The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any such contract. No contractor is entitled to rely on the information herein for support of a claim or any other purpose. This is information of a general nature, intended only to provide a brief introduction to the topics referenced – it is by no means complete or comprehensive. Viewing this material is not a substitute for a contractor reviewing actual contract documents and consulting with its own legal counsel about the content of such contract documents. 1 Disclaimer

Upload: anthony-lyons

Post on 25-Dec-2015

215 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

1

The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any such contract.  No contractor is entitled to rely on the information herein for support of a claim or any other purpose.   This is information of a general nature, intended only to provide a brief introduction to the topics referenced – it is by no means complete or comprehensive. 

Viewing this material is not a substitute for a contractor reviewing actual contract documents and consulting with its own legal counsel about the content of such contract documents.

Disclaimer

Page 2: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

Specification Book Training Minnesota DOT

Division 1

2

Page 3: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

3

Introduction

Over the last 3 years, MnDOT has completely rewritten its standard specifications. Though almost every sentence in the book has been revised, some of the most significant revisions were made to Division I.

Page 4: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

4

Key Division 1 Revisions

Within Division I, the most significant revisions were made to the provisions governing changes, schedules, time extensions, claims, compensation, and the definitions associated with these provisions.

Page 5: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

5

Key Division 1 Revisions

The sections that were the focus of the Division 1 revisions were:

1103, 1205, 1402, 1403, 1517, 1806, 1807, 1808, 1809, 1903, 1904, and 1905.

Page 6: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

6

The Active Voice

In addition to significant revisions to content, Division 1 was also rewritten in the active voice.

Page 7: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

7

Today’s English Lesson

The “voice” of a sentence refers to the relationship of the verb to the other parts of the sentence.

Page 8: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

8

Today’s English Lesson

“Voice” comes in two basic “flavors”

ACTIVE VOICEPASSIVE VOICE

(Unless you count Yoda’s voice – “Three voices there are.”)

Page 9: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

9

Today’s English Lesson

In a passive sentence, the subject of the clause doesn’t perform the action of the verb. This is because a passive sentence either puts the action (the verb) first and the actor (the subject) second, or leaves the actor out altogether, making it hard for a reader to understand who is doing what to whom.

Page 10: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

10

Example of a Passive Sentence

“Extra Work shall be performed in accordance with these Specifications as they apply to the particular class of work involved, unless otherwise stipulated in the agreement authorizing the Extra Work.”

30 Words

Page 11: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

11

The English Lesson Continued

In a passive sentence, the actor is often omitted. As a consequence, it can be a way of dodging responsibility and greatly detracts from clarity, particularly in a specification.

(Consequently, it’s a staple of politicians.)

Page 12: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

12

The 5 “C’s” of Specifications Clear Concise Complete Correct Consistent

Page 13: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

13

What’s Wrong with the Passive Voice? It adds unnecessary words. (It’s not

concise.) It fails to say clearly who will do what. (It’s

not clear.)

Page 14: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

14

The Active Voice

A sentence written in the active voice is the solution to the problems of the passive voice.

Page 15: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

15

The Active Voice

In a sentence written in the active voice, the actor is clearly identified.

Page 16: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

16

Active Voice Example

“The Contractor shall perform Extra Work in accordance with the specifications unless otherwise specified in the Supplemental Agreement authorizing the Extra Work.”

22 Words

Page 17: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

17

Active v. Passive

Passive example – 30 wordsActive example – 22 words

Savings: 8 words or 27%

(If we could do this with a 1,000-page book, we could save 270 pages and, if we have to print 1,000 books, we could save a forest.)

Page 18: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

Module I Sections 1200 and 1400

18

Page 19: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

19

Caution This presentation cannot address every

revision made to the standard specifications.

This presentation is not part of the Contract and has no bearing on the interpretation of the Contract.

You must read the revised specification carefully and interpret the requirements independently.

Page 20: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

20

Scope of Rewrite

1201, “Prequalification of Bidders,” illustrates many of the standard features of the rewrite:

1. Use of the active voice.2. Use of lists.3. Standardized capitalization.4. Standardized and defined terminology –

“Proposal” versus “Bid.”5. Two shorter sentences versus one long

sentence.

Page 21: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

21

1203, Access to Proposal Package Original 1203: “Issuance of Proposal Forms”

Proposal forms will be issued to prospective bidders upon request and payment of the fee stated in the Advertisement for Bids.”

New 1203: “ACCESS TO PROPOSAL PACKAGE” The Department will provide Bidders with access to the Proposal Package through the online E-Plan Room. The Department may require a fee for Bidders to purchase and download copies of the Proposal Package.”

Page 22: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

22

1203 Note the use of the active voice, “The

Department will…” Note the incorporation of electronic bidding

requirements. Note the emphasis on consistent

terminology – “Proposal Package” versus “Proposal Form.”

Note elimination of redundancy – “prospective bidders” are now “Bidders.”

Page 23: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

23

By Convention

The Department WILL… The Contractor SHALL…

Page 24: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

24

1205, “Examination of Proposal Package and Site of Work”

The original title was “Examination of Plans, Specifications, Special Provisions, and…”

Why was this changed?

Page 25: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

25

Reasonable Site Investigation

The original specification required a site investigation. The new specification requires, “a reasonable investigation of the site of Work,” defined as an investigation of the: (1) Project Site; (2) Borrow sites; (3) Haul routes; (4) Utility property in accordance with 1507, “Utility Property and Service;” (5) All other locations related to the performance of the Work, and (6) Any additional information the Department makes available in accordance with 1205.2, “Additional Information.”

Page 26: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

26

1402 Original Title: “Alteration of the Work and

Changed Condition” New Title: “Contract Revisions”

Page 27: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

27

Goals Gather as many provisions as possible that

define a revision to the Contract to one location.

Provide a “nest” for the clauses mandated by the FHWA.

Provide a comprehensive “notice provision.” Provide a clear process for revising the

Contract.

Page 28: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

28

1402

1402.1 General1402.2 Differing Site Conditions (Formerly

1402.A.)1402.3 Significant Changes in the Character

of the work (Formerly 1402.C.)1402.4 Suspensions of Work Ordered by the

Engineer (Formerly 1402.B.)1402.5 Extra Work (Formerly 1403)1402.6 Eliminated Items (Formerly 1905)

Page 29: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

29

1402.1 General Specifies MnDOT’s right to make a revision. Obligates the Contractor to perform the

work as revised. Requires the Contractor to provide notice

for each type of revision IAW 1403. Specifies the consequences of failing to

provide notice. Defines the term “adjustment.”

Page 30: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

30

“Adjustment”

The original specifications did not really define the term “adjustment” as used in the FHWA-mandated clauses (DSC, Significant Changes, or Suspensions). The new specification defines an adjustment as compensation IAW 1904, “Compensation for Contract Revisions,” and a time extension IAW 1806, “Determination and Extension of Contract Time.”

Page 31: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

31

1403, “Notification of Contract Revisions”

The following notification requirements apply to all potential Contract revisions including those defined in 1402, “Contract Revisions.” The Engineer will consider requests for Contract revisions only if the notification procedures in this section are followed. The specified time limits may only be extended through a written, jointly-signed agreement between the Contractor and the Engineer. The Engineer will address the underlying issue prompting the notification in a timely and satisfactory manner.

Page 32: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

32

1403.2, “First Notice, By Contractor”

The Contractor shall notify the Engineer verbally as soon as a Contract revision appears necessary. The Contractor shall not start or continue with an activity or Contract Item for which a Contract revision may be necessary without authorization from the Engineer.

Page 33: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

33

1403.3, “Written Notice, By Contractor”

If the Contractor disagrees with the Engineer’s response or the Engineer does not respond to the first notice, the Contractor shall provide a written notice. Provide this written notice within 5 business days of first notice if Engineer has not responded or within 5 business days of receiving the Engineer’s response to the first notice. The written notice shall include the following:

Page 34: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

34

BUSINESS DAY. Every day on the calendar, except Saturday, Sunday, and Holidays.

1103 “Definitions”

Page 35: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

35

1403.4, “Written Acknowledgement, By Engineer”

The Engineer will provide a written acknowledgment of receipt of the Contractor’s written notice.

Page 36: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

36

1403.5, “Written Response, By Engineer”

Within 10 business days of receiving the Contractor’s written notice, the Engineer will provide a written response that includes one of the following: (1) Confirmation of the need for a contract revision…(2) Denial of the request for a contract revision… (3) A request for additional information…

Page 37: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

37

1403.6, “Contractor’s Recourse”

If the Contractor disagrees with the Engineer’s final written response or the Engineer’s response is untimely, the Contractor may pursue a claim in accordance with 1517, “Claims for Compensation Adjustment.” The Contractor shall give the Engineer written notice of the intent to pursue a claim within 5 business days of receiving the Engineer’s final written response.

Page 38: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

Module 21800

38

Page 39: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

39

1803, Progress Schedules This specification was completely rewritten. It now incorporates a bar chart schedule

requirement OR A CPM schedule requirement. The CPM schedule requirement is designed

to accommodate the implementation of Oracle/Primavera’s P6 software.

Page 40: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

40

A. General RequirementsThe Contractor shall prepare the Progress Schedule as specified in 1803.2, “Bar Chart Schedules,” or 1803.3, “CPM Schedule.”

1803.1 “All Schedules”

Page 41: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

41

…acceptance of any schedule does not modify the Contract or constitute endorsement or validation … of the Contractor's means, methods, logic, activity durations, or assumptions…

… acceptance of a schedule is not an “approval.” Review…of a portion of a schedule or an incomplete schedule

submittal will not indicate acceptance of the entire schedule. The responsibility for the validity and accuracy of all accepted

schedules is solely the Contractor’s. …acceptance of schedules will not relieve the Contractor of its

obligation or responsibility to submit complete and accurate information.

Failure to include any element of required Work in the Progress Schedule shall not relieve the Contractor from completing all Work…

By accepting the schedule, the Department does not guaranty that the project can be performed or completed as scheduled…[or] waive any Contract requirements.

1803.1.A.1 “Acceptance”

Page 42: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

42

Contract time between the planned completion and the date specified in the Contract is Float. Should the Contractor intend to, or complete the work, or any portion thereof, earlier than the Contract Dates, it is understood that the Project benefits from the increased shared Float. The Contractor agrees that delays shall only be based on impacts to the Contract Dates, not the planned dates. Time extensions shall only be based on delays to the Contract Milestone dates or a revised Contract Milestone date executed by a Change Order/Supplemental Agreement. The Contractor is not entitled to a time extension until an Excusable Delay as defined in 1806, “Determination and Extension of Contact Time,” is incurred.

1803.1.A.2 “Early Completion"

Page 43: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

43

For example, if the Contract Time expires on May 15 and the Contractor submits a schedule that is accepted by the Department that shows early completion of the Project on May 1, the schedule is required to show this difference as float. This float is available to all parties to the Contract on an as-needed basis until it is consumed.

1803.1.A.2 “Early Completion” Example

Page 44: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

44

The Contractor's refusal, failure, or neglect to pursue timely acceptance of any schedule shall constitute reasonable evidence that the Contractor is not prosecuting the Work with the diligence that will ensure its completion within the applicable Contract Time… The Engineer will determine which of the following option(s) will best facilitate compliance:

1803.1.A.3 “Non-Compliance”

Page 45: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

45

(1) 100 Percent Withholding: The Engineer may withhold an amount up to 100 percent of the estimated value of work performed.

(2) Monetary Deduction: The Engineer may assess a non-recoverable Monetary Deduction of up to $1,000/day…

1803.1.A.3 “Non-Compliance”

Page 46: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

46

The Contractor shall plan and manage the Project, and report progress using the Bar Chart Method for the Contractor’s Progress Schedules.

The Contractor shall not start any permanent work before Baseline Schedule Acceptance.

1803.2 “Bar Chart Schedules”

Page 47: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

47

Whether bar charts or CPM schedules are required, there are six schedule “types” specified:

1. Preliminary2. Baseline3. Update4. Look-Ahead5. Revised6. Impact

“Types” of Schedules

Page 48: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

48

The Department will consider all schedules submitted before Baseline Acceptance to be Preliminary Schedules until the Preliminary Schedule is accepted as the Baseline in accordance with 1803.3.B.2, “Baseline Schedule”…

1803.2.B.1 “Preliminary Schedule”

Page 49: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

49

…the Contractor shall continue to improve upon the Preliminary Schedules and show the status of Work actually completed, by incorporating actual start and finish dates and by reasonably estimating the remaining duration for each incomplete activity.

1803.2.B.1 “Preliminary Schedule”

Page 50: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

50

The Baseline shall indicate:

(1) Actual Dates of Work performed if the Contractor chooses to perform any Work before the Department’s Acceptance of the Baseline Schedule.

(2) All Contract Time dates, Milestones, and staging restrictions are understood and scheduled to complete within the Contract Time.

(3) Each Activity…(4) The Critical Path. (5) The following minimum level of detail…

1803.2.B.2 “Baseline Schedule”

Page 51: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

51

The Contractor shall update the last accepted Schedule by incorporating actual start and finish dates and by reasonably estimating the remaining duration for each incomplete activity.

1803.2.B.3 “Update Schedule”

Page 52: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

52

The Contractor shall minimize the number of changes. The Contractor shall describe the reason for changes to the schedule in the Narrative Report submitted with the Update Schedule.

The Department will not allow changes to an Update Schedule that disrupts the continuity or comparative relationship between the last accepted schedule and the Update Schedule, such as, renaming of activities or changing activity descriptions.

1803.2.B.3 “Update Schedule”

Page 53: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

53

The Contractor shall submit a Revised Schedule upon one of the following:

(1) The Contractor desires to substantially deviate from the current Progress Schedule…

(2) Department’s Request. (3) The issuance of a Contract Revision

document that changes the planned sequence of Work or the method and manner of its performance.

1803.2.B.5 “Revised Schedule”

Page 54: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

54

(2) Department’s Request. (2.1) Where the Department requires the

Contractor to demonstrate how to recover any Milestone date(s) beyond any Contract Dates.

(2.2) The Department deems a substantial difference between actual sequence, or actual duration, of Work, than is depicted in the Progress Schedule.

1803.2.B.5 “Revised Schedule”

Page 55: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

55

The requirement to prepare a Revised Schedule is not a directive by the Department to accelerate the Work but rather a directive for the Contractor to seek the Department’s Acceptance of a proposal to revise the accepted Progress Schedule.

1803.2.B.5 “Revised Schedule”

Page 56: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

56

The Contractor shall prepare an Impact Schedule:

(1) To quantify the effects of any contemporaneous or prospective impacts to the Progress Schedule;

(2) To establish the need for a time extension to a Milestone; or

(3) At the Department’s request…

1803.2.B.6 “Impact Schedule”

Page 57: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

57

C.1 Narrative Reports C.2 Gantt Charts C.3 Electronic Files (Blank for bar chart

schedules)

1803.2.C “Schedule Submission Requirements”

Page 58: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

58

Table 1803-1

Schedule Type Section Data Date Submission Due Date

Department Review Length

Resubmission Due Date

Baseline 1803.2.B.2 Letting Date 10 Business days prior to any permanent Work

7 Business Days after submitted

3 Business Days

Update 1803.2.B.3 15th of Every Month

4 Business Days after Data Date

7 Business Days after submitted

3 Business Days

Revised 1803.2.B.5 As needed or directed by the Department.

4 Business Days after Data Date

7 Business Days after submitted

7 Calendar Days

Impact 1803.2.B.6 No earlier than last accepted schedule’s data date

7 Business Days after Data Date

7 Business Days after submitted

As directed by Department

Schedule Submission Timeline

Page 59: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

59

The Contractor shall allow for normal weather delays when developing the Progress Schedule. The Department will extend the Contract Time for delays in excess of the normally anticipated work days lost to inclement weather between April 16 and November 14, inclusive, as specified in Table 1803-2.

1803.2.D “Weather…Contingency”

Page 60: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

60

For example, if Contract Time starts April 16, then the Contractor must lose more than two days to weather during the rest of April in order to be eligible for a time extension for weather in April.

1803.2.D “Weather…Contingency”

Page 61: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

61

Table 1803-2 Anticipated Work Days Lost Due to Weather Per Time Period

Time Period Anticipated Work Days Lost

January 20 *

February 15 *

March 9 *

April 1-15 3 *

April 16-30 2

May 4

June 5

July 4

August 3

September 3

October 3

November 1-14 2

November 15-30 5*

December 17*

Table 1803-2, “Anticipated Work Days Lost to Weather…”

Page 62: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

62

If the Contractor intends to use Critical Path Method (CPM) schedules, or when the Department specifies the Work under this Contract shall be scheduled using CPM, the Work shall be planned, accomplished, and reported using CPM for the Contractor’s Progress Schedules.

CPM Schedules1803.3.A “General Requirements”

Page 63: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

63

The Department uses “Primavera Project Manager (P6).” If the Contractor uses software other than (P6), the Contractor is responsible for any conversion discrepancies.

1803.3.A.1 “Software”

Page 64: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

64

The Contractor shall not suppress or sequester float.

The Contractor shall obtain the Engineer’s approval before using lags or leads…

The Contractor shall not be entitled to compensation or a time extension for delays that could have been avoided by revising activity durations or logic used to sequester float.

1803.3.A.4 “Float Suppression…”

Page 65: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

65

Examples of prohibited float suppression or sequestration include, but are not limited to:

(1) Logic relationships that provide no tangible or sequential value between unrelated activities.

(2) Logic relationships that demand completion of an activity that could otherwise continue beyond a Successor’s start or finish dates.

(3) Excessively long durations.

Examples of Float Suppression

Page 66: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

66

The Contractor acknowledges that all float (including Total Float, Free Float, and Sequestered Float) is a shared commodity available to the Project and is not for the exclusive benefit of any party…

…float is an expiring resource available to accommodate changes in the Work, however originated, or to mitigate the effect of events that may delay performance or completion…

…identified contingencies, as described in 1803.3.D…become available Float as time elapses and the contingency is not used.

1803.3.A.5 “Use of Float”

Page 67: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

67

FLOAT/TOTAL FLOAT. The number of days by which an activity may be delayed without delaying the Project or a Milestone.

FREE FLOAT. The number of days by which an activity may be delayed from its early dates without delaying the early start date of a successor activity. Free Float is a unique attribute of an activity.

1103 “Definitions”

Page 68: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

68

Acceptance of the first Preliminary Schedule is a condition of Contract Approval… A delay in submitting the Preliminary Schedule is a non-excusable delay under 1806.3.A, “Non-Excusable Delays,” and the Contractor is not entitled to an extension of the Contract Time.

1803.3.B.1 “Preliminary Schedules”

Page 69: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

69

All schedules submitted before the Department accepts the Baseline Schedule will be considered Preliminary Schedules until the Preliminary Schedule is accepted as the Baseline Schedule…

…the Contractor shall continue to improve upon the Preliminary Schedules and show the status of Work actually completed…

1803.3.B.1 “Preliminary Schedule”

Page 70: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

70

The Baseline Schedule shall include the entire scope of work and how the Contractor plans to complete all work contracted. The Engineer may review the resource allocations using historical data, Means Productivity Standards, or equivalents to determine if the Schedule is practicable.

1803.3.B.2 “Baseline Schedule”

Page 71: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

71

Table 1803-4 CPM Submission Timelines Schedule Type Section Data Date Submission Due

Date Department Review Length

Resubmission Due Date

First Preliminary 1803.3.B.1 Project Letting Date Condition of Contract Approval

7 Calendar Days after Submitted

Condition of Contract Approval

Subsequent Preliminary

1803.3.B.1 No later than the 15th of the month following the last accepted Preliminary Schedule.

4 Business Days after Data Date

7 Calendar Days after Submitted

7 Calendar Days

Baseline* 1803.3.B.2 *See Note *See Note *See Note *See Note

Update 1803.3.B.3 15th of Every Month

4 Business Days after Data Date

7 Business Days after submitted

3 Business Days

Revised 1803.3.B.4 As needed or directed by the Department.

4 Business Days after Data Date

7 Business Days after submitted

7 Calendar Days

Impact 1803.3.B.5 No earlier than last accepted schedule’s data date

7 Business Days after Data Date

7 Business Days after submitted

As directed by Department

*The Preliminary Schedule becomes the Baseline after Baseline criteria is met.

1803.3.C.4 “Submission Timeline”

Page 72: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

72

The duration of each activity shall include the necessary working days to actually complete the work defined by the activity; contingency shall not be built into the durations but shall be accounted for in accordance within the project calendars.

Each activity shall be assigned an appropriate calendar. The Project calendars shall indicate planned working and nonworking days. Each calendar, with the exception of the calendar used for tracking calendar days, shall include contingent nonworking days. Contingent nonworking days must be placed on Monday-Friday only. The Contractor shall include a minimum of 15 percent weather contingency for each major item of Work affected by weather. It is the responsibility of the Contractor to estimate the amount of weather and duration contingency required above the stated minimum. The Engineer reserves the right to accept or reject the estimated amount of contingency in accordance with “Acceptance of Schedule” section contained herein.

1803.3.D “Weather…Contingency”

Page 73: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

73

The Schedule shall use a minimum of the following calendars: (1) Calendar to indicate calendar days (cure time, etc), (2) Calendar for work that can progress year round, and (3) Calendar for each major item of Work affected by weather or seasonal limitations.

1803.3.D “Weather…Contingency”

Page 74: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

74

Contingency will be the numbers of indicated nonworking days compared to a description of the duration (in hours) of the normal working day, as indicated in the narrative, of the work week, e.g., M-F (10 hrs) and Sat (6 hrs) for every calendar.

1803.3.D “Weather…Contingency”

Page 75: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

75

The Proposal Package will specify the Contract Time. The Contractor shall prosecute the Work continuously and effectively, with the least possible delay, to the end that all Work is completed within the Contract Time.

If the Department issues a Notice to Proceed, the Contract Start Date established in the Notice to Proceed takes precedence over the Contract Start Date specified in the Proposal Package.

1806.1 “General”

Page 76: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

76

The Department will not consider a plea by the Contractor that the Contract Time was not sufficient as a valid reason for an extension of the Contract Time.

If the Department grants an extension of the Contract Time, the extended time for completion will be in full force and effect as though it was originally specified.

1806.1 “General”

Page 77: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

77

The Department will only extend the Contract Time if an excusable delay, as specified in 1806.2.A, “Excusable, Non-Compensable Delays,” or 1806.2.B, “Excusable, Compensable Delays,” delays Work on the Critical Path as described in items 1, 2, 3, and 4, below.

1806.1 “General”

Page 78: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

78

Mitigation of delay, whether caused by the Department, Contractor, a third-party, or an event, is a shared contract and legal requirement. Mitigation efforts include, but are not limited to, re-sequencing work activities, acceleration, and continuation of work through an otherwise planned shutdown period. The Contractor and Engineer will explore and discuss potential mitigation efforts promptly and agree upon costs or cost-sharing responsibilities prior to the implementation of mitigation efforts.

1806.1 “General”

Page 79: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

79

The Department will not evaluate a request for extension of the Contract Time unless the Contractor notifies the Engineer as specified in 1403, “Notice for Contract Revisions,” and provides the required analysis as follows.

1806.1 “General”

Page 80: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

80

(1) The Contractor shall base all evaluations of delay and all calculations of the appropriate time extensions due on the schedules submitted to and accepted by the Department. The Contractor shall not use schedules that did not exist on the project or create schedules after the delay has occurred to demonstrate entitlement to a time extension.

1806.1 “General”

Page 81: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

81

(2) The Contractor shall base evaluations and calculations related to the determination of extensions of time on the Critical Path as established by the schedules submitted to and accepted by the Department. The Contractor is not entitled to a time extension for delays that do not delay the Critical Path.

1806.1 “General”

Page 82: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

82

(3) The evaluations and calculations required to establish entitlement to a time extension will vary depending on the nature and timing of the delay and whether the Contract Time is measured in working days, calendar days, or based on a fixed completion date. It will also vary depending on whether the Contract requires a bar chart or CPM schedule.

1806.1 “General”

Page 83: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

83

(4) The schedules relevant to the evaluation and calculation of time extensions are the most current schedules submitted to and accepted by the Department. For example, if the Department determines that Extra Work is required and the Supplemental Agreement adding this work will be dated June 2, then the determination of the time extension due the Contractor will be based on the last schedule submitted and accepted by the Department prior to June 2 of the same year.

1806.1 “General”

Page 84: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

84

(5) The Contractor’s evaluations and calculations shall comply with the following Recommended Practices published by the Association for the Advancement of Cost Engineering, International:

(5.1) Recommended Practice No. 52R-06, Time Impact Analysis As Applied in Construction. The Contractor shall use this Recommended Practice for delays that are in the future (prospective). The Contractor shall not use this recommended practice to evaluate delays that have already occurred (retrospective).

(5.2) Recommended Practice No. 29R-03, Forensic Schedule Analysis, MIP 3.4 Observational/ Dynamic/Contemporaneous Split approach. The Contractor shall use MIP 3.4 when evaluating delays that have already occurred.

1806.1 “General”

Page 85: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

85

The example that follows illustrates the use of Recommended Practice No. 52R-06, Time Impact Analysis.

Example of Prospective Analysis

Page 86: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

The Project

86

Page 87: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

Baseline Schedule

Original Project Completion: July 13, 2010

Original Project Completion: July 13, 2010 87

Page 88: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

The Change

On February 1, the owner informed the contractor that to accommodate the spawning season this year, the project’s environmental permit had been modified. The second cofferdam, located in a flowing portion of the river, could not be installed until March.

88

Page 89: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

Update for Change

FIRST, Update the Schedule to the date of the change: February 1, 2010

FIRST, Update the Schedule to the date of the change: February 1, 2010

89

Page 90: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

Update for Change

SECOND, Identify the Current Project Completion Date: July 19, 2010

SECOND, Identify the Current Project Completion Date: July 19, 2010 90

Page 91: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

Adjust for Change

THIRD, Adjust the schedule for the change,Adding in an activity for the restricted period, which could also have used a constraint or calendar.

THIRD, Adjust the schedule for the change,Adding in an activity for the restricted period, which could also have used a constraint or calendar.

91

Page 92: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

Adjust for Change

THIRD, Adjust the schedule for the change,Adding in an activity for the restricted period, which could also have used a constraint or calendar.

THIRD, Adjust the schedule for the change,Adding in an activity for the restricted period, which could also have used a constraint or calendar.

92

Page 93: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

Adjust for Change

FOURTH, Identify the Current Project Completion Date: July 22, 2010

FOURTH, Identify the Current Project Completion Date: July 22, 2010

Note that the critical path has changed

Note that the critical path has changed

Don’t forget to run the schedule

Don’t forget to run the schedule

93

Page 94: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

Adjust for Change

94

FOURTH, Identify the Current Project Completion Date: July 22, 2010

FOURTH, Identify the Current Project Completion Date: July 22, 2010

Page 95: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

1. What was the completion date?◦ Before the change: July 19◦ After the change: July 22

2. The change order issued for the permit revision should include a 3-day time extension.

3. Alternately, the work could be accelerated to mitigate the delay and achieve timely completion.

Analyzing Delays: Beforehand

95

Page 96: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

96

(5.2) The Contractor shall use a Contemporaneous Analysis when evaluating delays that have already occurred.

1806.1 “General”

Page 97: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

97

The following example illustrates the use of Recommended Practice No. 29R-03, Forensic Schedule Analysis, MIP 3.4 Observational/ Dynamic/Contemporaneous Split approach.

Retrospective Analysis Example

Page 98: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

9898

Page 99: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

99

Page 100: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

100

1/6 1/19As-Planned

January

7 14 21 28

As-Planned Schedule

Page 101: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

101

Page 102: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

102

1/6 1/19As-Planned

1/6A 1/22AUpdate No. 1

January

7 14 21 28

As-Planned Schedule

Schedule Update, 2FEB98

Page 103: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

103

1/6 1/19As-Planned

1/6A 1/22AUpdate No. 1

January

7 14 21 28

As-Planned Schedule

Schedule Update, 2FEB98

3-day DELAY

Page 104: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

104

1806.1 “General”

The Engineer will review the Contractor’s evaluations and calculations and determine the time extension due, if any. The Engineer will measure extensions to the Contract Time in working days for Working Day Contracts and in calendar days for Completion Date and Calendar Day Contracts.

Page 105: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

105

1806.2.A “Excusable, Non-Compensable Delays”

Excusable, non-compensable delays are delays that are not the Contractor’s or the Department’s fault or responsibility, and that could not have been foreseen by the Contractor. The Department will not compensate the Contractor for excusable, non-compensable delays.

Page 106: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

106

1806.2.A “Excusable, Non-Compensable Delays”(1) Delays due to fires, floods…or other

cataclysmic phenomena of nature. (2) Delays due to weather… (3) Extraordinary delays in material deliveries… (4) Delays due to civil disturbances. (5) Delays due to acts of the public enemy. (6) Delays due to labor strikes... (7) Delays due to acts of the government… (8) All other delays not the Contractor’s or

Department’s fault or responsibility and which could not have been foreseen by the Contractor.

Page 107: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

107

1806.2.B “Excusable, Compensable Delays”

Excusable, compensable delays are delays that are not the Contractor’s fault or responsibility, and are the Department’s fault or responsibility, or are determined by judicial proceeding to be the Department’s sole responsibility.

Page 108: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

108

1806.2.A “Excusable, Compensable Delays”1) Delays due to revised Work as specified in

1402.2, “Differing Site Conditions,” 1402.3, “Significant Changes to the Character of the Work,” and 1402.5, “Extra Work.”

(2) Delays due to utility or railroad interference…

(3) Delays due to an Engineer-ordered suspension…

(4) Delays due to the neglect of the Department or its failure to act in a timely manner.

Page 109: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

109

1806.2.C “Non-Excusable Delays”

Non-excusable delays are delays that are the Contractor’s fault or responsibility. All non-excusable delays are non-compensable

Page 110: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

110

1806.2.C “Non-Excusable Delays”(1) Delays due to the Contractor’s…insolvency or

mismanagement. (2) Delays due to slow delivery of materials from

the supplier or fabricator… (3) Delays due to the Contractor's failure to…

maintain satisfactory progress… (4) Delays caused by plant and equipment failure…

due to the Contractor's failure to provide and maintain the equipment…

(5) Delays caused by conditions on the project, including traffic conditions that could be foreseen or anticipated before the date of bid opening…

Page 111: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

111

1806.2.D “Concurrent Delays”

Concurrent delays are separate delays to Critical Activities occurring at the same time. When a non-excusable delay is concurrent with an excusable delay, the Contractor is not entitled to an extension of Contract Time for the period the non-excusable delay is concurrent with the excusable delay. When a non-compensable delay is concurrent with a compensable delay, the Contractor is entitled to an extension of Contract Time, but not entitled to compensation for the period the non-compensable delay is concurrent with the compensable delay.

Page 112: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

112

Will charge:(1) One whole day for each day of work that the Contractor

makes progress or could have made progress during a working day on one or more Critical Activities for at least 6 continuous hours.

(2) One whole day when the Engineer orders a work suspension for reasons of Contractor’s fault or negligence.

(3) One whole day for Non-Excusable Delays as specified in 1806.2.C, “Non-Excusable Delays.”

(4) One half (1/2) day for each day of work that the Contractor makes progress or could have made progress during a working day on one or more Critical Activities for at least 2 continuous hours.

1806.3 “Determination of Time … on Working Day Contracts”

Page 113: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

113

Will not charge:(1) When the Contractor could not effectively

prosecute Critical Activities for at least 2 continuous hours during a working day due to: (1.1) Excusable, Non-Compensable Delays… (1.2) Excusable, Compensable Delays… (1.3) Concurrent Delays as specified in 1806.2.D…

(2) On Saturdays, Sundays, and legal holidays. (3) During the inclusive period from November 15

through April 15… (4) During Suspensions of Work Ordered by the

Engineer as specified in 1402.4…

1806.3 “Determination of Time … on Working Day Contracts”

Page 114: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

114

The number of working days to be added or subtracted will be determined as specified in 1806.1, “Determination and Extension of Contract Time, General”:

(1) For Differing Site Conditions… (2) For Significant Changes in the Character

of the Work...(3) For Extra Work…

1806.3 “Determination of Time … on Working Day Contracts”

Page 115: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

115

The Engineer will furnish the Contractor a weekly statement showing the working days charged to the project… The statement will include an accounting of all delays affecting the Critical Path. The Engineer will classify each of these delays as excusable non-compensable… excusable compensable, or non-excusable…or weather-related…

1806.3 “Determination of Time … on Working Day Contracts”

Page 116: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

116

The Department will not consider weekends, holidays, or any days between November 15 and April 15, inclusive, as eligible for extensions of Contract Time due to weather unless the Engineer directs the Contractor to work those days, or the Contractor’s accepted progress schedule in place at the time the delay occurred indicated that the Contractor intended to perform Critical Path Work on those days.

1806.4 “Extension…Due to Weather on CD Contracts”

Page 117: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

Module 31900

117

Page 118: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

118

Contract Estimates Actual Cost Total Cost Modified Total Cost

Methods of Pricing Revisions

Page 119: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

119

1902 – Payments provided by the contract compensate the contractor for all costs incurred by the contractor.

1903 – When the actual quantities vary from the estimated quantities, the unit price is used to adjust the amount paid to the contractor.

1904 – Everything else that is to be paid to the contractor is paid in accordance with 1904, “Compensation for Contract Revisions.”

Payments Provided by the Contract

Page 120: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

120

If the Department revises the Contract as provided in 1402, “Contract Revisions,” the Department will compensate the Contractor for the Contract revision following the sequence specified in 1904.2 through 1904.4. Such compensation for the Contract revision constitutes final and full compensation for performing the revised Work, delay costs, and all other costs not expressly precluded by 1904.5, “Non-Allowable Charges.”

1904 . 1 “General”

Page 121: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

121

If the Contract revision includes a time extension for compensable delays as provided by 1806, “Determination and Extension of Contract Time,” the Department will compensate the Contractor for the costs associated with the time extension in accordance with 1904.6, “Compensation for Delay.”

1904.1 “General”

Page 122: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

122

Use 1904.2, if possible, which provides for payment of the revisions at the Contract unit prices.

But if you can’t… Use 1904.3, whereby the Engineer and the

Contractor will try to negotiate a price.But if they can’t…

Use 1904.4, “Force Account”

How to Pay for a Revision

Page 123: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

123

Before proceeding to another pricing method, the Engineer will attempt to price and pay for the Contract revision using Contract Unit Prices.

1904.2 “Contract Unit Prices”

Page 124: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

124

If the Engineer and Contractor are unable to agree on compensation in accordance with 1904.2, “Contract Unit Prices,” they will attempt to negotiate unit or lump sum prices using one or more of the following methods:

1904.3 “Negotiated Prices”

Page 125: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

125

(1) Original Contract Unit Prices…adjusted for increased or decreased Material costs;

(2) State-wide average unit prices…as listed in the Department’s…“Summary of Contracts Awarded”;

(3) The average of unit prices awarded on three different projects of similar work and quantity;

(4) Unit prices computed by the Office of Estimating; or

(5) Cost analysis of labor, material, equipment, and mark ups as allowed in 1904.4, “Force Account.”

Methods for Negotiating a Price

Page 126: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

126

The Department will not compensate by a negotiated price for Contract Revision work performed by a subcontractor that includes a Contractor mark-up that exceeds that provided for in 1904.4.H, “Contractor Mark-Up.”

1904.3 “Negotiated Prices”

Page 127: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

127

Within 5 business days of the Department’s request, the Contractor shall submit proposed pricing and cost justification for the Contract revision. The Department will respond within 5 business days after receipt of the Contractor’s submittal. The Department and the Contractor can mutually agree to extend these 5-business-day time limits.

1904.3 “Negotiated Prices”

Page 128: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

128

If the Engineer and Contractor are unable to negotiate a price for the Contract revision in accordance with 1904.3, “Negotiated Prices,” the Engineer may direct the Contractor to perform all or part of the revised Work on a force account basis. When the Engineer directs the Contractor to perform revised Work on a force account basis, the Department will pay the Contractor as specified in 1904.4.A through 1904.4.J.

1904.4 “Force Account”

Page 129: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

129

A. LaborB. MaterialsC. EquipmentD. Miscellaneous CompensationG. Specialty Contract WorkH. Contractor Mark Up

Force Account Components

Page 130: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

130

Actual hourly rate of wage paidX

Number of hours worked

+ 62% for overhead, profit, additional bond,

property damage and liability insurance, workers’ compensation insurance, unemployment insurance, employer’s Social Security taxes, and indirect labor costs

1904.4.A “Labor”

Page 131: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

131

Actual cost of materials

+ 15% for field and home office overhead

costs and profit

1904.4.B “Material”

Page 132: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

132

Hourly rental rate specified by the Commissioner’s Equipment Rental Schedule

X Actual time equipment is in operation There is no mark up on equipment costs

1904.4.C “Equipment”

Page 133: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

133

If the Engineer directs the Contractor to perform the revised Work on the right of way of a railroad, in addition to the compensation for labor, Materials, and Equipment, the Department will pay the Contractor for actual costs related to satisfying the requirements of 1708, “Railroad-Highway Provisions.”

The Department will pay the Contractor for the actual cost plus five percent ++of miscellaneous fees incurred in performing the revised Work, including but not limited to dump fees, permits, and licenses.

1904.4.D “Miscellaneous Compensation”

Page 134: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

134

If the Contractor uses specialty contracting firms to perform the revised Work, the Department will pay the Contractor by reasonable invoice at the discretion of the Engineer.

1904.4.G “Specialty Contract Work”

Page 135: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

135

For any force account work performed by a subcontractor (including work performed by a specialty contractor), the Department will pay the Contractor one additional mark-up on revised Work performed by a subcontractor to cover administration, general superintendence, overhead, profit, and expenses not otherwise recoverable. The additional mark-up will be a percentage of the total force account invoice for the subcontractor’s portion of the revised Work equal to 10 percent of the first $50,000.00 plus 2 percent of the balance in excess of $50,000.00.

1904.4.H. “Contractor Mark Up”

Page 136: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

136

The Engineer may order the Contractor to accelerate the Work to avoid delay costs or to complete the Project early. The Department will pay for accelerations in accordance with this section (1904).

1904.4.I “Acceleration”

Page 137: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

137

The Department will compensate the Contractor for inefficiency or loss of productivity resulting from 1402, “Contract Revisions.” Use the Measured Mile analysis, or other reliable methods, comparing the productivity of work impacted by a change to the productivity of similar work performed under unimpacted (unchanged) conditions to quantify the inefficiency. The Department will pay for inefficiencies in accordance with this section (1904).

1904.4.J “Inefficiency”

Page 138: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

138

A "measured mile" analysis compares the productivity of a period that has been impacted by a revision to the productivity of similar work under normal, unimpacted conditions. The theory is that the difference between a contractor's actual inefficient productivity and an identified normal productivity is a measure of the inefficiency associated with the revision.

Measured Mile

Page 139: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

139

The Department will not pay the Contractor for the following, regardless of the method of payment for the revised Work:

(1) Loss of anticipated profits; (2) Consequential damages, including loss

of bonding capacity, loss of bidding opportunities, and insolvency;

(3) Indirect costs; (4) Attorneys fees, claims preparation

expenses, or costs of litigation.

1904.5 “Non-Allowable Costs”

Page 140: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

140

Per 1402.4, “Suspensions of Work Ordered by the Engineer,” the Department will not pay the Contractor for profit on suspensions or delays ordered by the Engineer. The Department will remove profit from the mark-ups in 1904.4.A, “Labor,”1904.4.B, “Materials,” and 1904.4.H, “Contractor Mark-Up,” by reducing the mark-up percentages as follows:

(1) Labor: from 62 percent to 57 percent; (2) Materials: from 15 percent to 10 percent; and (3) Contractor mark-up: from 10 percent for the

first $50,000.00 to 5 percent for the first $50,000.00.

1904.5 “Non-Allowable Cost”

Page 141: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

141

For compensable delays as identified in 1806, “Determination and Extension of Contract Time,” the Department will pay for the costs specified in 1904.6.B, “Allowable Delay Costs.” The Department will not pay for non-allowable charges specified in 1904.5, “Non-Allowable Charges,” or duplicate payment made under 1904.2 through 1904.4.

1904.6 “Compensation for Delay”

Page 142: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

142

The Department will not pay for delay costs before the Contractor submits an itemized statement of those costs. The Contractor shall include the following content for the applicable items in the statement.

1904.6 “Compensation for Delay”

Page 143: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

143

Extended Field Overhead Idle Labor Escalated Labor Idle Equipment and Mobilization Material Escalation and Storage

Allowable Delay Cost Components

Page 144: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

144

Field Overhead Costs

Field Overhead consists of time-dependent costs chargeable to the project, but not chargeable to a particular item of work

Page 145: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

145

The Department will pay the Contractor for extended field overhead costs that include costs for general field supervision, field office facilities and supplies, and for maintenance of field operations.

1904.6.B.1 “Extended Field Office Overhead”

Page 146: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

146

General field supervision labor costs include, but are not limited to, field supervisors, assistants, watchman, clerical, and other field support staff. The Contractor shall calculate these labor costs as specified in 1904.4.A, “Labor.” For salaried personnel, the Contractor shall calculate the daily wage rate actually paid by dividing the weekly salary by 5 days per week.

1904.6.B.1 “Extended Field Office Overhead”

Page 147: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

147

Field office facility and supply costs include, but are not limited to, field office trailers, tool trailers, office equipment rental, temporary toilets, and other incidental facilities and supplies. The Contractor shall calculate these costs to provide these services on a calendar-day basis using actual costs incurred due to the delay.

1904.6.B.1 “Extended Field Office Overhead”

Page 148: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

148

Maintenance of field operations costs include, but are not limited to, telephone, electric, water, and other similar expenses. The Contractor shall calculate these costs to maintain these services on a calendar-day basis using actual costs incurred due to the delay.

1904.6.B.1 “Extended Field Office Overhead”

Page 149: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

149

The Contractor shall calculate labor costs during delays as specified in 1904.4.A, “Labor,” for all non-salaried personnel remaining on the Project as required under collective bargaining agreements or for other Engineer-approved reasons.

1904.6.B.2 “Idle Labor”

Page 150: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

150

To receive payment for escalated labor, the Contractor shall demonstrate that the Department-caused delay forced the work to be performed during a period when labor costs were higher than planned at the time of bid. The Contractor shall provide adequate support documentation for labor costs, allowances, and benefits.

1904.6.B.3 “Escalated Labor”

Page 151: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

151

The Department will pay the Contractor for equipment, other than small tools, that must remain on the Project during Department-caused delays at the idle Equipment rate calculated in 1904.4.C, “Equipment.” The Department will pay the Contractor's transportation costs to remove and return Equipment not required on the Project during Department-caused delays.

1904.6.B.4 “Idle Equipment”

Page 152: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

152

The Department will pay the Contractor for increased Material costs or Material storage costs due to the Department-caused delay. The Contractor shall obtain the Engineer’s approval before storing Material due to a delay.

1904.6.B.5 “Material Escalation and…Storage”

Page 153: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

153

Home Office Overhead Costs

Home Office Overhead consists of costs that are difficult to apportion to specific projects.

Page 154: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

154

The Department will pay the Contractor for unabsorbed or extended home office overhead costs in accordance with the Federal Acquisition Regulations, specifically 48 C.F.R. § 31. The Department will audit all extended or unabsorbed home office overhead claims in accordance with 1721. The Department will compensate the Contractor using the standard Eichleay formula.

1904.6.B.6, …Unabsorbed Home Office Overhead

Page 155: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

155

Eichleay Formula

Actual Contract Billings

Total Actual Overhead

During Actual Contract Period

Allocable Overhead

Total Actual Company Billings

x =

Allocable Overhead Daily

OverheadTotal Days of Contract Performance Including

Delay

=

Daily Overhead

Days of Compensable

Delay

Unabsorbed Overhead

x =

Page 156: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

156

(1) the delay or suspension was caused by the Owner (i.e., forgivable and compensable);

(2) the delay or suspension required the Contractor to standby during the delay or suspension period;

(3) it was impractical for the Contractor to obtain replacement work during the delay or suspension period;

(4) the delay or suspension caused the contractor to be unable to complete the contract within the original contract performance period, as extended by any modifications; and

(5) the Contractor suffered actual damages as a result of the delay or suspension.

Requirements to Recover HOO

Page 157: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

157

(1) it was not impractical to obtain replacement work during the delay or suspension period;

(2) the inability to obtain other work was not caused by the delay or suspension; or

(3) the Contractor or Sub-contractor was able to reduce fixed overhead expenses during the period of delay or suspension.

Other Requirements for HOO Recovery

Page 158: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

158

(1) For completed quantities of eliminated Contract Items, the Department will compensate the Contractor for the accepted quantities at the Contract Unit Price.

1905 “Compensation for Eliminated Items”

Page 159: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

159

(2) For materials that the Contractor has ordered but not incorporated in the Work, the Department will compensate the Contractor in accordance with 1907, “Payment for Surplus Material.”

1905 “Compensation for Eliminated Items”

Page 160: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

160

(3) For partially completed quantities of eliminated Contract Items, the Department will compensate the Contractor for that portion of the quantity of the work the Contractor has performed on the eliminated Contract Item on the basis of a percentage of the Contract Unit Price equal to the percentage of work performed toward completion of that quantity of the Contract Item. To calculate this percentage, the Engineer will consider the value of materials incorporated in the partially completed quantity of the eliminated Contract Items to be the invoice cost of the materials plus transportation costs. The Engineer will add a 15 percent mark-up to the sum of the invoice and transportation costs.

1905 “Compensation for Eliminated Items”

Page 161: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

161

(4) For the cost of equipment, mobilization, and overhead that the Engineer considers directly attributable to the eliminated Contract Items and that the Department has not compensated the Contractor for through provisions (1), (2), and (3) of this list, the Department will compensate the Contractor in accordance with 1904, “Compensation for Contract Revisions.”

1905 “Compensation for Eliminated Items”

Page 162: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

162

The Department will not compensate the Contractor for loss of anticipated profits on completely or partially eliminated Work. The Department’s compensation to the Contractor for completed or partially completed quantities of Work on eliminated Contract Items in accordance with 1905 constitutes final and full compensation for the Work the Contractor has performed on eliminated or partially eliminated Contract Items.

1905 “Compensation for Eliminated Items”

Page 163: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

Module 41500

163

Page 164: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

164

A claim is an unresolved dispute.

Definition of a “Claim”

Page 165: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

165

Given the definition of a claim, claims avoidance requires both a reduction in the number of things that might be disputed and the implementation of approaches that encourage dispute resolution.

Avoiding Claims

Page 166: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

166

The Contractor shall not file a claim until the Contractor has exhausted the requirements of 1402, “Contract Revisions,” and 1403, “Notification for Contract Revisions.” The Contractor is not entitled to compensation or time extensions for disputed work under this section (1517) unless the compensation or time extension is required or provided for elsewhere in the Contract.

1517 “Claims for Compensation Adjustment”

Page 167: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

167

Allows owner to: Investigate Mitigate Document

Purpose of Notice

Page 168: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

168

The Contractor shall notify the Engineer in writing of any intent to file a claim for compensation or time extension. The Contractor shall not be entitled to compensation or a time extension if: (1) The Contractor fails to notify the Department. (2) The Contractor’s actions or inactions prevent

the Department from keeping strict account… (3) The Contractor’s actions or inactions prevent

the Department from mitigating the impacts and costs of the disputed work.

1517.1 “Notification”

Page 169: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

169

Every claim has three parts:

Entitlement Was there a revision?

ImpactIf yes, how did it affect the project?

CostWhat is the cost of the impact?

Parts of a Claim

Page 170: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

170

The Department requires that the Contractor establish entitlement for all claims before the Department will consider impact and cost.

1517.2.A “Entitlement”

Page 171: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

171

(1) A detailed factual statement of the claim providing a description of the claim issues and all relevant facts…a description of what Work was affected and how this Work was affected by the claim.

(2) A narrative that identifies all of the specific Contract provisions that support the claim, why they support the claim, and how the details of the factual statement in item (1) above establish entitlement based on the referenced Contract provisions.

(3) All pertinent documents, electronic files, and the substance of any oral communications related to the information provided in item (1) and (2) above.

1517.2.A “Entitlement”

Page 172: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

172

If the Department determines that the Contractor has established entitlement, the Contractor shall submit the following to the Department as a minimum to determine impact and cost:

1517.2.B “Impact and Cost”

Page 173: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

173

(1) If a delay is alleged, submit a narrative, all documentation (including applicable project schedules substantiating the delay), and a schedule analysis in accordance with 1806.1, “Determination and Extension of Contract Time, General.”

1517.2.B “Impact and Cost”

Page 174: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

174

(2) If additional costs are alleged, submit a narrative and all documentation that substantiates the claimed costs. The Contractor shall submit cost documentation for the claim submittal in a format that allows the Department to perform an audit under the authority of 1721, “Audits.”

1517.2.B “Impact and Cost”

Page 175: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

175

The Contractor may not submit a claim that fails to establish the causal link between the Department’s responsibility and the Contractor’s impacts and costs.

1517.2.B “Impact and Cost”

Page 176: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

176

The Contractor shall certify the claim attesting to the following: (1) The claim is made in good faith, based

on documented fact and the value is not overstated.

(2) Supportive data is true, accurate, and complete to the Contractor’s best knowledge and belief.

(3) The claim value is not based on a total cost calculation.

1517.3 “Required Certification of Claims”

Page 177: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

177

All claim submittals filed will be subject to review by the Department at any time following the filing of the claim submittal. The Contractor and Department shall exhaust the claim process reflected in this section (1517) before seeking compensation or extension of the Contract Time by filing an action in the courts of this State.

1517.4 “Review of Claims Submittals”

Page 178: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

178

(1) Daily time sheets and foreman’s daily reports. (2) Union agreements, if any. (3) Subcontracts. (4) Insurance, welfare, and benefits records. (5) Payroll register. (6) Earnings records. (7) Payroll tax returns. (8) Material invoices, purchase orders, and all

material and supply requisition contracts. (9) Material cost distribution worksheets.

1517.4 “Review of Claims Submittals”

Page 179: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

179

(10) Equipment records. (11) Vendor rental agreements, and…invoices. (12) Subcontractor payment certificates. (13) Canceled checks (payroll and vendors). (14) Job cost report. (15) Job payroll ledger. (16) General ledger, general journal… (17) Cash disbursements journal. (18) Financial statements for all years

reflecting the operations on this Project.

1517.4 “Review of Claims Submittals”

Page 180: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

180

(19) Income tax returns… (20) Depreciation records on all company equipment. (21) All other documents used to develop…actual

cost of owning and operating equipment. (22) …documents that reflect the Contractor’s actual

profit and overhead during the time the Project…and for each of the five years before the commencement of this Project.

(23) …documents related to the preparation of the Contractor’s Proposal…

(24) Worksheets used to prepare the claim submittal…

1517.4 “Review of Claims Submittals”

Page 181: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

181

In accordance with MN Statute § 16C.05, Subdivision 5, the Department and the Legislative Auditor or the State Auditor may examine and audit the following for at least 6 years after the end of the Contract: (1) Books, (2) Records, (3) Documents, (4) Accounting procedures, and (5) Accounting practices of the Contractor or

the Subcontractors

1721 “Audits”

Page 182: The information contained in this presentation is not part of any contract between MnDOT and any contractor, nor will it create an implied term in any

182

The provisions of the Minnesota “False Claims Against the State” Act (Minnesota Statutes Chapter 15C) apply to the Contractor’s actions under this Contract. The Contractor certifies or affirms the truthfulness and accuracy of any statement it made in connection with the Award of this Contract, and certifies or affirms that it will not make or use a false or fraudulent claim, statement, or record in connection with the performance of this Contract.

1701.3 “False Claims Act”