who among the following approves the Project Product Descriptions and the Quality Management Strategy?

Team Manager Project Support Senior Supplier Project Assurance

© 2010 PROJstudy.com 56Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 57:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Quality

Sample TestQuestion

No Answer Comment

1

2

3

4

5

6

7

Chapter TestQuestion

No Answer Comment

1

2

3

4

5

6

7

8

9

10

11

12

13

© 2010 PROJstudy.com 57Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 58:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Quality

Case Study Format Questions

Questions 1 and 2 contain an assertion statement and a reason statement. For each question identify the appropriate option, from options A to E, that applies. Each option may be used once, more than once, or not at all.Option Assertion ReasonA True True And the reason explains the assertionB True True And the reason does not explain the assertionC True FalseD False TrueE False False

1. Assertion: Project Assurance is independent of the Project Manager but unlike quality assurance it is not independent of the project.Because Reason: At times, activities of Project Assurance and quality assurance overlap.

Correct Answer: B

Justification:Project Assurance is independent of the Project Manager, unlike quality assurance it is not independent of the project.Project Assurance and quality assurance do overlap.Reference: Managing Successful Projects with PRINCE2, page 49

PROJstudy.com comments:Though both the statements are correct, the reason does not justify the assertion. Hence, choice B is the correct option.

2.

Assertion: The presence of quality controls assures the project stakeholders that the project is being conducted appropriately.Because Reason: Quality control focuses on the operational techniques and activities used by those involved in the project.

Correct Answer: D

Justification:Project Assurance provides assurance to the project’s stakeholders that the project is being conducted appropriately and properly.Quality control focuses on the operational techniques and activities used by those involved in the project.Reference: Managing Successful Projects with PRINCE2, page 48

© 2010 PROJstudy.com 58Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 59:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Plans

Section 1 (7.1 to 7.3.2)7.1 PURPOSE

The purpose of the Plans theme is to facilitate _________________ and ____________________ by defining the means of delivering the products.

7.2.1 What is a plan? (For Composition, refer to Appendix A, p.250 of the manual.)

It is a document describing how, when and by whom a specific target or set of targets is to be achieved. These targets will include the project’s _______________,____________, _____________, _________________ and _________________.

In PRINCE2 there are only the following types of plan: Project Plan, Stage Plan, Team Plan, Exception Plan and Benefits Review Plan.

It is important that plans are kept in line with the __________________ at all times.

7.2.2 What is planning? Planning is the act or process of making and maintaining a plan.

PRINCE2 requires a ______________________ approach to Planning.

7.2.3 Levels of plan The period of time for which it is possible to accurately plan is known as the

_____________________.

Plans need to be produced at different levels of scope and detail.

The Project Plan is created by the__________________________.

Figure 7.1 Reference: Managing Successful Project with PRINCE2, page 62 “©Crown copyright 2009 Reproduced under licence from OGC”

© 2010 PROJstudy.com 59Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 60:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Plans

The Initiation Stage Plan is created by the _____________________________ and each subsequent Stage Plan is created by the__________________________ process.

Team Plans are created by the ____________________ process.

The_________________________________ covers corporate, project and stage levels.

7.2.4 The Project Plan The Project Plan provides a statement of _________________ a project’s

time, cost, scope and quality performance targets are to be achieved, by showing the major products, activities and resources required for the project.

The Project Plan:o Provides the ____________________ with planned project costs and

timescales, and identifies the major __________________, such as management stages and milestones

o Is used by the __________________ as a baseline against which to monitor project progress stage by stage

o Should align with the ___________________________ plan.

7.2.5 Stage Plans A stage Plan is required for each _________________________.

The Stage Plan is similar to the ________________________ in content.

But each element will be broken down to the level of detail required to be an adequate basis for day-to-day control by the ___________________.

Each Stage Plan for the next management stage is produced near the end of the _______________________.

7.2.6 Team Plans A Team Plan is produced by a ___________________ to facilitate the

execution of one or more Work Packages.

Team Plans are ____________________ .

Their need and number will be determined by the ______________ and _________________ of the project.

PRINCE2 does not prescribe the _________________ of a Team Plan.

© 2010 PROJstudy.com 60Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 61:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Plans

7.2.7 Exception Plans An Exception Plan is a plan prepared for the appropriate management level to

show the actions required to recover from the effect of a ______________________.

If approved, the Exception Plan will replace the plan that is in exception and it will become the new baselined _________________ or ____________________, as appropriate.

If a Stage Plan is being replaced, this needs the approval of the ________________. Replacement of a Project Plan should be referred by the Project Board to_________________________ if it is beyond the authority of the Project Board.

An Exception Plan is prepared to the same level of detail as the plan it replaces.

Exception Plans are not produced for ___________________.

Should a Team Manager forecast that the assigned Work Package may exceed tolerances, they will notify the _________________ _____________ by raising an issue.

7.3 THE PRINCE2 APPROACH TO PLANS7.3.1 PhilosophyThe products required are identified first, and only then are the activities, dependencies and resources required to deliver those products identified. This is known as _____________________________________________.

Figure 7.2, Managing Successful Project with PRINCE2, page 63“©Crown copyright 2009 Reproduced under licence from OGC”7.3.2 Prerequisites for planning – design the plan

© 2010 PROJstudy.com 61Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 62:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Plans

Figure 7.3 Reference: Managing Successful Project with PRINCE2, page 64 “©Crown copyright 2009 Reproduced under licence from OGC”

Decisions need to be made about how the plan can best be presented.

Where the project is part of a programme, the programme may have developed a common approach to project planning. This may cover standards – for example, level of planning – and tools. These will be the starting point for designing any Project Plan.

© 2010 PROJstudy.com 62Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 63:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Plans

Section 1 - Questions

Sl. No Question1. PRINCE2 requires a ___________ approach to

planning.2. ‘Team plans are created by the Starting up a

Project process’ – True or False?3. Which of the following is used by the Project

Board as a baseline against which to monitor project progress stage by stage?

A. Stage PlanB. Project PlanC. Team PlanD. Exception Plan

4. What are the determining factors of the number and requirements of the team plans?

5. Exception plan is prepared for the appropriate management level to show the actions required to recover from the effect of a ___________.

6. Whose approval is required for the replacement of a Stage Plan?

7. ‘Exception plans are produced for Work Packages’ – True or False?

© 2010 PROJstudy.com 63Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 64:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Plans

Section 2 (7.3.3 to 7.3.8)

7.3.3 Define and analyse the products Product-based planning is likely to be iterative.

7.3.3.1 Write the Project Product Description Although the____________________________ is responsible for specifying

the project product, in practice the Project Product Description is often written by the__________________________ in consultation with the Senior User and Executive.

7.3.3.2 Create the product breakdown structure The plan is broken down into its major products, which are then further broken

down until an appropriate level of detail for the plan is reached. A lower-level product can be a component of only one higher-level product.

When creating a product breakdown structure, consider the following:o It is usual to involve a team of people, perhaps representing the different

interests and various skill sets involved in the plan’s output.o It is common to identify products by running a structured

_______________________________ session.o There is likely to be discussion on the way in which to break down the

products. The project management team must reach a consensus on which approach will be used in the product breakdown structure.

o It is useful to identify any _______________________ required by the plan. For each external product there should be a corresponding entry on the ________________________ detailing the threat to the plan if they are late or not to the required specification.

o When using product-based planning, it is important to consider whether to include different_________________ of a particular product.

o When presenting the product breakdown structure, consider the use of different_________________________ for different types of product.

o If the project is broken down into several stages, the products for each stage are extracted from the project product breakdown structure to form the _____________________. Care must be taken to use the same names in the Stage Plan diagrams as were used in the Project Plan.

7.3.3.3 Write the Product Descriptions Product Descriptions should be written as soon as possible after the need for

the product has been identified.

A Product Description should be baselined when the plan containing the creation of that product is baselined.

It is wise to involve representatives from the area with expertise in the product.

Successful Product Descriptions may be reused for other projects.

© 2010 PROJstudy.com 64Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 65:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Plans

For a small project, it may only be necessary to write the ___________________________.

7.3.3.4 Create the product flow diagram A product flow diagram needs to be created to identify and define the

__________________ in which the products of the plan will be developed and any __________________ between them.

The product flow diagram also identifies dependencies on any products outside the _____________________ of the plan.

A product flow diagram needs very few symbols. Each product to be developed within the plan in question is identified, and the sequence in which they are to be created is shown (the rectangles may be connected by arrows, for example). Any products that already exist or that come from work outside the scope of the plan should be clearly identified as _____________________ (for example, they may be enclosed in a different shape, such as an ellipse)

It may be useful to add a starting point in the product flow diagram from which all entry points are attached.

There is always ____________________ exit on a product flow diagram.

The symbol becomes the predecessor for all entry points and would be the only symbol on a product flow diagram that is not on the product breakdown structure.

7.3.4 Identify activities and dependencies

7.3.4.1 Activities The activities required to create or change each of the planned products need

to be identified to give a fuller picture of the plan’s workload. There are several ways to identify activities:

o Making a separate list of the activities, while still using the product flow diagram as the source of the information

o Taking the products from the product breakdown structure and creating a work breakdown structure to define the activities required.

The activities should include management and quality-checking activities.7.3.4.2 Dependencies

Any dependencies between activities should also be identified.

There are two types of dependency: ______________________ and__________________________.

© 2010 PROJstudy.com 65Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 66:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Plans

7.3.5 Prepare estimates

A decision about how much time and resource are required to carry out a piece of work to acceptable standards of performance must be made by:

o Identifying the type of __________________ required.

o Estimating the ________________ required for each activity by resource type.

Basic rules for estimating:o Assume that resources will only be productive for, say, 80% of their timeo People are generally optimistic and often underestimate how long tasks will takeo Make use of other people’s experiences and your owno Ensure that the person responsible for creating the product is also responsible for creating the effort

estimateso Build in provision for problem solving, meetings and other unexpected eventso Cost each activity rather than trying to cost the plan as a wholeo Communicate any assumptions, exclusions or constraints you have to the user(s).

Examples of estimating techniques:o Top-down estimatingo Bottom-up estimatingo Top-down and bottom-up approacho Comparative estimatingo Parametric estimatingo Single-point estimatingo Three-point estimatingo Delphi technique

7.3.6 Prepare the schedule7.3.6.1 Define activity sequence

Figure 7.4 Reference: Managing Successful Project with PRINCE2, page 69

“©Crown copyright 2009 Reproduced under licence from OGC”

This is an iterative task.

The amount of time that an activity can be delayed without affecting the completion time of the overall plan is known as the_______________ (sometimes referred to as slack). Float can either be regarded as a provision within the plan, or as spare time.

The critical path(s) through the diagram is the sequence of activities that have________________ float.

© 2010 PROJstudy.com 66Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 67:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Plans

The activity-on-node diagram displays interdependencies between activities through the use of boxes and arrows.

7.3.6.3 Assign resources Using the resource availability and the information from the activity sequence

allows the ________________ to assign resources to activities.

A useful approach is to allocate resources to those activities with __________________ first.

It is important that task owners be defined. If a group needs to complete a task, ask one person from the group to be accountable to the group for that task.

Collaborate, communicate and follow up with each task owner to make sure that they understand what it means to complete the task.

Re-check the critical path as actual resources assigned may be more or less productive than the assumption made when calculating activity effort and duration.

7.3.6.4 Level resource usage The first allocation of resources may lead to uneven resource usage or over-

utilization of some resources. It may therefore be necessary to rearrange resources – this is called _____________.

Activities may be reassigned, or they may have start dates and durations changed within the slack available.

The critical chain technique

o The critical chain method of planning puts more emphasis on the ________________ required to execute the plan and their availability.

o A critical chain network will tend to keep the resources levelly loaded, but will require them to be flexible in their start times and to switch quickly between tasks and task chains to keep the whole plan on schedule.

7.3.6.6 Define milestones In a commercial environment, reaching a milestone may be the trigger for a

payment to a supplier.

While there is no ’correct’ number of milestones or duration between them, they lose their value when there are too many or too few.

There should be far _______________________ milestones than deliverables or Work Packages, but there should be enough milestones at major intervals to gauge whether or not the plan is proceeding as expected.

7.3.6.8 Present the schedule A schedule is best presented in a graphical form

Examples of presentation formats for the schedule: Gantt charts

© 2010 PROJstudy.com 67Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 68:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Plans

o A Gantt chart is a graphical representation of the _______________________________ against the progression of time.

Critical path diagramo A __________________________ highlights those tasks which cannot

be delayed without causing the plan to be delayed.

Spreadsheetso It is possible to create a list of tasks ‘down’ the spreadsheet and a

timeline ‘across’ it, then colour in the cells to represent where the tasks will occur in the timeline, and progress to date.

Product checklisto A product checklist is a list of the major products of a plan, plus key

dates in their delivery.

7.3.7 Analyse the risk All identified risks should be entered into the Risk Register.

Examples of planning risks Omission of plans at the appropriate management level(s)

Lots of resources joining the project at the same time can slow progress and cause communication issues

The plan includes unnamed resourceso The plan contains a high proportion of external dependencies

The plan uses untested suppliers

7.3.8 Document the plan Having completed the schedule satisfactorily, the plan, its costs, the required

controls and its supporting text need to be consolidated in accordance with the plan design.

It is necessary to keep plans as simple as is appropriate.

© 2010 PROJstudy.com 68Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 69:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Plans

Section 2 – QuestionsSl. No Question

1. In practice, the Project Product Description is often written by the Project Manager in consultation with the __________ and ___________.

2. The plan is broken down into its major products, which are then further broken down until an appropriate level of detail for the plan is reached. The resultant hierarchy of products is known as ______________.

3. Who is responsible for preparing the schedules for each Work Package?

© 2010 PROJstudy.com 69Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 70:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Plans

Sample TestQuestion

No Answer Comment

1

2

3

4

5

Chapter TestQuestion

No Answer Comment

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

© 2010 PROJstudy.com 70Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 71:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Plans

Case Study Format Questions

1. Which two statements apply to the rules of estimating?A. Resources will be productive 100% of their time.B. People are generally realistic and often overestimate how long tasks will take.C. Person responsible for creating the product is also responsible for creating the

effort estimates.D. Resources working on multiple projects take longer time to complete task

because of time lost switching between them.E. Other people’s experiences are not taken into consideration.

Correct Answer: C, D

Justification:Basic rules for estimating:

Assume that resources will only be productive for, say, 80% of their time Resources working on multiple projects take longer time to complete task

because of time lost switching between them People are generally optimistic and often underestimate how long tasks will

take Make use of other people’s experiences and your own Ensure that the person responsible for creating the product is also responsible

for creating the effort estimates

Reference: Managing Successful Project with PRINCE2, page 68

2. Which two of the following statements are NOT true?F. PRINCE2 prescribes the format of composition of a Team Plan.G. An Exception Plan is presented to the same level of details as the plan it

replaces. H. Team plans are compulsory.I. A Stage Plan is required for each management stage. J. The product flow diagram identifies dependencies on any products outside the

scope of the plan.

Correct Answer: A, C

Justification: A Team Plan is produced by a Team Manager to facilitate the execution of

one or more Work Packages. Team Plans are optional Their need and number will be determined by the size and complexity of the

project. PRINCE2 does not prescribe the format or composition of a Team Plan.

Reference: Managing Successful Project with PRINCE2, pages 62 and 63.

© 2010 PROJstudy.com 71Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 72:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Risk

Section 1 (8.1 to 8.3.5.1)

8.1 PURPOSE The purpose of the Risk theme is to identify, assess and control uncertainty

and, as a result, improve the ability of the project to succeed.

Risk management is about the __________________ identification, assessment and control of risks.

Management of risk is a_________________ activity, performed throughout the life of the ____________________.

8.2.1 What is a risk? A risk is an ______________ event or set of events that, should it occur, will

have an effect on the achievement of objectives.

It consists of a combination of the probability of a perceived ______________ or ____________ occurring.

8.2.2 What is at risk?

It is the project’s ______________that are at risk. These include completing the project to a number of targets typically covering __________________, ________________, _____________________, ___________________, ____________________ and ____________________.

8.2.3 What is risk management? Management of risk is a continual activity. The ongoing and effective risk

management procedure will give confidence that the project is able to meet its objectives and therefore whether it is worthwhile for it to continue. Hence effective risk management is a prerequisite of the continued business justification principle.

During risk response planning, consideration should be given to the effect the possible risk responses could have on the Project Plan, Stage Plan, Work Packages, the Business Case, and corporate and/or programme management.

The systematic application of procedures to the tasks of identifying and assessing risks, and then planning and implementing risk responses.

For risk management to be effective, risks need to be: Identified Assessed Controlled

© 2010 PROJstudy.com 72Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 73:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Risk

Figure 8.1 Reference: Managing Successful Project with PRINCE2, page 78 “©Crown copyright 2009 Reproduced under licence from OGC”

8.3 THE PRINCE2 APPROACH TO RISK

8.3.1 Management of Risk (M_o_R ® ) principles PRINCE2’s approach to the management of risk is based on OGC’s

publication Management of Risk: Guidance for Practitioners (TSO, 2007).

8.3.2 Risk management in projects Identify whether there are any corporate or programme policies and

processes that need to be applied. This information may be in the form of a risk management policy and/or a risk management process guide (or similar documents).

An organization’s risk management policy should communicate how risk management will be implemented throughout the organization.

An organization’s risk management process guide should describe the series of steps and their respective associated activities necessary to implement risk management.

8.3.3 Risk Management Strategy

(For Composition, refer Appendix A, p.259 of the manual.) A strategy describing the goals of applying risk management, as well as the

procedure that will be adopted, roles and responsibilities, risk tolerances, the tools and techniques and the reporting requirements.

A key decision that needs to be recorded within the Risk Management Strategy is the risk appetite of the organisation, i.e., its attitude towards risk taking, which in turn dictates the amount of risk that it considers acceptable. This information is captured in the form of _____________________________.

© 2010 PROJstudy.com 73Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 74:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Risk

Risk appetite varies with organisation, culture, industry, etc., for example, risk appetite of venture capital firms is generally high whereas that of organisations managing provident funds is generally low.

8.3.4 Risk Register(For Composition, refer Appendix A, p.260 of the manual.)

Risk Register captures and maintains information on all of the identified _______________ and _____________________ relating to the project.

8.3.5 Risk management procedure Identify Assess Plan Implement Communicate

The first ___________ steps are sequential, with the ’Communicate’ step running in parallel.

Figure 8.2, page 80, Managing Successful Project with PRINCE2 “©Crown copyright 2009 Reproduced under licence from OGC”

8.3.5.1 Identify Context

The primary goal of the ’Identify context’ step is to obtain information about the project in order to understand the specific objectives that are at risk and to formulate the ______ ________________ for the project.

The early warning indicators will provide advanced warning that one or more of the project’s _________________________could be at risk. Early warning indicators include progress performance data, non-project data such as customer satisfaction, absenteeism levels, staff attrition rates etc.

Risk identification techniques Review lessons: review similar previous projects to see what threats and

opportunities affected them.

© 2010 PROJstudy.com 74Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 75:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Risk

Risk checklists: in-house lists of risks that have either been identified or have occurred on previous similar projects.

Risk prompt lists: publicly available lists that categorize risks into types or areas and are normally relevant to a wide range of projects, e.g., organizations in the Broking industry need not prepare risk checklists as there are many sources of risk prompt lists readily available like websites, etc.

Brainstorming: enables group thinking.

Risk breakdown structure: a hierarchical _________________________ of the project environment assembled to illustrate potential ________________________ of risk. A risk breakdown structure could be broken down by PESTLE (political, economical, sociological, technological, legal/legislative, environmental), product breakdown structure, stage, benefits/objectives etc.

Figure 8.3, page 82, Managing Successful Project with PRINCE2, “©Crown copyright 2009 Reproduced under licence from OGC”

© 2010 PROJstudy.com 75Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 76:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Risk

Section 1 – Questions

Sl. No Question1. _____________ describes an uncertain event

that could have a favourable impact on objectives.

2. Which among the five steps for risk management procedure run in parallel to the other steps?

A. IdentifyB. ImplementC. AssessD. CommunicateE. Plan

3. The purpose of the _________ is to capture and maintain information on all of the identified threats and opportunities relating to the project.

4. In the context of a project, it is the project’s __________ that are at risk.

© 2010 PROJstudy.com 76Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 77:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Risk

Section 2 (8.3.5.1 to 8.3.6)

8.3.5.1 Identify risks The primary goal of the ’Identify risks’ step is to recognize the ____________

and _________________ that may affect the project’s objectives.

PRINCE2 recommends the following actions: Capture identified threats and opportunities in the

_____________________ Prepare early warning indicators Understand the _________________ view of the specific risks captured.

Identify risks using risk workshop.

A useful way of expressing risk is to consider the following aspects of each risk: Risk cause: source of the risk Risk event: describes the area of uncertainty Risk effect: impact of risk on the project

Figure 8.4, page 82, Managing Successful Project with PRINCE2“©Crown copyright 2009 Reproduced under licence from OGC”

The cause, event and effect relationship can be expressed in a sentence, for example: Threat: Because it has been raining heavily (risk cause), there is a

threat that the river flowing through the farmer’s field might overflow (risk event), which would severely damage the farmer’s crop (risk effect)

Opportunity: Because the weather has been particularly mild this winter (risk cause), there is an opportunity that fewer people will be hospitalized with influenza (risk event), which will mean that there will be less disruption to planned routine operations (risk effect).

© 2010 PROJstudy.com 77Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 78:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Risk

8.3.5.2 AssessThe ‘assess’ procedure includes two steps ‘estimate’ and ‘evaluate’

Estimate: The ‘Estimate’ step assesses the threats and the opportunities to the project

in terms of their probability and impact. The risk proximity will also be of interest.

Risk Estimation Techniques: Probability trees: These are graphical representations of possible

__________________ resulting from given circumstances.

Expected value: This technique quantifies risk by combining the cost of the ___________ ______________ with the probability of the __________________________ occurring.

Pareto analysis: This technique ___________________ or ________________ risks once they have been assessed to determine the order in which they should be addressed.

Probability impact grid: This grid contains ranking values that may be used to _________ threats and opportunities __________________. The probability scales are measures of probability derived from ________, and the impact scales are selected to reflect the level of __________.

PRINCE2 recommends that the following is understood:

The probability of the threats and opportunities in terms of how ____________________ they are to occur

The ___________________ of each threat and opportunity in terms of the project objectives.

The ___________________ of these threats and opportunities with regard to when they might materialize

How the impact of the threats and opportunities may change over the life of the _______________________.

Plot risks and their estimations onto a summary risk profile which represents a situation at a specific point in time, i.e. a snapshot of the risk environment.

Evaluate: The ’Evaluate’ step assesses the __________________ of all the identified

threats and opportunities on a project when aggregated together.Risk evaluation techniques:

Risk Models: The _____________________ enables simulation of ’what if’ scenarios using random numbers.

Expected monetary value: This technique takes the ___________________ of a number of risks and sums them to arrive at an overall value.

8.3.5.3 Plan The primary goal of the ’Plan’ step is to prepare specific management

responses to the threats and opportunities identified, ideally to ____________________ or _____________________ the threats and to maximize the _______________________.

© 2010 PROJstudy.com 78Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 79:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Risk

A key factor in the selection of responses will be __________________________ the cost of implementing the responses against the probability and impact of allowing the risk to occur.

Risk responses do not necessarily remove the ________________ in its entirety, leaving residual risk.

Secondary risks are risks that may occur as a result of invoking a _______________________.

Figure 8.7, page 85, Managing Successful Project with PRINCE2 “©Crown copyright 2009 Reproduced under licence from OGC”

Table: Risk responsesResponse Definition

Avoid (threat) Typically involves changing some aspect of the project, i.e. the scope, procurement route, supplier or sequence of activities, so that the threat either can no longer have an impact or can no longer happen. For example, to avoid the risk of ‘data loss’ buy new computers with the latest software instead of upgrading the software of the old computers.

Reduce (threat) Proactive actions taken to reduce the probability of the event occurring, by performing some form of control. For example, to reduce the risk of ‘computer crashes’ increase the RAM of all the computers.

Fallback (threat) Putting in place a fallback plan for the actions that will be taken to reduce the impact of the threat should the risk occur. For example, plan that if the computers crash, RAM of the computers that have crashed will be increased from 2GB to 3GB.

Transfer (threat) A third party takes on responsibility for some of the financial impact of the threat. For example, taking insurance.

Accept (threat) A conscious and deliberate decision is taken to retain the threat, having discerned that it is more economical to do so than to attempt a threat response action. For example, accepting that some users will face difficulty in using the new software.

Share (threat or opportunity)

Modern procurement methods commonly entail a form of risk sharing through the application of a pain/gain formula: both parties share the gain (within pre-agreed limits) if the cost is less than the cost plan; and share the pain (again within pre-agreed limits) if the cost plan is exceeded. For example, including penalty clauses or benefits sharing clauses in contracts with the suppliers.

Exploit (opportunity)

Seizing an opportunity to ensure that the opportunity will happen and that the impact will be realized.

Enhance (opportunity)

Proactive actions taken to: Enhance the probability of the event occurring Enhance the impact of the event should it occur.

Reject (opportunity)

A conscious and deliberate decision is taken not to exploit or enhance the opportunity.

Mnemonic for memorizing Risk Responses: ARFTASEER

© 2010 PROJstudy.com 79Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 80:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Risk

8.3.5.4 Implement The primary goal of the ’Implement’ step is to ensure that the planned risk

responses are actioned, their effectiveness monitored, and corrective action taken where responses do not match expectations.

The main roles in this respect are:o Risk owner : A named individual who is responsible for the

management, monitoring and control of all aspects of a particular risk assigned to them, including the implementation of the selected responses.

o Risk actionee : An individual assigned to carry out a risk response action or actions to respond to a particular risk or set of risks. They support and take direction from the risk owner.

In many cases, the risk owner and risk actionee are likely to be the ____________________.

8.3.5.5 Communicate The ’Communicate’ step should ensure that information related to the threats

and opportunities faced by the project is communicated both within the ___________________ and externally to ________________.

Risks are communicated as part of the following management products:o Checkpoint Reportso Highlight Reportso End Stage Reportso End Project Reportso Lessons Reports.

Other communication methods are bulletins, notice boards, dashboards, discussion threads, briefings etc.

A project’s exposure to risk is never ____________________. Effective risk management is dependent on __________________.

8.3.6 Risk budget A sum of money included within the project budget and set aside to fund

specific management responses to the project’s threats and opportunities. The aggregation of the costs (for responses and impact) weighted by each risk’s probability generates the expected monetary value

for the set of risks. The expected monetary value can be used to determine a risk budget. Care needs to be taken that the aggregation of the factored costs is not skewed by a small number of large risks. This is where

analytical techniques, such as Monte Carlo analysis and associated software tools, can help.

As the project progresses, some of the risks previously identified will occur and others will not.

It is prudent to set the risk budget to cover the ___________________ (as identified) and to make a __________________for unknown risks (yet to be identified)

© 2010 PROJstudy.com 80Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 81:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Risk

Section 2 – Questions

Sl. No Question1. Who is responsible for carrying out a risk

response action or actions to respond to a particular risk or set of risks?

2. ‘Risk owner and risk actionee cannot be the same person’ – True or False?

3. ‘A project’s exposure to risk is never static’ – True or False?

4. Which among the following risk responses can be a threat or opportunity?

A. TransferB. ExploitC. ShareD. Fallback

5. Risk cause describes the area of uncertainty’ – True or False?

© 2010 PROJstudy.com 81Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 82:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Risk

Sample TestQuestion

No Answer Comment

1

2

3

4

5

6

7

8

Chapter TestQuestion

No Answer Comment

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

© 2010 PROJstudy.com 82Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 83:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Risk

Case Study Format Questions:

1. Which 2 are recommended as possible risk response type for opportunity?a) Acceptb) Rejectc) Reduced) Enhancee) Fall-back Correct Answer: B, DJustification:

Reference: Managing Successful Project with PRINCE2, page 85

2. Column 1 contains a number of risk responses identified by the Project Manager following an assessment of risk. Column 2 contains a list of threat response types. For each risk response in column 1, select from column 2 the type of response it represents. Each option from column 2 can be used once, more than once or not at all.

Column 1 Column 21. Concluded the project to remain incomplete and scrapped

A. Accept

2. Bringing the delivery date forward B. Reduce3. Monitor the situation after recording the risk in the Risk Register

C. Avoid

Correct Answer: 1. Correct [C]2. Correct [B]3. Correct [A]Justification:1. Correct [C] ‘Avoid’ – instead of not completing the project, change

some aspects of the project so that the threat can no longer have an impact or can no longer happen.

2. Correct [B] ‘Reduce’ – it is a form of proactive action taken to reduce the probability and/or impact of the event should it occur.

3. Correct [A] ‘Accept’ – a conscious and deliberate decision to do nothing but monitor and ensure that the threat remains tolerable.

Reference: Table 8.2 Managing Successful Project with PRINCE2, page 86.

© 2010 PROJstudy.com 83Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 84:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Change

Section 1 (9.1 to 9.3.1.3)9.1 PURPOSE

The purpose of the Change theme is to identify, assess and control any potential and approved changes to the ______________________.

PRINCE2 provides a common approach to issue and change control.

Issues possibly affecting the project’s ____________________(time, cost, quality, scope, risk and benefits) are appropriately managed.

Issue and change control is a ______________________ activity, performed throughout the life of the project. Without an ongoing and effective issue and change control procedure, a project will either become totally unresponsive to its stakeholders or quickly drift out of control.

The aim of issue and change control procedures is not to ________________________ changes; it is to ensure that every change is agreed by the relevant authority before it takes place.

A prerequisite of effective issue and change control is the establishment of an appropriate _______________________ which records baselines for the project’s products.

9.2.2 Configuration management Configuration management is the technical and administrative activity

concerned with the creation, maintenance and controlled change of configuration throughout the life of a product.

A _____________________________ is an entity that is subject to configuration management. The entity may be a component of a product, a product or a set of products that form a release.

A___________________________ is a complete and consistent set of products that are managed, tested and deployed as a single entity to be handed over to the user(s).

___________________________________ procedures need to be integrated with the configuration management system used by the project.

9.2.3 Issues PRINCE2 uses the term _________________ to cover any relevant event

that has happened, was not planned, and requires management action.

It can be a concern, query, request for change, suggestion or off specification raised during a project.

Project issues can be about anything to do with the project.9.2.4 Types of issue

© 2010 PROJstudy.com 84Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 85:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Change

Issues may be raised at any time during the _______________________, by anyone with an interest in the project or its outcome.

Types of issue DefinitionRequest for change A proposal for a change to a baseline.Off-specification Something that should be provided by the project, but

currently is not provided.Problem/concern Any other issue that the Project Manager needs to

resolve or escalate.

9.3 THE PRINCE2 APPROACH TO CHANGE9.3.1 Establish controls

The project’s controls for issues, changes and configuration management will be defined and established by the__________________________________ process and then reviewed and (if necessary) updated towards the end of each management stage by the ________________________________ process.

The following management products are used to establish and maintain the project’s controls for issues, changes and configuration management:

o Configuration Management Strategyo Configuration Item Recordso Product Status Accountso Daily Logo Issue Registero Issue Reports

9.3.1.1 Configuration Management Strategy The project’s Configuration Management Strategy should define:

o The configuration management procedureo The issue and change control procedureo The tools and techniques that will be usedo The records that will be kepto How the performances of the procedures will be reportedo Timing of configuration management and issue and change control

activitieso The roles and responsibilities for configuration management and issue

and change control activities.

The Configuration Management Strategy should define the way ______________________ are handled.

During the ____________________ stage, the Project Manager and Project Board need to agree:

o The scale for prioritizing issueso The scale for rating the severity of issueso What severity of issues can be handled at what management level.

© 2010 PROJstudy.com 85Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 86:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Change

Example of priority and severity: There are numerous ways to prioritize issues, one of which is called

____________________________ where the issue is rated as either:o Must haveo Should haveo Could haveo Won’t have (for now)

There are numerous ways to rate the severity of issues, such as numeric or descriptive

When deciding what severity of issues can be dealt with by what level of management, the ___________________ may consider delegating some decision making for accepting/rejecting requests for change or off-specifications to a Change Authority and whether to provide a budget to pay for changes:

o Change Authority: For projects where there are likely to be lots of changes, the Project Board may choose to delegate some decisions to a person or group, called the Change Authority. It may be appropriate, for example, to make the ______________________________ the Change Authority for Work Packages

o Change budget: This is a sum of money that the customer and supplier agree will be used to fund the cost of requests for change, and possibly also their analysis costs. This arrangement can reduce the number of trivial exceptions arising in projects where the frequency of requests for change is forecast to be high. Including a change budget provides for a more realistic expectation of the overall costs/timeframe of the project.

9.3.1.2 Configuration Item Records

(For Composition, refer Appendix A, p.240 of the manual.) Provide a set of records that describe information such as the

_________________, ___________________, and _______________ of each configuration item and any details of important relationships between the items.

9.3.1.3 Product Status Account Provides information about the state of the ________________ within defined

limits.For example, let us consider a project involving creation of a new car design. The project’s product (car design) will have Project Product Description, whereas the individual parts of the project’s product will have product descriptions. The product description will be documented in the Product Status Account along with the following information: product identifier, state, owner, version, etc.

© 2010 PROJstudy.com 86Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 87:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Change

Section 1 – Questions

Sl. No Question1. ‘The aim of issue and change control procedure

is to prevent changes as well as to ensure that every change is agreed by the relevant authority before it takes place’ – True or False?

2. ____________ is a prerequisite of effective issue and change control.

3. What are the three recommended types of issue?

4. Which of the following management products is NOT used to establish and maintain the project’s controls for issues, changes and configuration management?a) Configuration Management Strategyb) Configuration Item Recordsc) Daily Logd) Communication Management Strategy

5. What is the purpose of a Configuration Item Record?

6. PRINCE2 uses the term _______ to cover any relevant event that has happened, was not planned, and requires management actions.

7. The purpose of the ______________ is to provide information about the state of the products within defined limits.

© 2010 PROJstudy.com 87Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 88:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Change

Section 2 (9.3.1.4 to 9.3.3.4)

9.3.1.4 Daily Log Used to record _______________________ that can be handled by the

Project Manager informally.

Issues initially captured on the Daily Log may later be transferred to the ____________________.

9.3.1.5 Issue Register(For Composition, refer Appendix A, p.246 of the manual.)

Captures and maintains information on all of the issues that are being managed ________________. It should be monitored by the Project Manager on a regular basis.

9.3.1.6 Issue Report(For Composition, refer Appendix A, p.247 of the manual.)

An ____________________________ is a report containing the description, impact assessment and recommendations for a request for change, off-specification or a problem/concern.

It is only created for those issues that need to be handled formally. 9.3.2 Configuration management ProcedureConfiguration management procedures can vary, but they typically comprise five core activities:

Planningo Deciding what level of configuration management will be required by

the project and planning how this level is to be achieved.

o The maximum level of control possible is determined by breaking down the project’s products until the level is reached at which a component can be independently installed, replaced or modified.

o The level of control exercised will be influenced by the ________ of the project and the __________ between its products.

Identification o Specifying and identifying all components of the project’s products at the required level of control.

o A coding system should be established, enabling a unique identifier for each configuration item to be allocated and various attributes of the product recorded.

Control o The ability to approve and baseline products and to make changes only

with the agreement of appropriate authorities.

o Once a product has been approved, the motto is ‘Nothing changes without __________________________’.

© 2010 PROJstudy.com 88Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 89:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Change

o A baseline is a reference level against which an entity is __________________.

o If the product that has been baselined is to be changed, a new ____________________ is created to accommodate the change, and the baseline version is kept unchanged.

o Old baseline versions should be archived where possible, not discarded.o Configuration control also includes:

The storing and retrieving of all information relevant to the management of the project Ensuring the safety and security of configuration items Distribution of copies of all configuration items

o Both _____________________ and ___________________ products are subject to configuration control.

Status accounting:

o The reporting of all current and historical data concerning each product is done in the form of a Product Status Account. (For Composition, refer Appendix A, p.253 of the manual.)

Verification and audito A series of reviews and configuration audits to compare the actual

status of all products against the authorized state of products.

9.3.3 Issue and change control procedure

Figure 9.1, page 95, Managing Successful Project with PRINCE2 “©Crown copyright 2009 Reproduced under licence from OGC”

© 2010 PROJstudy.com 89Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 90:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Change

9.3.3.1 Capture The Project Manager is likely to receive many issues that can be handled

without having to treat them formally. The Project Manager should decide on the best course of corrective action. Issues being managed formally should be entered in the Issue Register and given a unique identifier. An issue register should be created to capture what is already known about the issue.

9.3.3.2 Examine The next step is to examine the issue by undertaking an

___________________. Impact analysis must cover the three areas of _________________,

__________________ and _____________________________. It may be necessary to request advice from the Project Board to check their understanding of the issue’s priority or

severity before proposing resolutions.

9.3.3.3 Propose The next step is to consider alternative options for responding to it and proposing a course of action to take. There must be a balance between the advantage to be gained by implementing the option, and the time, cost and

risk of implementing it. The risk considerations should include both project risks and operational risks.

If any of the proposed options would take the stage or project beyond any tolerances, consider preparing an ________________________.

9.3.3.4 Decide The Project Manager may be able to resolve issues without the need to

escalate them to the _______________________________.

Other issues may need to be escalated to the Project Board for a decision.

The escalation could be in the form of an ________________________ (as part of a request for advice) or in the form of an _______________________________ (if the selected option to address the issue would cause an exception).

9.3.3.5 Implement

How the change theme supports the manage-by- exception principle:

Refer to table 9.2 (p.97) in the manual.

© 2010 PROJstudy.com 90Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 91:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Change

Section 2 – Questions

Sl. No Question1. Which management product is used to record

problems/concerns that can be handled by the Project Manager informally?

2. Which management product is used to capture and maintain information on all of the issues that are being managed formally?

3. ______________ is only created for those issues that need to be handled formally.

4. Any requests for change, which require Project Board approval, should be recorded in the _________ and their status monitored by the Project Manager.

5. Mention the steps involved in the issue and change control procedure.

6. Some issues may require escalation to the Project Board and the escalation could be in the form of ____________ or ______________.

© 2010 PROJstudy.com 91Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 92:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Change

Sample TestQuestion

No Answer Comment

1

2

3

4

5

6

Chapter TestQuestion

No Answer Comment

1

2

3

4

5

© 2010 PROJstudy.com 92Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 93:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Change

Case Study Format Questions:

1. Which two are related to the ‘Propose’ step of the issue and change control procedure?a) Check severity/priorityb) Approve, reject or defer recommended optionc) Recommend options d) Log registere) Evaluate options Correct Answer: C, EJustification:

Reference: Figure 9.1 Managing Successful Project with PRINCE2, page 95“©Crown copyright 2009 Reproduced under licence from OGC”

2. Some issues may need to be escalated to the Project Board for a decision. The escalation could be in the form of 2 management products. Identify them from the following list:

A. Highlight ReportB. Issue ReportC. End Stage ReportD. Exception ReportE. Lessons Report

Correct Answer: B, DJustification:

The Project Manager may be able to resolve issues without the need to escalate them to the Project Board.

Other issues may need to be escalated to the Project Board for a decision. The escalation could be in the form of an issue Report (as part of a request

for advice) or in the form of an Exception Report (if the selected option to address the issue would cause an exception)

Reference: Managing Successful Project with PRINCE2, page 96.

© 2010 PROJstudy.com 93Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 94:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Progress

Section 1 (10.1 to 10.3.1.2)

10.1 PURPOSE The purpose of the Progress theme is to establish mechanisms to monitor

and compare actual achievements against those planned; provide a forecast for the project objectives and the project’s continued viability; and control any unacceptable deviations.

Two of the principles of PRINCE2 are ___________________ and _______________________________.

Another PRINCE2 principle is that projects are _____________________, setting tolerances for project objectives.

10.2.1 What is progress? Progress is the measure of the achievement of the objectives of a

_____________________. It can be monitored at Work Package, stage and project level.

10.2.2 What are progress controls? Progress controls ensure that for each level of the project management

team the next level of management can:o Monitor progresso Compare level of achievement with plano Review plans and options against future situations o Detect problems and identify riskso Initiate corrective actiono Authorize further work

10.2.3 Exceptions and tolerances An exception is a deviation beyond the agreed

____________________________.

Tolerances are the _________________ above and below a plan’s target for time and cost without escalating the deviation to the_________________________ of management.

If tolerances are not implemented, there is no clear measure of discretion if things do not go to plan.

© 2010 PROJstudy.com 94Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 95:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Progress

Tolerance Areas Project Level Tolerances

Stage Level Tolerances

Work Package Level Tolerances

Project Level Tolerances

Time+/- amounts of time on target completion dates

Project Plan Stage Plan Work Package

N/A

Cost+/- amounts of planned budget

Project Plan Stage Plan Work Package

N/A

ScopePermitted variation of the scope of a project solution, e.g. MoSCoW prioritization of requirements (Must have, Should have, Could have, Won’t have for now)

Project Plan (Note1)

Stage Plan (Note1)

Work Package(Note1)

NA

RiskLimit on the aggregated values of threats (e.g. expected monetary value to remain less than 10% of the plan’s budget); and Limit on any individual threat (e.g. any threat to operational service)

Risk Management Strategy

Stage Plan (Note2)

Work Package (Note2)

N/A

QualityDefining quality targets in terms of ranges, e.g. a product that weighs 300g +/- 10g

Project Product Description

N/A(Note 3)

N/A(Note 3)

Product Description

BenefitsDefining target benefits in terms of ranges, e.g. to achieve minimum cost savings of 5% per branch, with an average of 7% across all branches

Business Case N/A N/A N/A

Note 1 – the scope of a plan is defined by the set of products to be delivered. Scope tolerance (if used) should be in the form of a note on or reference to the product breakdown structure for the plan. Scope tolerance at the stage or Work Package level is of particular use if applying a time bound iterative development method such as AgileNote 2 – more specific stage level risk tolerances may be set by the Project Board when authorizing a stage or by the Project Manager when commissioning Work Packages, especially from External Suppliers.Note 3 – quality tolerances are not summarily defined at the stage or Work Package level but are defined per Product Description within the scope of the plan.Table 10.1 Managing Successful Project with PRINCE2, page 102

“©Crown copyright 2009 Reproduced under licence from OGC”

© 2010 PROJstudy.com 95Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 96:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Progress

10.3 THE PRINCE2 APPROACH TO PROGRESS Progress control involves measuring actual progress against the

performance targets of time, cost, quality, scope, benefits and risk, and then using this information to make decisions and to take actions as required.

PRINCE2 provides progress control through:o Delegating authorityo Dividing the project into management stageso Time-driven and event-driven progress reporting and reviewso Raising exceptions.

10.3.1 Delegating authority10.3.1.1 The four levels of management

_______________________sets tolerance levels for the project.

_____________________ has overall control at a project level, and allocates tolerances for each management stage to the Project Manager.

_____________________ has day-to-day control for a management stage.

_______________________ has control for a Work Package, but only within the Work Package tolerances agreed with the Project Manager.

Figure 10.1 Managing Successful Project with PRINCE2, page 103“©Crown copyright 2009 Reproduced under licence from OGC”

10.3.1.2 Project Board controls The main controls available to the Project Board include:

© 2010 PROJstudy.com 96Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 97:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Progress

Authorizations: The Project Board uses the__________________ process to authorize initiation, authorize the project, authorize each stage and, finally, authorize project closure:o After the pre-project process _____________________, the Project

Board authorizes progress to the initiation stage.o After the _________________________, the Project Board reviews

the information from the__________________ and can approve the __________________________ and authorize the project itself.

o After the__________________________ process, the Project Board reviews a Stage Plan or Exception Plan, and can approve the plan, with its relevant tolerances for the next management stage.

o After the ______________________ process, the Project Board reviews the End Project Report and, if satisfied that the project is complete or has nothing more to offer, can authorize its closure.

Progress updates: Including _________________ and ____________________

Exceptions and changes: Including ________________ and ____________________.

© 2010 PROJstudy.com 97Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 98:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Progress

Section 1 – Questions

Sl. No Question1. An _________ is a situation where it can be

forecast that will be a deviation beyond the agreed tolerance level.

2. ____________ are the permissible deviation above and below a plan’s target for time and cost without escalating the deviation to the next level of management.

3. What are the four levels of the project management followed by the allocation of tolerances?

4. Which document does the Project Board review after the Initiating a Project process, following which it authorises the project itself if satisfied?

5. After which process does the Project Board review a Stage Plan or Exception Plan and approve it, with its relevant tolerances for the next management stage?

6. Progress updates includes _________ and ___________.

7. Who has the control for a work package?

© 2010 PROJstudy.com 98Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 99:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Progress

Section 2 (10.3.1.3 to 10.3.3.4)

10.3.1.3 Project Manager controls The main controls available to the Project Manager include:

Authorizations: During the process _________________, the Project Manager will be responsible for agreeing and authorizing Work Packages and Work Package __________________.

Progress updates: Including _____________________ produced by Team Managers or team members.

Exceptions and changes: Use of project registers and logs to review progress and identify issues and risks that may need to be resolved.

10.3.2. Use of management stages for control A________________________ is a collection of activities and products

whose delivery is managed as a unit.

Management stages:o Provide review and decision pointso Give the ability to ensure that key decisions are made prior to the

detailed work

The Project Board authorizes ________________ management stage of the project at a time. Towards the end of each stage, an ___________________ and ____________________ are created to request authorization to commence the next management stage.

The End Stage Report, together with the Stage Plan for the next stage, should contain all the information necessary to enable the___________________ to conduct an end stage assessment and make a decision as to whether to proceed.

10.3.2.1 Number of stages The use of management stages in a PRINCE2 project is ____________________, but the number of stages is_______________________ and depends on the_________________ and __________________________ of the project. Every PRINCE2 project consists of at least two management stages. Defining management stages is fundamentally a process of balancing

o too many short management stages (increasing the project management overhead) versus too few lengthy ones (reducing the level of control),

o how confident the _________________and ________________ are in proceeding.

© 2010 PROJstudy.com 99Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 100:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Progress

10.3.2.2 Length of stages Stages should be shorter when there is

__________.___________________.

They can be longer when risk is _______________, typically in the _________________.

Factors that will influence this decision include:o The planning horizon at any point in time

o The technical stages within the project: The end of management stages do not necessarily need to occur at the same time as the end of technical stages, but there are often benefits if they do.

o Alignment with programme activities: It may be a requirement to align the end of a management stage with the end-of-tranche review within the programme.

o The level of risk Management stages can be very useful as a means of bringing Project Board control to risky projects.

10.3.2.3 Technical stages Technical stages are a method of grouping work by the set of techniques

used or the products created, and are a separate concept from the _____________________________ already introduced.

Technical stages often ________________ but management stages__________________. Technical stages are typified by the use of a particular set of _________________ skills. Management stages equate to commitment of resources and authority to spend.

Where a technical stage spans __________________________ boundary, the extent to which the product(s) of the ________________ stage should be complete at the stage boundary should be clear in the Product Description(s) concerned.

The PRINCE2 approach is to concentrate the management of the project on the management stages since these will form the basis of the planning and control processes described throughout the method.

© 2010 PROJstudy.com 100Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 101:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Progress

Figure 10.3 Managing Successful Project with PRINCE2, page 106 “©Crown copyright 2009 Reproduced under licence from OGC”

10.3.3 Event-driven and time-driven controls PRINCE2 provides _____________ types of progress control throughout

the life of a project:o Event-driven controls: Take place when a specific event occurs.

This could be, for example, the end of a stage, the completion of the ______________________________ or the creation of an _____________________. It could also include organizational events that might affect the project, such as the end of the financial year

o Time-driven controls: Take place at predefined periodic intervals. For example, monthly ________________, or weekly _________________________

Monitoring and reporting requires a time-based approach, whereas control (decision making) is an event-based activity.

10.3.3.1 Baselines for progress control It is only possible to control at the level of resolution in the plans, i.e. if you

want to have Checkpoint Reports weekly, you need to know what you expect to achieve week by week.

Management products that assist the Project Manager in establishing baselines for progress control:

o Project Plan: This will include the ___________________ performance targets and tolerances.

o Stage Plans: These form the basis of the ______________________ control of the stage.

o Exception Plan: The Project Board may request an Exception Plan after having considered an Exception Report during the

© 2010 PROJstudy.com 101Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 102:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Progress

process________________. The Exception Plan should be produced at the same level as the plan that it replaces.

o Work Packages: The individuals or teams monitor progress against the _________________________ and report back to the Project Manager via _____________________. It may be valid to use a mixture of formal and informal Work Packages of varying sizes, with tight or loose tolerances, depending on the needs of the project.

10.3.3.2 Reviewing progress The Project Manager will regularly review the progress of work through

_________________ and maintain a set of project registers and logs to update the _____________ with actual progress achieved.

It is also useful to look at trends to get a view of the overall ’health’ of the stage.

The following management products assist the Project Manager in reviewing progress:

o Daily Log records actions. Small actions may simply be recorded on the Daily Log and marked off when completed. Actions involving significant effort may need to be incorporated into the__________________. If such actions cannot be incorporated into the plan within tolerances, then an issue should be raised to examine their impact on the stage and project.

o The Daily Log can also be used to record informal issues and any other notes or observations that are not captured by any other registers or logs. It also helps alert the Project Manager to a new issue or risk. (For Composition, refer Appendix A, p.242 of the manual.)

o Issue Register contains details of all _________________ raised during the project, which could take the form of requests for change, off-specifications or problems/concerns. (For Composition, refer Appendix A, p.247 of the manual.)

o Product Status Account provides a snapshot of the status of products within the project, management stage or a particular area of the project. (For Composition, refer Appendix A, p.253 of the manual.)

o Quality Register This is a record of all planned and implemented quality activities. (For Composition, refer Appendix A, p.258 of the manual.)

o Risk Register This is a record of all identified risks. The number of risks should generally decrease as the ___________________ and the level of certainty __________________. (For Composition, refer Appendix A, p.260 of the manual.

Progress evaluation techniquesMilestone chart shows key planned and actual milestones. S-curve graph shows cumulative actual figures (for example, costs or hours) plotted against time. The steeper the curve, the

more resources required.Earned value management technique measures the scope, schedule and cost performance compared with plans.

© 2010 PROJstudy.com 102Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 103:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Progress

10.3.3.3 Capturing and reporting lessons

Lessons Log: One of the principles of a PRINCE2 project is that the project management team learns from experience. Lessons are sought, recorded and actioned throughout.(For Composition, refer Appendix A, p.248 of the manual)

Lessons Report: The purpose of the report is to provoke action so that the positive lessons from a project become embedded in the organization’s way of working and that the organization is able to avoid the negative lessons on future projects. If a lesson is significant and has relevance for future projects, it should be included in the Lessons Report. The ________________________ is created at any appropriate time during a project. As a minimum, however, a Lessons Report should be produced during the _____________________________ process.(For Composition , refer Appendix A, p.249 of the manual.)

10.3.3.4 Reporting Progress The frequency of reporting should reflect the level of control required.

o During the design stage, less frequent control may be required.o If the team is highly experienced then less frequent reporting may

be appropriate.

The following management products are used for progress reporting:o Checkpoint Report: The Team Manager will produce this to

provide the Project Manager with details of progress against the __________________. The Work Package will include the ____________ of Checkpoint Reports required. (For Composition, refer Appendix A, p.238 of the manual.)

o Highlight Report: The Project Manager produces this report on ______________________ stage progress for the Project Board. The Project Board will determine the frequency of Highlight Reports required, and document this in the_____________________________. The Highlight Report should confirm that progress is being made. As part of the Communication Management Strategy, the Project Board can request that copies of the Highlight Report be sent to the other interested parties outside the project and to _________________________ management. (For Composition, refer Appendix A, p.245 of the manual.)

o End Stage Report: Towards the end of each _________________ the Project Manager provides the Project Board with the information on the progress performance, the overall project situation and sufficient information on what to do next with the project.

© 2010 PROJstudy.com 103Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 104:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Progress

(For Composition, refer Appendix A, p.244 of the manual.)o End Project Report: A report given by the Project Manager to the

Project Board that confirms the handover of all products and provides an updated Business Case and an assessment of how well the project has done against the original Project Initiation Documentation. (For Composition, refer Appendix A, p.243 of the manual.)

10.3.4 Raising exceptions Work-Package-level exceptions The Project Manager should be kept

informed of progress through regular___________________. If a Work Package is forecast to exceed its tolerances, the Team Manager should inform the Project Manager by raising an__________________. The Project Manager will advise of any corrective actions required.

Stage-level exceptions If the stage is forecast to exceed its tolerances, the Project Manager should produce an ___________________to capture and analyse the details of the deviation and then provide an _________________for the Project Board. The Project Board may request that the Project Manager produces an Exception Plan to replace the plan that was forecast to exceed tolerance. If an Exception Plan is requested, the Project Board will conduct an______________________, similar to the end stage assessment.

Project-level exceptions If the forecast is for project tolerances to be exceeded the ___________________ must refer the matter to corporate or programme management for a decision. The Project Board may request the Project Manager to produce an ________________for the project.

© 2010 PROJstudy.com 104Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 105:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Progress

Section 2 – QuestionsSl. No Question

1. ‘The use of management stages in a PRINCE2 project is optional’ – True or False?

2. What are the factors that influence the number of management stages ?

3. Every PRINCE2 project consists of __________ management stage(s).

4. Length of the management stages depends on ______________.

5. ‘Management stages often overlap but technical stages do not’ – True or False?

6. Highlight report is prepared by __________.

© 2010 PROJstudy.com 105Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 106:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Progress

Sample TestQuestion

No Answer Comment

1

2

3

4

5

6

7

8

9

Chapter TestQuestion

No Answer Comment

1

2

3

4

5

6

7

8

9

10

11

12

13

Case Study Format Questions:

© 2010 PROJstudy.com 106Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 107:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Progress

1. Which two management products among the following are NOT used for progress reporting?a) Exception Reportb) Checkpoint Reportc) End Stage Reportd) Issue Reporte) Highlight ReportCorrect Answer: A, DJustification:The following management products are used for progress reporting:

Checkpoint Report Highlight Report End Stage Report End Project Report

Reference: Figure 9.1 Managing Successful Project with PRINCE2, page 109

2. Which two of the following do NOT assist the Project Manager in establishing the baselines for progress control?a) Exception Planb) Work Packages c) Stage Plans d) Daily Loge) Quality RegisterCorrect Answer: D, EJustification:The following management products assist the Project Manager in establishing baselines for progress control

Project plan Stage plan Exception plan Work package

Reference: Managing Successful Project with PRINCE2, page 106

© 2010 PROJstudy.com 107Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 108:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Starting up a Project

Key to Process Diagrams

Table 11.2 Managing Successful Project with PRINCE2, page 117“©Crown copyright 2009 Reproduced under licence from OGC”

© 2010 PROJstudy.com 108Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 109:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Starting up a Project

Section 1 (12.1 to 12.4.1)

12.1 PURPOSE

The purpose of the Starting up a Project process is to ensure that the prerequisites for _____________________ are in place by answering the question: do we have a viable and worthwhile project?

Starting up a Project is a lighter process compared to the more detailed and thorough Initiating a Project process. The aim is to do the minimum necessary in order to decide whether it is worthwhile to even initiate the project.

12.2 OBJECTIVE

The objectives of the Starting up a Project process are to ensure that: There is a ___________________ justification for initiating the project

(documented in an outline Business Case).

All the necessary ___________________ exist for initiating the project.

Sufficient information is available to define and confirm the scope of the project (in the form of a Project Brief)

The various ways the project can be delivered are evaluated and a project ___________________ selected

Individuals are appointed who will undertake the work required in project _____________________________ and/or will take significant project management roles in the project

The work required for project initiation is planned (documented in a Stage Plan)

Time is not wasted initiating a project based on unsound assumptions regarding the project’s scope, timescales, acceptance criteria and constraints.

© 2010 PROJstudy.com 109Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 110:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Starting up a Project

Figure 12.1, page 121, Managing Successful Projects with PRINCE2, “©Crown copyright 2009 Reproduced under licence from OGC”

Please look at the above diagram and answer the following questions:

1) What is the process interacting with the Starting up a Project process?

© 2010 PROJstudy.com 110Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 111:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Starting up a Project

2) What are the triggers to and from this process?

3) List the sequence of activities in this process:

© 2010 PROJstudy.com 111Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 112:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Starting up a Project

12.3 CONTEXT

PRINCE2 calls the trigger for the project the project mandate, which is provided by the responsible authority which is commissioning the project - typically the corporate or programme management organization.

In a supplier environment, the term __________________applies to whatever information is used to trigger the project, be it a feasibility study or the receipt of a 'request for proposal'.

The project mandate should provide the terms of reference for the project and should contain sufficient information to identify at least the prospective __________________ of the Project Board.

If the project is part of a programme, the programme itself should provide the Project Brief and will appoint some, if not all, members of the _____________________.

Project Brief(For Composition, refer Appendix A, p.253 of the manual.)

It is a statement that describes the purpose, cost, time and performance requirements, and constraints for a project. It is created pre-project during the Starting up a Project process and is used during the Initiating a Project process to create the Project Initiation Documentation.

The contents of the _________________ are later extended and refined into the Project Initiation Documentation via the Initiating a Project process.12.4 ACTIVITIES

The activities within the Starting up a Project process are likely to be shared between corporate or programme management, the Executive and the_____________________.

The activities within the Starting up a Project process are:o Appoint the Executive and the Project Managero Capture previous lessonso Design and appoint the project management teamo Prepare the outline Business Caseo Select the project approach and assemble the Project Briefo Plan the initiation stage.

Figure 12.2, Managing Successful Projects with PRINCE2, page 122 “©Crown copyright 2009 Reproduced under licence from OGC”

12.4.1 Appoint the Executive and the Project Manager The appointment of the ___________________ is a prerequisite to ensure that the project is justified. The appointment of a ________________ allows for the project to be managed on a day-to-day basis on behalf of the ________________.PRINCE2 recommended actions: The Executive will appoint the Project Manager Create the Daily Log as a repository for project information that is not yet being captured elsewhere

Section 1 – QuestionsSL. No Question

1. The purpose of the Starting up a Project process is to ensure that the prerequisites for ___________ process are in place.

2. Is the following statement true?“Starting up a Project is a much lighter process than Initiating a Project process and aims to do the minimum necessary in order to enable the corporate management to decide whether it is worthwhile to even initiate the project.”

3. Which of the following is NOT an objective of Starting up a Project process?o To ensure that there is a business justification for initiating the projecto To ensure that all the necessary authorities exist for initiating the projecto To ensure that there is sufficient information available to define and confirm the

scope of the projecto To ensure that there is common understanding of how and when the project’s

products will be delivered and at what cost4. Which of the following best defines the Project Mandate?

o It is a special type of product description, which is used to gain Senior User’s approval on the project scope.

o It is a trigger for the project, which is provided by the authority responsible for commissioning the project.

o It is a high-level plan showing the important products of the project.o It is a statement describing the purpose, cost, time, performance requirements and

constraints of the project.5. The project mandate should provide the terms of reference for the project and should contain sufficient

information to identify at least the prospective ________ of the Project Board.6. The contents of the Project Brief are extended and refined into the ______________ through the

Initiating a Project process.7. Which of the following is NOT an activity within the Starting up a Project process?

o Appoint the Executive and the Project Managero Capture previous lessonso Select the project approach and assemble the Project Briefo Refine the Business Case and prepare the Configuration Management Strategy

Section 2 (12.4.2 – 12.4.6)12.4.2 Capture previous lessons

When moving from the general view in Starting up a Project to the detailed view in Initiating a Project and updated view in Managing a Stage Boundary, it may be necessary to look beyond the ________________, by repeating this activity, to capture any further relevant external lessons.Figure 12.3, Managing Successful Projects with PRINCE2, page 124

“©Crown copyright 2009 Reproduced under licence from OGC”12.4.3 Design and appoint the project management team

PRINCE2 recommended actions Consider whether separate individuals are likely to be needed as Team Manager(s) or whether the Project Manager

will be filling this role. Consider whether the Project Manager will be performing the Project Support role or whether a separate individual(s)

will be required. Figure 12.4, Managing Successful Projects with PRINCE2, page 125 “©Crown copyright 2009 Reproduced under licence from OGC”

12.4.4 Prepare the outline Business Case The _______________ states______________ the work is worth doing and, as such, is a crucial element of the

project. lf the project is part of a programme, then the Business Case may already have been defined at the _____________

level, e.g., a programme of building and launching a satellite system will include projects that involve creation of various parts of the satellite system like wings, rocket motors, solar panels, fuel tanks, etc. The Business Case for these projects will be provided by the programme itself.

© 2010 PROJstudy.com 112Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 113:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Starting up a Project

The outline _________________ provides an agreed foundation for a more extensive Business Case developed in the _________________ process.

Figure 12.5, Managing Successful Projects with PRINCE2, page 127 “©Crown copyright 2009 Reproduced under licence from OGC”PRINCE2 recommended actions _______________ will draft the outline Business Case based on what is currently known about the project:

o Understand the objectives of, and the reasons for, the project as defined in the project mandateo Understand how the project will contribute toward corporate and/or programme objectiveso Understand how the project will be fundedo Review the Lessons Log for lessons related to business justificationo Check for any standards mandated for the format and presentation of the Business Case (templates, cost

metrics etc.)o Assemble any relevant background information, e.g. contracts, feasibility reports, service level agreements

etc.o lf necessary, seek approval of the outline Business Case from corporate or programme management

_________________ to consult with the Senior _________and__________ to define what the project is to deliver and create the Project Product Description (see Chapter 6).

12.4.5 Select the project approach and assemble the Project Brief Project Approach: how the work of the project is going to be approached. For example, will the solution be developed

in-house or contracted to third parties? Will the solution be a modification to an existing product or built from scratch? The way in which the work is to be conducted will depend on any customer or supplier standards, practices and

guidelines. An agreed _____________ ensures that the project has a commonly understood and well-defined start point.Assemble the Project Brief: Define the project

o Confirm the objectives and desired outcomeso Confirm the project scope and exclusionso Identify any constraints and assumptionso Identify the project toleranceso Identify the user(s) and any other known interested partieso Identify the interfaces that the project must maintain

Incorporate the outline Business Case Incorporate the Project Product Description Incorporate the project approach

Figure 12.6, page 129, Managing Successful Projects with PRINCE2 “©Crown copyright 2009 Reproduced under licence from OGC”

12.4.6 Plan the Initiation Stage If the project is part of a programme, the end date for the __________________ should be checked against that held

in the programme's plans. The __________________ for the initiation stage will also give the programme management team warning of any

requirements from the programme.PRINCE2 recommended actions:

Review the Lessons Log for lessons related to project controls Define the reporting and control arrangements for the initiation stage Request authorization to initiate the project.

Figure 12.7, page 130, Managing Successful Projects with PRINCE2 “©Crown copyright 2009 Reproduced under licence from OGC”Responsibilities in the Starting up a Project process:

Section 2 – QuestionsSl. No Question

1 An ____________ ensures that the project has a commonly understood and well-defined start point

2 Who drafts the outline Business case?3 Which of the following provides an agreed foundation for a more extensive

Business Case developed in the Initiating a Project process?A. Product DescriptionB. Lessons LogC. Outline Business CaseD. Project Product Description

4 Who creates the Project Product Description?5 If the project is part of a Programme, then the Business Case may already

have been defined at the programme level: True or False6 Which of the following states why the project is worth taking up?

A. Product Status AccountB. Project mandateC. Investment analysisD. Business Case

© 2010 PROJstudy.com 113Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 114:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Starting up a Project

Sample TestQuestion

No Answer Comment

1

2

3

Chapter TestQuestion

No Answer Comment

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

© 2010 PROJstudy.com 114Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 115:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Starting up a Project

Case Study Format Questions

Which two of the following activities/actions will the Executive and the Project Manager perform to assemble the Project Brief?A. Identify and use the aspects of corporate strategies that are related to configuration management to develop a strategy suitable for the project. B. Create the Risk Register and update it with preliminary information on identified risks.C. Prepare and get the approval from the Project Board for all the relevant plans of the project.D. Select and decide on how the project work will be approached.E. Determine whether the Project Management Team needs any additional training to carry out the project work efficiently.Correct Answer: D & EJustification:A. Incorrect. Plan project closure is an activity done within the Directing a Project process.B. Incorrect. Risk Register is created during the Initiation stage.C. Incorrect. The plans related to the project are created and authorized after the project is initiated. D. Correct. The project approach has to be selected and included in the Project Brief before it is sent to the corporate management for approval of project initiation. Ref: ‘PRINCE2 OGC Managing Successful Projects with Prince2’. 12.4. Page 122E. Correct. The Project Manager must consider whether the appointed Project Management Team requires any additional training to aid them in project execution.

2. Column 1 contains an activity that is performed under a management strategy. Select from column 2 the management strategy responsible for the activity.

Column 1 Column 21 The Project Support must maintain the project

records in a manner that is accessible to the Project Board and the Project Management Team at any point time during project execution.

A. Configuration Management Strategy

B. Communication Management StrategyC. Quality Management StrategyD. Risk Management Strategy

Correct Answer: AJustification:1 Correct [A] This should be included in the configuration Management

strategy because it relates to maintenance of project records. Ref: 14.4.2. Prince2 Managing Successful Projects with Prince2. Page 152

© 2010 PROJstudy.com 115Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 116:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Directing a Project

13.1 PURPOSE The purpose of the Directing a Project process is to enable the __________

______________ to be accountable for the____________ success by making key decisions and exercising overall control while delegating day-to- day management of the project to the ___________ _____________.

13.2 OBJECTIVE

The main objectives of the process are:

a) To ensure that there is authority to initiate the project, to deliver the project’s products, to close the project.

b) To ensure that there is management direction and control throughout the project’s life, and that project remains viable.

c) To ensure that the corporate or programme management has an interface to the project.

d) To ensure that there are plans for realizing the post-project benefits.

Figure 13.1, Managing Successful Projects with PRINCE2, page 135 “©Crown copyright 2009 Reproduced under licence from OGC”

Please look at the above diagram and answer the following questions:

© 2010 PROJstudy.com 116Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 117:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Directing a Project

1) What are the processes interacting with the Directing a Project process?

2) What are the triggers to and from this process?

3) List the sequence of activities in this process:

© 2010 PROJstudy.com 117Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 118:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Directing a Project

13.3 CONTEXT

The Directing a Project process starts on completion of the ____________________ process and is triggered by the request to________________.

The Project Board manages by exception. There needs to be a two-way flow of information between the _______________ and corporate or programme

management during the project. The Project Board should provide unified direction and guidance to the_____________________. If the Project Board is unable to provide a single view or if independent, possibly contradictory, advice is given, then the

risk of project failure significantly increases. In such cases, the Project Manager should defer to the __________________.

The Project ______________ is responsible for assuring that there is continued business justification.13.4 ACTIVITIES

Figure 13.2, Managing Successful Projects with PRINCE2, page 136 “©Crown copyright 2009 Reproduced under licence from OGC”13.4.1 Authorize initiation

The Project Board may appoint _______________to undertake some of the reviewing and assessing actions. PRINCE2 recommends the following actions:

o Review and approve the ___________o Review and approve the ___________________o Verify the outline _________________o Review and approve the Stage Plan for the __________________o Authorize the ____________________ to proceed with the initiation stage

13.4.2 Authorize the project This activity will be triggered by a request from the _______________for authorization to ______________________

the project It should be performed in parallel with authorizing a ________________or_____________________ plan If the project is not authorized by the Project Board, then it should be prematurely ____________________.

Figure 13.3, Managing Successful Projects with PRINCE2, page 138 “©Crown copyright 2009 Reproduced under licence from OGC”

PRINCE2 recommends the following actions: Review and approve the ______________________ :

o Confirm that the project definition is accurate and complete and that the project approach is achievableo Confirm that lessons from previous similar projects have been reviewed and incorporatedo Confirm that the _________________ Strategy is sufficient to ensure that the quality expectations will be met,

and approve ito Confirm that the procedures defined in the __________________ Strategy are sufficient to keep the risks under

control, and approve it. o Confirm that the ______________________ Strategy will adequately control the status (versions and variants)

of the project’s products, and approve ito Ensure that the _______________ information needs and timing of communications, as defined in the

_____________________ Strategy, are adequateo Ensure that the project ___________ are adequate for the nature of the projecto Review and approve the Product Description(s)o Review the tolerances for the project provided by corporate or programme management to ensure they are

appropriate and realistico Verify that the ________________ demonstrates a viable project

Review and approve the ______________________ Plan. Notify _____________________ management and other interested parties that the project has been authorized.

13.4.3 Authorize a Stage or Exception Plan The ___________________ authorizes a management stage by reviewing the performance of the current stage and

approving the Stage Plan for the next stage. If an exception has occurred during the stage, the Project Board may request that the Project Manager produces

an_________________ Plan for Project Board approval. ____________________ exceptions are managed by the Project Manager using the ___________________

process

Figure 13.4, Managing Successful Projects with PRINCE2, page 140 “©Crown copyright 2009 Reproduced under licence from OGC”

PRINCE2 recommends the following actions:o Review the Stage Plan or Exception Plan for which the __________________ is seeking approval:

Confirm the validity and achievability of the Stage Plan/Exception Plan Review and approve any new Product Description(s) Confirm the validity and achievability of the ________ Plan. If necessary Secure appropriate approvals

from corporate or programme Management Confirm the strategies and project controls in the (updated) ___________________________ are

adequate for the remainder of the projecto Make a decision:

Approve the plan(s) and authorize the Project Manager to proceed with the submitted plan(s) Or instruct the Project Manager to initiate premature closure of the project

13.4.4 Give ad hoc direction

© 2010 PROJstudy.com 118Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 119:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Directing a Project

The need for consultation between the Project Manager and Project Board is likely to be particularly frequent during the ___________________ stage and when approaching stage boundaries.

Ad hoc direction may be given collectively or by individual __________________ members.

There are a variety of circumstances that might prompt ad hoc direction, including:o Responding to requests o Responding to reports o Responding to external influences o Project Board members’ individual concernso Responding to changes in Project Board composition

Figure 13.5, Managing Successful Projects with PRINCE2, page 142 “©Crown copyright 2009 Reproduced under licence from OGC”

PRINCE2 recommends the following actions:o In response to informal requests for advice and guidance:

Assist the Project Manager as required (this may include asking the Project Manager to produce an Issue Report and/or an Exception Report)

o In response to an escalated Issue Report: Seek advice from ____________________management if necessary. Make a decision within the Project Board’s delegated limits of _______________. This decision could

be regarding: A problem/concern An off-specification: Grant a concession, defer, reject or ask for more information.

In response to an Exception Report :o Increase the tolerances that are forecast to be breachedo Instruct the Project Manager to produce an __________________Plan o Instruct the Project Manager to close the project prematurelyo Defer the ___________________for a fixed period of time.

In response to the receipt of a Highlight Report:o Review the Highlight Reporto Ensure that the project remains focused on the corporate or programme objectives seto Ensure that the stage is progressing according to____________________o Keep corporate or programme management and other interested parties informed about project

progresso Take actions as necessary.

13.4.5 Authorize project closure There must be a point when the objectives set out in the original and current versions of the

_____________________________________ and _______________ Plan are assessed in order to understand:o Whether the objectives have been achievedo How the project has deviated from its initial basiso That the project has nothing more to contribute.Figure 13.6, Managing Successful Projects with PRINCE2, page 144 “©Crown copyright 2009 Reproduced under licence from OGC”

PRINCE2 recommends the following actions:o Review the ______ Report and agree who should receive it.o Verify that the handover of the project’s ________ was in accordance with the ____________________

Strategyo Confirm the updated Business Case by comparing actual and forecast benefits, costs and risks against the

original Business Case that was used to justify the project.Responsibilities in the Directing a Project process:

QuestionsSl. No Question

1 Which of the following is not an objective of Directing a Project process? Ensuring that there is management direction and control

throughout the project’s life. Ensuring that plans are in place for realizing the post-project

benefits. Ensuring that there is authority to initiate the project. Ensuring that Team Managers send Checkpoint Reports as

agreed format and frequency documented in the accepted Work Packages.

2 The Project Board activity that ensures that project initiation is planned, monitored, and controlled is:

3 The ___________ instructs the Project Manager to proceed with project initiation.

4 Authorize the project activity should be performed in parallel with __________________________ activity.

5 If the Project Board does not authorize the project, then the project will be prematurely ____________.

6 During authorize the project activity; the Project Board reviews the

© 2010 PROJstudy.com 119Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 120:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Directing a Project

_________ __________ __________ to confirm that the project definition is accurate and complete.

7 Which of the following strategies ensures that the project’s products are adequately controlled and managed?

Communication Management Strategy Configuration Management Strategy Risk Management Strategy

8 The ____________ management must approve the Project Plan if it is found that the project tolerance limits will be exceeded.

9 Who will produce the Exception Plan?10 Who will manage the exceptions related to Work Packages?11 The management strategies and the controls pertaining to the project are

documented in_________________.12 ________ _________ Plan ensures that any benefits planned to be

achieved are measured and reviewed.13 The need for consultation between the Project Manager and Project Board

is likely to be particularly frequent during the _______ stage and when approaching stage boundaries.

14 The last activity undertaken by the Project Board before it is disbanded is ______ ________ _________.

© 2010 PROJstudy.com 120Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 121:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Directing a Project

Sample TestQuestion

No Answer Comment

1

2

3

Chapter TestQuestion

No Answer Comment

1

2

3

4

5

6

7

8

9

10

11

12

13

14

© 2010 PROJstudy.com 121Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 122:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Directing a Project

Case Study Format QuestionsQuestions 1 and 2 contain an assertion statement and a reason statement. For each question identify the appropriate option, from options A to E, that applies. Each option may be used once, more than once, or not at all.Option Assertion ReasonA True True And the reason explains the assertionB True True And the reason does not explain the assertionC True FalseD False TrueE False False1. Assertion: The Project Board can appoint Project Assurance to review the Initiation Stage Plan.Because Reason: The Project Board can delegate its responsibility of reviewing and assessing the Initiation Stage Plan to Project Assurance.Correct Answer: CJustification:The Project Board may appoint Project Assurance to undertake some of the reviewing and assessing actions (e.g. inspecting the Initiation Stage Plan to confirm it is viable).Reference: Managing Successful Project with PRINCE2, page 136APMGstudy.com comments:The Project Board cannot delegate its responsibilities; however, it can delegate its authority to perform certain actions. So, the reason statement is not true.

2.Assertion: Handing over of the project’s products should be in accordance with the Configuration Management Strategy.Because Reason: The Configuration Management strategy describes how and by whom the project’s products will be controlled and protected.Correct Answer: AJustification:PRINCE2 recommends the Project Board to verify whether the handing over of the project’s products was in accordance with the Configuration Management Strategy.The Configuration Management strategy is a description of how and by whom the project’s products will be controlled and protected.

Reference: Managing Successful Project with PRINCE2, pages 144 and 304

© 2010 PROJstudy.com 122Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 123:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Initiating a Project

14.1 PURPOSE

The purpose of the _____________________ process is to establish solid foundations for the project, enabling the organization to understand the work that needs to be done to deliver the project’s ________________________ before committing to a significant spend.

14.2 OBJECTIVE

The objective of the Initiating a Project process is to ensure that there is a common understanding of:

The reasons for doing the project, the benefits expected and the associated risks

The scope of what is to be done and the products to be delivered How and when the project’s products will be delivered and at what cost Who is to be involved in the project decision making How the quality required will be achieved How baselines will be established and controlled How risks, issues and changes will be identified, assessed and

controlled How progress will be monitored and controlled Who needs information, in what format, and at what time

© 2010 PROJstudy.com 123Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 124:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Initiating a Project

Figure 14.1, Managing Successful Projects with PRINCE2, page 149 “©Crown copyright 2009 Reproduced under licence from OGC”

Please look at the above diagram and answer the following questions:

1) What are the processes interacting with the Initiating a Project process?

© 2010 PROJstudy.com 124Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 125:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Initiating a Project

2) What are the triggers to and from this process?

3) List the sequence of activities in this process:

© 2010 PROJstudy.com 125Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 126:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Initiating a Project

The Directing a Project process starts on completion of the ____________________ process and is triggered by the request to________________.

The Project Board manages by exception. There needs to be a two-way flow of information between the _______________ and corporate or programme

management during the project. The Project Board should provide unified direction and guidance to the_____________________. If the Project Board is unable to provide a single view or if independent, possibly contradictory, advice is given, then the

risk of project failure significantly increases. In such cases, the Project Manager should defer to the __________________.

The Project ______________ is responsible for assuring that there is continued business justification.13.4 ACTIVITIES

Figure 13.2, Managing Successful Projects with PRINCE2, page 136 “©Crown copyright 2009 Reproduced under licence from OGC”13.4.1 Authorize initiation

The Project Board may appoint _______________to undertake some of the reviewing and assessing actions. PRINCE2 recommends the following actions:

o Review and approve the ___________o Review and approve the ___________________o Verify the outline _________________o Review and approve the Stage Plan for the __________________o Authorize the ____________________ to proceed with the initiation stage

13.4.2 Authorize the project This activity will be triggered by a request from the _______________for authorization to ______________________

the project It should be performed in parallel with authorizing a ________________or_____________________ plan If the project is not authorized by the Project Board, then it should be prematurely ____________________.

Figure 13.3, Managing Successful Projects with PRINCE2, page 138 “©Crown copyright 2009 Reproduced under licence from OGC”

PRINCE2 recommends the following actions: Review and approve the ______________________ :

o Confirm that the project definition is accurate and complete and that the project approach is achievableo Confirm that lessons from previous similar projects have been reviewed and incorporatedo Confirm that the _________________ Strategy is sufficient to ensure that the quality expectations will be met,

and approve ito Confirm that the procedures defined in the __________________ Strategy are sufficient to keep the risks under

control, and approve it. o Confirm that the ______________________ Strategy will adequately control the status (versions and variants)

of the project’s products, and approve ito Ensure that the _______________ information needs and timing of communications, as defined in the

_____________________ Strategy, are adequateo Ensure that the project ___________ are adequate for the nature of the projecto Review and approve the Product Description(s)o Review the tolerances for the project provided by corporate or programme management to ensure they are

appropriate and realistico Verify that the ________________ demonstrates a viable project

Review and approve the ______________________ Plan. Notify _____________________ management and other interested parties that the project has been authorized.

13.4.3 Authorize a Stage or Exception Plan The ___________________ authorizes a management stage by reviewing the performance of the current stage and

approving the Stage Plan for the next stage. If an exception has occurred during the stage, the Project Board may request that the Project Manager produces

an_________________ Plan for Project Board approval. ____________________ exceptions are managed by the Project Manager using the ___________________

process

Figure 13.4, Managing Successful Projects with PRINCE2, page 140 “©Crown copyright 2009 Reproduced under licence from OGC”

PRINCE2 recommends the following actions:o Review the Stage Plan or Exception Plan for which the __________________ is seeking approval:

Confirm the validity and achievability of the Stage Plan/Exception Plan Review and approve any new Product Description(s) Confirm the validity and achievability of the ________ Plan. If necessary Secure appropriate approvals

from corporate or programme Management Confirm the strategies and project controls in the (updated) ___________________________ are

adequate for the remainder of the projecto Make a decision:

Approve the plan(s) and authorize the Project Manager to proceed with the submitted plan(s) Or instruct the Project Manager to initiate premature closure of the project

13.4.4 Give ad hoc direction The need for consultation between the Project Manager and Project Board is likely to be particularly frequent during

the ___________________ stage and when approaching stage boundaries.

© 2010 PROJstudy.com 126Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 127:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Initiating a Project

Ad hoc direction may be given collectively or by individual __________________ members.

There are a variety of circumstances that might prompt ad hoc direction, including:o Responding to requests o Responding to reports o Responding to external influences o Project Board members’ individual concernso Responding to changes in Project Board composition

Figure 13.5, Managing Successful Projects with PRINCE2, page 142 “©Crown copyright 2009 Reproduced under licence from OGC”

PRINCE2 recommends the following actions:o In response to informal requests for advice and guidance:

Assist the Project Manager as required (this may include asking the Project Manager to produce an Issue Report and/or an Exception Report)

o In response to an escalated Issue Report: Seek advice from ____________________management if necessary. Make a decision within the Project Board’s delegated limits of _______________. This decision could

be regarding: A problem/concern An off-specification: Grant a concession, defer, reject or ask for more information.

In response to an Exception Report :o Increase the tolerances that are forecast to be breachedo Instruct the Project Manager to produce an __________________Plan o Instruct the Project Manager to close the project prematurelyo Defer the ___________________for a fixed period of time.

In response to the receipt of a Highlight Report:o Review the Highlight Reporto Ensure that the project remains focused on the corporate or programme objectives seto Ensure that the stage is progressing according to____________________o Keep corporate or programme management and other interested parties informed about project

progresso Take actions as necessary.

13.4.5 Authorize project closure There must be a point when the objectives set out in the original and current versions of the

_____________________________________ and _______________ Plan are assessed in order to understand:o Whether the objectives have been achievedo How the project has deviated from its initial basiso That the project has nothing more to contribute.Figure 13.6, Managing Successful Projects with PRINCE2, page 144 “©Crown copyright 2009 Reproduced under licence from OGC”

PRINCE2 recommends the following actions:o Review the ______ Report and agree who should receive it.o Verify that the handover of the project’s ________ was in accordance with the ____________________

Strategyo Confirm the updated Business Case by comparing actual and forecast benefits, costs and risks against the

original Business Case that was used to justify the project.Responsibilities in the Directing a Project process:

QuestionsSl. No Question

1 Which of the following is not an objective of Directing a Project process? Ensuring that there is management direction and control

throughout the project’s life. Ensuring that plans are in place for realizing the post-project

benefits. Ensuring that there is authority to initiate the project. Ensuring that Team Managers send Checkpoint Reports as

agreed format and frequency documented in the accepted Work Packages.

2 The Project Board activity that ensures that project initiation is planned, monitored, and controlled is:

3 The ___________ instructs the Project Manager to proceed with project initiation.

4 Authorize the project activity should be performed in parallel with __________________________ activity.

5 If the Project Board does not authorize the project, then the project will be prematurely ____________.

6 During authorize the project activity; the Project Board reviews the _________ __________ __________ to confirm that the project definition is accurate and complete.

© 2010 PROJstudy.com 127Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 128:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Initiating a Project

7 Which of the following strategies ensures that the project’s products are adequately controlled and managed?

Communication Management Strategy Configuration Management Strategy Risk Management Strategy

8 The ____________ management must approve the Project Plan if it is found that the project tolerance limits will be exceeded.

9 Who will produce the Exception Plan?10 Who will manage the exceptions related to Work Packages?11 The management strategies and the controls pertaining to the project are

documented in_________________.12 ________ _________ Plan ensures that any benefits planned to be

achieved are measured and reviewed.13 The need for consultation between the Project Manager and Project Board

is likely to be particularly frequent during the _______ stage and when approaching stage boundaries.

14 The last activity undertaken by the Project Board before it is disbanded is ______ ________ _________.

© 2010 PROJstudy.com 128Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 129:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Initiating a Project

Sample TestQuestion

No Answer Comment

1

2

3

Chapter TestQuestion

No Answer Comment

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

© 2010 PROJstudy.com 129Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 130:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Initiating a Project

Case Study Format Questions

Questions 1 and 2 contain an assertion statement and a reason statement. For each line identify the appropriate option from among A, B, C, D and E. Each option may be used once, more than once, or not at all.Option Assertion ReasonA True True And the reason explains the assertionB True True And the reason does not explain the assertionC True FalseD False TrueE False False

1. Assertion: The activities for creating the management strategies can be performed in parallel but it is preferable to create the Communications Management Strategy last.

Because

Reason: Communications Management Strategy should include all the communication requirements documented in all the management strategies.

Correct Answer: AJustification:

The activities to establish the strategies for the project may be executed in parallel, but it is recommended that the Communications Management Strategy is completed last as it will need to include any communications required of the other strategies.

Reference: Managing Successful Projects with PRINCE2, page 150

2.Assertion: To prepare the Risk Management Strategy, the Executive must review the Project Brief and ascertain corporate or programme management strategies, standards or practices relating to risk management.

Because

Reason: The Risk Management Strategy is produced by the Project Manager and approved by the Project Board.

Correct Answer: D

Justification:

Refer table 14.1 in page 151 of Managing Successful Projects with PRINCE2

Reference: Managing Successful Projects with PRINCE2, page 151

© 2010 PROJstudy.com 130Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 131:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Section 1 (15.1 to 15.4.3)

15.1 PURPOSE The purpose of the Controlling a Stage process is to assign work to be done,

monitor such work, deal with issues, report progress to the _________________, and take corrective actions to ensure that the __________________ remains within tolerance.

15.2 OBJECTIVE

The objective of the Controlling a Stage process is to ensure that:o Any movement away from the direction and products agreed at the

start of the stage is ________________to avoid uncontrolled change (‘scope creep’)

o ____________ and issues are kept under controlo The _______________ is kept under reviewo The agreed __________________ for the stage are delivered to stated

quality standards, within cost, effort and time agreedThe project management team is focused on delivery within the tolerances laid down.

© 2010 PROJstudy.com 131Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Controlling a Stage

Page 132:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Figure 15.1, Managing Successful Projects with PRINCE2, page 167“©Crown copyright 2009 Reproduced under licence from OGC”

Please look at the above diagram and answer the following questions:

1) What are the processes interacting with the Controlling a Stage process?

© 2010 PROJstudy.com 132Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Controlling a Stage

Page 133:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

2) What are the triggers to and from this process?

3) List the sequence of activities in this process:

© 2010 PROJstudy.com 133Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Controlling a Stage

Page 134:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

13.3 CONTEXT The Directing a Project process starts on completion of the ____________________ process and is triggered by the

request to________________. The Project Board manages by exception. There needs to be a two-way flow of information between the _______________ and corporate or programme

management during the project. The Project Board should provide unified direction and guidance to the_____________________. If the Project Board is unable to provide a single view or if independent, possibly contradictory, advice is given, then the

risk of project failure significantly increases. In such cases, the Project Manager should defer to the __________________.

The Project ______________ is responsible for assuring that there is continued business justification.13.4 ACTIVITIES

Figure 13.2, Managing Successful Projects with PRINCE2, page 136 “©Crown copyright 2009 Reproduced under licence from OGC”13.4.1 Authorize initiation

The Project Board may appoint _______________to undertake some of the reviewing and assessing actions. PRINCE2 recommends the following actions:

o Review and approve the ___________o Review and approve the ___________________o Verify the outline _________________o Review and approve the Stage Plan for the __________________o Authorize the ____________________ to proceed with the initiation stage

13.4.2 Authorize the project This activity will be triggered by a request from the _______________for authorization to ______________________

the project It should be performed in parallel with authorizing a ________________or_____________________ plan If the project is not authorized by the Project Board, then it should be prematurely ____________________.

Figure 13.3, Managing Successful Projects with PRINCE2, page 138 “©Crown copyright 2009 Reproduced under licence from OGC”

PRINCE2 recommends the following actions: Review and approve the ______________________ :

o Confirm that the project definition is accurate and complete and that the project approach is achievableo Confirm that lessons from previous similar projects have been reviewed and incorporatedo Confirm that the _________________ Strategy is sufficient to ensure that the quality expectations will be met,

and approve ito Confirm that the procedures defined in the __________________ Strategy are sufficient to keep the risks under

control, and approve it. o Confirm that the ______________________ Strategy will adequately control the status (versions and variants)

of the project’s products, and approve ito Ensure that the _______________ information needs and timing of communications, as defined in the

_____________________ Strategy, are adequateo Ensure that the project ___________ are adequate for the nature of the projecto Review and approve the Product Description(s)o Review the tolerances for the project provided by corporate or programme management to ensure they are

appropriate and realistico Verify that the ________________ demonstrates a viable project

Review and approve the ______________________ Plan. Notify _____________________ management and other interested parties that the project has been authorized.

13.4.3 Authorize a Stage or Exception Plan The ___________________ authorizes a management stage by reviewing the performance of the current stage and

approving the Stage Plan for the next stage. If an exception has occurred during the stage, the Project Board may request that the Project Manager produces

an_________________ Plan for Project Board approval. ____________________ exceptions are managed by the Project Manager using the ___________________

process

Figure 13.4, Managing Successful Projects with PRINCE2, page 140 “©Crown copyright 2009 Reproduced under licence from OGC”

PRINCE2 recommends the following actions:o Review the Stage Plan or Exception Plan for which the __________________ is seeking approval:

Confirm the validity and achievability of the Stage Plan/Exception Plan Review and approve any new Product Description(s) Confirm the validity and achievability of the ________ Plan. If necessary Secure appropriate approvals

from corporate or programme Management Confirm the strategies and project controls in the (updated) ___________________________ are

adequate for the remainder of the projecto Make a decision:

Approve the plan(s) and authorize the Project Manager to proceed with the submitted plan(s) Or instruct the Project Manager to initiate premature closure of the project

© 2010 PROJstudy.com 134Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Controlling a Stage

Page 135:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

13.4.4 Give ad hoc direction The need for consultation between the Project Manager and Project Board is likely to be particularly frequent during

the ___________________ stage and when approaching stage boundaries. Ad hoc direction may be given collectively or by individual __________________ members. There are a variety of circumstances that might prompt ad hoc direction, including:

o Responding to requests o Responding to reports o Responding to external influences o Project Board members’ individual concernso Responding to changes in Project Board composition

Figure 13.5, Managing Successful Projects with PRINCE2, page 142 “©Crown copyright 2009 Reproduced under licence from OGC”

PRINCE2 recommends the following actions:o In response to informal requests for advice and guidance:

Assist the Project Manager as required (this may include asking the Project Manager to produce an Issue Report and/or an Exception Report)

o In response to an escalated Issue Report: Seek advice from ____________________management if necessary. Make a decision within the Project Board’s delegated limits of _______________. This decision could

be regarding: A problem/concern An off-specification: Grant a concession, defer, reject or ask for more information.

In response to an Exception Report :o Increase the tolerances that are forecast to be breachedo Instruct the Project Manager to produce an __________________Plan o Instruct the Project Manager to close the project prematurelyo Defer the ___________________for a fixed period of time.

In response to the receipt of a Highlight Report:o Review the Highlight Reporto Ensure that the project remains focused on the corporate or programme objectives seto Ensure that the stage is progressing according to____________________o Keep corporate or programme management and other interested parties informed about project

progresso Take actions as necessary.

13.4.5 Authorize project closure There must be a point when the objectives set out in the original and current versions of the

_____________________________________ and _______________ Plan are assessed in order to understand:o Whether the objectives have been achievedo How the project has deviated from its initial basiso That the project has nothing more to contribute.Figure 13.6, Managing Successful Projects with PRINCE2, page 144 “©Crown copyright 2009 Reproduced under licence from OGC”

PRINCE2 recommends the following actions:o Review the ______ Report and agree who should receive it.o Verify that the handover of the project’s ________ was in accordance with the ____________________

Strategyo Confirm the updated Business Case by comparing actual and forecast benefits, costs and risks against the

original Business Case that was used to justify the project.Responsibilities in the Directing a Project process:

QuestionsSl. No Question

1 Which of the following is not an objective of Directing a Project process? Ensuring that there is management direction and control

throughout the project’s life. Ensuring that plans are in place for realizing the post-project

benefits. Ensuring that there is authority to initiate the project. Ensuring that Team Managers send Checkpoint Reports as

agreed format and frequency documented in the accepted Work Packages.

2 The Project Board activity that ensures that project initiation is planned, monitored, and controlled is:

3 The ___________ instructs the Project Manager to proceed with project initiation.

4 Authorize the project activity should be performed in parallel with __________________________ activity.

5 If the Project Board does not authorize the project, then the project will be prematurely ____________.

© 2010 PROJstudy.com 135Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Controlling a Stage

Page 136:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

6 During authorize the project activity; the Project Board reviews the _________ __________ __________ to confirm that the project definition is accurate and complete.

7 Which of the following strategies ensures that the project’s products are adequately controlled and managed?

Communication Management Strategy Configuration Management Strategy Risk Management Strategy

8 The ____________ management must approve the Project Plan if it is found that the project tolerance limits will be exceeded.

9 Who will produce the Exception Plan?10 Who will manage the exceptions related to Work Packages?11 The management strategies and the controls pertaining to the project are

documented in_________________.12 ________ _________ Plan ensures that any benefits planned to be

achieved are measured and reviewed.13 The need for consultation between the Project Manager and Project Board

is likely to be particularly frequent during the _______ stage and when approaching stage boundaries.

14 The last activity undertaken by the Project Board before it is disbanded is ______ ________ _________.

© 2010 PROJstudy.com 136Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Controlling a Stage

Page 137:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Sample TestQuestion

No Answer Comment

1

2

3

Chapter TestQuestion

No Answer Comment

1

2

3

4

5

6

7

8

9

10

11

12

13

14

© 2010 PROJstudy.com 137Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Controlling a Stage

Page 138:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Case Study Format Question

1. Which of the following activities does a Project Manager perform when the Stage Plan for a management stage is approved by the Project Board?A. Review the Checkpoint Report of the previous stage.B. Update the issues in the Issue Register.C. Agree the Work Package tolerances with the Team Manager/s.D. Prepare the Stage Plan for the next management stage.Correct Answer: CJustification:Option A: This option is incorrect. This activity is performed before the Stage Plan for the ensuing stage is authorized.Option B: This option is incorrect. This is done during the review of received Work Packages.Option C: This option is correct. Stage authorization is a trigger to the Project Manager to agree and authorize Work Packages for the concerned stage.Option D: This option is incorrect. This is carried out at the end of a stage and not at the beginning.Reference: OGC Managing Successful Projects with PRINCE2, page 168

© 2010 PROJstudy.com 138Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Controlling a Stage

Page 139:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Managing Product Delivery

16.1 PURPOSE The purpose of the Managing Product Delivery process is to control the link

between the __________________ and the_____________________, by placing formal requirements on accepting, executing and delivering project work.

16.2 OBJECTIVE This process aims to ensure that the Work Packages are authorized and

agreed; the team knows what, when, and how products are to be delivered; the work is carried out and monitored as per the plan.

Figure 16.1, Managing Successful Projects with PRINCE2, page 18“©Crown copyright 2009 Reproduced under licence from OGC”

Please look at the above diagram and answer the following questions:

1) What is the process interacting with the Managing Product Delivery process?

© 2010 PROJstudy.com 139Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 140:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Managing Product Delivery

2) What are the triggers to and from this process?

3) List the sequence of activities in this process:

© 2010 PROJstudy.com 140Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 141:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Managing Product Delivery

13.3 CONTEXT The Directing a Project process starts on completion of the ____________________ process and is triggered by the

request to________________. The Project Board manages by exception. There needs to be a two-way flow of information between the _______________ and corporate or programme

management during the project. The Project Board should provide unified direction and guidance to the_____________________. If the Project Board is unable to provide a single view or if independent, possibly contradictory, advice is given, then the

risk of project failure significantly increases. In such cases, the Project Manager should defer to the __________________.

The Project ______________ is responsible for assuring that there is continued business justification.13.4 ACTIVITIES

Figure 13.2, Managing Successful Projects with PRINCE2, page 136 “©Crown copyright 2009 Reproduced under licence from OGC”13.4.1 Authorize initiation

The Project Board may appoint _______________to undertake some of the reviewing and assessing actions. PRINCE2 recommends the following actions:

o Review and approve the ___________o Review and approve the ___________________o Verify the outline _________________o Review and approve the Stage Plan for the __________________o Authorize the ____________________ to proceed with the initiation stage

13.4.2 Authorize the project This activity will be triggered by a request from the _______________for authorization to ______________________

the project It should be performed in parallel with authorizing a ________________or_____________________ plan If the project is not authorized by the Project Board, then it should be prematurely ____________________.

Figure 13.3, Managing Successful Projects with PRINCE2, page 138 “©Crown copyright 2009 Reproduced under licence from OGC”

PRINCE2 recommends the following actions: Review and approve the ______________________ :

o Confirm that the project definition is accurate and complete and that the project approach is achievableo Confirm that lessons from previous similar projects have been reviewed and incorporatedo Confirm that the _________________ Strategy is sufficient to ensure that the quality expectations will be met,

and approve ito Confirm that the procedures defined in the __________________ Strategy are sufficient to keep the risks under

control, and approve it. o Confirm that the ______________________ Strategy will adequately control the status (versions and variants)

of the project’s products, and approve ito Ensure that the _______________ information needs and timing of communications, as defined in the

_____________________ Strategy, are adequateo Ensure that the project ___________ are adequate for the nature of the projecto Review and approve the Product Description(s)o Review the tolerances for the project provided by corporate or programme management to ensure they are

appropriate and realistico Verify that the ________________ demonstrates a viable project

Review and approve the ______________________ Plan. Notify _____________________ management and other interested parties that the project has been authorized.

13.4.3 Authorize a Stage or Exception Plan The ___________________ authorizes a management stage by reviewing the performance of the current stage and

approving the Stage Plan for the next stage. If an exception has occurred during the stage, the Project Board may request that the Project Manager produces

an_________________ Plan for Project Board approval. ____________________ exceptions are managed by the Project Manager using the ___________________

process

Figure 13.4, Managing Successful Projects with PRINCE2, page 140 “©Crown copyright 2009 Reproduced under licence from OGC”

PRINCE2 recommends the following actions:o Review the Stage Plan or Exception Plan for which the __________________ is seeking approval:

Confirm the validity and achievability of the Stage Plan/Exception Plan Review and approve any new Product Description(s) Confirm the validity and achievability of the ________ Plan. If necessary Secure appropriate approvals

from corporate or programme Management Confirm the strategies and project controls in the (updated) ___________________________ are

adequate for the remainder of the projecto Make a decision:

Approve the plan(s) and authorize the Project Manager to proceed with the submitted plan(s)

© 2010 PROJstudy.com 141Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 142:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Managing Product Delivery

Or instruct the Project Manager to initiate premature closure of the project13.4.4 Give ad hoc direction

The need for consultation between the Project Manager and Project Board is likely to be particularly frequent during the ___________________ stage and when approaching stage boundaries.

Ad hoc direction may be given collectively or by individual __________________ members.

There are a variety of circumstances that might prompt ad hoc direction, including:o Responding to requests o Responding to reports o Responding to external influences o Project Board members’ individual concernso Responding to changes in Project Board composition

Figure 13.5, Managing Successful Projects with PRINCE2, page 142 “©Crown copyright 2009 Reproduced under licence from OGC”

PRINCE2 recommends the following actions:o In response to informal requests for advice and guidance:

Assist the Project Manager as required (this may include asking the Project Manager to produce an Issue Report and/or an Exception Report)

o In response to an escalated Issue Report: Seek advice from ____________________management if necessary. Make a decision within the Project Board’s delegated limits of _______________. This decision could

be regarding: A problem/concern An off-specification: Grant a concession, defer, reject or ask for more information.

In response to an Exception Report :o Increase the tolerances that are forecast to be breachedo Instruct the Project Manager to produce an __________________Plan o Instruct the Project Manager to close the project prematurelyo Defer the ___________________for a fixed period of time.

In response to the receipt of a Highlight Report:o Review the Highlight Reporto Ensure that the project remains focused on the corporate or programme objectives seto Ensure that the stage is progressing according to____________________o Keep corporate or programme management and other interested parties informed about project

progresso Take actions as necessary.

13.4.5 Authorize project closure There must be a point when the objectives set out in the original and current versions of the

_____________________________________ and _______________ Plan are assessed in order to understand:o Whether the objectives have been achievedo How the project has deviated from its initial basiso That the project has nothing more to contribute.Figure 13.6, Managing Successful Projects with PRINCE2, page 144 “©Crown copyright 2009 Reproduced under licence from OGC”

PRINCE2 recommends the following actions:o Review the ______ Report and agree who should receive it.o Verify that the handover of the project’s ________ was in accordance with the ____________________

Strategyo Confirm the updated Business Case by comparing actual and forecast benefits, costs and risks against the

original Business Case that was used to justify the project.Responsibilities in the Directing a Project process:

QuestionsSl. No Question

1 Which of the following is not an objective of Directing a Project process? Ensuring that there is management direction and control

throughout the project’s life. Ensuring that plans are in place for realizing the post-project

benefits. Ensuring that there is authority to initiate the project. Ensuring that Team Managers send Checkpoint Reports as

agreed format and frequency documented in the accepted Work Packages.

2 The Project Board activity that ensures that project initiation is planned, monitored, and controlled is:

3 The ___________ instructs the Project Manager to proceed with project initiation.

4 Authorize the project activity should be performed in parallel with

© 2010 PROJstudy.com 142Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 143:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Managing Product Delivery

__________________________ activity.5 If the Project Board does not authorize the project, then the project will be

prematurely ____________.6 During authorize the project activity; the Project Board reviews the

_________ __________ __________ to confirm that the project definition is accurate and complete.

7 Which of the following strategies ensures that the project’s products are adequately controlled and managed?

Communication Management Strategy Configuration Management Strategy Risk Management Strategy

8 The ____________ management must approve the Project Plan if it is found that the project tolerance limits will be exceeded.

9 Who will produce the Exception Plan?10 Who will manage the exceptions related to Work Packages?11 The management strategies and the controls pertaining to the project are

documented in_________________.12 ________ _________ Plan ensures that any benefits planned to be

achieved are measured and reviewed.13 The need for consultation between the Project Manager and Project Board

is likely to be particularly frequent during the _______ stage and when approaching stage boundaries.

14 The last activity undertaken by the Project Board before it is disbanded is ______ ________ _________.

© 2010 PROJstudy.com 143Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 144:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Managing Product Delivery

Sample TestQuestion

No Answer Comment

1

2

3

Chapter TestQuestion

No Answer Comment

1

2

3

4

5

6

7

8

9

10

11

12

© 2010 PROJstudy.com 144Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 145:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Managing Product Delivery

Case Study Format Questions:

Question 1 contains an assertion statement and a reason statement. For the question, identify the appropriate option, from among A, B, C, D, and E.

Option Assertion ReasonA True True And the reason explains the assertionB True True And the reason does not explain the assertionC True FalseD False TrueE False False

1. Assertion: A Team Manager will update the Project Manager on the status of the Work Packages for a stage through Checkpoint Report.

Because

Reason: Checkpoint Report is a progress report of the information gathered at a checkpoint, which the Project Manager provides to the Project Board.

Correct Answer: C

Justification:

During execution of the Work Packages, the Team Manager must update the Project Manager on the status of the work through Checkpoint Reports in the manner and at the frequency defined in the Work Package.

Reference: PROJstudy.com Comments

Checkpoint Report is a progress report of the information gathered at a checkpoint, which is given by a team to the Project Manager and which provides reporting data as defined in the Work Package.

Reference: Managing Successful Project with PRINCE2, page 304

2.Which two of the following actions does the Team Manager perform to ensure that the team creates and delivers the products in a manner that is desired by the project?

a) Creates a Stage Plan for the Work Packages being assigned

b) Produces the Highlight Report to communicate progress

© 2010 PROJstudy.com 145Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 146:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Managing Product Delivery

c) Obtains approval for completed products

d) Uses quality method(s), specified in the Product Description, to demonstrate that each product meets its quality criteria

e) Creates a Team Plan for the Work Packages being assigned

Correct Answer: A and B

Justification:

The Team Manager ensures that products are created and delivered by the team to the project by:Accepting and checking authorized Work Packages from the Project Manager......Obtaining approval for completed products from the authorities identified in the Product Description.

Reference: Managing Successful Project with PRINCE2, page 185

© 2010 PROJstudy.com 146Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 147:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Managing a Stage Boundary

17.1 PURPOSE The purpose of the Managing a Stage Boundary process is to enable the

______________ to be provided with sufficient information by the ______________ so that it can review the success of the current stage, approve the next Stage Plan, review the updated ________________ Plan, and confirm continued business justification and acceptability of the risks.

The process should be executed at or close to the end of each management stage.

The output from re-planning is an ______________ Plan which is submitted for Project Board approval in the same way that a Stage Plan is submitted for approval.

17.2 OBJECTIVE For exceptions:

o Prepare an Exception Plan

o Seek approval to replace the Project Plan or Stage Plan for the current stage with the _________________ Plan.

o Assure the Project Board that all products in the Stage Plan for the current stage have been completed and approved

o Prepare the Stage Plan for the next stage

o Review and, if necessary, update the Project Initiation Documentation (in particular the Business Case, Project Plan, project approach, strategies, project management team structure and role descriptions)

o Provide the information needed for the Project Board to assess the continuing viability of the project – including the aggregated risk exposure

o Record any information or lessons that can help later stages of this project and/or other projects

o Request authorization to start the next stage.

o For exceptions, the objectives of the Managing a Stage Boundary process are to:

Prepare an Exception Plan as directed by the Project Board Seek approval to replace the Project Plan or Stage Plan for the

current stage with the Exception Plan

© 2010 PROJstudy.com 147Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 148:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Managing a Stage Boundary

Figure 17.1, Managing Successful Projects with PRINCE2, page 193“©Crown copyright 2009 Reproduced under licence from OGC”

Please look at the above diagram and answer the following questions:

1) What are the processes interacting with the Managing a Stage Boundary process?

© 2010 PROJstudy.com 148Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 149:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Managing a Stage Boundary

2) What are the triggers to and from this process?

3) List the sequence of activities in this process:

© 2010 PROJstudy.com 149Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 150:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Managing a Stage Boundary

13.3 CONTEXT The Directing a Project process starts on completion of the ____________________ process and is triggered by the

request to________________. The Project Board manages by exception. There needs to be a two-way flow of information between the _______________ and corporate or programme

management during the project. The Project Board should provide unified direction and guidance to the_____________________. If the Project Board is unable to provide a single view or if independent, possibly contradictory, advice is given, then the

risk of project failure significantly increases. In such cases, the Project Manager should defer to the __________________.

The Project ______________ is responsible for assuring that there is continued business justification.13.4 ACTIVITIES

Figure 13.2, Managing Successful Projects with PRINCE2, page 136 “©Crown copyright 2009 Reproduced under licence from OGC”13.4.1 Authorize initiation

The Project Board may appoint _______________to undertake some of the reviewing and assessing actions. PRINCE2 recommends the following actions:

o Review and approve the ___________o Review and approve the ___________________o Verify the outline _________________o Review and approve the Stage Plan for the __________________o Authorize the ____________________ to proceed with the initiation stage

13.4.2 Authorize the project This activity will be triggered by a request from the _______________for authorization to ______________________

the project It should be performed in parallel with authorizing a ________________or_____________________ plan If the project is not authorized by the Project Board, then it should be prematurely ____________________.

Figure 13.3, Managing Successful Projects with PRINCE2, page 138 “©Crown copyright 2009 Reproduced under licence from OGC”

PRINCE2 recommends the following actions: Review and approve the ______________________ :

o Confirm that the project definition is accurate and complete and that the project approach is achievableo Confirm that lessons from previous similar projects have been reviewed and incorporatedo Confirm that the _________________ Strategy is sufficient to ensure that the quality expectations will be met,

and approve ito Confirm that the procedures defined in the __________________ Strategy are sufficient to keep the risks under

control, and approve it. o Confirm that the ______________________ Strategy will adequately control the status (versions and variants)

of the project’s products, and approve ito Ensure that the _______________ information needs and timing of communications, as defined in the

_____________________ Strategy, are adequateo Ensure that the project ___________ are adequate for the nature of the projecto Review and approve the Product Description(s)o Review the tolerances for the project provided by corporate or programme management to ensure they are

appropriate and realistico Verify that the ________________ demonstrates a viable project

Review and approve the ______________________ Plan. Notify _____________________ management and other interested parties that the project has been authorized.

13.4.3 Authorize a Stage or Exception Plan The ___________________ authorizes a management stage by reviewing the performance of the current stage and

approving the Stage Plan for the next stage. If an exception has occurred during the stage, the Project Board may request that the Project Manager produces

an_________________ Plan for Project Board approval. ____________________ exceptions are managed by the Project Manager using the ___________________

process

Figure 13.4, Managing Successful Projects with PRINCE2, page 140 “©Crown copyright 2009 Reproduced under licence from OGC”

PRINCE2 recommends the following actions:o Review the Stage Plan or Exception Plan for which the __________________ is seeking approval:

Confirm the validity and achievability of the Stage Plan/Exception Plan Review and approve any new Product Description(s) Confirm the validity and achievability of the ________ Plan. If necessary Secure appropriate approvals

from corporate or programme Management Confirm the strategies and project controls in the (updated) ___________________________ are

adequate for the remainder of the projecto Make a decision:

Approve the plan(s) and authorize the Project Manager to proceed with the submitted plan(s)

© 2010 PROJstudy.com 150Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 151:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Managing a Stage Boundary

Or instruct the Project Manager to initiate premature closure of the project13.4.4 Give ad hoc direction

The need for consultation between the Project Manager and Project Board is likely to be particularly frequent during the ___________________ stage and when approaching stage boundaries.

Ad hoc direction may be given collectively or by individual __________________ members.

There are a variety of circumstances that might prompt ad hoc direction, including:o Responding to requests o Responding to reports o Responding to external influences o Project Board members’ individual concernso Responding to changes in Project Board composition

Figure 13.5, Managing Successful Projects with PRINCE2, page 142 “©Crown copyright 2009 Reproduced under licence from OGC”

PRINCE2 recommends the following actions:o In response to informal requests for advice and guidance:

Assist the Project Manager as required (this may include asking the Project Manager to produce an Issue Report and/or an Exception Report)

o In response to an escalated Issue Report: Seek advice from ____________________management if necessary. Make a decision within the Project Board’s delegated limits of _______________. This decision could

be regarding: A problem/concern An off-specification: Grant a concession, defer, reject or ask for more information.

In response to an Exception Report :o Increase the tolerances that are forecast to be breachedo Instruct the Project Manager to produce an __________________Plan o Instruct the Project Manager to close the project prematurelyo Defer the ___________________for a fixed period of time.

In response to the receipt of a Highlight Report:o Review the Highlight Reporto Ensure that the project remains focused on the corporate or programme objectives seto Ensure that the stage is progressing according to____________________o Keep corporate or programme management and other interested parties informed about project

progresso Take actions as necessary.

13.4.5 Authorize project closure There must be a point when the objectives set out in the original and current versions of the

_____________________________________ and _______________ Plan are assessed in order to understand:o Whether the objectives have been achievedo How the project has deviated from its initial basiso That the project has nothing more to contribute.Figure 13.6, Managing Successful Projects with PRINCE2, page 144 “©Crown copyright 2009 Reproduced under licence from OGC”

PRINCE2 recommends the following actions:o Review the ______ Report and agree who should receive it.o Verify that the handover of the project’s ________ was in accordance with the ____________________

Strategyo Confirm the updated Business Case by comparing actual and forecast benefits, costs and risks against the

original Business Case that was used to justify the project.Responsibilities in the Directing a Project process:

QuestionsSl. No Question

1 Which of the following is not an objective of Directing a Project process? Ensuring that there is management direction and control

throughout the project’s life. Ensuring that plans are in place for realizing the post-project

benefits. Ensuring that there is authority to initiate the project. Ensuring that Team Managers send Checkpoint Reports as

agreed format and frequency documented in the accepted Work Packages.

2 The Project Board activity that ensures that project initiation is planned, monitored, and controlled is:

3 The ___________ instructs the Project Manager to proceed with project initiation.

4 Authorize the project activity should be performed in parallel with

© 2010 PROJstudy.com 151Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 152:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Managing a Stage Boundary

__________________________ activity.5 If the Project Board does not authorize the project, then the project will be

prematurely ____________.6 During authorize the project activity; the Project Board reviews the

_________ __________ __________ to confirm that the project definition is accurate and complete.

7 Which of the following strategies ensures that the project’s products are adequately controlled and managed?

Communication Management Strategy Configuration Management Strategy Risk Management Strategy

8 The ____________ management must approve the Project Plan if it is found that the project tolerance limits will be exceeded.

9 Who will produce the Exception Plan?10 Who will manage the exceptions related to Work Packages?11 The management strategies and the controls pertaining to the project are

documented in_________________.12 ________ _________ Plan ensures that any benefits planned to be

achieved are measured and reviewed.13 The need for consultation between the Project Manager and Project Board

is likely to be particularly frequent during the _______ stage and when approaching stage boundaries.

14 The last activity undertaken by the Project Board before it is disbanded is ______ ________ _________.

© 2010 PROJstudy.com 152Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 153:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Managing a Stage Boundary

Sample TestQuestion

No Answer Comment

1

2

3

4

Chapter TestQuestion

No Answer Comment

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

© 2010 PROJstudy.com 153Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 154:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Managing a Stage Boundary

Case Study Format Questions

Question 1 contains an assertion statement and a reason statement. For the question, identify the appropriate option from among A, B, C, D, and E.

OptionAssertion ReasonA True True And the reason explains the assertionB True True And the reason does not explain the assertionC True FalseD False TrueE False False

1. Assertion: The Managing a Stage Boundary process will not be used in the final stage of a project unless there is a request from the Project Board for an Exception Plan.

Because

Reason: Closing a Project process includes activities to review the performance of the whole project including the performance of the final stage.

Correct Answer: A

Justification:

Managing a Stage Boundary is not used towards the end of the final stage (unless there is a need to create an Exception Plan) because the activities to review the performance of the final stage are included in the activities to review the performance of the whole project as part of the Closing a Project process.

Reference: Managing Successful Project with PRINCE2, page 194

2.

Which two of the following statements on ‘Managing a Stage Boundary’ process are true?

a) The Project Manager uses this process to create the Stage Plan for the next stage.

b) The Project Board uses this process to approve Exception Plans.

c) The Project Manager uses this process to create the End Stage Report.d) The Project Manager uses this process to authorize a Work Package.

© 2010 PROJstudy.com 154Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 155:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Managing a Stage Boundary

e) The Team Manager uses this process to accept and deliver a Work Package.

Correct Answer: A and C

Justification:

Option A: This statement is true. One of the activities within the Managing a Stage Boundary process is ‘plan the next stage’.

Option B: This statement is inaccurate. The Project Board uses the Directing a Project process to authorize project’s plans.

Option C: This statement is true. One of the activities within the Managing a Stage Boundary process is ‘report stage end’.

Option D: This statement is inaccurate. The Project Manager uses the Controlling a Stage process to authorize Work Packages.

Option E: This statement is inaccurate. The Team Manager uses the Managing Product Delivery process to accept and deliver Work Packages.

Reference: PROJstudy.com comments

© 2010 PROJstudy.com 155Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 156:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Closing a Project

18.1 PURPOSE The purpose of the Closing a Project process is to provide

a_______________ at which acceptance for the project product is confirmed, and to recognize that objectives set out in the original ________________________ have been achieved or that the project has nothing more to contribute.

18.2 OBJECTIVE The objective of the Closing a Project process is to:

o Verify ________________ of the project’s productso Ensure that the host site is able to support the products when the

project is disbandedo Review the performance of the project against its baselineso Assess any benefits that have already been realized, update the

forecast of the remaining benefits, and plan for a review of those unrealized benefits

o Ensure that provision has been made to address all open issues and risks, with follow-on action recommendations.

© 2010 PROJstudy.com 156Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 157:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Closing a Project

Figure 18.1, Managing Successful Projects with PRINCE2, page 205“©Crown copyright 2009 Reproduced under licence from OGC”

Please look at the above diagram and answer the following questions:

1) What are the processes interacting with the Closing a Project process?

© 2010 PROJstudy.com 157Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 158:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Closing a Project

2) What are the triggers and from to this process?

3) List the sequence of activities in this process:

© 2010 PROJstudy.com 158Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 159:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Closing a Project

13.3 CONTEXT The Directing a Project process starts on completion of the ____________________ process and is triggered by the

request to________________. The Project Board manages by exception. There needs to be a two-way flow of information between the _______________ and corporate or programme

management during the project. The Project Board should provide unified direction and guidance to the_____________________. If the Project Board is unable to provide a single view or if independent, possibly contradictory, advice is given, then the

risk of project failure significantly increases. In such cases, the Project Manager should defer to the __________________.

The Project ______________ is responsible for assuring that there is continued business justification.13.4 ACTIVITIES

Figure 13.2, Managing Successful Projects with PRINCE2, page 136 “©Crown copyright 2009 Reproduced under licence from OGC”13.4.1 Authorize initiation

The Project Board may appoint _______________to undertake some of the reviewing and assessing actions. PRINCE2 recommends the following actions:

o Review and approve the ___________o Review and approve the ___________________o Verify the outline _________________o Review and approve the Stage Plan for the __________________o Authorize the ____________________ to proceed with the initiation stage

13.4.2 Authorize the project This activity will be triggered by a request from the _______________for authorization to ______________________

the project It should be performed in parallel with authorizing a ________________or_____________________ plan If the project is not authorized by the Project Board, then it should be prematurely ____________________.

Figure 13.3, Managing Successful Projects with PRINCE2, page 138 “©Crown copyright 2009 Reproduced under licence from OGC”

PRINCE2 recommends the following actions: Review and approve the ______________________ :

o Confirm that the project definition is accurate and complete and that the project approach is achievableo Confirm that lessons from previous similar projects have been reviewed and incorporatedo Confirm that the _________________ Strategy is sufficient to ensure that the quality expectations will be met,

and approve ito Confirm that the procedures defined in the __________________ Strategy are sufficient to keep the risks under

control, and approve it. o Confirm that the ______________________ Strategy will adequately control the status (versions and variants)

of the project’s products, and approve ito Ensure that the _______________ information needs and timing of communications, as defined in the

_____________________ Strategy, are adequateo Ensure that the project ___________ are adequate for the nature of the projecto Review and approve the Product Description(s)o Review the tolerances for the project provided by corporate or programme management to ensure they are

appropriate and realistico Verify that the ________________ demonstrates a viable project

Review and approve the ______________________ Plan. Notify _____________________ management and other interested parties that the project has been authorized.

13.4.3 Authorize a Stage or Exception Plan The ___________________ authorizes a management stage by reviewing the performance of the current stage and

approving the Stage Plan for the next stage. If an exception has occurred during the stage, the Project Board may request that the Project Manager produces

an_________________ Plan for Project Board approval. ____________________ exceptions are managed by the Project Manager using the ___________________

process

Figure 13.4, Managing Successful Projects with PRINCE2, page 140 “©Crown copyright 2009 Reproduced under licence from OGC”

PRINCE2 recommends the following actions:o Review the Stage Plan or Exception Plan for which the __________________ is seeking approval:

Confirm the validity and achievability of the Stage Plan/Exception Plan Review and approve any new Product Description(s) Confirm the validity and achievability of the ________ Plan. If necessary Secure appropriate approvals

from corporate or programme Management Confirm the strategies and project controls in the (updated) ___________________________ are

adequate for the remainder of the projecto Make a decision:

Approve the plan(s) and authorize the Project Manager to proceed with the submitted plan(s) Or instruct the Project Manager to initiate premature closure of the project

13.4.4 Give ad hoc direction

© 2010 PROJstudy.com 159Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 160:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Closing a Project

The need for consultation between the Project Manager and Project Board is likely to be particularly frequent during the ___________________ stage and when approaching stage boundaries.

Ad hoc direction may be given collectively or by individual __________________ members.

There are a variety of circumstances that might prompt ad hoc direction, including:o Responding to requests o Responding to reports o Responding to external influences o Project Board members’ individual concernso Responding to changes in Project Board composition

Figure 13.5, Managing Successful Projects with PRINCE2, page 142 “©Crown copyright 2009 Reproduced under licence from OGC”

PRINCE2 recommends the following actions:o In response to informal requests for advice and guidance:

Assist the Project Manager as required (this may include asking the Project Manager to produce an Issue Report and/or an Exception Report)

o In response to an escalated Issue Report: Seek advice from ____________________management if necessary. Make a decision within the Project Board’s delegated limits of _______________. This decision could

be regarding: A problem/concern An off-specification: Grant a concession, defer, reject or ask for more information.

In response to an Exception Report :o Increase the tolerances that are forecast to be breachedo Instruct the Project Manager to produce an __________________Plan o Instruct the Project Manager to close the project prematurelyo Defer the ___________________for a fixed period of time.

In response to the receipt of a Highlight Report:o Review the Highlight Reporto Ensure that the project remains focused on the corporate or programme objectives seto Ensure that the stage is progressing according to____________________o Keep corporate or programme management and other interested parties informed about project

progresso Take actions as necessary.

13.4.5 Authorize project closure There must be a point when the objectives set out in the original and current versions of the

_____________________________________ and _______________ Plan are assessed in order to understand:o Whether the objectives have been achievedo How the project has deviated from its initial basiso That the project has nothing more to contribute.Figure 13.6, Managing Successful Projects with PRINCE2, page 144 “©Crown copyright 2009 Reproduced under licence from OGC”

PRINCE2 recommends the following actions:o Review the ______ Report and agree who should receive it.o Verify that the handover of the project’s ________ was in accordance with the ____________________

Strategyo Confirm the updated Business Case by comparing actual and forecast benefits, costs and risks against the

original Business Case that was used to justify the project.Responsibilities in the Directing a Project process:

QuestionsSl. No Question

1 Which of the following is not an objective of Directing a Project process? Ensuring that there is management direction and control

throughout the project’s life. Ensuring that plans are in place for realizing the post-project

benefits. Ensuring that there is authority to initiate the project. Ensuring that Team Managers send Checkpoint Reports as

agreed format and frequency documented in the accepted Work Packages.

2 The Project Board activity that ensures that project initiation is planned, monitored, and controlled is:

3 The ___________ instructs the Project Manager to proceed with project initiation.

4 Authorize the project activity should be performed in parallel with __________________________ activity.

5 If the Project Board does not authorize the project, then the project will be

© 2010 PROJstudy.com 160Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 161:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Closing a Project

prematurely ____________.6 During authorize the project activity; the Project Board reviews the

_________ __________ __________ to confirm that the project definition is accurate and complete.

7 Which of the following strategies ensures that the project’s products are adequately controlled and managed?

Communication Management Strategy Configuration Management Strategy Risk Management Strategy

8 The ____________ management must approve the Project Plan if it is found that the project tolerance limits will be exceeded.

9 Who will produce the Exception Plan?10 Who will manage the exceptions related to Work Packages?11 The management strategies and the controls pertaining to the project are

documented in_________________.12 ________ _________ Plan ensures that any benefits planned to be

achieved are measured and reviewed.13 The need for consultation between the Project Manager and Project Board

is likely to be particularly frequent during the _______ stage and when approaching stage boundaries.

14 The last activity undertaken by the Project Board before it is disbanded is ______ ________ _________.

© 2010 PROJstudy.com 161Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 162:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Closing a Project

Sample TestQuestion

No Answer Comment

1

2

3

Chapter TestQuestion

No Answer Comment

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

© 2010 PROJstudy.com 162Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 163:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Closing a Project

Case Study Format Questions

Questions 1 and 2 contain an assertion statement and a reason statement. For the questions, identify the appropriate option from among A, B, C, D, and E.

Option Assertion ReasonA True True And the reason explains the assertionB True True And the reason does not explain the assertionC True FalseD False TrueE False False

1. Assertion: The Project Manager must confirm if the objectives of the project have been achieved before recommending Project Closure to the Project Board and issuing closure notification to the corporate management.

Because

Reason: After Project Board’s approval, the Project Manager should send the closure notification to all the parties as determined in the Communication Management Strategy.

Correct Answer: B

Justification:

The Project Manager must evaluate the project to determine how successful or unsuccessful the project has been.

PRINCE2 recommends that the Communication Management Strategy be used to identify any organization or interested party who needs to know that the project is closing.

Reference: Managing Successful Project with PRINCE2, pages 210, 211

© 2010 PROJstudy.com 163Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 164:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Closing a Project

2.

Assertion: If the Project Manager finds that the project is not going to deliver the desired benefits, he/she can close the project prematurely, release the project resources, salvage the products that have value for future projects, and then inform the Project Board.

Because

Reason: The Project Manager should get the approval of the Project Board before informing the corporate management that the project has nothing more to offer and that the resources can be released from the project.

Correct Answer: D

Justification:

Assertion is incorrect because the Project Manager cannot close the project without the approval of the Project Board.

PROJstudy.com comments

Once the Project Manager has confirmed that the project can be closed, a closure recommendation should be raised to the Project Board.

The Project Manager must also seek approval from the Project Board to give notice to corporate or programme management that resources can be (or are about to be) released.

Reference: Managing Successful Project with PRINCE2, pages 207, 211

© 2010 PROJstudy.com 164Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 165:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Tailoring PRINCE2 to Project Environment

Section 1 (19.1 to 19.4.1.3)

19.1 WHAT IS TAILORING?

Tailoring refers to the appropriate use of PRINCE2 on any given project, ensuring that there is the correct amount of planning, control, governance and use of the processes and themes, whereas the adoption of PRINCE2 across an organization is known as embedding.

PRINCE2 can be used whatever the project ________, ____________, ________________ or _________, or whether it is part of a __________________ or is being managed as a __________________ project.

The following table is for the Practitioner examination:

Differences between embedding and tailoring:Embedding TailoringDone by the organization to adopt PRINCE2. Done by the project management team to adapt the

method to the context of a specific project.Focus on:

Process responsibilities Scaling rules/guidance (e.g. score card) Standards (templates, definitions) Training and development Integration with business processes Tools Process assurance.

Focus on: Adapting the themes (through the strategies

and controls) Incorporating specific terms/language Revising the Product Descriptions for the

management products Revising the role descriptions for the PRINCE2

project roles Adjusting the processes to match the above.

19.2 GENERAL APPROACH TO TAILORING

Tailoring PRINCE2 appropriately is ‘full PRINCE2’.Tailoring does not consist of omitting elements of PRINCE2.

PRINCE2 is a web of interlinking elements: themes are used in processes; techniques are undertaken to bring themes to life; and individuals fulfilling project roles create management products. If the practitioner omits an element, project management for the project is weakened.

The goal is to apply a level of project management that does not overburden the project but provides an appropriate level of control given the external and project factors.

19.2.1 Applying the principles As PRINCE2’s principles are ______________, they will always apply and are not tailored.

19.2.2 Adapting the themes Adapting a theme does not necessarily mean modifying the method. In most cases, the environmental and project

factors are incorporated into the project’s strategies and controls. Relevant corporate or programme policies and standards are captured and documented in the project’s ___________________.

The level of control required will influence the formality and frequency of monitoring, reviewing and reporting.

© 2010 PROJstudy.com 165Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 166:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Tailoring PRINCE2 to Project Environment

Figure 19.1 Managing Successful Project with PRINCE2, page 216“©Crown copyright 2009 Reproduced under licence from OGC”

19.2.3 Applying the organization’s terms and language The method may need to be adapted to incorporate the terms and language of the _______________________. For

example, if the corporate or programme organization uses the term ‘investment case’ rather than ‘Business Case’, it may be appropriate to substitute the term within all of the project’s documentation if that improves understanding.

19.2.4 Adapting the management products In tailoring PRINCE2, the management products may be adapted, in which case it may be necessary to modify their

__________________ or to provide a template for them. For everyone involved in the project, it should remain clear as to what the purpose of the management product is.

19.2.5 Adapting the roles Standard role description outlines need to be adapted to match individuals’ actual capability and authority in the

context of the project role they will be assigned.

19.2.6 Adapting the processes All the PRINCE2 process activities need to be done; it is just that the responsibilities for performing the activities may

change and any references to the management products may need to change.

19.3 EXAMPLES OF TAILORING PRINCE2

19.4 PROJECTS IN A PROGRAMME ENVIRONMENT

A programme is a structure created to coordinate, direct and oversee the implementation of a set of______________ projects and activities in order to deliver outcomes and benefits relating to an organization’s _______________ objectives.

19.4.1 Themes19.4.1.1 Business Case

The Business Case might be produced and maintained by the programme and even exist in detail prior to _____________________.

Benefits will be defined, tracked and managed by the programme management team.

Figure 19.2 Managing Successful Project with PRINCE2, page 218“©Crown copyright 2009 Reproduced under licence from OGC”

© 2010 PROJstudy.com 166Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 167:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Tailoring PRINCE2 to Project Environment

19.4.1.2 Organization OGC’s managing Successful Programmes (MSP) framework defines a programme board that comprises a

programme Senior Responsible Owner (SRO), a programme manager, one or more business change managers etc.

will confirm the appointment of the project Executive.

The programme manager is responsible for the setup and day-to-day management and delivery of the programme on behalf of the ____________.

The ________________ is responsible for benefits definition and management throughout the programme.

The programme and project management team structures need to be integrated such that:o There are clear lines of ________________o ________________ is avoidedo and ______________ are efficient.

The integration of roles may include:o The programme manager being the______________ for one or more of the projectso A business change manager from the programme fulfilling the project role of _________________o Project Support being provided by the _______________o The programme’s design authority fulfilling the project role of ________________________________.

for the project may be performed by the programme, or the programme may require the project to take a lead with certain stakeholder groups with which it has good engagement.

19.4.1.3 Quality The project’s Quality Management Strategy is derived from the programme’s Quality Management Strategy.

© 2010 PROJstudy.com 167Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 168:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Tailoring PRINCE2 to Project Environment

Section 1 – Questions

Sl. No Question

1. PRINCE2’s principles are ___________.

2. ‘A programme is a temporary flexible organization structure created to coordinate, direct and oversee the implementation of a set of projects (need not be related) and activities’ – True or False?

3. ‘Programmes are driven by vision of __________.

4. Who is responsible for benefits definition and management throughout the programme in case of projects in a programme environment?

5. When are the benefits of a programme realized?

6. Who confirms the appointment of the project executive in case of projects in a programme environment?

7. The ___________ (if used) fulfils the role of Change Authority or Project Assurance for one or more of the projects (in case of projects in programme environment).

Section 2 (19.4.1.4 to 19.6.1.1)

19.4.1.4 Plans Any specific standards that the project planners should work to will be described in

the____________________________________.

19.4.1.5 Risk The project’s Risk Management Strategy will be derived from the programme’s Risk Management Strategy.

19.4.1.6 Change The project’s Configuration Management Strategy will be derived from the programme’s ________________

__________________ strategy.

19.4.1.7 Progress The programme’s monitoring and control strategy may influence the formality, frequency and content of the project’s

reviews and reports.

19.4.2 Processes The PRINCE2 process most affected by working in a programme will be _________________________. This

process could be undertaken almost entirely by the programme.

19.4.3 Management products There are numerous management products that exist for both the project and programme. When in a programme

environment, it may be desirable to prefix the management product with ‘project’ and ‘programme’ to distinguish the difference. Another consideration is to make the project and programme document templates look very different in style so that it is immediately obvious where they apply.

Consideration should be given to whether the project’s logs and registers will be maintained _______________ to the project, or __________________ by the programme. For example, a choice needs to be made as to whether there is a single Risk Register, administered by the programme for the programme-level risks and all the risks for each project within the programme, or whether each project should maintain its own Risk Register.

© 2010 PROJstudy.com 168Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 169:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Tailoring PRINCE2 to Project Environment

19.5 PROJECT SCALE19.5.1 Simple project

Even simple projects should adhere to the _____________ PRINCE2 principles if the project is to be managed using PRINCE2. It is in the way the themes, processes and management products are used that PRINCE2 is ‘tailored’.

Table 19.2 Managing Successful Project with PRINCE2, page 222“©Crown copyright 2009 Reproduced under licence from OGC”

19.5.1.1 Themes The theme most affected by simple projects is the Organization theme:

o Roles can be ____________ but not__________________.o and ______________ roles can often be combined.o Members of the ____________________are often in a better position to carry out their own Project Assurance.o For small teams it may not be necessary to appoint Team Managers. The __________________ of a small

project can carry out those responsibilities.o The Project Manager may undertake the role of ____________________ and be a team member.

Product Descriptions for the key deliverables and a simple plan, in the form of a schedule of who is involved in producing, reviewing and approving products, together with key milestones, is often referred to as a _____________________.

19.5.1.2 Processes remain relevant even in simple projects. The Starting up a Project process can usually be

handled in a less ______________. In some cases it may be appropriate to combine the________________________ and_______________ processes

(i.e. creating the Project Initiation Documentation straight from the ______________ and skipping the production of a _________________.

19.5.1.3 Management Products The Project Board may decide to receive some, or all, reports orally or have a verbal exchange of information. In

such cases, the Project Manager should document the exchange in the ____________________. Reports could be in the form of an _________________. The Project Initiation Documentation could be a set of ______________________. It is possible to manage a small PRINCE2 project with just four sets of documentation:

o The _________________________which includes ______________o The ________________o ______________________

The following management products may not be needed:o __________________ for undertaking the projecto __________________ o __________________ o __________________ o __________________

Section 19.6 is for the Practitioner examination:

19.6 COMMERCIAL CUSTOMER/SUPPLIER ENVIRONMENT If the relationship between the ______________________ is a commercial one, then additional considerations apply.

The main consideration is to recognize that there are at least ___________________ of: o ______________________

© 2010 PROJstudy.com 169Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 170:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Tailoring PRINCE2 to Project Environment

o ______________________ o ______________________o ______________________

End of Practitioner Section

19.6.1 Themes

19.6.1.1 Business Case In a commercial context, there are at least two Business Cases – the __________________and

the____________________. The customer’s Business Case covers the___________________. The costs should include the

___________________ and _______________________.

19.6.1.2 Organization Who should take the role of Senior Supplier?

o One option could be to simply exclude the __________________ from the part of the reviews that involve the _____________________. Another option would be to appoint the person who is responsible for the performance of the ____________________ (e.g. a contracts manager).

o What if there are multiple suppliers? If there are only a few (say three or four), then it is recommended that all of them are on the _____________________. If there are more than three or four suppliers, then the ______________________ responsible for the performance of all the supplier contracts could sit on the Project Board on their behalf.

o If the project includes a procurement stage, project may need a temporary appointment for the Senior Supplier role – perhaps from the customer’s procurement department.

Who provides the Project Manager? In PRINCE2, the Project Manager will normally come from the___________________________, with the suppliers’ Project Manager(s) fulfilling the role of Team Managers for the project.

There may be projects where the Project Manager comes from the _______________________. Customers may choose to stay ‘at arm’s length’ and are likely to increase the rigour in ___________________. Consideration should be given to the Project Board dynamics if the Project Manager has a project reporting line to the ___________________, and a line management (or commercial) reporting line to the ________________________.

The supplier’s governance rules may mean that they have to treat their _____________________ within the customer’s project as a project within the supplier’s organization. This may mean establishing a separate supplier Project Board. Consideration should be given to:o Who fulfils the Senior User role if not someone from the customer’s organizationo How the customer and supplier Project Board roles relate.

19.6.1.4 Plans The contract may cover the whole project, with purchase orders and milestone payments aligned to each

____________________.

The customer has a choice as to how to manage the procurement activities – either manage them as part of the _________________ or add a ______________ ___________after initiation.

19.6.1.5 Risk In a commercial context there may be a need for more than one ____________________ as some project risks

could be unique to only one party, with good reasons for them not to be visible to the other party.

19.6.1.6 Change The change control procedure in the Configuration Management strategy and the provisions in the contract must be

aligned.

If a change budget is used it will need to be aligned to the customer’s purchasing procedures and the supplier’s business approval procedures.

19.6.1.7 Progress Team Managers may need to produce two __________________, one for the _______________________ and one

for the _______________________.

19.6.2 Processes As PRINCE2 is based on a____________________ context from the customer perspective, it is unlikely that the

processes need to be tailored from the customer perspective.

© 2010 PROJstudy.com 170Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 171:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Tailoring PRINCE2 to Project Environment

From a supplier’s perspective, the key change to the processes will be to the _________________and _____________________ processes.

Some of the _____________________ process will be pre-contract as the supplier will need to formulate the strategies.

19.6.3 Management products The content of the _____________________ should focus on how to make sure that each party’s obligations are

fulfilled. The ____________________________could be part of the contract documentation, but care should be taken as it may stifle the project’s ability to adapt if the ______________________________ has to go through legal review for each change.

19.7 MULTI-ORGANIZATION PROJECTS

Examples of projects involving multiple organizations are:o ___________________ o ___________________

There may be one main ____________________, but there may be several ________________. Likewise, there may be several __________________________.

The guidance to using PRINCE2 in a multi-owned project is similar to the ______________________context with respect to tailoring the themes with any reference to ‘contract’ being substituted for ‘agreement’.

Project Boards, for example, can have _______________than can practically make effective decisions.

Large consensual Project Boards work very slowly.

Consideration should then be given to adopting the organizational structures of programme management.

19.8 PROJECT TYPE

19.8.1 Lifecycle models Many industries or professions have developed lifecycle models for particular types of projects, such as

____________ or___________________ methods. PRINCE2 works well with such models as they primarily focus on the activities to create and verify the project’s ________________, the aspect of projects thatPRINCE2 deliberately ___________________ address.

Tailoring PRINCE2 to work with specialist lifecycle models principally involves:o Aligning the management stages to the _________________ – e.g. design, build, test, transition

o Using _______________________to match the development focus

o Integrating any __________________ into the project management team structure

o Using PRINCE2 for the __________________________(e.g. Project Brief) and using the specialist method to define the purpose, format, composition and quality criteria for the specialist management products

o Providing hooks from the _________________________ process to the specialist product development processes.

19.8.2 The evolving project Today’s projects tend not to start with a _________________, but have specifications that evolve as the project

progresses.

The specifications are often contestable and open to negotiation throughout the project’s life.

A project may not start with a ____________________.

The Business Case represents a _________________________ at a particular point in a project’s lifecycle, which will evolve as the project moves from discovery to implementation.

The value of the evolving Business Case is that it enables the organization to make an investment commitment that is commensurate with the expected benefits and risks forecast at that time in the project’s evolution.

Projects involving research and development, the development of a new policy or the undertaking of a_____________________ are typical of the evolving project paradigm.

© 2010 PROJstudy.com 171Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 172:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Tailoring PRINCE2 to Project Environment

19.8.3 The feasibility project A feasibility study might be required to investigate the situation and determine options for the way ahead. Using

PRINCE2, one approach would be to handle the study as a _________________________ project.

At the end of the feasibility study project there is one recommendation.

The justification for a policy project may be valid, but it is still important to ensure that the investment in the project provides ________________________.

19.9 SECTOR DIFFRENCES

Within the UK public sector there are two considerations that may require PRINCE2 to be tailored:o Whether the project requires an _________________o Whether the project is subject to OGC __________________Review

19.9.1 Senior Responsible Owner The Senior Responsible Owner is the single individual with overall responsibility for ensuring that a project or

programme meets its objectives and delivers the projected benefits.

The SRO is ______________a PRINCE2 role.o The _________________ would report to the SRO appointed to the programme. It might also be

appropriate for the SRO to act as the ______________ for major projects.o Where an SRO is appointed in the context of a single large project, the person undertaking the SRO role

would also undertake the _____________ role or appoint the person who will undertake the _______________ role.

19.9.2 OGC Gateway Review The OGC Gateway Review examines projects at ___________________ in their lifecycle. It looks ahead to provide

assurance that they can progress successfully to the _________________. OGC Gateway Review delivers a _______________ in which independent practitioners from outside the project use

their experience and expertise to examine the progress and likelihood of successful delivery of the project. Gateway review can align with PRINCE2 as follows:

o Review 1: Business justificationo Reviews 2 and 3: Delivery strategy and investment decision These reviews align with the

___________________ activity of authorizing a Stage or Exception Plan.o Review 4: Readiness for service This focuses on the readiness of the organization to implement the

project and aligns with the Directing a Project activity of authorizing a ________________ or __________________.

A gateway review is not the same as a _____________ or _______________ but a means of providing added assurance as input to the actual ______________________ on whether the project is able to meet its objectives.

19.10 PROJECT MANAGEMENT BODIES OF KNOWLEDGE

PRINCE2 is an integrated project management method providing a set of _______________ and ________________ that can be applied to manage a project from ________________.

A Body of Knowledge (BoK) covers the broad spectrum of project management competencies and techniques that Project Managers may need to apply, such as leadership and negotiation.

The differences between PRINCE2 (a method) and a BoK make them highly _______________________. PRINCE2 provides a framework of what needs to be done, by whom and by when. The BoK provides a range of

techniques of how those things can be done. In PRINCE2 a critical step in creating a plan is estimating. A BoK provides an explanation and analysis of the range of estimating techniques available.

Tailoring PRINCE2 if the organization is aligned to any particular BoK should include:o Agreeing a ____________________ to apply.o Aligning PRINCE2’s _______________________ with any management products recommended by the

BoK. For example, in PMBoK the project charter is equivalent to PRINCE2’s Project Brief.

© 2010 PROJstudy.com 172Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 173:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Tailoring PRINCE2 to Project Environment

Section 2 – Questions

Sl. No Question

1. Which PRINCE2 process is most affected by working in a programme?

2. ‘Quality Management Strategy is a management product that exists for both the project and the programme’ – True or False?

3. ‘Simple PRINCE2 projects need not adhere to the seven PRINCE2 principles’ – True or False?

4. In some cases, for a simple project it may be appropriate to combine the Starting up a Project and Initiating a Project processes. In this case the Project Initiation Documentation will be created directly from the ___________.

5. Mention the 4 sets of documentations with which a small project can be managed?

6. PRINCE2 is based on a ________________ environment.

7. What is the minimum number of Business Cases required in a commercial context?

8. Joint venture is an example of which of the following?A. Projects in a programme environmentB. Project management Bodies of knowledgeC. Multi-organization projectsD. Sector differences

9. In a commercial context, there may be a need for _______________ Risk Registers.

10. Mention the processes where key changes are required from a supplier’s perspective?

11. ‘Lifecycle models primarily focus on the activities to create and verify the project’s specialist products’ – True or False?

12. ‘SRO is a PRINCE2 role’ – True or False?

13. Which of the following statements is correct?A. PRINCE2 is non-prescriptiveB. Body of knowledge is targeted at Project ManagersC. PRINCE2 covers interpersonal skillsD. Body of knowledge references techniques

14. ____________ delivers a ‘peer review’ in which independent practitioners from outside the project use their experience and expertise to examine the progress and likelihood of successful delivery of the project.

Case Study Format Questions:1. Which two (2) management products among the following may NOT be needed for a small PRINCE2 project?

a. Daily Log

b. Checkpoint Report

c. End Stage Report

d. Lessons Report

e. Highlight Report

© 2010 PROJstudy.com 173Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 174:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Tailoring PRINCE2 to Project Environment

2. Which two (2) of the following statements are correct?

a. Programmes have definite start and end pointb. Projects are bounded and scoped deliverables

c. Programme benefits are realized during the programme and afterwards

d. Projects are driven by vision of ‘end state’

e. Programmes are driven by deliverables

© 2010 PROJstudy.com 174Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 175:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Sample Test

Sample Test 2Question

No Answer Comment

123456789

101112131415161718192021222324252627282930313233343536

© 2010 PROJstudy.com 175Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce

Page 176:  · Web viewQuality Quality Quality Risk Risk Risk Organization Organization Organization Change Change Change Directing a Project Directing a Project Directing a Project Tailoring

Sample Test

373839404142434445464748495051525354555657585960616263646566676869707172737475

© 2010 PROJstudy.com 176Content is based on OGC (PRINCE2®) material. Reproduced under licence from OGC.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.The Swirl logo™ is a Trade Mark of the Office of Government Commerce