Objective
To establish and maintain the integrity of the configuration items throughout the lifecycle of the project or process
To ensure that all concerned groups are kept informed about the status of software configuration
Mahindra Satyam Confidential
3
© Mahindra Satyam 2009
Process
Configuration Planning
Configuration Control
Configuration Status Reporting and Accounting
Configuration Audits
Mahindra Satyam Confidential
4
© Mahindra Satyam 2009
Configuration Planning
Identify Resources for SCM
Version Control of SCIs
Identify SCIs
Mahindra Satyam Confidential
5
© Mahindra Satyam 2009
Identify Resources for SCM
SCM group
SCM Tools
Specific Hardware Requirements for SCM
Mahindra Satyam Confidential
6
© Mahindra Satyam 2009
Identify Resources for SCM
SCM group:
During the project planning stage, the PL and PM identify a group for performing SCM activities. Depending on the project's SCM requirements, this group consists of:
– The PL only, with additional responsibility for SCM, or
– One resource from the project team, with a part time or full time responsibility for SCM, or
– More than one resource from the project team, with part time or full time responsibility for SCM. In this case, one of these resources will be identified as the head of the group
Mahindra Satyam Confidential
7
© Mahindra Satyam 2009
Identify Resources for SCM
SCM Tools:
Microsoft VSS is the default tool for SCM
– In case the customer requires that a different tool be used, this will be documented in the project plan
PL specifies the access requirements for VSS to SCM group
SCM group gives the required access
Project server VSS where source code will be controlled will be administered by the project team itself
Mahindra Satyam Confidential
8
© Mahindra Satyam 2009
Identify Resources for SCM
Specific Hardware Requirements for SCM:
These requirements, if any, will be documented in the project plan
Mahindra Satyam Confidential
9
© Mahindra Satyam 2009
Identify SCIs
PL identifies all SCIs for the project as a part of the project plan
This includes, the naming convention storage location, and when the baseline is acquiredThis also includes information on how traceability is maintained across SCIs
Definitions:Managed and controlled Documents Change control process (impact analysis, approval etc.,) needn’t be done to
change the baselined documents. Examples of Managed & Controlled documents are estimation sheets, project
plan, work request plan.Documents under configuration management A rigorous change control process is applied to baselined items. Some software
work products, e.g., the software design and the code, should have baselines established at predetermined points. These baselines are formally reviewed and agreed on and serve as the basis for further development. A rigorous change control process is applied to baselined items.
Mahindra Satyam Confidential
10
© Mahindra Satyam 2009
Version Control of SCIs
The SCM group controls and manages the versions of SCIs using VSS
Following information is recorded in VSS as a version history while checking in each version of an SCI:
SCI Version No.
Date
Description of Change
Change Request Id
Change implemented by (Name)
Mahindra Satyam Confidential
11
© Mahindra Satyam 2009
Version Control of SCIs
The SCM group controls and manages the versions of source code in the project using VSS
The SCM group maintains a copy of VSS on the respective project volume allocated to the project and maintains the source code
Mahindra Satyam Confidential
12
© Mahindra Satyam 2009
Version Control of SCIs
The SCM group manages the versions of
Documents
Customer Supplied /included software products
Mahindra Satyam Confidential
13
© Mahindra Satyam 2009
Configuration Control
Each project maintains a Change Request Log with high level information on all change requests
This is used for broad tracking and status monitoring of change requests
A Change Request Form is used for recording and tracking activities for each Change Request in detail
Mahindra Satyam Confidential
14
© Mahindra Satyam 2009
Configuration Control
Request Change
Evaluate the Change
Approve / Disapprove the Change
Check out the SCIs
Modify the SCIs
Validate the SCIs
Create Executables
Mahindra Satyam Confidential
15
© Mahindra Satyam 2009
Request Change
The customer or member(s) of the project team may raise change requests
The change request is recorded on a Change Request Form by the requester of the change
If the change request is by phone, e mail , fax, etc.. then it will be recorded in a Change Request Form by the SCM group
The SCM group assigns a unique Change Request ID for the request at this stage
The Change Request Log will also be updated by the SCM group with details of the new change request
Mahindra Satyam Confidential
16
© Mahindra Satyam 2009
Evaluate the Change
PL evaluates the change requestsThe evaluation has the following steps: Identify the SCIs that need to be changed
Estimate the change impact in terms of time and effort
Identify the impact on statutory and regulatory requirements if applicable
Identify the impact on Integrity and Security features if applicable
Mahindra Satyam Confidential
17
© Mahindra Satyam 2009
Approve / Disapprove the Change
If the change impact is
small and can be absorbed in the existing schedules for the project, PL may approve the change request
– PM may be consulted at this stage, if required
large, the PL decides if it needs approval from the customer
– If yes, then it shall be forwarded to the customer for approval
The decision for approval / disapproval is to be recorded in change request form and change request log
Mahindra Satyam Confidential
18
© Mahindra Satyam 2009
Check out the SCIs
PL plans the schedule and resources for implementing the change
This is updated in the MS Project file
The SCM group checks out the identified SCI(s) and informs the concerned project team member(s)
These activities will be recorded with proper justification in change request form and change request log
Mahindra Satyam Confidential
19
© Mahindra Satyam 2009
Modify the SCIs
The SCI(s) will be changed by the concerned team members as per the change request
These activities are recorded in Change Request Form and Change Request Log
Traceability matrix is updated wherever necessary to reflect the changes
Mahindra Satyam Confidential
20
© Mahindra Satyam 2009
Validate the SCIs
The updated SCI(s) will be validated by the concerned project team member(s) to ensure proper implementation of the change
Validation consists of :
For document changes: An inspection/review
For source code changes: A code inspection/review of the impacted programs and testing of the change, including regression testing.
These activities will be recorded Change Request Form and Change Request Log
Mahindra Satyam Confidential
21
© Mahindra Satyam 2009
Check in the SCIs
Once the changes are validated, the concerned project team member(s) inform the SCM group about the readiness of the SCI(s) to be checked in
The SCM group then checks in the SCI(s) into VSS
Following information is recorded in VSS as a version history while checking in the SCI into VSS:
SCI Version No. and Date
Description of Change
Change Request Id
Change implemented by (Name)
These activities are recorded in Change Request Form and Change Request Log
Mahindra Satyam Confidential
22
© Mahindra Satyam 2009
Create Executables
After source code changes, the new version of the software product will be built by the concerned project team member(s) using relevant versions of SCIs
This will be then delivered to the customer
Mahindra Satyam Confidential
23
© Mahindra Satyam 2009
Configuration Status Reporting and AccountingSCM group sends configuration status reports to the affected groups as identified in the project plan
The inputs for these reports are :
Change Request Log for the project
SCI Status (a print out from VSS giving the current status of all SCIs)
Mahindra Satyam Confidential
24
© Mahindra Satyam 2009
Configuration Audits
Physical configuration audit (PCA)
Functional Configuration audit (FCA)
Mahindra Satyam Confidential
25
© Mahindra Satyam 2009
Configuration Audits
PL plans for these audits to coincide with the delivery of the project documents in the project plan
SCM Group conducts these audits
It is recommended that the audit team includes system testers and other project team members
Audit Team
Records the audit results in the configuration audit reports
Submits the report to the PM
Mahindra Satyam Confidential
26
© Mahindra Satyam 2009
Configuration Audits
PCA
is an audit of the SCI(s) and Quality records
has to be carried out for completeness and compliance verification usually during the following baselines:
Functional baseline (established by requirements)
Allocated baseline (established by high level design)
Product baseline (established by finished code)
Mahindra Satyam Confidential
27
© Mahindra Satyam 2009
Configuration Audits
FCA
ensures that the work products
accurately reflect the functional characteristics as expected
conform to the necessary interface characteristics
verifies that the work product has achieved the expected performance by examining the test data
Mahindra Satyam Confidential
28
© Mahindra Satyam 2009
Configuration Audits
FCA
has to be performed progressively throughout the development of the product and finalized when testing is complete
In some cases FCA has to be done during integrated system testing, in which case FCA will be delayed until that time
is conducted on the first baseline of the product, which is a representative of the final deliverable