© the mcgraw-hill companies, inc., 2004 1 project management cpm and pert
TRANSCRIPT
![Page 1: © The McGraw-Hill Companies, Inc., 2004 1 Project Management CPM and PERT](https://reader036.vdocuments.mx/reader036/viewer/2022062305/5697bf871a28abf838c89007/html5/thumbnails/1.jpg)
©The McGraw-Hill Companies, Inc., 2004
1
Project ManagementCPM and PERT
![Page 2: © The McGraw-Hill Companies, Inc., 2004 1 Project Management CPM and PERT](https://reader036.vdocuments.mx/reader036/viewer/2022062305/5697bf871a28abf838c89007/html5/thumbnails/2.jpg)
©The McGraw-Hill Companies, Inc., 2004
2
Project is a series of related jobs usually directed toward some major output and requiring a significant period of time to perform
Project Management are the management activities of planning, directing, and controlling resources (people, equipment, material) to meet the technical, cost, and time constraints of a project
![Page 3: © The McGraw-Hill Companies, Inc., 2004 1 Project Management CPM and PERT](https://reader036.vdocuments.mx/reader036/viewer/2022062305/5697bf871a28abf838c89007/html5/thumbnails/3.jpg)
©The McGraw-Hill Companies, Inc., 2004
3
A project is made up of a sequence of activities that form a network representing a project
The path taking longest time through this
network of activities is called the “critical path”
The critical path provides a wide range of scheduling information useful in managing a project
Critical Path Method (CPM) helps to identify the critical path(s) in the project networks
![Page 4: © The McGraw-Hill Companies, Inc., 2004 1 Project Management CPM and PERT](https://reader036.vdocuments.mx/reader036/viewer/2022062305/5697bf871a28abf838c89007/html5/thumbnails/4.jpg)
©The McGraw-Hill Companies, Inc., 2004
4
A project must have:
well-defined jobs or tasks whose completion marks the end of the project;
independent jobs or tasks;
and tasks that follow a given sequence.
![Page 5: © The McGraw-Hill Companies, Inc., 2004 1 Project Management CPM and PERT](https://reader036.vdocuments.mx/reader036/viewer/2022062305/5697bf871a28abf838c89007/html5/thumbnails/5.jpg)
©The McGraw-Hill Companies, Inc., 2004
5
CPM with a Single Time Estimate› Used when activity times are known with
certainty› Used to determine timing estimates for the
project, each activity in the project, and slack time for activities
CPM with Three Activity Time Estimates› Used when activity times are uncertain › Used to obtain the same information as the Single
Time Estimate model and probability information
Time-Cost Models› Used when cost trade-off information is a major
consideration in planning› Used to determine the least cost in reducing total
project time
![Page 6: © The McGraw-Hill Companies, Inc., 2004 1 Project Management CPM and PERT](https://reader036.vdocuments.mx/reader036/viewer/2022062305/5697bf871a28abf838c89007/html5/thumbnails/6.jpg)
©The McGraw-Hill Companies, Inc., 2004
6
1. Activity Identification
2. Activity Sequencing and Network Construction
3. Determine the critical path
› From the critical path all of the project and activity timing information can be obtained
![Page 7: © The McGraw-Hill Companies, Inc., 2004 1 Project Management CPM and PERT](https://reader036.vdocuments.mx/reader036/viewer/2022062305/5697bf871a28abf838c89007/html5/thumbnails/7.jpg)
©The McGraw-Hill Companies, Inc., 2004
7
Consider the following consulting project:
Develop a critical path diagram and determine the duration of the critical path and slack times for all activities.
Activity Designation Immed. Pred. Time (Weeks)Assess customer's needs A None 2Write and submit proposal B A 1Obtain approval C B 1Develop service vision and goals D C 2Train employees E C 5Quality improvement pilot groups F D, E 5Write assessment report G F 1
![Page 8: © The McGraw-Hill Companies, Inc., 2004 1 Project Management CPM and PERT](https://reader036.vdocuments.mx/reader036/viewer/2022062305/5697bf871a28abf838c89007/html5/thumbnails/8.jpg)
©The McGraw-Hill Companies, Inc., 2004
8
A(2) B(1) C(1)
D(2)
E(5)
F(5) G(1)
A None 2
B A 1
C B 1
D C 2
E C 5
F D,E 5
G F 1
Act. Imed. Pred. Time
![Page 9: © The McGraw-Hill Companies, Inc., 2004 1 Project Management CPM and PERT](https://reader036.vdocuments.mx/reader036/viewer/2022062305/5697bf871a28abf838c89007/html5/thumbnails/9.jpg)
©The McGraw-Hill Companies, Inc., 2004
9
ES=9EF=14
ES=14EF=15
ES=0EF=2
ES=2EF=3 ES=3
EF=4
ES=4EF=9
ES=4EF=6
A(2) B(1) C(1)
D(2)
E(5)
F(5) G(1)
Hint: Start with ES=0 and go forward in the network from A to G.
Hint: Start with ES=0 and go forward in the network from A to G.
![Page 10: © The McGraw-Hill Companies, Inc., 2004 1 Project Management CPM and PERT](https://reader036.vdocuments.mx/reader036/viewer/2022062305/5697bf871a28abf838c89007/html5/thumbnails/10.jpg)
©The McGraw-Hill Companies, Inc., 2004
10
ES=9EF=14
ES=14EF=15
ES=0EF=2
ES=2EF=3
ES=3EF=4
ES=4EF=9
ES=4EF=6
A(2) B(1) C(1)
D(2)
E(5)
F(5) G(1)
LS=14LF=15
LS=9LF=14
LS=4LF=9
LS=7LF=9
LS=3LF=4
LS=2LF=3
LS=0LF=2
Hint: Start with LF=15 or the total time of the project and go backward in the network from G to A.
Hint: Start with LF=15 or the total time of the project and go backward in the network from G to A.
![Page 11: © The McGraw-Hill Companies, Inc., 2004 1 Project Management CPM and PERT](https://reader036.vdocuments.mx/reader036/viewer/2022062305/5697bf871a28abf838c89007/html5/thumbnails/11.jpg)
©The McGraw-Hill Companies, Inc., 2004
11
ES=9EF=14
ES=14EF=15
ES=0EF=2
ES=2EF=3
ES=3EF=4
ES=4EF=9
ES=4EF=6
A(2) B(1) C(1)
D(2)
E(5)
F(5) G(1)
LS=14LF=15
LS=9LF=14
LS=4LF=9
LS=7LF=9
LS=3LF=4
LS=2LF=3
LS=0LF=2
Duration = 15 weeks
Slack=(7-4)=(9-6)= 3 Wks
![Page 12: © The McGraw-Hill Companies, Inc., 2004 1 Project Management CPM and PERT](https://reader036.vdocuments.mx/reader036/viewer/2022062305/5697bf871a28abf838c89007/html5/thumbnails/12.jpg)
©The McGraw-Hill Companies, Inc., 2004
12
TaskImmediate
Predecesors Optimistic Most Likely PessimisticA None 3 6 15B None 2 4 14C A 6 12 30D A 2 5 8E C 5 11 17F D 3 6 15G B 3 9 27H E,F 1 4 7I G,H 4 19 28
![Page 13: © The McGraw-Hill Companies, Inc., 2004 1 Project Management CPM and PERT](https://reader036.vdocuments.mx/reader036/viewer/2022062305/5697bf871a28abf838c89007/html5/thumbnails/13.jpg)
©The McGraw-Hill Companies, Inc., 2004
13
ET(A)= 3+4(6)+15
6
ET(A)= 3+4(6)+15
6
ET(A)=42/6=7ET(A)=42/6=7Task
Immediate Predecesors
Expected Time
A None 7B None 5.333C A 14D A 5E C 11F D 7G B 11H E,F 4I G,H 18
TaskImmediate
Predecesors Optimistic Most Likely PessimisticA None 3 6 15B None 2 4 14C A 6 12 30D A 2 5 8E C 5 11 17F D 3 6 15G B 3 9 27H E,F 1 4 7I G,H 4 19 28
Expected Time = Opt. Time + 4(Most Likely Time) + Pess. Time
6Expected Time =
Opt. Time + 4(Most Likely Time) + Pess. Time
6
![Page 14: © The McGraw-Hill Companies, Inc., 2004 1 Project Management CPM and PERT](https://reader036.vdocuments.mx/reader036/viewer/2022062305/5697bf871a28abf838c89007/html5/thumbnails/14.jpg)
©The McGraw-Hill Companies, Inc., 2004
14
TaskImmediate
PredecesorsExpected
TimeA None 7B None 5.333C A 14D A 5E C 11F D 7G B 11H E,F 4I G,H 18
ET(B)=32/6=5.333ET(B)=32/6=5.333
ET(B)= 2+4(4)+14
6
ET(B)= 2+4(4)+14
6
TaskImmediate
Predecesors Optimistic Most Likely PessimisticA None 3 6 15B None 2 4 14C A 6 12 30D A 2 5 8E C 5 11 17F D 3 6 15G B 3 9 27H E,F 1 4 7I G,H 4 19 28
Expected Time = Opt. Time + 4(Most Likely Time) + Pess. Time
6Expected Time =
Opt. Time + 4(Most Likely Time) + Pess. Time
6
![Page 15: © The McGraw-Hill Companies, Inc., 2004 1 Project Management CPM and PERT](https://reader036.vdocuments.mx/reader036/viewer/2022062305/5697bf871a28abf838c89007/html5/thumbnails/15.jpg)
©The McGraw-Hill Companies, Inc., 2004
15
TaskImmediate
PredecesorsExpected
TimeA None 7B None 5.333C A 14D A 5E C 11F D 7G B 11H E,F 4I G,H 18
ET(C)= 6+4(12)+30
6
ET(C)= 6+4(12)+30
6
ET(C)=84/6=14ET(C)=84/6=14
TaskImmediate
Predecesors Optimistic Most Likely PessimisticA None 3 6 15B None 2 4 14C A 6 12 30D A 2 5 8E C 5 11 17F D 3 6 15G B 3 9 27H E,F 1 4 7I G,H 4 19 28
Expected Time = Opt. Time + 4(Most Likely Time) + Pess. Time
6Expected Time =
Opt. Time + 4(Most Likely Time) + Pess. Time
6
![Page 16: © The McGraw-Hill Companies, Inc., 2004 1 Project Management CPM and PERT](https://reader036.vdocuments.mx/reader036/viewer/2022062305/5697bf871a28abf838c89007/html5/thumbnails/16.jpg)
©The McGraw-Hill Companies, Inc., 2004
16
Step 2. Draw the Network DiagramAnd determine the Critical Path
A(7)
B(5.333)
C(14)
D(5)
E(11)
F(7)
H(4)
G(11)
I(18)
Duration = 54 Days
![Page 17: © The McGraw-Hill Companies, Inc., 2004 1 Project Management CPM and PERT](https://reader036.vdocuments.mx/reader036/viewer/2022062305/5697bf871a28abf838c89007/html5/thumbnails/17.jpg)
©The McGraw-Hill Companies, Inc., 2004
17
Step 3 : Probability Exercise
What is the probability of finishing this project in less than 53 days?
What is the probability of finishing this project in less than 53 days?
p(t < D)
TE = 54
Z = D - TE
cp2
Z = D - TE
cp2
tD=53
![Page 18: © The McGraw-Hill Companies, Inc., 2004 1 Project Management CPM and PERT](https://reader036.vdocuments.mx/reader036/viewer/2022062305/5697bf871a28abf838c89007/html5/thumbnails/18.jpg)
©The McGraw-Hill Companies, Inc., 2004
18
Activity variance, = (Pessim. - Optim.
6)2 2Activity variance, = (
Pessim. - Optim.
6)2 2
Task Optimistic Most Likely Pessimistic VarianceA 3 6 15 4B 2 4 14C 6 12 30 16D 2 5 8E 5 11 17 4F 3 6 15G 3 9 27H 1 4 7 1I 4 19 28 16
(Sum the variance along the critical path) 2 = 41 2 = 41
![Page 19: © The McGraw-Hill Companies, Inc., 2004 1 Project Management CPM and PERT](https://reader036.vdocuments.mx/reader036/viewer/2022062305/5697bf871a28abf838c89007/html5/thumbnails/19.jpg)
©The McGraw-Hill Companies, Inc., 2004
19
There is a 43.64% probability that this project will be completed in less than 53 weeks.
There is a 43.64% probability that this project will be completed in less than 53 weeks.
P(Z < -.16) = 0.5- 0.0636=0 .4364, or 43.64% (NORMSDIST(-.16)
P(Z < -.16) = 0.5- 0.0636=0 .4364, or 43.64% (NORMSDIST(-.16)
Z = D - T
=53- 54
41= -.156E
cp2
Z = D - T
=53- 54
41= -.156E
cp2
TE = 54
p(t < D)
t
D=53
Z ( - 0.16) = 0.0636
0.0636 = 6.36 %
![Page 20: © The McGraw-Hill Companies, Inc., 2004 1 Project Management CPM and PERT](https://reader036.vdocuments.mx/reader036/viewer/2022062305/5697bf871a28abf838c89007/html5/thumbnails/20.jpg)
©The McGraw-Hill Companies, Inc., 2004
20
What is the probability that the project duration will exceed 56 weeks?
What is the probability that the project duration will exceed 56 weeks?
![Page 21: © The McGraw-Hill Companies, Inc., 2004 1 Project Management CPM and PERT](https://reader036.vdocuments.mx/reader036/viewer/2022062305/5697bf871a28abf838c89007/html5/thumbnails/21.jpg)
©The McGraw-Hill Companies, Inc., 2004
21
tTE = 54
P(t < D)
D=56
Z = D - T
=56 - 54
41= .312E
cp2
Z = D - T
=56 - 54
41= .312E
cp2
P (Z > .31) = 1- 0.6217= 0.3783, or 37.83 %P (Z > .31) = 1- 0.6217= 0.3783, or 37.83 %
Z( 0.31) = 0.1217So, P( Z= 0.31) = 0.5 + 0.1217 = 0.6217
0.1217 = 12.17 %P= 50% = 0.5
![Page 22: © The McGraw-Hill Companies, Inc., 2004 1 Project Management CPM and PERT](https://reader036.vdocuments.mx/reader036/viewer/2022062305/5697bf871a28abf838c89007/html5/thumbnails/22.jpg)
©The McGraw-Hill Companies, Inc., 2004
22
Basic Assumption: Relationship between activity completion time and project cost
Time Cost Models: Determine the optimum point in time-cost tradeoffs› Activity direct costs› Project indirect costs› Activity completion times
![Page 23: © The McGraw-Hill Companies, Inc., 2004 1 Project Management CPM and PERT](https://reader036.vdocuments.mx/reader036/viewer/2022062305/5697bf871a28abf838c89007/html5/thumbnails/23.jpg)
©The McGraw-Hill Companies, Inc., 2004
23
Project activities can be identified as entities (There is a clear beginning and ending point for each activity.)
Project activity sequence relationships can be specified and networked.
Project control should focus on the critical
path
The activity times follow the beta distribution, with the variance of the project assumed to equal the sum of the variances along the critical path.
![Page 24: © The McGraw-Hill Companies, Inc., 2004 1 Project Management CPM and PERT](https://reader036.vdocuments.mx/reader036/viewer/2022062305/5697bf871a28abf838c89007/html5/thumbnails/24.jpg)
©The McGraw-Hill Companies, Inc., 2004
24