NEC3 Engineering & Construction Contract Between ESKOM HOLDINGS SOC LTD (Reg No. 2002/015527/30) and [Insert at award stage] (Reg No. ___________ ) for THE DESIGN, MANUFACTURE, SUPPLY, DELIVERY, OFFLOADING, ERECTION AND COMMISSIONING OF 13 X 315 KVA 22KV/400V AND 1 X 315 KVA 22/0.38KV OIL FILLED AUXILIARY TRANSFORMERS FOR TRANSMISSION DIVISION AND POWER DELIVERY PROJECT DIVISION. Contents: Part C1 Agreements & Contract Data Part C2 Pricing Data Part C3 Scope of Work Part C4 Site Information CONTRACT No. [Insert at award stage]

Upload: ngodien

Post on 23-Jun-2018

212 views

Category:

Documents


0 download

TRANSCRIPT

NEC3 Engineering & Construction Contract

Between ESKOM HOLDINGS SOC LTD(Reg No. 2002/015527/30)

and [Insert at award stage](Reg No. ___________ )

for THE DESIGN, MANUFACTURE, SUPPLY, DELIVERY, OFFLOADING, ERECTION AND COMMISSIONING OF 13 X 315 KVA 22KV/400V AND 1 X 315 KVA 22/0.38KV OIL FILLED AUXILIARY TRANSFORMERS FOR TRANSMISSION DIVISION AND POWER DELIVERY PROJECT DIVISION.

Contents:

Part C1 Agreements & Contract Data

Part C2 Pricing Data

Part C3 Scope of Work

Part C4 Site Information

CONTRACT No. [Insert at award stage]

REQUEST FOR QUOTATION

UNIQUE IDENTIFIER 240-54568432

REVISION 1

REVISION DATE NOVEMBER 2015GROUP TECHNOLOGY & COMMERCIAL DIVISION

Part C1: Agreements & Contract Data

Contents:

C1.1 Form of Offer and Acceptance

[to be inserted from Returnable Documents at award stage]

C1.2a Contract Data provided by the Employer

C1.2b Contract Data provided by the Contractor

[to be inserted from Returnable Documents at award stage]

C1.3 Proforma Guarantees

CONTRACT 2 ECC3 COVER PAGES

ESKOM HOLDINGS SOC Ltd. CONTRACT NUMBER ______________PROJECT & CONTRACT TITLE

C1.1 Form of Offer & Acceptance

Offer

The Employer, identified in the Acceptance signature block, has solicited offers to enter into a contract for the procurement of:

THE DESIGN, MANUFACTURE, SUPPLY, DELIVERY, OFFLOADING, ERECTION AND COMMISSIONING OF 13 X 315 KVA 22KV/400V AND 1 X 315 KVA 22/0.38KV OIL FILLED AUXILIARY TRANSFORMERS FOR TRANSMISSION DIVISION AND POWER DELIVERY PROJECT DIVISION..

The tenderer, identified in the Offer signature block, has examined the documents listed in the Tender Data and addenda thereto and by submitting this Offer has accepted the Conditions of Tender.

By the representative of the tenderer, deemed to be duly authorised, signing this part of this Form of Offer and Acceptance the tenderer offers to perform all of the obligations and liabilities of the Contractor under the contract including compliance with all its terms and conditions according to their true intent and meaning for an amount to be determined in accordance with the conditions of contract identified in the Contract Data.

Options A The offered total of the Prices exclusive of VAT is R [●]Sub total R [●]

Value Added Tax @ 14% is R [●]The offered total of the amount due inclusive of VAT is1 R [●](in words) [●]

This Offer may be accepted by the Employer by signing the Acceptance part of this Form of Offer and Acceptance and returning one copy of this document including the Schedule of Deviations (if any) to the tenderer before the end of the period of validity stated in the Tender Data, or other period as agreed, whereupon the tenderer becomes the party named as the Contractor in the conditions of contract identified in the Contract Data.

Signature(s)

Name(s)

Capacity

1 This total is required by the Employer for budgeting purposes only. Actual amounts due will be assessed in terms of the conditions of contract.

PART C1: AGREEMENT & CONTRACT DATA PAGE 3 C1.1 ECC3 FORM OF OFFER AND ACCEPTANCE

ESKOM HOLDINGS SOC Ltd. CONTRACT NUMBER ______________PROJECT & CONTRACT TITLE

For the tenderer:

Name & signature of witness

(Insert name and address of organisation)

Date

Tenderer’s CIDB registration number (if applicable)

PART C1: AGREEMENT & CONTRACT DATA PAGE 4 C1.1 ECC3 FORM OF OFFER AND ACCEPTANCE

ESKOM HOLDINGS SOC Ltd. CONTRACT NUMBER ______________PROJECT & CONTRACT TITLE

Acceptance

By signing this part of this Form of Offer and Acceptance, the Employer identified below accepts the tenderer’s Offer. In consideration thereof, the Employer shall pay the Contractor the amount due in accordance with the conditions of contract identified in the Contract Data. Acceptance of the tenderer’s Offer shall form an agreement between the Employer and the tenderer upon the terms and conditions contained in this agreement and in the contract that is the subject of this agreement.

The terms of the contract, are contained in:

Part C1 Agreements and Contract Data, (which includes this Form of Offer and Acceptance)

Part C2 Pricing Data

Part C3 Scope of Work: Works Information

Part C4 Site Information

and drawings and documents (or parts thereof), which may be incorporated by reference into the above listed Parts.

Deviations from and amendments to the documents listed in the Tender Data and any addenda thereto listed in the Returnable Schedules as well as any changes to the terms of the Offer agreed by the tenderer and the Employer during this process of offer and acceptance, are contained in the Schedule of Deviations attached to and forming part of this Form of Offer and Acceptance. No amendments to or deviations from said documents are valid unless contained in this Schedule.

The tenderer shall within two weeks of receiving a completed copy of this agreement, including the Schedule of Deviations (if any), contact the Employer’s agent (whose details are given in the Contract Data) to arrange the delivery of any securities, bonds, guarantees, proof of insurance and any other documentation to be provided in terms of the conditions of contract identified in the Contract Data at, or just after, the date this agreement comes into effect. Failure to fulfil any of these obligations in accordance with those terms shall constitute a repudiation of this agreement.

Notwithstanding anything contained herein, this agreement comes into effect on the date when the tenderer receives one fully completed original copy signed between them of this document, including the Schedule of Deviations (if any).

Unless the tenderer (now Contractor) within five working days of the date of such receipt notifies the Employer in writing of any reason why he cannot accept the contents of this agreement, this agreement shall constitute a binding contract between the Parties.

Signature(s)

Name(s)

Capacity

PART C1: AGREEMENT & CONTRACT DATA PAGE 5 C1.1 ECC3 FORM OF OFFER AND ACCEPTANCE

ESKOM HOLDINGS SOC Ltd. CONTRACT NUMBER ______________PROJECT & CONTRACT TITLE

for the Employer

Name & signature of witness

(Insert name and address of organisation)

Date

Note: If a tenderer wishes to submit alternative tenders, use another copy of this Form of Offer and Acceptance.

Schedule of Deviations to be completed by the Employer prior to contract awardNote:

1. This part of the Offer & Acceptance would not be required if the contract has been developed by negotiation between the Parties and is not the result of a process of competitive tendering.

2. The extent of deviations from the tender documents issued by the Employer prior to the tender closing date is limited to those permitted in terms of the Conditions of Tender.

3. A tenderer’s covering letter must not be included in the final contract document. Should any matter in such letter, which constitutes a deviation as aforesaid be the subject of agreement reached during the process of Offer and Acceptance, the outcome of such agreement shall be recorded here and the final draft of the contract documents shall be revised to incorporate the effect of it.

No. Subject Details

1 [●] [●]

2 [●] [●]

3 [●] [●]

4 [●] [●]

5 [●] [●]

6 [●] [●]

7 [●] [●]

By the duly authorised representatives signing this Schedule of Deviations below, the Employer and the tenderer agree to and accept this Schedule of Deviations as the only deviations from and amendments to the documents listed in the Tender Data and any addenda thereto listed in the Tender Schedules, as well as any confirmation, clarification or changes to the terms of the Offer agreed by the tenderer and the Employer during this process of Offer and Acceptance.

It is expressly agreed that no other matter whether in writing, oral communication or implied during the period between the issue of the tender documents and the receipt by the tenderer of a completed signed copy of this Form shall have any meaning or effect in the contract between the parties arising from this Agreement.

For the tenderer: For the Employer

Signature

Name

Capacity

PART C1: AGREEMENT & CONTRACT DATA PAGE 6 C1.1 ECC3 FORM OF OFFER AND ACCEPTANCE

ESKOM HOLDINGS SOC Ltd. CONTRACT NUMBER ______________PROJECT & CONTRACT TITLE

On behalf of

(Insert name and address of organisation) (Insert name and address of organisation)

Name & signature of witness

Date

PART C1: AGREEMENT & CONTRACT DATA PAGE 7 C1.1 ECC3 FORM OF OFFER AND ACCEPTANCE

ESKOM HOLDINGS SOC Ltd CONTRACT NUMBER ____________PROJECT & CONTRACT TITLE

C1.2 ECC3 Contract Data

PART ONE - DATA PROVIDED BY THE EMPLOYER

Completion of the data in full, according to the Options chosen, is essential to create a complete contract.

Clause Statement Data

1General

The conditions of contract are the core clauses and the clauses for main Option

A: Priced contract with activity schedule

dispute resolution Option W1: Dispute resolution procedure

and secondary Options

X1: Price adjustment for inflation

X2 Changes in the law

X4: Parent company guarantee

X5: Sectional Completion

X7: Delay damages

X13: Performance Bond

X15: Limitation of Contractor’s liability for design to reasonable skill and care

X16: Retention

X17: Low performance damages

X18: Limitation of liability

Z: Additional conditions of contract

of the NEC3 Engineering and Construction Contract, April 2013 (ECC3)

10.1 The Employer is (Name): Eskom Holdings SOC Ltd (reg no: 2002/015527/30), a state owned company incorporated in terms of the company laws of the Republic of South Africa

Address Registered office at Megawatt Park, Maxwell

PART C1: AGREEMENTS AND CONTRACT DATA PAGE 8 C1.2B ECC3 CONTRACT DATA PART 2

ESKOM HOLDINGS SOC Ltd CONTRACT NUMBER ____________PROJECT & CONTRACT TITLE

Drive, Sandton, Johannesburg

10.1 The Project Manager is: (Name) Will be stated on the Purchase order

10.1 The Supervisor is: (Name) Will be stated on the Purchase order

11.2(13) The works are The design, manufacturing,supply, delivery, offloading, and commissioning of 13 X 315 KVA 22KV/400V AND 1 X 315 KVA 22/0.38KV oil filled Auxiliary transformers for Transmition division and Power Delivery project division

11.2(14) The following matters will be included in the Risk Register Will be stated on the Purchase order

11.2(15) The boundaries of the site are Within the Eskom site security area or the designated storage area

11.2(16) The Site Information is in Part 4: Site Information to be advised per Purchase order

11.2(19) The Works Information is in Part 3: Scope of Work and all documents and drawings to which it makes reference.

12.2 The law of the contract is the law of the Republic of South Africa

13.1 The language of this contract is English

13.3 The period for reply is 1 (one) week

2 The Contractor's main responsibilities

Data required by this section of the core clauses is provided by the Contractor in Part 2 and terms in italics used in this section are identified elsewhere in this Contract Data.

3 Time

11.2(3) The completion date for the whole of the works is The completion date will be stated on the

Purchase order

11.2(9) The key dates and the conditions to be met are:

Condition to be metwill be stated on Purchase order

30.1 The access dates are: will be stated on Purchase order

31.1 The Contractor is to submit a first programme for acceptance within

1 week after purchase order acknowledgement.

31.2 The starting date is The starting date will be stated on the Purchase order

32.2 The Contractor submits revised programmes at intervals no longer than

4 (four) weeks

PART C1: AGREEMENTS AND CONTRACT DATA PAGE 9 C1.2B ECC3 CONTRACT DATA PART 2

ESKOM HOLDINGS SOC Ltd CONTRACT NUMBER ____________PROJECT & CONTRACT TITLE

35.1 The Employer is not willing to take over the works before the Completion Date.

4 Testing and Defects

42.2 The defects date is Three (3) years after the completion of the works relative to a transformer in service or five (5) years after DAP for transformers put into long term storage whichever expires first.The Employer complies with the Contractor’s instructions for long term storage.

Latent defect is seven (7) years from the take-over date relative to a transformer after the three (3) or five (5) years defects period, whichever is applicable.

43.2 The defect correction period is One (1) week. The contractor is to correct the defect within the period or if not possible, then to have responded and submitted a schedule (to be approved by the Project Manager) for the correction period.

5 Payment

50.1 The assessment interval is Hand over

51.1 The currency of this contract is the South African Rand.

51.2 The period within which payments are made is Thirty (30) days after the submission of a

valid Tax Invoice with supporting documentation based on the agreed assessment.

51.4 The interest rate is Zero %

6 Compensation events

60.1(13) The place where weather is to be recorded is:

The location of ESKOM site as described in Part 3C Works Information

The weather measurements to be recorded for each calendar month are, the cumulative rainfall (mm)

the number of days with rainfall more than 10 mm

the number of days with minimum air temperature less than 0 degrees Celsius

PART C1: AGREEMENTS AND CONTRACT DATA PAGE 10 C1.2B ECC3 CONTRACT DATA PART 2

ESKOM HOLDINGS SOC Ltd CONTRACT NUMBER ____________PROJECT & CONTRACT TITLE

the number of days with snow lying at 09:00 hours South African Time

the South African Weather Bureau

The weather measurements are supplied by

the South African Weather Bureau

The weather data are the records of past weather measurements for each calendar month which were recorded at:

The location of ESKOM site as described in Part 3C Works Information

and which are available from:the cumulative rainfall (mm)

7 TitleThere is no reference to Contract Data in this section of the core clauses and terms in italics used in this section are identified elsewhere in this Contract Data.

8 Risks and insurance

80.1 These are additional Employer's risks 1.Design Complications2.Reliability and performance of

equipment3.Sea freight risks4.Inadequate storage5.Transportation damage6.Road Transport Embargo7.Commodity price fluctuations8.Supplier Failure to deliver9.Late Deliveries10.Weather11.Installation is dependent on availability of

outages12.Integration between Local and Off-shore

Project ManagementAdditional risks will be managed by the Parties as they arise.

84.1 The Employer provides these insurances from the Insurance Table

as stated for “Format A” available on http://www.eskom.co.za/Tenders/InsurancePoliciesProcedures

84.1 The Employer provides these additional insurances

as stated for “Format A” available on http://www.eskom.co.za/Tenders/InsurancePoliciesProcedures

84.1 The Contractor provides these additional insurances:

whatever the Contractor deems necessary in addition to that provided by the Employer

84.2 The insurance against loss of or damage to the works, Plant and Materials is to include cover for Plant

whatever the Contractor deems necessary in addition to that provided by the Employer

PART C1: AGREEMENTS AND CONTRACT DATA PAGE 11 C1.2B ECC3 CONTRACT DATA PART 2

ESKOM HOLDINGS SOC Ltd CONTRACT NUMBER ____________PROJECT & CONTRACT TITLE

and Materials provided by the Employer for an amount of

84.2 The minimum limit of indemnity for insurance in respect of loss of or damage to property (except the works, Plant, Materials and Equipment) and liability for bodily injury to or death of a person (not an employee of the Contractor) caused by activity in connection with this contract for any one event is

whatever the Contractor deems necessary in addition to that provided by the Employer plus the amount applicable in terms of the Employer’s asset property damage insurance deductible in the amount of R2 000 000 (two million Rands) per event and without limit to the number of events that may arise.

84.2 The minimum limit of indemnity for insurance in respect of death of or bodily injury to employees of the Contractor arising out of and in the course of their employment in connection with this contract for any one event is

As prescribed by the Compensation for Occupational Injuries and Diseases Act No. 130 of 1993 and the Contractor’s common law liability for people falling outside the scope of the Act with a limit of Indemnity of not less than R500 000 (Five hundred thousand Rands).

9 TerminationThere is no reference to Contract Data in this section of the core clauses and terms in italics used in this section are identified elsewhere in this Contract Data.

10 Data for main Option clause

A Priced contract with activity schedule

There is no reference to Contract Data in this Option and terms in italics are identified elsewhere in this Contract Data.

1 Data for Option W1

W1.1 The Adjudicator is the person selected from the ICE-SA Division (or its successor body) of the South African Institution of Civil Engineering Panel of Adjudicators by the Party intending to refer a dispute to him. (see www.ice-sa.org.za). If the Parties do not agree on an Adjudicator the Adjudicator will be appointed by the Arbitration Foundation of Southern Africa (AFSA).

W1.2(3) The Adjudicator nominating body is: the Chairman of ICE-SA a joint Division of the South African Institution of Civil Engineering and the London Institution of Civil Engineers. (See www.ice-sa.org.za ) or its successor body.

W1.4(2) The tribunal is: arbitration.

W1.4(5) The arbitration procedure is the latest edition of Rules for the Conduct of Arbitrations published by The Association of

PART C1: AGREEMENTS AND CONTRACT DATA PAGE 12 C1.2B ECC3 CONTRACT DATA PART 2

ESKOM HOLDINGS SOC Ltd CONTRACT NUMBER ____________PROJECT & CONTRACT TITLE

Arbitrators (Southern Africa) or its successor body.

The place where arbitration is to be held is

South Africa

The person or organisation who will choose an arbitrator- if the Parties cannot agree a

choice or- if the arbitration procedure does

not state who selects an arbitrator, is

the Chairman for the time being or his nominee of the Association of Arbitrators (Southern Africa) or its successor body.

12 Data for secondary Option clauses

X1 Price adjustment for inflation

X1.1(a) The base date for indices is As stated in PART C2: PRICING DATA

X1.1(c) The proportions used to calculate the Price Adjustment Factor are:

In compliance with the price adjustment instructions as provided in PART C2: PRICING DATA

X2 Changes in the law There is no reference to Contract Data in this Option and terms in italics are identified elsewhere in this Contract Data.

X3 Multiple currencies

X3.1 The Employer will pay for these items or activities in the currencies stated Items & activities Other

currency

Maximum payment in other currency

[●] [●] [●]

[●] [●] [●]

[●] [●] [●]

[●] [●] [●]

X3.1 The exchange rates are those published in

X4 Parent company guarantee There is no reference to Contract Data in this Option and terms in italics are identified elsewhere in this Contract Data.

X5 Sectional Completion

PART C1: AGREEMENTS AND CONTRACT DATA PAGE 13 C1.2B ECC3 CONTRACT DATA PART 2

ESKOM HOLDINGS SOC Ltd CONTRACT NUMBER ____________PROJECT & CONTRACT TITLE

X5.1 The completion date for each section of the works is: Section Description Completion

date

1 Ex works As per Purchase order2 Handover

X7.1X5.1

Delay damages for late Completion of the sections of the works are:

R 15 000.00 per day up to 10% of the order value

X15 Limitation of the Contractor’s liability for his design to reasonable skill & care

There is no reference to Contract Data in this Option and terms in italics are identified elsewhere in this Contract Data.

X16 Retention

X16.1 The retention free amount is None

The retention percentage is 5% Reducing Retention Bond of the purchase order value to be issued and submitted together with the first invoice for payment of which 2.5% to be reduced at hand over and the remaining 2.5% valid for the Defects Period.

X17 Low performance damages

X17.1 The amounts for low performance damages are:

The total additional loss above the guarantee level is multiplied by the R/MW given to obtain the performance damage.  Determined by using the criteria in schedules A&B and as provided in the signed and approved specification 240-57648800

X18 Limitation of liability

X18.1 The Contractor’s liability to the Employer for indirect or consequential loss is limited to:

R0.0 (zero Rand)

X18.2 For any one event, the Contractor’s liability to the Employer for loss of or damage to the Employer’s property is limited to:

the amount of the deductibles relevant to the event described in the insurance policy format selected in the data for clause 84.1 above, which policy is available on http://www.eskom.co.za/Tenders/InsurancePoliciesProcedures

X18.3 The Contractor’s liability for Defects due to his design which are not listed on the Defects Certificate is limited to

The greater of the total of the Prices at the Contract Date

and the amounts excluded and unrecoverable

from the Employer’s assets policy for correcting the Defect (other than the resulting physical damage which is not

PART C1: AGREEMENTS AND CONTRACT DATA PAGE 14 C1.2B ECC3 CONTRACT DATA PART 2

ESKOM HOLDINGS SOC Ltd CONTRACT NUMBER ____________PROJECT & CONTRACT TITLE

excluded) plus R2M first amount payable in terms of the Employer’s assets policy.

X18.4 The Contractor’s total liability to the Employer for all matters arising under or in connection with this contract, other than excluded matters, is limited to:

the total of the Prices other than for the additional excluded matters.

The Contractor’s total liability for the additional excluded matters is not limited.

The additional excluded matters are amounts for which the Contractor is liable under this contract for

Defects due to his design which arise before the Defects Certificate is issued,

Defects due to manufacture and fabrication outside the Site,

loss of or damage to property (other than the works, Plant and Materials),

death of or injury to a person and infringement of an intellectual property

right.

X18.5 The end of liability date is (i) 7 years after the defects date for latent Defects and

(ii) the date on which the liability in question prescribes in accordance with the Prescription Act No. 68 of 1969 (as amended or in terms of any replacement legislation) for any other matter.

A latent Defect is a Defect which would not have been discovered on reasonable inspection by the Employer or the Supervisor before the defects date, without requiring any inspection not ordinarily carried out by the Employer or the Supervisor during that period.If the Employer or the Supervisor do undertake any inspection over and above the reasonable inspection, this does not place a greater responsibility on the Employer or the Supervisor to have discovered the Defect.

Z The Additional conditions of contract are Z1 to Z12 always apply.

Z1 Cession delegation and assignment

Z1.1 The Contractor does not cede, delegate or assign any of its rights or obligations to any person without the written consent of the Employer.

Z1.2 Notwithstanding the above, the Employer may on written notice to the Contractor cede

PART C1: AGREEMENTS AND CONTRACT DATA PAGE 15 C1.2B ECC3 CONTRACT DATA PART 2

ESKOM HOLDINGS SOC Ltd CONTRACT NUMBER ____________PROJECT & CONTRACT TITLE

and delegate its rights and obligations under this contract to any of its subsidiaries or any of its present divisions or operations which may be converted into separate legal entities as a result of the restructuring of the Electricity Supply Industry.

Z2 Joint ventures

Z2.1 If the Contractor constitutes a joint venture, consortium or other unincorporated grouping of two or more persons or organisations then these persons or organisations are deemed to be jointly and severally liable to the Employer for the performance of this contract.

Z2.2 Unless already notified to the Employer, the persons or organisations notify the Project Manager within two weeks of the Contract Date of the key person who has the authority to bind the Contractor on their behalf.

Z2.3 The Contractor does not alter the composition of the joint venture, consortium or other unincorporated grouping of two or more persons without the consent of the Employer having been given to the Contractor in writing.

Z3 Change of Broad Based Black Economic Empowerment (B-BBEE) status

Z3.1 Where a change in the Contractor’s legal status, ownership or any other change to his business composition or business dealings results in a change to the Contractor’s B-BBEE status, the Contractor notifies the Employer within seven days of the change.

Z3.2 The Contractor is required to submit an updated verification certificate and necessary supporting documentation confirming the change in his B-BBEE status to the Project Manager within thirty days of the notification or as otherwise instructed by the Project Manager.

Z3.3 Where, as a result, the Contractor’s B-BBEE status has decreased since the Contract Date the Employer may either re-negotiate this contract or alternatively, terminate the Contractor’s obligation to Provide the Works.

Z3.4 Failure by the Contractor to notify the Employer of a change in its B-BBEE status may constitute a reason for termination. If the Employer terminates in terms of this clause, the procedures on termination are P1, P2 and P3 as stated in clause 92, and the amount due is A1 and A3 as stated in clause 93.

Z4 Ethics

Z4.1 Any offer, payment, consideration, or benefit of any kind made by the Contractor, which constitutes or could be construed either directly or indirectly as an illegal or corrupt practice, as an inducement or reward for the award or in execution of this contract constitutes grounds for terminating the Contractor’s obligation to Provide the Works or taking any other action as appropriate against the Contractor (including civil or criminal action).

Z4.2 The Employer may terminate the Contractor’s obligation to Provide the Works if the Contractor (or any member of the Contractor where the Contractor constitutes a joint venture, consortium or other unincorporated grouping of two or more persons or organisations) is found guilty by a competent court, administrative or regulatory body of participating in illegal or corrupt practices.

PART C1: AGREEMENTS AND CONTRACT DATA PAGE 16 C1.2B ECC3 CONTRACT DATA PART 2

ESKOM HOLDINGS SOC Ltd CONTRACT NUMBER ____________PROJECT & CONTRACT TITLE

Such practices include making of offers, payments, considerations, or benefits of any kind or otherwise, whether in connection with any procurement process or contract with the Employer or other people or organisations and including in circumstances where the Contractor or any such member is removed from the an approved vendor data base of the Employer as a consequence of such practice.

Z4.3 Notwithstanding the provisions of core clause 90.2, the procedures on termination in terms of this clause are P1, P2 and P3 as stated in the core clause 92 and the amount due is A1 and A3 as stated in core clause 93.

Z5 Confidentiality

Z5.1 The Contractor does not disclose or make any information arising from or in connection with this contract available to Others. This undertaking does not, however, apply to information which at the time of disclosure or thereafter, without default on the part of the Contractor, enters the public domain or to information which was already in the possession of the Contractor at the time of disclosure (evidenced by written records in existence at that time). Should the Contractor disclose information to Others in terms of clause 25.1, the Contractor ensures that the provisions of this clause are complied with by the recipient.

Z5.2 If the Contractor is uncertain about whether any such information is confidential, it is to be regarded as such until notified otherwise by the Project Manager.

Z5.3 In the event that the Contractor is, at any time, required by law to disclose any such information which is required to be kept confidential, the Contractor, to the extent permitted by law prior to disclosure, notifies the Employer so that an appropriate protection order and/or any other action can be taken if possible, prior to any disclosure. In the event that such protective order is not, or cannot, be obtained, then the Contractor may disclose that portion of the information which it is required to be disclosed by law and uses reasonable efforts to obtain assurances that confidential treatment will be afforded to the information so disclosed.

Z5.4 The taking of images (whether photographs, video footage or otherwise) of the works or any portion thereof, in the course of Providing the Works and after Completion, requires the prior written consent of the Project Manager. All rights in and to all such images vests exclusively in the Employer.

Z5.5 The Contractor ensures that all his subcontractors abide by the undertakings in this clause.

Z6 Waiver and estoppel: Add to core clause 12.3:

Z6.1 Any extension, concession, waiver or relaxation of any action stated in this contract by the Parties, the Project Manager, the Supervisor, or the Adjudicator does not constitute a waiver of rights, and does not give rise to an estoppel unless the Parties agree otherwise and confirm such agreement in writing.

Z7 Health, safety and the environment: Add to core clause 27.4

Z7.1 The Contractor undertakes to take all reasonable precautions to maintain the health and

PART C1: AGREEMENTS AND CONTRACT DATA PAGE 17 C1.2B ECC3 CONTRACT DATA PART 2

ESKOM HOLDINGS SOC Ltd CONTRACT NUMBER ____________PROJECT & CONTRACT TITLE

safety of persons in and about the execution of the works. Without limitation the Contractor: accepts that the Employer may appoint him as the “Principal Contractor” (as defined

and provided for under the Construction Regulations 2014 (promulgated under the Occupational Health & Safety Act 85 of 1993) (“the Construction Regulations”) for the Site;

warrants that the total of the Prices as at the Contract Date includes a sufficient amount for proper compliance with the Construction Regulations, all applicable health & safety laws and regulations and the health and safety rules, guidelines and procedures provided for in this contract and generally for the proper maintenance of health & safety in and about the execution of works; and

undertakes, in and about the execution of the works, to comply with the Construction Regulations and with all applicable health & safety laws and regulations and rules, guidelines and procedures otherwise provided for under this contract and ensures that his Subcontractors, employees and others under the Contractor’s direction and control, likewise observe and comply with the foregoing.

Z7.2 The Contractor, in and about the execution of the works, complies with all applicable environmental laws and regulations and rules, guidelines and procedures otherwise provided for under this contract and ensures that his Subcontractors, employees and others under the Contractor’s direction and control, likewise observe and comply with the foregoing.

Z8 Provision of a Tax Invoice and interest. Add to core clause 51

Z8.1 Within one week of receiving a payment certificate from the Project Manager in terms of core clause 51.1, the Contractor provides the Employer with a tax invoice in accordance with the Employer's procedures stated in the Works Information, showing the amount due for payment equal to that stated in the payment certificate.

Z8.2 If the Contractor does not provide a tax invoice in the form and by the time required by this contract, the time by when the Employer is to make a payment is extended by a period equal in time to the delayed submission of the correct tax invoice. Interest due by the Employer in terms of core clause 51.2 is then calculated from the delayed date by when payment is to be made.

Z8.3 The Contractor (if registered in South Africa in terms of the companies Act) is required to comply with the requirements of the Value Added Tax Act, no 89 of 1991 (as amended) and to include the Employer’s VAT number 4740101508 on each invoice he submits for payment.

Z9 Notifying compensation events

Z9.1 Delete from the last sentence in core clause 61.3, “unless the Project Manager should have notified the event to the Contractor but did not”.

Z10 Employer’s limitation of liability

Z10.1 The Employer’s liability to the Contractor for the Contractor’s indirect or consequential loss is limited to R0.00 (zero Rand)

Z10.2 The Contractor’s entitlement under the indemnity in 83.1 is provided for in 60.1(14) and

PART C1: AGREEMENTS AND CONTRACT DATA PAGE 18 C1.2B ECC3 CONTRACT DATA PART 2

ESKOM HOLDINGS SOC Ltd CONTRACT NUMBER ____________PROJECT & CONTRACT TITLE

the Employer’s liability under the indemnity is limited.

Z11 Termination: Add to core clause 91.1, at the second main bullet point, fourth sub-bullet point, after the words "against it":

Z11.1 or had a business rescue order granted against it.

Z12 Addition to secondary Option X7 Delay damages (if applicable in this contract)

Z12.1 If the amount due for the Contractor’s payment of delay damages reaches the limits stated in this Contract Data for Option X7 or Options X5 and X7 used together, the Employer may terminate the Contractor’s obligation to Provide the Works using the same procedures and payment on termination as those applied for reasons R1 to R15 or R18 stated in the Termination Table.

Z13 The employer reserves the right to cancel the contract and claim any losses which it has suffered as a result of having to make less favourable agreements due to the purchasing of the designated material in line with the stipulated thresholds.

PART C1: AGREEMENTS AND CONTRACT DATA PAGE 19 C1.2B ECC3 CONTRACT DATA PART 2

ESKOM HOLDINGS SOC Ltd CONTRACT NUMBER ____________PROJECT & CONTRACT TITLE

ANNEXURE A: INSURANCE PROVIDED BY THE EMPLOYER

These notes are provided as guidance to tendering contractors and the Contractor about the insurance provided by the Employer. The Contractor must obtain its own advice. Details of the insurance itself are available from the internet web link given below.

1. For the purpose of works contracts, insurance provided by Eskom (the Employer) has been arranged on the basis of “project” or “contract” value, where the value is the total of the Prices at Completion of the whole of the works including VAT.

A “project” is a collection of contracts or work packages to be undertaken as part of a single identified capital expansion or refurbishment of a particular asset or facility.

A “contract” is a single contract not linked to or being part of a “project”.

For ECC3 the applicable Insurance format is Format “A” .

Format A is for a project or contract value less than or equal to R350M (three hundred and fifty million Rand) inclusive of VAT.

Format A generally applies to Generation ,Transmission and Distribution Division projects and contracts. If a project or contract exceeds the Format A limit, the Eskom Insurance Management Services [EIMS] need to be contacted for advice on how to formulate the insurance cover.

2. Tendering contractors should note that cover provided by the Employer is only per the policies available on the internet web link listed below and may not be the cover required by the tendering contractor or as intended by each of the listed insurances in the left hand column of the Insurance Table in clause 84.2. In terms of clause 84.1 “the Contractor provides the insurances stated in the Insurance Table except any insurance which the Employer is to provide”. Hence the Contractor provides insurance which the Employer does not provide and in cases where the Employer does provide insurance the Contractor insures for the difference between what the Insurance Table requires and what the Employer provides.

3. When the Marine Insurance is required the Contractor needs to obtain a copy of the latest edition of Eskom’s Marine Policies Procedures found at internet website given below.

4. Further information and full details of all Eskom provided policies and procedures may be obtained from:

http://www.eskom.co.za/tenders/insurancepoliciesandprocedures

PART C1: AGREEMENTS AND CONTRACT DATA PAGE 20 C1.2B ECC3 CONTRACT DATA PART 2

ESKOM HOLDINGS SOC Ltd CONTRACT NUMBER ____________PROJECT & CONTRACT TITLE

Annexure B:The Employer’s Panel of Adjudicators

The following persons listed in alphabetical order of their surname have indicated their willingness to be included in the Eskom Panel of Adjudicators. Their CV’s may be obtained by using the contact details provided.

Name Location Contact details (phone & e mail)

Nigel ANDREWS Gauteng +27 11 305 [email protected]

Andrew BAIRD Gauteng +27 11 803 [email protected]

Christopher BINNINGTON Gauteng +27 11 [email protected]

Bruce LEECH Gauteng +27 11 290 [email protected]

Nigel NILEN Gauteng +27 11 465 3601; [email protected]

Peter THURLOW Gauteng +27 11 787 [email protected]

Information about the Panel and appointment of the selected Adjudicator is available from Eskom Supply Chain Operations management, by contacting Marumo Lekoto (Tel.: +27 (0)11 800 5383)(Fax :+27 (0)86 6674012) E-mail: [email protected]

PART C1: AGREEMENTS AND CONTRACT DATA PAGE 21 C1.2B ECC3 CONTRACT DATA PART 2

ESKOM HOLDINGS SOC Ltd CONTRACT NUMBER ____________PROJECT & CONTRACT TITLE

C1.2 Contract Data

PART TWO - DATA PROVIDED BY THE CONTRACTOR

Notes to a tendering contractor:

1. Please read both the NEC3 Engineering and Construction Contract (April 2013) and the relevant parts of its Guidance Notes (ECC3-GN)2 in order to understand the implications of this Data which the tenderer is required to complete. An example of the completed Data is provided on pages 156 to 158 of the ECC3 (April 2013) Guidance Notes.

2. The number of the clause which requires the data is shown in the left hand column for each statement however other clauses may also use the same data

3. Where a form field like this [     ] appears, data is required to be inserted relevant to the option selected. Click on the form field once and type in the data. Otherwise complete by hand and in ink.

Completion of the data in full, according to Options chosen, is essential to create a complete contract.

Clause Statement Data

10.1 The Contractor is (Name):      

Address      

Tel No.      

Fax No.      

11.2(8) The direct fee percentage is      %

The subcontracted fee percentage is      %

11.2(18) The working areas are the Site and      

24.1 The Contractor's key persons are:

1 Name:      

Job:      

Responsibilities:      

Qualifications:      

Experience:      

2 Name:      

Job      

Responsibilities:      

Qualifications:      

2 Available from Engineering Contract Strategies Tel 011 803 3008, Fax 011 803 3009 or see www.ecs.co.za

PART C1: AGREEMENTS AND CONTRACT DATA PAGE 22 C1.2B ECC3 CONTRACT DATA PART 2

ESKOM HOLDINGS SOC Ltd CONTRACT NUMBER ____________PROJECT & CONTRACT TITLE

Experience:      

CV's (and further key persons data including CVs) are appended to Tender Schedule entitled     .

11.2(3) The completion date for the whole of the works is      

11.2(14) The following matters will be included in the Risk Register      

11.2(19) The Works Information for the Contractor’s design is in:      

31.1 The programme identified in the Contract Data is      

A Priced contract with activity schedule

11.2(20) The activity schedule is in      

11.2(30) The tendered total of the Prices is       (in figures)

      (in words), excluding VAT

Data for Schedules of Cost Components

Note “SCC” means Schedule of Cost Components starting on page 60, and “SSCC” means Shorter Schedule of Cost Components starting on page 63 of ECC3 (April 2013).

A Priced contract with activity schedule

Data for the Shorter Schedule of Cost Components

41 in SSCC

The percentage for people overheads is:

     %

21 in SSCC

The published list of Equipment is the last edition of the list published by      

The percentage for adjustment for Equipment in the published list is Minus      %

22 in SSCC

The rates of other Equipment are: Equipment Size or capacity

Rate

                 

                 

                 

                 

                 

61 in SSCC

The hourly rates for Defined Cost of design outside the Working Areas are Category of employee Hourly rate

PART C1: AGREEMENTS AND CONTRACT DATA PAGE 23 C1.2B ECC3 CONTRACT DATA PART 2

ESKOM HOLDINGS SOC Ltd CONTRACT NUMBER ____________PROJECT & CONTRACT TITLE

Note: Hourly rates are estimated ‘cost to company of the employee’ and not selling rates.

           

Please insert another schedule if foreign resources may also be used

           

           

           

62 in SSCC

The percentage for design overheads is

     %

63 in SSCC

The categories of design employees whose travelling expenses to and from the Working Areas are included in Defined Cost are:      

PART C1: AGREEMENTS AND CONTRACT DATA PAGE 24 C1.2B ECC3 CONTRACT DATA PART 2

ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________PROJECT & CONTRACT TITLE

C1.3 Forms of Securities

Pro formas for Bonds & Guarantees

For use with the NEC3 Engineering & Construction Contract (June 2005)

The conditions of contract stated in the Contract Data Part 1 include the following Secondary Options:

Option X4: Parent company guarantee

Each of these secondary Options requires a bond or guarantee “in the form set out in the Works Information”. Pro forma documents for these bonds and guarantees are provided here for convenience but are to be treated as part of the Works Information.

Option X16: Retention (not used with Option F)

The Contractor may provide a Retention Money Guarantee in the form stated here. When the Employer receives and accepts a Retention Money Guarantee exactly in the form stated he will instruct the Project Manager not to assess any amount be retained in terms of secondary Option X16.

The organisation providing the bond / guarantee does so by copying the pro forma document onto his letterhead without any change to the text or format and completing the required details. The completed document is then given to the Employer within the time stated in the contract.

PART C2: PRICING DATA PAGE 1 C2 ECC3/A COVER

ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________PROJECT & CONTRACT TITLE

PRO FORMA PARENT COMPANY GUARANTEE (FOR USE WITH OPTION X4)(to be reproduced exactly as shown below on the letterhead of the Contractor’s Parent Company)

Eskom Holdings SOC LtdMegawatt ParkMaxwell DriveSandtonJohannesburg Date:

Dear Sirs,

Parent Company Guarantee for Contract No

With reference to the above numbered contract made or to be made between

Eskom Holdings SOC Ltd (the Employer) and

{Insert registered name and address of the Contractor}(the Contractor), for

{Insert details of the works from the Contract Data} (the works).

I/We the undersigned

on behalf of the Contractor’s parent company

of physical address

and duly authorised thereto do hereby unconditionally guarantee to the Employer that the Contractor shall Provide the Works in accordance with the above numbered Contract.

1. If for any reason the Contractor fails to Provide the Works, we hereby agree to cause to Provide the Works at no additional cost to the Employer.

2. If we fail to comply with the terms of this Deed of Guarantee, the Employer may itself procure such performance (whether or not the Agreement be formally determined). The Employer is to notify us and we shall indemnify the Employer for any additional cost or expense it incurs.

3. Our liability shall be as primary obligor and not merely as surety and shall not be impaired or discharged by reason of any arrangement or change in relationship made between the Contractor and the Employer and/or between us and Contractor; nor any alteration in the obligations undertaken by the Contractor or in the terms of the Agreement; nor any indulgence, failure, delay by you as to any matter; nor any dissolution or liquidation or such other analogous event of the Contractor.

4. The Employer shall not be obliged before taking steps to enforce the terms of this Deed of Guarantee to obtain judgement against the Contractor in any court or other tribunal, to make or file any claim in liquidation (or analogous proceedings) or to seek any remedy or proceed first against the Contractor.

PART C2: PRICING DATA PAGE 2 C2 ECC3/A COVER

ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________PROJECT & CONTRACT TITLE

5. This Deed of Guarantee shall be governed by and construed in accordance with the laws of the Republic of South Africa and we hereby submit to the non-exclusive jurisdiction of the High Court of South Africa.

Signed at

on this day of 200_

Signature(s)

Name(s) (printed)

Position in parent company

Signature of Witness(s)

Name(s) (printed)

PART C2: PRICING DATA PAGE 3 C2 ECC3/A COVER

ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________PROJECT & CONTRACT TITLE

PRO FORMA RETENTION MONEY GUARANTEE (MAY BE USED WHEN OPTION X16 APPLIES)(to be reproduced exactly as shown below on the letterhead of the Bank providing the Guarantee)

Eskom Holdings SOC LimitedMegawatt ParkMaxwell DriveSandtonJohannesburg Date:

Dear Sirs

Reference No. [●] [Drafting Note: Bank reference number to be inserted]

Retention Money Guarantee: [Drafting Note: Name of Contractor to be inserted]

Project [ ] : Contract Reference: [Drafting Note: Contractor contract reference number to be inserted]

1. In this Guarantee the following words and expressions shall have the following meanings:-

1.1 “Bank” - means [●], [●] Branch, (Registration No. [●]); [Drafting Note: Name of Bank to be inserted]

1.2 “Bank’s Address” - means [●]; [Drafting Note: Bank’s physical address to be inserted]

1.3 “Contract” – means the written agreement relating to the Project, entered into between Eskom and the Contractor, on or about the [●] day of [●] 200[●] (Contract Reference No. ………. as amended, varied, restated, novated or substituted from time to time; [Drafting Note: Signature Date and Contract reference number to be inserted]

1.4 “Contractor” – means [●] a company registered in accordance with the laws of [●] under Registration Number [●]. [Drafting Note: Name and details of Contractor to be inserted]

1.5 “Eskom” - means Eskom Holdings SOC Limited, a company registered in accordance with the laws of the Republic of South Africa under Registration Number 2002/015527/30

1.6 “Expiry Date” - means the date on which the Defects Certificate is issued in terms of the Contract.

1.7 “Guaranteed Sum” - means the sum of R [●] ([●] Rand); [Drafting Note: Insert amount of Retention Money Guarantee.].

1.8 “Project” - means the…………………………………..

2. At the instance of the Contractor, we the undersigned ______________ and ______________, in our respective capacities as _____________ and ___________ of the Bank, and duly authorized thereto, confirm that we hold the Guaranteed Sum at the disposal of Eskom, as security for the proper performance by the Contractor of all of its obligations in terms of and arising from the Contract and hereby undertake to pay to Eskom, on written demand from Eskom received prior to the Expiry Date, any sum or sums not exceeding in total the Guaranteed Sum.

3. A demand for payment under this guarantee shall be made in writing at the Bank’s address and shall:

PART C2: PRICING DATA PAGE 4 C2 ECC3/A COVER

ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________PROJECT & CONTRACT TITLE

3.1 be signed on behalf of Eskom by a director of Eskom or his authorised delegate.

3.2 state the amount claimed (“the Demand Amount’);

3.3 state that the Contractor has failed to carry out his obligation(s) to rectify certain defect(s) for which he is responsible under the Contract (and the nature of such defect(s)) alternatively that the Demand Amount is payable to Eskom in the circumstances contemplated in the Contract.

4. Notwithstanding the reference herein to the Contract the liability of the Bank in terms hereof is as principal and not as surety and the Bank’s obligation/s to make payment:

4.1 is and shall be absolute provided demand is made in terms of this bond in all circumstances; and

4.2 is not, and shall not be construed to be, accessory or collateral on any basis whatsoever.

5. The Bank’s obligations in terms of this Guarantee:

5.1 shall be restricted to the payment of money only and shall be limited to the maximum of the Guaranteed Sum; and

5.2 shall not be discharged and compliance with any demand for payment received by the Bank in terms hereof shall not be delayed by the fact that a dispute may exist between Eskom and the Contractor.

6. Eskom shall be entitled to arrange its affairs with the Contractor in any manner which it sees fit, without advising us and without affecting our liability under this Guarantee. This includes, without limitation, any extensions, indulgences, release or compromise granted to the Contractor or any variation under or to the Contract.

7. Should Eskom cede its rights against the Contractor to a third party where such cession is permitted under the Contract, then Eskom shall be entitled to cede to such third party the rights of Eskom under this Guarantee on written notification to the Bank of such cession.

8. This Guarantee:

8.1 shall expire on the Expiry Date until which time it is irrevocable;

8.2 is, save as provided for in Error: Reference source not found above, personal to Eskom and is neither negotiable nor transferable;

8.3 shall be returned to the Bank upon the earlier of payment of the full Guaranteed Sum or expiry hereof;

8.4 shall be regarded as a liquid document for the purpose of obtaining a court order; and

8.5 shall be governed by and construed in accordance with the law of the Republic of South Africa and shall be subject to the jurisdiction of the Courts of the Republic of South Africa.

8.6 Any claim which arises or demand for payment received after expiry date will be invalid and unenforceable.

9. The Bank chooses domicilium citandi et executandi for all purposes in connection with this Guarantee at the Bank’s Address.

Signed at _____________________ Date ____________ Bank’s seal or stamp

For and behalf of the Bank

PART C2: PRICING DATA PAGE 5 C2 ECC3/A COVER

ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________PROJECT & CONTRACT TITLE

Bank Signatory: ___________________ Bank Signatory: ___________________

Witness: ________________________ Witness: _________________________

PART C2: PRICING DATA PAGE 6 C2 ECC3/A COVER

ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________PROJECT & CONTRACT TITLE

PART 2: PRICING DATAECC3 Option A

Document reference

Title

C2.1 Pricing assumptions: Option A

C2.2 The activity schedule

PART C2: PRICING DATA PAGE 7 C2 ECC3/A COVER

ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________PROJECT & CONTRACT TITLE

C2.1 Pricing assumptions: Option A

HOW WORK IS PRICED AND ASSESSED FOR PAYMENT

Clause 11 in NEC3 Engineering and Construction Contract, (ECC3) Option A states:

Identified and defined terms

1111.2 (20) The Activity Schedule is the activity schedule unless later changed

in accordance with this contract.

(27) The Price for Work Done to Date is the total of the Prices for

each group of completed activities and each completed activity which is not in a group.

A completed activity is one which is without Defects which would either delay or be covered by immediately following work.

(30) The Prices are the lump sum prices for each of the activities on the Activity Schedule unless later changed in accordance with this contract.

This confirms that Option A is a lump sum form of contract where the work is broken down into activities, each of which is priced by the tendering contractor as a lump sum. Only completed activities are assessed for payment at each assessment date; no part payment is made if the activity is not completed by the assessment date.

FUNCTION OF THE ACTIVITY SCHEDULE

Clause 54.1 in Option A states: “Information in the Activity Schedule is not Works Information or Site Information”. This confirms that specifications and descriptions of the work or any constraints on how it is to be done are not included in the Activity Schedule but in the Works Information. This is further confirmed by Clause 20.1 which states, “The Contractor Provides the Works in accordance with the Works Information”. Hence the Contractor does not Provide the Works in accordance with the Activity Schedule. The Activity Schedule is only a pricing document.

LINK TO THE PROGRAMME

Clause 31.4 states that “The Contractor provides information which shows how each activity on the Activity Schedule relates to the operations on each programme which he submits for acceptance”. Ideally the tendering contractor will develop a high level programme first then resource each activity and thus arrive at the lump sum price for that activity both of which can be entered into the activity schedule.

PREPARING THE ACTIVITY SCHEDULE

Generally it is the tendering contractor who prepares the activity schedule by breaking down the work described within the Works Information into suitable activities which can be well defined, shown on a programme and priced as a lump sum.

PART C2: PRICING DATA PAGE 1 C2.1 ECC3/A PRICING ASSUMPTIONS

ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________PROJECT & CONTRACT TITLE

The Employer, in his Instructions to Tenderers or in a Tender Schedule, may have listed some items that he requires the Contractor to include in his activity schedule and be priced accordingly.

It is assumed that in preparing his activity schedule the Contractor:

Has taken account of the guidance given in the ECC3 Guidance Notes pages 19 and 20; Understands the function of the Activity Schedule and how work is priced and paid for; Is aware of the need to link the Activity Schedule to activities shown on his programme; Has listed and priced activities in the activity schedule which are inclusive of everything

necessary and incidental to Providing the Works in accordance with the Works Information, as it was at the time of tender, as well as correct any Defects not caused by an Employer’s risk;

Has priced work he decides not to show as a separate activity within the Prices of other listed activities in order to fulfil the obligation to complete the works for the tendered total of the Prices.

Understands there is no adjustment to the lump sum Activity Schedule price if the amount, or quantity, of work within that activity later turns out to be different to that which the Contractor estimated at time of tender. The only basis for a change to the Prices is as a result of a compensation event.

PART C2: PRICING DATA PAGE 2 C2.1 ECC3/A PRICING ASSUMPTIONS

ESKOM HOLDINGS SOC Ltd CONTRACT NO. _________PROJECT & CONTRACT TITLE

C2.2 the activity schedule

Refer attached activity schedule.

PART C2: PRICING DATA PAGE 1 C2.2 ECC3/A ACTIVITY SCHEDULE

ESKOM HOLDINGS SOC Ltd CONTRACT NUMBER _____________PROJECT & CONTRACT TITLE

PART 3: SCOPE OF WORK

Document reference

Title

This cover page

C3.1 Employer’s Works Information

C3.2 Contractor’s Works Information

PART C3: SCOPE OF WORK 1 C3 ECC3 COVER PAGE

Works Information

The works includesTHE DESIGN, MANUFACTURE, SUPPLY, DELIVERY, OFFLOADING, ERECTION AND COMMISSIONING OF 13 X 315 KVA 22KV/400V AND 1 X 315 KVA 22/0.38KV OIL FILLED AUXILIARY TRANSFORMERS FOR TRANSMISSION DIVISION AND POWER DELIVERY PROJECT DIVISION.

1 Description of the Works2 Work to be performed by the Contractor for the Works3 Accountability for the Works Installation4 Programme5 Completion6 Quality management7 Labour8 Restrictions applicable to the Contractor9 Entitlement to site materials10 Accounts and records11 Drawings12 Specifications and Special Requirements13 Appendices

Eskom Holdings SOC Limited Reg No 2002/015527/06

Page 2

INDEX

1. DESCRIPTION OF THE WORKS

2 WORK TO BE PERFORMED BY THE CONTRACTOR FOR THE WORKS2.1 SCOPE OF WORK

2.1.1 Contractor’s design responsibilities2.1.2 Manufacturing and Testing2.1.3 Transport, Delivery, Offloading and Installation2.1.4 Testing and Commissioning

2.2 QUALITY ASSURANCE AND QUALITY CONTROL2.2.1 Reviews2.2.2 Quality2.2.3 Factory Testing

2.3 MISCELLANEOUS2.3.1 Tools2.3.2 Blanking Plates2.3.3 Recommended Spares List2.3.4 Summary table of documentation

2.4 TRAINING

2.5 WARRANTY

2.6 SCHEDULES A & B – As referred in Annexure A and B per transformer2.6.1 Schedule A: Particulars of Employer’s requirements.2.6.2 Schedule B: Guarantees and technical particulars of equipment offered.

3. ACCOUNTABILITY FOR THE WORKS INSTALLATION3.1 SITE WORK 3.2 SITE SERVICES

4 PROGRAM

5 COMPLETION5.1 SECTIONAL COMPLETION

5.1.1 Design freeze5.1.2 Installation 5.1.3 Unit completion

5.2 WORK PROVIDED BY THE CONTRACTOR BY THE COMPLETION DATE

6 QUALITY MANAGEMENT

7 LABOUR

8 RESTRICTIONS APPLICABLE TO THE CONTRACTOR8.1 DETAILS OF OTHER CONTRACTORS

9 ENTITLEMENT TO SITE MATERIALS

10 ACCOUNTS AND RECORDS

PART C3: SCOPE OF WORK 3 C3 ECC3 COVER PAGE

11 DRAWINGS

12 SPECIFICATIONS AND SPECIAL REQUIREMENTS12.1 SPECIFICATIONS

12.2 SPECIAL REQUIREMENTS12.2.1 Transportation requirements and limitations12.2.2 Notification Time12.2.3 Factory Performance Figures

13 ANNEXURES

PART C3: SCOPE OF WORK 4 C3 ECC3 COVER PAGE

1. DESCRIPTION OF THE WORKS

The works includes design, detailed engineering, design review, manufacturing, testing (at Contractor’s works), shipping , local transport, offloading, installation and assembly, oil filling, testing, commissioning and supply of fully functional power transformers as stipulated in the purchase order. The works is done strictly in accordance with:

1. The Employer’s Specification 240-57648800, Specification for Power Transformers rated for 1.25 MVA and above with a highest voltage of 2.2kV and above, including documents listed in the Normative references

2.All accompanying commercial annexures and documents, and3.Agreed test and inspection plan.

The Employer will ensure maintenance and operations are in accordance with manufacturer’s instruction.

All bushing types, tap changers and accessories are as confirmed to the Employer within signed A & B Schedules.

The Contractor provides all engineering services, materials, tools, transport and labour necessary to provide the works for fully completed installation and commissioning.

The works includes the entire power transformer auxiliary equipment normally supplied with a new transformer including but not limited to conservator tank, breathers, HV and MV Bushings, Radiators and Fans, Tap Changer, Protection equipment, Instrumentation, Valves, controls and marshalling kiosks. These are elaborated on in the specification document - 240-57648800.

The works operates effectively for at least 40 years. (Expected design life).

2. WORK TO BE PERFORMED BY THE CONTRACTOR FOR THE WORKS

2.1 SCOPE OF WORK

2.1.1 Contractors Design ResponsibilitiesThe Contractor performs the design and detailed engineering with drawings of the works and affected power transformer auxiliary equipment as detailed in the specification and accompanying schedules “A&B” for each unit.

The scope of supply includes but is not limited to the following:

a) All windings,b) Tank and supporting structures,c) Core,d) Bushings ,e) Tap changer (on-load),f) Radiators, Fans (including motors) and cooling equipment,g) Protection equipment, such as PRV, Buchholz relays, etch) Digital temperature Indicators,i) Bagged Conservator tank, (where applicable),j) Cabling to the Marshalling interface box from each transformer

component,k) Kiosks , panelsl) On-line Dissolved Gas Monitors (where applicable),m) Corrosion Protection painting,

PART C3: SCOPE OF WORK PAGE 5 C3.2 ECC3 CONTRACTOR’S WORKS INFORMATION

n) Dehydrating Breathers,o) Insulating Oilp) Transformer Fast Depressurisation and Fire Prevention Equipment

(where applicable)

The Employer requires that all the individual units of the same SAP Number to be such that they are interchangeable with each other. This is also applicable to all the major components used for each individual unit of the Works, such as fans, bushings, oil pumps etc.

The Contractor shall, after the initial completion of the electrical and mechanical design, perform a design review with the Employer present before closure of the design detail. The Contractor must also provide outline drawings, design details and supporting documents of the works, to the Employers Project Manager within 6 weeks of the order placement, prior to ordering of any materials.

The Contractor provides the finalized outline drawings of the works to the Project Manager before closure of the detail design.

2.1.2 Manufacturing and Testing

During manufacturing, the Employer, reserves the right, at any time, to perform any product or equipment inspections as long as prior notice is given to the Contractor.

The employer reserves the right for its representatives to attend and witness the factory acceptance testing. The Employer’s Project Manager must be notified 12 weeks before the intended test date.

2.1.3 Transport, Delivery , Off-loading and Installation

The Contractor is responsible for the transport of the transformer from the factory to the Employer’s applicable Strategic Store, and for the commissioning and installation, of the transformer at the store. Transformers are to be delivered and off-loaded to the applicable store in accordance with A&B Schedules as stated in the Purchase Orders. On completion of the installation and commissioning, the transformer must be handed over to the Employer with all relevant test results and signed certificates.

In accordance with 240-57648800, a minimum of 2 impact recorders are to be fitted to the transformer before being loaded for transport at the factory. One impact recorder will be mounted inside the transformer tank, on the active part and the other recorder on the outside on the wall, of the transformer tank.

The recorder is only stopped or removed once the transformer is in its final position at the applicable store, witnessed by the Employers’ representative and signed by both parties. One continuous record of horizontal, vertical and longitudinal shock and vibration is recorded starting at the commencement of lifting in the factory ex works and ending after final placement at the various sub-stations. The impact recorders remain the property of the Contractor.

PART C3: SCOPE OF WORK PAGE 6 C3.2 ECC3 CONTRACTOR’S WORKS INFORMATION

All bushings must be transported with shock/impact indicators per the bushing specification 240-56062799.

The Contractor must provide information by means of completing the B schedule for the allowable “G” Force for the units in question, and indicate the tolerances applicable to this value.

The Employer requires results of the impact recorders at the following points to be included in the inspection and test plan:

Loading at the factory After loading onto vehicle After off-loading on to plinth

In addition, Sweep Frequency Response Analysis tests (SFRA) and insulation resistance is done on all the windings prior to the transformer being loaded in the factory. The SFRA will be performed on the highest tap position, which in the case of Eskom Distribution transformers is tap position = 1. The SFRA and insulation resistance tests must be repeated at the once the transformer is in position at the applicable store. If the transformer is being supplied from abroad, the SFRA and insulation resistance tests must be repeated once on the ship and before offloading at the harbour. SFRA is aimed at the early detection of winding movement during the transportation of the transformer as well as to provide a baseline for future condition monitoring of the windings.

The Contractor must submit the results of the SFRA tests, insulation resistance and the, transport vibration and shock monitoring results, to the Employer’s Project Manager and illustrates that no damage or movement of the windings has taken place during the transport process.

Dry-air pressure indication must be provided and must be readable from ground level.

Any information from checks performed by the Contractor, on the impact recorder and the dry-air system, during any transportation phases will be handed to the Employer for assessment, prior to the handing over of the unit.

Whenever plant is dispatched ex works, the Contractor must notify the Project Manager at least 6 weeks in advance of the proposed transport dates, giving the relevant dates of the total transport, a description of the plant, the packing list, the mass, and any other information deemed necessary for identification.

2.1.4 Testing and Commissioning

The Contractor is responsible for the comprehensive installation of the transformer, including all the auxiliary plant necessary for the proper operation of the transformer such as, but not limited to, the bushings, tap changer, conservator tank, radiators, marshalling kiosk, buchholz relay, etc,

The Contractor must perform all the necessary testing and inspections on the plant to ensure safe commissioning of the works, and must ensure that

PART C3: SCOPE OF WORK PAGE 7 C3.2 ECC3 CONTRACTOR’S WORKS INFORMATION

all the tests listed in 240-57648800 are performed and the results properly documented.

The Contractor must maintain a safe and clean condition working environment for the duration of the Contract whilst at Eskom Strategic Stores.

2.2 QUALITY ASSURANCE AND QUALITY CONTROL

2.2.1 Reviews

Design review meetings are scheduled to ensure that there is a common understanding of the specific requirements and the applicable standards. These review meetings are structured as detailed in 240-57648800, and is scheduled by the Contractor at least 12 weeks before the design review meeting. This period will be 6 weeks for the design reviews for local factories.

The design review meeting will be held at the manufacturer’s works or as otherwise specified.

The Contractor minutes all-important information during the design review process and ensures that all outstanding actions are addressed and agreed upon by all parties before manufacturing starts.

2.2.2 Quality

Power transformers are to be manufactured in accordance with a quality assurance management system complying with the latest ISO 9001 and ISO 14001 standards, and must be accepted by the Employer. The Employer reserves the right to conduct surveillance and periodic inspections at the Contractor’s works during the manufacturing phase. The Contractor submits his Process Quality Plans (PQPs) to the Employer for acceptances 6 weeks after the Purchase Order date, and includes all witness and hold points. Draft copies are submitted and discussed during the design review phase.

The Contractor compiles PQPs to cover the following processes:

Manufacturing (includes the design stages and all processes during manufacturing, up to and including testing). This quality documentation must be agreed to by not later than the design freeze date.

Transport ex-works from factory up to the final position at the applicable store. This quality documentation must be agreed to by not later than one (1) month prior to FAT date.

Assembly and commissioning at site. This quality documentation must be agreed to by not later than FAT date.

The PQPs must include and provide for the following:

Details of the process and reference to the project Acceptance by the Employer A list of signatures (and reference to the owner) which will be used to

complete all the steps for the process. This is necessary for identification of the relevant Authority for signing off certain steps or tasks in the process.

PART C3: SCOPE OF WORK PAGE 8 C3.2 ECC3 CONTRACTOR’S WORKS INFORMATION

Hold Points and Witness Points as required by various steps in the processes.

Reference to certificates or any important documentation e.g acceptance criteria for inspection points or tests.

The main process is broken down into individual tasks or steps, to a point as to reflect logical building blocks necessary to complete the main process.

For each step/task there must be place for signature (with date of signature) of a relevant Authority (Supervisor, Inspector etc.).

2.2.3 Factory Testing

The scope is detailed in the A&B schedules, the standard 240- 68973110 and the acceptance criteria shall be in accordance with the relevant and latest IEC standard as per date of the order. The Employer reserves the right to be present during any or all of tests.The Contractor shall inform the Employer of the testing date 12 weeks in advance.

The Employer’s Project Manager only releases a power transformer for despatch when all tests have been successfully completed, and all the necessary quality documentation completed. The Employer’s Project Manager must give the instruction for the despatch within 48 hours from successful test.

2.3 MISCELLANEOUS

2.3.1 Tools

The Contractor provides any special tools or keys, if any, that are required for maintenance or affecting adjustments. Excluded are special tools required for long-term tap changer maintenance.

2.3.2 Blanking Plates

The Contractor supplies the transformers with all the blanking plates, which should be kept as the property of the Employer. The blanking plates must be painted to the same specification as the transformer tank.

2.3.3 Recommended Spares List

The Contractor supplies a list of recommended spares for the works for the transformer after final design. This list includes item descriptions, reference numbers quantity recommended, prices, and guaranteed supply period. The Contractor also details the recommended routine maintenance required to maintain maximum availability. Where possible, the local supply of plant and material must be indicated.

2.3.4 Summary table of documentation

The Contractor supplies the following minimum documentation:

DOCUMENT NAME

COPIES REQUIRED

WHEN TO SUBMIT REFER TO

SECTION

PART C3: SCOPE OF WORK PAGE 9 C3.2 ECC3 CONTRACTOR’S WORKS INFORMATION

QA Manual 2 Ex-works + 2 weeks 2.2.2

Operating & Maintenance Manual (Training)

2Before commissioning of the Works

2.4

Operating & Maintenance Manual

5 Ex-works + 2 weeks

240-68973110 and 240-60725684

Soft copy of above 1 Ex-works + 2 weeks

2.4 TRAINING

The Contractor shall provide training to the Employer. The training shall be given at different levels

Site staff - It is the responsibility of the Contractor to provide training to the Employer’s personnel in the operation and maintenance of the works. The Contractor provides a list of recommended training activities including duration and location.

The Contractor provides two (2) Master Training Manuals and an electronic media like video is accepted. Each person trained receives his/her own individual copy of the training manual, which allows him/her to make notes in the manual during the training sessions. The Project Manager will provide the number of Employer’s personnel to be trained up to a maximum of 15 people and duration up to two days.

Training is given to the following site staff Store people for units being delivered and erected for storage Site staff responsible for maintenance for units being installed and commissioned at the Employer’s premises.

Training must be completed before the hand-over of the works. The Contractor shall submit proof of training conducted as part of the handing over documents.

Engineering staff: The training for engineers shall be arranged on ad-hoc basis and this shall be in line with the design, manufacturing, testing, and life management of transformers. The Contractor shall bring proposal to the Employer for acceptance. During each contract review, the OEM shall produce the records of the training done.

2.5 WARRANTY

The warranty is only applicable provided that the transformer has been installed by, or has been under the supervision of an engineer/technician approved by the respective factory. The preparation for storage, or moving to required destination after storage, must be supervised by the manufacturer's supervisor or an engineer / technician approved by the respective manufacturer.

In the case where the site is not ready for installation and commissioning, the Employer will be responsible for the unit until the site is ready. The Employer has to adhere to the storage procedure of the Contractor. In all other circumstances provided the Employer had handed the unit back to the Contractor, the Contractor remains responsible for handling and storage of items.

PART C3: SCOPE OF WORK PAGE 10 C3.2 ECC3 CONTRACTOR’S WORKS INFORMATION

The equipment is handled and maintained in compliance with the manufacturer's instructions and the equipment is not exposed to the conditions other than those defined by provisions of the Contract.

Normal wear and tear, inadequate maintenance, conditions of Force Majeure and any other damage that cannot be considered as Contractor’s fault are not covered by warranty.

2.6 SCHEDULES A & B

2.6.1Schedule A: Specific requirements by the Employer’s.

2.6.2 Schedule B: Guarantees and technical particulars of equipment offered by the Contractor. The Contractor guarantees the values entered in Schedule B.

SCHEDULE A&B takes precedence over all other specifications.

3. ACCOUNTABILITY FOR THE WORKS INSTALLATION

3.1 SITE WORK

The Employer performs the following specific tasks at the strategic store:

a) Bonding of the transformer bushings to ground using the appropriate materials.b) Earthing of the transformer tank.c) Cabling from Marshalling interface box.d) Connection of the tap changer heater to the relevant supplye) Provision of unobstructed access to site in order to ensure completion of the

works.

The Contractor is responsible for all cabling from the transformer and its components to the marshalling interface box as well as the supply and installation of all components necessary for the completion the works.

3.2 SITE SERVICES

The Employer will provide all relevant information pertaining to the site.

4 PROGRAM

The Contractor submits a first program to the Employer for acceptance within six weeks of the Purchase Order date.

The program contains all activities, durations, resource details, start date and completion date and relevant milestone dates.

The program is submitted utilising MS Projects format.

PART C3: SCOPE OF WORK PAGE 11 C3.2 ECC3 CONTRACTOR’S WORKS INFORMATION

5 COMPLETION

5.1 SECTIONAL COMPLETIONThe following phases of work are to be completed for sectional completion for the transformer

5.1.1 Design freeze- Design review has been completed- The design in totality according to the Works Information- Single line, general arrangement and detail drawings- All new plant interfaces- Commissioning / re-commissioning procedures- Quality Assurance plans- Inspection and test plans- Manufacturing PQP’s

5.1.2 Installation- Signed clearance and test certificates- One set of red lined (as-built) drawings available - Completed PQPs- Training manuals available- Personnel fully trained - Operating and maintenance manuals delivered- No defects and installation according to Works Information- Oil samples taken before and after installation of the works

5.1.3 Unit completion- No outstanding defects. - All documentation as required in Section 2.3.4 delivered.- All Quality Control documentation signed off, with no outstanding issues

to address.

5.2 WORK PROVIDED BY THE CONTRACTOR BY THE COMPLETION DATE

The following works are provided by the Contractor in accordance with the Works Information:

a. Designb. Supply whole of the worksc. Deliver whole of the worksd. Removal of all debris, tools and equipment used during erection of the works. e. Corrosion protection on whole of the worksf. Installation and Commissioning of the Worksg. Operating and Maintenance Manualsh. Employer Staff Training and Training Manualsi. "As Built" Drawings for whole of the worksj. All the Quality Documentation signed off with no outstanding actions to be

resolved

6. QUALITY MANAGEMENT

The Contractor demonstrates compliance to the applicable Quality documents as referenced in the specifications.

PART C3: SCOPE OF WORK PAGE 12 C3.2 ECC3 CONTRACTOR’S WORKS INFORMATION

The Contractor authorises all documents submitted as demonstration of compliance to the quality requirements of the contract.

Before Plant is placed in service the Contractor is to certify that it is in safe condition.

7. LABOUR

All staff whether, permanent, non-permanent, part-time, sub-contracted, and labour only supply, is the Contractor’s responsibility in terms of supervision and control.

8 RESTRICTIONS APPLICABLE TO THE CONTRACTOR

8.1 DETAILS OF OTHER CONTRACTORS The Contractor could be interfacing with the following Contractorso The Employer’s Protection and Metering department (PT&M)o The Employer’s maintenance departmentso Any other

9 ENTITLEMENT TO SITE MATERIALS

All Plant and Material that are removed remains the property of the Employer. It is important to note that the Contractor stores the removed Plant and Material at a dedicated area.

10 ACCOUNTS AND RECORDS

10.1 THE FOLLOWING INFORMATION MUST BE AVAILABLE ON THE INVOICE:The Supplier shall address the tax invoice to Purchaser and include on each invoice the following information:

Name and address of the Supplier and the Supply Manager; The contract number and title;Supplier’s VAT registration number;The Purchaser’s VAT registration number.Description of goods and services provided for each item invoiced based on the Price Schedule;Total amount invoiced excluding VAT, the VAT and the invoiced amount including VAT;

The method and conditions of payment are:

Electronic payment in full to supplier’s nominated South African Bank Account within 30 (thirty) days for a BEE/Other Supplier after the receipt of an acceptable tax invoice.

The invoices must contain the following additional information:

Employer’s name should be stated Eskom Holdings SOC Ltd The registered name of the Supplier. The VAT registration number of the Supplier. The address of the Supplier. Invoice number Date of invoice Supplier’s   Banking Details Copy of Delivery note attached to invoice

PART C3: SCOPE OF WORK PAGE 13 C3.2 ECC3 CONTRACTOR’S WORKS INFORMATION

The Purchaser’s contract/order number Accurate description of the goods, as per the purchase order VAT must be shown separately at the bottom of the invoice The Purchaser’s VAT registration number 4740101508 and company registration number 2002/015527/06.

Foreign Payment: Invoice (Local Supplier) Commercial Invoice (Overseas Supplier) SARS Release Notification SAD 500 Customs Worksheet Bill of Lading

Three options of invoice delivery are available, namely hand delivered to Eskom, posted to Eskom or e-mailed to Eskom as described below; 

Electronic submission of invoices via e-mail:

Details on how to submit invoices and additional information: Ensure that the Eskom order number is clearly indicated on your invoice together with the

line number on the order you are billing for. All Electronic invoices must be sent in PDF format only. Each PDF file should contain one invoice; or one debit note; or one credit note only as

Eskom’s SAP system does not support more than one PDF being linked into workflow at a time.

Only one PDF file per email. (one invoice or debit note or credit note) Send all invoices in PDF straight from your system to an Eskom email address (see email

addresses below) For Foreign invoices, suppliers will still be required to physically deliver hard copies of

original documents to the respective documentation management centers even though you have e-mailed those invoices (Eskom is still seeking clarity from the South African Reserve Bank regarding e-invoicing for Foreign Invoices or invoices in foreign currency. Current requirements are that these manual invoices should still be submitted. You can send the invoice copy to the email addresses indicated below).

Please ensure that you comply with the tax Requirement for submitting invoices electronically.

If there is Cost Price Adjustment (CPA) on your invoice we recommend that you issue a separate invoice for CPA so that if there are any issues on the CPA the rest of the invoice can be paid while resolving the CPA issues.

Introduction of electronic invoicing does not guarantee payment but will ensure visibility of all invoices and ensure that no invoices get lost. If the goods receipt is not done the invoice will be parked and the system will automatically send an e-mail to the end user to do the goods receipt. This is also tracked by Eskom through the park invoice report.

Your company can request a park invoice report from the Finance Shared Services (FSS) contact centre which can then be followed up and corrected. You are welcome to forward the details of invoices corrected to the FSS contact centre.

Email address for invoice submission: [email protected]

11 DRAWINGS

PART C3: SCOPE OF WORK PAGE 14 C3.2 ECC3 CONTRACTOR’S WORKS INFORMATION

Applicable drawings for this contract are contained in the Annexures.Additional drawings required to supply the works can be applied for by the Contractor.

All new drawings become the property of the Employer. All drawings provided by the Contractor must adhere to 240-57648800.

12 SPECIFICATIONS AND SPECIAL REQUIREMENTS

12.1 Specifications

The following standards and those listed in the annexure; contain provisions that, through reference in text, constitute requirements of this document, including reference documents referred to in these standards. The revision as at the date of Contract placement is applicable. The Contractor is responsible for obtaining the latest revision of these documents.

12.2 Special requirements

12.2.1 Transportation requirements and limitationsThe transport limitations are reflected in the drawings and additional information provided in Annexure B.

12.2.2 Notification TimeFor local factories, the Contractor will inform the Employer 6 weeks prior to F.A.T’s. For factories outside the borders of South Africa, the Contractor will inform the Employer 12 weeks prior to F.A.T’s.

12.2.3 Factory Performance FiguresThe Contractor must provide the Employer with the factory performance figures every 6 months. The annual performance figures must have been audited by an independent body. The Contractor must inform the Employer of any deviations from the quoted Factory failure rates or on time delivery rate.

13 ANNEXURES:

Annexure ADocumentation, Configuration Management, and Drawings

PART C3: SCOPE OF WORK PAGE 15 C3.2 ECC3 CONTRACTOR’S WORKS INFORMATION

Contents

C3.2 CONTRACTOR’S WORKS INFORMATION

This section of the Works Information will always be contract specific depending on the nature of the works.It is most likely to be required for design and construct contracts where the tendering contractor will have proposed specifications and schedules for items of Plant and Materials and workmanship, which once accepted by the Employer prior to award of contract now become obligations of the Contractor per core clause 20.1.

Typical sub headings could be

a) Contractor’s designb) Plant and Materials specifications and schedulesc) Other

This section could also be compiled as a separate file.

PART C3: SCOPE OF WORK PAGE 16 C3.2 ECC3 CONTRACTOR’S WORKS INFORMATION

PART 4: SITE INFORMATION

Document reference Title

This cover page

C4 Site Information

Total number of pages

Eskom Holdings SOC Limited Reg No 2002/015527/06

Page 17

PART 4: SITE INFORMATION

INSTALLATION OF THE UNITS

1 Description of the Works2 Work to be performed by the Contractor for the Works3 Work and things for the Works supplied by the Employer4 Programme5 Completion6 Quality management7 Labour8 Restrictions applicable to the Contractor9 Title to site materials10 Accounts and records11 Drawings12 Specifications and Special Requirements13 Appendices

PART C3: SCOPE OF WORK PAGE 18 C3.2 ECC3 CONTRACTOR’S WORKS INFORMATION

INDEX

1. DESCRIPTION OF THE WORKS

2 WORK TO BE PERFORMED BY THE CONTRACTOR FOR THE WORKS2.1 SCOPE OF WORK

2.1.1 Contractor’s design responsibilities2.1.2 Delivery and Off-loading2.1.3 Testing and Commissioning2.1.4 Interface

2.2 QUALITY ASSURANCE AND QUALITY CONTROL2.2.1 Quality2.2.2 Reviews2.2.3 Factory Testing

2.3 MISCELLANEOUS2.3.1 Tools2.3.2 Blanking Plates2.3.3 Recommended Spares List2.3.4 Summary table of documentation

2.4 TRAINING

2.5 SCHEDULES A & B – As referred in Annexure A and B per transformer2.5.1 Schedule A: Particulars of Employer’s requirements.2.5.2 Schedule B: Guarantees and technical particulars of equipment offered.

2.6 DOCUMENTATION AND CONFIGURATION MANAGEMENT – As referred in Annexure D for each applicable unit

2.7 GENERAL SITE INFORMATION – As referred in Annexure A for each applicable unit

3. WORK AND THINGS FOR THE WORKS SUPPLIED BY THE EMPLOYER3.1 SITE WORK 3.2 SITE SERVICES

4 PROGRAM

PART C3: SCOPE OF WORK PAGE 19 C3.2 ECC3 CONTRACTOR’S WORKS INFORMATION

5 COMPLETION5.1 SECTIONAL COMPLETION

5.1.1 Design freeze5.1.2 Installation and Commissioning5.1.3 Unit completion

5.2 WORK PROVIDED BY THE CONTRACTOR BY THE COMPLETION DATE

6 QUALITY MANAGEMENT

7 LABOUR

8 RESTRICTIONS APPLICABLE TO THE CONTRACTOR8.1 DETAILS OF OTHER CONTRACTORS

9 TITLE TO SITE MATERIALS

10 ACCOUNTS AND RECORDS

11 DRAWINGS

12 SPECIFICATIONS AND SPECIAL REQUIREMENTS12.1 SPECIFICATIONS

12.2 SPECIAL REQUIREMENTS12.2.1 Transportation requirements and limitations12.2.2 Time

13 ANNEXURES

PART C3: SCOPE OF WORK PAGE 20 C3.2 ECC3 CONTRACTOR’S WORKS INFORMATION

EMPLOYER’S NAME CONTRACT NUMBER _____________PROJECT & CONTRACT TITLE

1. DESCRIPTION OF THE WORKS

THE DESIGN, MANUFACTURE, SUPPLY, DELIVERY, OFFLOADING, ERECTION AND COMMISSIONING e works includes design, detailed engineering, manufacture, testing (at Contractor’s works), supply, delivery, installation commissioning and training of the units as stipulated in Table 1.1, complete fully functional Auxiliary transformers. The works is done strictly in accordance with the Employer’s Specification 240-57648800 for Specification for New Oil Filled Auxiliary Transformers Rated 1 MVA and below and 33KV and below The Employer will ensure maintenance and operations are in accordance with manufacturer’s instruction.

All bushing types, tap changers and accessories are as confirmed to Employer within signed A & B Schedules.

TABLE 1.1Station Number of power

transformer required

TransformerMVA Rating

Voltage kVMV side / HV side

Tx Stores 13 315 KVA 22KV/400VVulcan Substation

1 315 22/0.38KV

The Contractor provides all engineering services, material and labour necessary to provide the works to fully completed installation and commissioning.

The works includes the entire power transformer auxiliary equipment normally supplied with a new transformer including but not limited to conservator tank, breathers, HV and MV Bushings, Radiators and Fans, Tap Changer, Protection equipment, Instrumentation, Valves, controls and marshalling kiosks.

The works operates effectively for at least 40 years. (Expected design life).

2. WORK TO BE PERFORMED BY THE CONTRACTOR FOR THE WORKS

2.1 SCOPE OF WORK

2.1.1 Contractors Design ResponsibilitiesThe Contractor performs the design and detailed engineering with drawings of the works and affected power transformer auxiliary equipment as detailed in the signed schedules “A&B” for these units.

The scope of supply includes but is not limited to the following:

q) All windings,r) Cores) Bushings t) Tap changer (on-load)u) Radiatorsv) Protection equipment, such as PRV, Buchholz relays, etcw) Digital temperature Indicators,x) Bagged Conservator tank, (where applicable)y) Cabling to the Marshalling interface box

PART C4: SITE INFORMATION PAGE 1 C4 ECC3 SITE INFORMATION

EMPLOYER’S NAME CONTRACT NUMBER _____________PROJECT & CONTRACT TITLE

z) Kiosks , panelsaa) Corrosion Protection paintingbb) Dehydrating Breatherscc) Fans, Motors

The Employer requires that all the individual units of the same rating (see fig.2 of 240-57648800 and capability of the Works be such that they are interchangeable with each other.

This is also applicable to all the major components used for each individual unit of the Works, such as fans, bushings, oil pumps etc.

2.1.2 Delivery , Off-loading and installation

The transformers are delivered and off-loaded to the applicable sub-station/s in accordance with A&B Schedules as stated in the Purchase Orders. In accordance with 240-57648800 a minimum of 2 impact recorders are fitted to the transformer before being loaded for transport at the factory. One (1) impact recorder will be mounted inside the transformer tank, on the active part and the other recorder on the outside on the wall of the transformer tank. The recorder is only stopped or removed once the transformer is finally positioned at the specific sub-station, witnessed by the Employers’ representative and signed by both parties. One continuous record of horizontal, vertical and longitudinal shock and vibration is recorded starting at the commencement of lifting in the factory ex works and ending after final placement at the various sub-stations. The impact recorders remain the property of the Contractor. Dry-air pressure indication must be provided and must be readable from ground level.

The Contractor must provide information by means of completing the B schedule for the allowable “G” Force for the units in question, and indicate the tolerances applicable to this value.

The Employer requires results of the impact recorders at the following to be included in the inspection and test plan:

Loading at the factory After loading onto vehicle After off-loading on to plinth

In addition, a Swept Frequency Response Analyses test (SFRA Test) (Fully assembled) is done on all the windings prior to the transformer being loaded in the factory. The SFRA will be performed under on the highest tap position, which in the case of Eskom Distribution transformers is tap position = 1. The SFRA test is repeated once the transformer is in position at the various sub stations. This test is aimed at the early detection of winding movement during the transportation of the transformer as well as to provide a baseline for future condition monitoring of the windings.

The Contractor submits the results of the SFRA tests and the transport vibration and shock monitoring results to the Project Manager (IARC) and illustrates that no damage or movement of the windings has taken place during the transport process.

PART C4: SITE INFORMATION PAGE 2 C4 ECC3 SITE INFORMATION

EMPLOYER’S NAME CONTRACT NUMBER _____________PROJECT & CONTRACT TITLE

Whenever plant is dispatched ex works, the Contractor notifiesthe Project Manager at least 6 weeks in advance of the proposed transport dates. Giving the relevant dates of the total transport and adescription of the plant, the packing list, the mass, and any otherinformation deemed necessary for identification.

2.1.3 Testing and Commissioning

All the tests as listed in 240-57648800 are done and the results are properly documented. The Contractor performs all the necessary testing and inspections on the plant to ensure safe commissioning of the works.

2.1.4 Interfaces

Earthing of the surge arrestors’ brackets to be done in accordance with 240-57648800.

2.2 QUALITY ASSURANCE AND QUALITY CONTROL

2.2.1 Quality

The power transformers are manufactured in accordance with a quality assurance management system complying with ISO 9001-2000 and ISO 14001 and accepted by the Project Manager. The Project Manager reserves the right to conduct surveillance and periodic inspections at the Contractor’s works during the manufacturing phase. The Contractor submits his QCP’s to the Project Manager for acceptance 6 weeks after the Purchase Order date, and includes all witness and hold points. Draft copies are submitted and discussed during the design review phase.

The Contractor compiles Process Quality Plans (PQPs) to cover the following processes:

Manufacturing (includes the design stages and all processes during manufacturing). This quality documentation must be agreed to by not later than the design freeze date.

Transport ex-works from factory up to final positioning at the various sub stations. This quality documentation must be agreed to by not later than one (1) month prior to FAT date.

Assembly and commissioning at site. This quality documentation must be agreed to by not later than FAT date.

The PQPs must include and provide for the following:

Details of the process and reference to the project Acceptance by the Employer A list of signatures (and reference to the owner) which will be used to

complete all the steps for the process. This is necessary for identification of the relevant Authority for signing off certain steps or tasks in the process.

Hold Points and Witness Points as required by various steps in the processes.

PART C4: SITE INFORMATION PAGE 3 C4 ECC3 SITE INFORMATION

EMPLOYER’S NAME CONTRACT NUMBER _____________PROJECT & CONTRACT TITLE

Reference to certificates or any important documentation e.g acceptance criteria for inspection points or tests.

The main process is broken down into individual tasks or steps, to a point as to reflect logical building blocks necessary to complete the main process.

For each step/task there must be place for signature (with date of signature) of a relevant Authority (Supervisor, Inspector etc.).

2.2.2 Reviews

Design review meetings are scheduled to ensure that there is a common understanding of the specific requirements and the applicable standards. These review meetings are structured as detailed in 240-57648800.

The design review meeting will be held at the manufacturer’s works or as otherwise specified.

The Contractor minutes all-important information during the design review process and ensures that all outstanding actions are addressed before manufacturing starts.

2.2.3 Factory Testing

The scope is detailed in the A & B schedules, the standard and the acceptance criteria shall be in accordance with the relevant and latest IEC standard as per date of contract. The Employer reserves the right to be present during any or all of tests.

The Project Manager only releases a power transformer for despatch when all tests have been successfully completed, and all the necessary quality documentation completed.

2.3 MISCELLANEOUS

2.3.1 Tools

The Contractor provides any special tools or keys, if any, that are required for maintenance or affecting adjustments. Excluded are special tools required for long-term tap changer maintenance.

2.3.2 Blanking Plates

The Contractor supplies the transformers with all the blanking plates.

2.3.3 Recommended Spares List

The Contractor supplies a list of recommended spares for the works for the transformer after final design. This list includes item descriptions, reference numbers quantity recommended, prices, and guaranteed supply period. The Contractor also details the recommended routine maintenance required to maintain maximum availability. Where possible, the local supply of plant and material must be indicated.

PART C4: SITE INFORMATION PAGE 4 C4 ECC3 SITE INFORMATION

EMPLOYER’S NAME CONTRACT NUMBER _____________PROJECT & CONTRACT TITLE

2.3.4 Summary table of documentation

The Contractor supplies the following minimum documentation:

DOCUMENT NAME

COPIES REQUIRED

WHEN TO SUBMIT REFER TO SECTION

QA Manual 2 Before delivery 2.2.1

Operating & Maintenance Manual

As per Schedules A& B

Before commissioning of the Works 240-

57648800

Soft copy of above 1 Before commissioning of

the WorksSoft copy of above

2.4 TRAINING

It is the responsibility of the Contractor to provide appropriate training to the Employer’s operating and engineering personnel in the transport, assembly, operation and maintenance of the works. The Contractor provides a list of recommended training activities including duration and location.

The Project Manager will provide the number of Employer’s personnel to be trained.

Training is performed during final installation and commissioning. Training is completed before Completion of the works.

Training is performed in accordance with 240-57648800.

2.5 SCHEDULES A & B

2.5.1 Schedule A: Specific requirements by the Employer’s.

2.5.2 Schedule B: Guarantees and technical particulars ofequipment offered by the Contractor.

The Contractor guarantees the values entered in Schedule B

Schedules A&B takes precedence over all other specifications.

PART C4: SITE INFORMATION PAGE 5 C4 ECC3 SITE INFORMATION

EMPLOYER’S NAME CONTRACT NUMBER _____________PROJECT & CONTRACT TITLE

3. WORK AND THINGS FOR THE WORKS SUPPLIED BY THE EMPLOYER

3.1 SITE WORK

The Employer performs the following specific tasks:

f) HV and MV cabling/conductors/connections to and from the transformer.g) Installation of surge arrestors and connection of same and bushings.h) Earthing of the transformer tank.i) Cabling from Marshalling interface box.j) Provision of unobstructed access to site in order to ensure completion of the

works.

The Contractor is responsible for all cabling from transformer to the Marshalling interface box as well as the supply and installation of everything else for completing the works.

3.2 SITE SERVICES

The Project Manager will provide all relevant information.

4 PROGRAM

The Contractor submits a first program to the Project Manager for acceptance within six weeks of the Purchase Order date.

The program contains all activities, durations, resource details, start date and completion date and relevant milestone dates.

The program is submitted utilising MS Projects format.

5 COMPLETION

5.1 SECTIONAL COMPLETION The following phases of work are to be completed for sectional completion for the transformer

5.1.1 Design freeze- Design review has been completed- The design in totality according to the Works Information- Single line, general arrangement and detail drawings- All new plant interfaces- Commissioning / re-commissioning procedures- Quality Assurance plans- Inspection and test plans- Manufacturing PQP’s

5.1.2 Installation- Signed clearance and test certificates- One set of red lined (as-built) drawings available - Completed PQPs- Training manuals available- Personnel fully trained - Operating and maintenance manuals delivered- No defects and installation according to Works Information

PART C4: SITE INFORMATION PAGE 6 C4 ECC3 SITE INFORMATION

EMPLOYER’S NAME CONTRACT NUMBER _____________PROJECT & CONTRACT TITLE

- Oil samples taken before and after installation of the works

5.1.3 Unit completion- No outstanding defects. - Unit in service for 2 weeks continuously with no abnormalities surfacing

providing that the Employer enable this.- All documentation as required in Section 2.3.4 delivered.- All Quality Control documentation signed off, with no outstanding issues

to address.

5.2 WORK PROVIDED BY THE CONTRACTOR BY THE COMPLETION DATE

The following works are provided by the Contractor in accordance with the Works Information:

a. Designb. Supply whole of the worksc. Deliver whole of the worksd. Removal of all debris, tools and equipment used during erection of the works. e. Corrosion protection on whole of the worksf. Installation and Commissioning of the Worksg. Operating and Maintenance Manualsh. Employer Staff Training and Training Manualsi. "As Built" Drawings for whole of the worksj. All the Quality Documentation signed off with no outstanding actions to be

resolvedk. The works have been in service for at least two weeks with no sign of any

abnormalities being present providing that the Employer enables this.

6. QUALITY MANAGEMENT

The Contractor demonstrates compliance to (a) ISO 9001 2000 & ISO 140001 quality standards(b) ESKASAAA3, ESKPVAADO.

The Contractor authorises all documents submitted as demonstration of compliance to the quality requirements of the contract.

Before Plant is placed in service the Contractor is to certify that it is in safe condition.

7. LABOUR

All staff whether permanent, non-permanent, part-time, sub-contracted, and labour only supply, is the Contractor’s responsibility in terms of supervision and control.

8 RESTRICTIONS APPLICABLE TO THE CONTRACTOR

8.1 DETAILS OF OTHER CONTRACTORS The Contractor could be interfacing with the following Contractorso The Employer’s Protection and Metering department (PT&M)o The Employer’s maintenance departmentso Any other

PART C4: SITE INFORMATION PAGE 7 C4 ECC3 SITE INFORMATION

EMPLOYER’S NAME CONTRACT NUMBER _____________PROJECT & CONTRACT TITLE

9 TITLE TO SITE MATERIALS

All Plant and Material that are removed remains the property of the Employer. It is important to note that the Contractor stores the removed Plant and Material at a dedicated area.

10 ACCOUNTS AND RECORDS

10.1 THE FOLLOWING INFORMATION MUST BE AVAILABLE ON THE INVOICE:- The Supplier shall address the tax invoice to Purchaser and include on each invoice the following information:

Name and address of the Supplier and the Supply Manager; The contract number and title;Supplier’s VAT registration number;The Purchaser’s VAT registration number.Description of goods and services provided for each item invoiced based on the Price

Schedule;Total amount invoiced excluding VAT, the VAT and the invoiced amount including

VAT;

The method and conditions of payment are:

Electronic payment in full to supplier’s nominated South African Bank Account within 30 (thirty) days for a BEE/Other Supplier after the receipt of an acceptable tax invoice.

The invoices must contain the following additional information:

Employer’s name should be stated Eskom Holdings SOC Ltd The registered name of the Supplier. The VAT registration number of the Supplier. The address of the Supplier. Invoice number Date of invoice Supplier’s   Banking Details Copy of Delivery note attached to invoice The Purchaser’s contract/order number Accurate description of the goods, as per the purchase order VAT must be shown separately at the bottom of the invoice The Purchaser’s VAT registration number 4740101508 and company registration number 2002/015527/06.

Foreign Payment: Invoice (Local Supplier) Commercial Invoice (Overseas Supplier) SARS Release Notification SAD 500 Customs Worksheet Bill of Lading

Three options of invoice delivery are available, namely hand delivered to Eskom, posted to Eskom or e-mailed to Eskom as described below; 

Electronic submission of invoices via e-mail:

PART C4: SITE INFORMATION PAGE 8 C4 ECC3 SITE INFORMATION

EMPLOYER’S NAME CONTRACT NUMBER _____________PROJECT & CONTRACT TITLE

Details on how to submit invoices and additional information: Ensure that the Eskom order number is clearly indicated on your invoice together with the

line number on the order you are billing for. All Electronic invoices must be sent in PDF format only. Each PDF file should contain one invoice; or one debit note; or one credit note only as

Eskom’s SAP system does not support more than one PDF being linked into workflow at a time.

Only one PDF file per email. (one invoice or debit note or credit note) Send all invoices in PDF straight from your system to an Eskom email address (see email

addresses below) For Foreign invoices, suppliers will still be required to physically deliver hard copies of

original documents to the respective documentation management centers even though you have e-mailed those invoices (Eskom is still seeking clarity from the South African Reserve Bank regarding e-invoicing for Foreign Invoices or invoices in foreign currency. Current requirements are that these manual invoices should still be submitted. You can send the invoice copy to the email addresses indicated below).

Please ensure that you comply with the tax Requirement for submitting invoices electronically.

If there is Cost Price Adjustment (CPA) on your invoice we recommend that you issue a separate invoice for CPA so that if there are any issues on the CPA the rest of the invoice can be paid while resolving the CPA issues.

Introduction of electronic invoicing does not guarantee payment but will ensure visibility of all invoices and ensure that no invoices get lost. If the goods receipt is not done the invoice will be parked and the system will automatically send an e-mail to the end user to do the goods receipt. This is also tracked by Eskom through the park invoice report.

Your company can request a park invoice report from the Finance Shared Services (FSS) contact centre which can then be followed up and corrected. You are welcome to forward the details of invoices corrected to the FSS contact centre.

Email address for invoice submission: [email protected]

11 DRAWINGS

Applicable drawings for this contract are contained in the Annexures.Additional drawings required to supply the works can be applied for by the Contractor.

All new drawings become the property of the Employer.

All drawings provided by the Contractor must adhere 240-57648800

12 SPECIFICATIONS AND SPECIAL REQUIREMENTS

12.1SpecificationsThe following standards and those listed in the annexure; contain provisions that, through reference in text, constitute requirements of this document, including reference documents referred to in these standards. The revision as at the date of Contract placement is applicable. The Contractor is responsible for obtaining the latest revision of these documents. Documents marked with an asterisk (*) are available from the Employer at no cost. 240-57648800 and NRS002 are issued with this enquiry.

OHASA is available from: LEXIS NEXIS BUTTERWORTHS, telephone: +27 11 784 8009.

* 240-57648800 Specification for Large Power Transformers up to 132

PART C4: SITE INFORMATION PAGE 9 C4 ECC3 SITE INFORMATION

EMPLOYER’S NAME CONTRACT NUMBER _____________PROJECT & CONTRACT TITLE

kV in the rating range of 1,25 MVA to 160 MVA* ESKASAAA3, Rev 1 (1998), Eskom Approvals of Personnel Performing Quality

Related Special Processes on All Eskom Plant

ISO 14001 (1996) Environmental Management Systems – Specification With Guidance for Use

ISO 9001 (2000) Quality Management Systems – Requirements

OHASA (1993) Occupational Health And Safety Act Of South Africa, Act 85 Of 1993

* SP SER 003, Rev 1 (1995) Safety Risk Management Directive for Contractors

*Q1 rev 0 Quality Schedule

12.2 Special requirements

12.2.1 Transportation requirements and limitationsThe transport limitations are reflected in the drawings and additional information provided in Annexure B.

12.2.2 TimeThe Contractor will inform the Employer four (6) weeks for local suppliers and eight (8) weeks for foreign suppliers, prior to HV test and factory visits.

The Contractor must inform the Employer of any deviations from the quoted Factory failure rates (FFR) or on time delivery rate (OTDR).

13 ANNEXURES:

Annexure ADocumentation, Configuration Management, and Drawings

PART C4: SITE INFORMATION PAGE 10 C4 ECC3 SITE INFORMATION

EMPLOYER’S NAME CONTRACT NUMBER _____________PROJECT & CONTRACT TITLE

PART C4: SITE INFORMATION PAGE 1 C4 ECC3 SITE INFORMATION