© execview 2011 execview portfolio management training october 2011 key functions guide for...
TRANSCRIPT
© Execview 2011Execview Portfolio Management Training
Execview Portfolio Management Training
October 2011
Key functions guide for Portfolio and Project Managers
© Execview 2011Execview Portfolio Management Training
Contents
Introduction1. Overview
62. Security
73. Access
84. Support
95. Structure
106. Login
11
Setting Up New Projects7. Creating a new Project – Set up process
138. Accessing Portfolio Activities “Tree View”
14a. Project Definition: Business Case 15b. Project Definition: People, Components and Strands 16c. Project Definition: Overview 17d. Project Workflow 18 – 19
Terminology9. Key to Typical Execview Icons
2110. Glossary of Terms
22
continue >>
2
© Execview 2011Execview Portfolio Management Training
ContentsProject Progress View11. Implementation Arrow – Progress View
2412. Navigation from the Progress View
25
Milestones, Deliverables and Tasks13. Milestones
2714. Deliverables
2815. Tasks
29
RAIDs and Actions16. RAIDs (Risks, Assumptions, Issues and Dependencies)
31 – 32a. A more detailed look: Risks 33 – 34b. A more detailed look: Issues 35c. A more detailed look: Assumptions 36d. A more detailed look: Dependencies 37
17. Creating and Managing Actions38
continue >>
3
© Execview 2011Execview Portfolio Management Training
ContentsStakeholders18. Enabling Stakeholder Groups
40a. Adding Stakeholders via the Definition View
41b. Adding Stakeholders - Stakeholder grid view
42 – 44c. Updating Stakeholders - Stakeholder grid view
45
Finance Information19. Managing and Recording Finance information
47a. Entering Finance Data
48b. Entering an Overall Budget
49c. Entering a Baseline Plan
50d. Creating a Forecast
51e. Entering Actuals and Budget Variances
52f. Show Progress / Updating your Forecast
53
Progress Reporting20. Progress Reporting
55a. Progress Reporting: Creating a Report 56b. Progress Reporting: Adding Commentaries 57c. Progress Reporting: Scoring Status using DAIs 58
4
© Execview 2011Execview Portfolio Management Training
Introduction
© Execview 2011Execview Portfolio Management Training
1. OverviewExecview is designed to provide an intuitive, simple to use framework for running large projects and programmes of work.
Some of the Execview advantages are:
• Simple portal that holds all portfolio, programme and project information.
• The production of progress reports is straightforward. Reporting at higher levels is almost automatic.
• Two way reporting hierarchy that allows different summaries from the same underlying report.
• Managers can record and track all key project “components” (tasks, milestones, risks, issues, costs, etc) in a standard way. Items can be selectively escalated.
• The resulting views and reports are highly graphical.
• Software configuration and customisation is easy and can fit with the way an organisation works.
6
Back to contents
© Execview 2011Execview Portfolio Management Training
2. SecurityExecview is a “hosted”, Internet-based service provided by Execview Ltd.
A number of measures exist to ensure the service and the data stored in it remain highly secure:
• Hosted in a high security facility by one of the world’s leading hosting companies with security clearance from customers such as the British Army, the BBC and many banks
• Highly secure initial passwords, followed by requirement to use at least eight characters with one capital and one digit
• Fully audited environment, with user actions stored and full audit trail available for almost all data items
• Strong processes and procedures for customer set-up and system administration
7
Back to contents
© Execview 2011Execview Portfolio Management Training
• Security of system (IT)– The Execview software is written by Execview Ltd. However, the service is hosted
under contract to them by ‘Rackspace’, a major international hosting provider with very high-level security accreditation
– New Execview users receive two emails confirming a) the URL and their login id for the service and b) their initial password. This must be changed the first time you log in.
– New passwords in Execview must be at least eight characters long, containing at least one capital letter and one digit.
– The system forces you to change your password once every 30 days; you cannot use previous ones.
• Access Levels – Each Execview user is allocated one or more ‘roles’. For example, programme
manager of a specific programme, project sponsor, etc.– The roles given to your Execview account dictate the permissions you have in the
system, i.e. what you can create, edit or delete, etc.
8
3. Access
Back to contents
© Execview 2011Execview Portfolio Management Training
For normal IT problems and/or issues with Execview please contact <service desk info>
Typical role of a Project Management Office– Managing the organisation’s use of the Portfolio Module of Execview
– Setting up new users– Setting up projects– Moving programmes/projects between stages– Setting up Portfolio module scorecards– Managing the Execview supplier relationship
9
4. Support
Back to contents
© Execview 2011Execview Portfolio Management Training
Portfolio Summary
Contracted Service
Programme 1
Sub-Prog C
Sub-Prog A
Project 2
IT Project
Other Project
Operations Summary Commercial
Execview will allow a complex portfolio of projects to be built and tracked. A project can exist on its own in a portfolio, or as part of a programme:
Components
• Progress Reports• Milestones• Tasks• Deliverables • Risks• Issues• CSFs & KPIs• Assumptions• Dependencies• Resources• Finances• Benefits• Documents• Definition (PID)• Workflow (status)
There is a four tier security model (security on four levels):
• Contracted Service (CS) – This forms a security boundary. The Execview system can be on a separate server for additional security.
• CS Administrator – controlling access and configuration of the system for one organisation
• Activity – managing Portfolios, Programmes and Projects
• User – preferences, password change
Portfolio
10
5. Structure - Flexible and Secure
Project 1
Back to contents
© Execview 2011Execview Portfolio Management Training
When you first log in to Execview you are taken to a personalised home page:
• The graph on the right displays the aggregate view of the items tasked for you to deliver.
• Further information below this lists things you must do or know about.
• There are a several navigation tabs located in the top left of the screen:
Home (this page) Operations (where service delivery
is tracked and reported) Portfolio (where projects are
tracked and reported) Resources (timesheets and work
assignment information) Administration (for admin users
only)
NB: Some of these tabs may not appear if you are not set up to use them.• Your name, and links to Support,
Feedback, Change Password and Logout are shown in the top right corner
Personalised home page dashboard, displays by project, programme and portfolio all of the Tasks, Actions, Risks, Issues, Dependencies, Assumptions, Change Requests, etc. that you are responsible forHome Page
Login ScreenExecview user login details
Reset password
Current overall RAG status
Date & links toMy ActionsMy Tasks My RAIDs
Delivery graph of Planned v Completed items
Main Navigation tabs
You can retain your username and password details between sessions if your PC is secure / private
11
6. Login
Back to contents
© Execview 2011Execview Portfolio Management Training
Setting Up New Projects
© Execview 2011Execview Portfolio Management Training
13
7. Creating a new project – Set up process
Back to contents
© Execview 2011Execview Portfolio Management Training
The standard method of accessing a programme or project is via the ‘tree view’:
• Click ‘Portfolio’ on the top level menu.• The ‘Status View’ that appears lists all
activities in your portfolio, together with managers’ names, dates of their most recent reports and status indicators (called ‘DAIs’).
• Reports are ‘produced’ and kept in an archive for each activity. You cannot produce a report prior to the date set for it.
• To enter an activity, click on its title: If you have the appropriate ‘role’ for a
project or programme, the link will be blue and you will be able to click the link to get to the project’s progress report.
If you do not have the right permission, the link will be black and you will be able to see the link in the treeview but not access it. Contact the CPO/PMO to gain access.
•As a shortcut, you can go straight to Tasks, RAIDS, Documents, Actions etc. in a project by selecting the component view.
Delivery Assurance Indicators (DAIs)
Add and edit new projects, programmes or portfolios hereComponent View
Status View
Project Manager & Date of last report
14
8. Accessing Portfolio Activities via the ‘Tree View’
Back to contents
© Execview 2011Execview Portfolio Management Training
Access this page by clicking into the project from the Portfolio tab
Then click the large ‘Definition’ arrow near the top of the screen
This page is split into four sections, described below and on the next slide:
Business Case
• Project purpose• Business problem definition• Context information• Business impacts summary• Delivery approach• What’s In and Out of Scope• Success Criteria (CSFs)• Performance Measures with Targets• Finances• Benefits
Overview
Aims & Measures
Select this icon to create a pdf version
Select this icon to add a measure
Select this icon to add a target
Finances & Benefits
Edit
Delete
Add
15
a. Project Definition: Business Case
Back to contents
© Execview 2011Execview Portfolio Management Training
People, Components & Strands
• People – this section lets the user define who the project manager and project sponsor will be via the use of name fields.
• Components – this is a quick way for components such as milestones, tasks and RAIDs to be entered.
• Strands – sets up strands into which components can be grouped.
Adding an item to these pages has two effects:
• Builds the project definition document for sign-off, including the governance of the project, and
• Automatically adds all trackable items to the database, so that later additional information and status can be managed
People
Components
StrandsEdit
Delete
Add
Edit
Delete
Add
16
b. Project Definition: People, Components and Strands
Back to contents
© Execview 2011Execview Portfolio Management Training
Overview
The Definition arrow’s Overview screen is a multi-screen form describing the project in full, which can also be generated as a pdf.
It includes all the information entered into the previous four tabs.
Overview
17
c. Project Definition: Overview
Back to contents
© Execview 2011Execview Portfolio Management Training
Execview’s workflow functionality moves an activity through a set of pre-defined states (see project lifecycle next page)
A project’s workflow has two key functions:
1. Allows the project definition to be drafted, and ‘Locked’ at the end of the first stage. The project workflow states are either ‘active’ or inactive’. Completed, On Hold or Closed are examples of inactive states –
most other states are Active.2. Allows the project status to be controlled by the CPO / PMO
An end date can be entered against each workflow state to signify when this stage should end and the next phase should commence. The CPO has the permissions to move a project from one state to another.
TIP:
• A project in an ‘Inactive’ state will not appear by default in the Portfolio tree view.
• Select Status: ‘– All –’ or ‘Inactive’ at the top of the Portfolio tree view in order to access a project that is not active.
d. Project Workflow
Back to contents
18
© Execview 2011Execview Portfolio Management Training
Idea stage
Concept stage
Definition stage
Impl’ment stage
Handover stage
Completed
Approval of project mandate
Approval of Outline Business
Case
Approval of Final Business Case
Approval of Implementation
stage
Approval of Handover and
Closeout
• Statement of requirements (SoR)
• Resourcing of PM, Sponsor• Delivery approach• Draft Contract• Design stage plan and
resourcing• Project Management Plan
(PMP)
• Business problem definition
• High level conceptual description
• High level project economics
• Technology assessment• Impact assessment• Project Charter
• Detailed planning• Technical design
specifications• Build stage plan and
resourcing
• Build deliverables (products, processes)
• Solution set-up• Testing stages• Training design• Comms plan• Rollout stage plan
• Project delivery• Handover documents• Project close-out report• Lessons Learnt
Meeting review of:• Outline analysis of the
problem and opportunity• Discussion of delivery
approach, complexity, risk, costs and benefits
• Start dates and duration• Fit with other work
Typical outputs from each stage (for information)
Gateway – this is the primary approval point (or transition) where a Steering Group or individual grants approval for the project to continue to the next stage thereby progressing the workflow (to move forward)- Typically workflow will be updated by the CPO on behalf of the project following an approval meeting
QA review – this is an optional approval in the workflow, typically by a specialist team that signs off the outputs from the previous stage. - Typically requires multiple signatures by the PM, Technical Design Architect, Business Design Architect, Project sponsor, in order for this review to have completed.
19
d. Project Workflow continued
Back to contents
© Execview 2011Execview Portfolio Management Training
Terminology
© Execview 2011Execview Portfolio Management Training
These icons are used in the project and programme components:
Update item definition
Update item status
Manage Actions
Store Documents
• BLUE – Completed and signed-off
• GREEN – High Delivery Confidence – On track to complete in the agreed timescale and to the required output criteria.
• AMBER – Medium Delivery Confidence - Some issues or risks impact this item, but it will be recovered by management action
• RED – Low Delivery Confidence - Will be impacted in output completion or timescale; cannot be recovered to original intent
• GREY – Not relevant or no status information is available
Note: a key to some of these symbols can be added to the bottom of your progress reports. Tick the checkbox in the Progress Report settings screen.
These icons are used in the tree view for setting up new Portfolios, projects, programmes:
Add new workstream Edit workstream
Add new programme / project Add Change Request
Workflow Deliverables
Tasks Milestones Finances Progress Report RAIDs Actions Aims and Measures Documents Resources Scorecards Import Rules Outcome Maps
21
9. Key to Typical Execview Icons
Back to contents
© Execview 2011Execview Portfolio Management Training
RAG Red, Amber, Green: Often used to express confidence that something will be delivered as expected (Red, Amber and Green respectively mean low, medium and high confidence). Blue, where used, means completed and Grey means not scored
DAI Delivery Assurance Indicator: RAG indicators relating to key aspects of running any programme or project
Milestone A single point in time at which something is now able start, or has been achieved
Deliverable Something a project must produce, whether tangible or intangible
Task Some work for people to do, with both a start and end date, a lead person, and from which a Deliverable will be produced
RAID A collective term for Risks, Assumptions, Issues and Dependencies. These are all entered and managed by Execview in much the same way.
Issue A problem that has arisen about which some action needs to be taken. Word these in the past tense.
Risk A problem that may arise but hasn’t yet, about which some action may be taken now to reduce its likelihood or to anticipate its consequences. Word these in the future tense.
Assumption A general fact you are relying on to be true over which you and your immediate colleagues have little control
Dependency Something you are relying on to be delivered which is the responsibility of someone outside your chain of command to provide (or the opposite, where you are delivering something for other people which they cannot influence)
Notes on In deciding whether to assign an item as a Risk, Issue, Dependency or Assumption considerationRAIDs: should be given to how you wish to manage any item. They are similar but, for example, if you want to
record a probability and/or mitigation approach, then create a Risk as this data only exists on Risks in Execview. Likewise, only a Dependency can record the name of the person who is responsible for delivering it.
A Dependency may slip, and an Assumption may turn out to be false. These could therefore also be regarded as Risks and added to Execview as such. But since it is more work to monitor and manage two things than one, and it is possible to indicate a RAG status on any Dependency or Assumption, it may well be sufficient to use just them. 22
10. Glossary of Terms
Back to contents
© Execview 2011Execview Portfolio Management Training
Project Progress
© Execview 2011Execview Portfolio Management Training
All projects and programmes have a standard initial page called the Progress View:
• This page carries the latest project status, and reports milestones, products, RAIDS (Risks, Assumptions, Issues and Dependencies) deliverables (if any) and finances.
The tracking menu contains a number of other Views:• Schedule (timeline)• Delivery (phases/milestones)• Scorecard (exception reports)• Change Request List• Actions• Finances• Measures• Stakeholder Map
Other things you can access:Left-hand grey floating menu buttons: take you to screens for managing the related project components.• Click the titles and status icons of items
on the report to access their definitions and latest status information.
Hover over the three small squares on the very left-hand edge of the screen to view these buttons
Back to tree view, up to parent or across to other projects
Milestones and Task progress graphs
Project, Programme, Portfolio name
Different Views are available under tracking
Progress View
Delivery Assurance Indicators (DAIs)
24
11. Implementation Arrow – Progress View
Back to contents
© Execview 2011Execview Portfolio Management Training
Schedule View
Progress View
Actions View
Delivery View
Finance View
25
12. Navigation from the Progress View
Back to contents
Scorecard View
© Execview 2011Execview Portfolio Management Training
Milestones, Deliverables, Tasks
© Execview 2011Execview Portfolio Management Training
Workflow Stage: this field dictates at which stage of the project the milestone relates
to
• A Milestone is a single point in time by which something has been achieved, or something is enabled or ready to happen.
• Milestones are managed in a very similar way to Tasks and Deliverables (see next two pages).
• You can attach to any Milestone: One or more documents One or more actions
TIP: Remember, Milestones are listed on your Project progress report – the quality of how you document them is important.
Search Filters Status filterShows Milestones at lower
levels and by activity
27
13. Milestones
Back to contents
Reporting Level field: controls whether this item is escalated to appear on higher level reports.
Decide whether to do so in discussion with the related
Portfolio manager
© Execview 2011Execview Portfolio Management Training
Deliverables are what your project is going to produce which will achieve business change
• Press the “Deliverables” button to manage them.
• Click “Add Deliverable” (top right) to create one.Select the title to update a Deliverable’s definition, including owner and approver and the level you want it reported at.
• The search box allows the user to filter on key words in the title or description
• Click the ‘status’ icon to update current status. You will see that an audit trail of all previous status updates is kept.
• You can attach to any Deliverable: One or more documents One or more actions
Deliverable definition screen
Status update screen
Excel report
The blue highlight signifies the last product to be accessed by that user
Search Filters Status and people filtersShows Deliverables at
lower levels and by activity
28
14. Deliverables
Back to contents
© Execview 2011Execview Portfolio Management Training
Tasks are major items of work to be completed for your project. They represent how effort and resources will produce your project’s deliverables
• Press the “Tasks” button to manage them.
• Click “Add Task” (top right) to create one.Select the title to update a Task’s definition, including its start and expected end date, a person leading its delivery and a the level you want it reported at.
• The search box allows the user to filter on key words in the title or description
• Click the Status icon to update current status. You will see that an audit trail of all previous status updates is kept.
• You can attach to any Task: One or more documents One or more actions
TIP: Remember that Tasks are listed on your Project progress report. The quality of how you document these is important. Try to be concise – a sentence or two in most cases is sufficient for all but the most complex tasks.
Task definition screen
29
15. Tasks
Status update screen
Excel export
The blue highlight signifies the last item accessed by
you
Task grid view
Back to contents
© Execview 2011Execview Portfolio Management Training
RAIDs and Actions
© Execview 2011Execview Portfolio Management Training
• Risks: problems that may arise (but haven’t yet)
• Assumptions: things you are relying on to be true but probably cannot influence
• Issues: problems that have arisen• Dependencies: something you need to
receive where delivery is outside your control
• RAIDs are managed in a very similar to Deliverables, Tasks and Milestones (see previous pages).
TIP: Keep items short and succinct – it helps the progress reporting. If you want lots of detail, attach a document to the RAIDs item
31
16. RAIDs (Risks, Assumptions, Issues, Dependencies)
Back to contents
© Execview 2011Execview Portfolio Management Training
There are two RAID reports available:
• A ‘Full RAID Report’ which is a formatted printable option that can be used to review RAIDs in meetings.
• An Excel document as with Milestones and Tasks that can be manipulated as you wish
The filter options allow for different views of RAIDs to be created. Both reports export whatever is displayed in list.
Search Filters Status Filters Shows RAIDs at lower levels and by activity
32
16. RAIDs (Risks, Assumptions, Issues, Dependencies)
Back to contents
© Execview 2011Execview Portfolio Management Training
Search Filters Status FiltersShows RAIDs at lower levels and by activity
Overdue Risks have red dates, otherwise
green (or amber if within one week)
33
a. RAIDs – A more detailed look: Risks
Back to contents
If categories have been set up by your administrators, then you have the option to
set them on the definition screen. Alternatively they can also be left to ‘Not set’.
Business Impact:4 – Critical3 – Major2 – Moderate1 – Minor
Risk Probabilities:4 – 99 percent3 – 66 percent2 – 33 percent1 – 0 percent
© Execview 2011Execview Portfolio Management Training
State what you are trying to do to mitigate (or provide contingency) for this risk in the ‘Mitigating Actions” field. Then state progress towards achieving this in the ‘Latest
Progress’ field.
This graphic shows you Execview’s estimation of the risk’s current severity (the black circle). It usually lies somewhere between
where the severity was initially judged to be and a target to be achieved.
Search Filters Status FiltersShows RAIDs at lower levels and by activity
State the current delivery confidence of completing
mitigation
Always state the current view of risk impact and probability on the Latest Progress screen
34
a. RAIDs – A more detailed look: Risks
Back to contents
Business Impact:4 – Critical3 – Major2 – Moderate1 – Minor
Risk Probabilities:4 – 99 percent3 – 66 percent2 – 33 percent1 – 0 percent
© Execview 2011Execview Portfolio Management Training
Use the Issue Definition screen’s Mitigation field to state what you are trying to do to resolve or mitigate this issue. Then state
progress towards achieving this on the Latest Progress screen’s ‘Latest Progress’ field.
Business Impact:1 – Low2 – Medium Low3 – Medium High4 – High5 – Extremely High
Issue severity relates directly to Business Impact.
Status – confidence that the issue will be resolved or
worked around.
Search Filters Status FiltersShows RAIDs at lower levels and by activity
If categories have been set up by your administrators, then you have the option to
set them on the definition screen. Alternatively they can also be left to ‘Not set’.
35
b. RAIDs – A more detailed look: Issues
Back to contents
© Execview 2011Execview Portfolio Management Training
Select a RAG symbol to express confidence that this
assumption is valid
Search Filters Status FiltersShows RAIDs at lower levels and by activity
36
c. RAIDs – A more detailed look: Assumptions
Back to contents
© Execview 2011Execview Portfolio Management Training
There are spaces here to record:
Direction: is this something where you are dependant on something else (incoming) or someone is dependent on you (outgoing) or both?
Reciprocal owner: the other party involved in this dependency
Type: Internal or External, i.e. Whether this relates to something within or outside the overall organisation.
Search Filters Status FiltersShows RAIDs at lower levels and by activity
37
d. RAIDs – A more detailed look: Dependencies
Back to contents
© Execview 2011Execview Portfolio Management Training
Actions are small items of work for one person to carry out in support of managing milestones, tasks or RAIDs.
Click the light bulb icon to open a screen showing all existing Actions and then:
• Click ‘Add Action’ to create a new Action
• Enter a title and description for the Action
• Enter a date by when you require the Action to be completed – Execview suggests one week from today
• Enter the person you want to perform the Action
• Tick or untick the email checkboxes to indicate if you wish them to receive notifications of differing types
• Click ‘Save’
You can review Actions for individual project components, or use the Action button or Action View to list all the Actions relating to a project or programme:
Filter Actions by type of component Filter by Owner Filter by Status (Open, In progress, etc.) Search on key words in title or description Include/exclude those of child projects within a
programme Display actions by activity The list of actions displayed can be exported to
Excel and as well as being able to import a list back into Execview
Add newaction button
Component or activity to which this
action belongs
Search Filters Status Filters Shows actions at lower levels and by activity
Action Definition Screen
38
17. Creating and Managing Actions
Back to contents
© Execview 2011Execview Portfolio Management Training
Stakeholders
© Execview 2011Execview Portfolio Management Training
• The Stakeholders button for a given activity is only enabled if its parent’s “Stakeholder groups of child activities” setting is not turned off.
• This setting is accessed via the Settings button of any parent activity by either a Portfolio manager or the CPO
• The options are: Off no stakeholder groups can be set up on child activities Enforce stakeholder groups on child activities can only be selected from those set up
on the parent Offer stakeholder groups on child activities can be chosen from the parent’s set or
added as new group names Independent stakeholder groups on child activities are only ever added as new group
names
• Thus, if the Stakeholder Groups button is greyed out on an activity, someone with permission to access the parent must set the setting as required
40
18. Enabling Stakeholder Groups
Back to contents
© Execview 2011Execview Portfolio Management Training
The screen above will be displayed when accessing the stakeholders via the definition view of the activity.
• Stakeholder Group - in the example above, the user would have to choose from a list of existing stakeholders set at the parent level as this would have been the setting chosen.
• Area Of Interest – this is a free text field where the user would enter the area of interest for this group.• High Influence – the tick box would be checked if the stakeholder group is of high influence on the project. A
‘smiley’ face symbol would be displayed if the this tick box is checked.• High Interest – the tick box would be checked if the stakeholder group is of high interest for this project. A blue
icon would be displayed if only the high interest tick box is checked.A key symbol would be displayed if both of the above boxes are ticked.
An example of where only the stakeholders
set at the parent level, can be chosen
This a free text field where the user indicates
the area of interest
Use these tick boxes to
indicate level of influence
and/or interest
The key symbol indicates this stakeholder group is of high influence and high interest
Select this icon to add a stakeholder group
Select this icon to edit the
stakeholder group
Deletes the stakeholder group
41
a. Adding Stakeholders via the Definition View
Back to contents
© Execview 2011Execview Portfolio Management Training
• The list of stakeholder groups can be exported to excel with the use of the icon displayed.
• The filter options allow for different views of stakeholder groups to be created. The excel export generates a sheet with whatever is displayed in the list.
• High influence and interest
• High influence only
• High interest only
• Influence and interest not set
Search Filters Status Filters Shows Stakeholder groups at lower levels and by
activity
The blue highlights the last record accessed in the grid view
Search by stakeholder type
42
b. Adding Stakeholders - Stakeholder grid view
Back to contents
© Execview 2011Execview Portfolio Management Training
When adding a stakeholder group the user is presented with the screen on the left.•Stakeholder Group Name – the user can enter or choose from a list depending on the settings.•Area of Interest – free text field for the user to enter area of interest•Communication Plan – free text field for the user to enter a communication plan•Influence and Interest – determined by the use of tick boxes•Owner – choose the owner for this group•Reporting Level – determines what level this stakeholder group is reported at
Search Filters Status Filters Search by stakeholder type
Shows Stakeholder groups at lower levels and by
activity
43
c. Adding Stakeholders - Stakeholder grid view
Back to contents
© Execview 2011Execview Portfolio Management Training
The People tab allows the user to select key users for this stakeholder group• Group Lead – the user should choose
a lead for this group using the auto complete drop-down
• Contact Point – the user should choose a contact point for this group using the auto complete drop-down
• Users & Group Members – the user can select users for this group using the list in the box. To add a user to the group member box, simply click on the name. This name will then display in the group member box. To remove a user from this box, simply click on the name again.
Search Filters Status Filters Search by stakeholder type
Shows Stakeholder groups at lower levels and by
activity
44
d. Adding Stakeholders - Stakeholder grid view
Back to contents
© Execview 2011Execview Portfolio Management Training
The latest progress tab allows you to enter details about on-going meetings with stakeholders• Latest progress –enter any status commentary
• Actions required –enter any actions required for the next meeting
• Date of last interaction – enter the date of the last communication with this stakeholder
• Date of next interaction – enter the date of the last communication with this stakeholder
• RAG status –a RAG to indicate how the communication plan is going
After the progress is entered it will then appear in the history tab as seen on the left
Search Filters Status Filters Search by stakeholder type
Shows Stakeholder groups at lower levels and by
activity
45
e. Updating Stakeholders - Stakeholder grid view
Back to contents
© Execview 2011Execview Portfolio Management Training
Finance Information
© Execview 2011Execview Portfolio Management Training
Execview’s finance functionality allows the entry of summarised cost and/or income information for management reporting.
The two types of finance can be displayed by choosing either option in a drop-down displayed.
Costs or income can be entered against any project or programme. Execview then automatically rolls up the information to higher levels. Even though some projects may appear under multiple programmes, finances are not double counted!
Projects can be set up in any required currency. You should then enter data across categories configured for your service (for example Resources, Assets and Other). Data can be created as follows:A “baseline plan” of how finance will be spent or received over the lifetime of a project can be set up. Actuals and a separate ‘forecast plan to completion’ are then entered or updated as the project progresses.A complete view of all finance data can be accessed from a ‘Show Progress’ button on the finance screen.
Overall budget
Actual spend so far (red solid line)
Phased forecast to completion (red dotted
line)
Baseline plan
Example extended finance graph
47
19. Managing and Recording Finance information
Back to contents
© Execview 2011Execview Portfolio Management Training
• Within any activity (project, programme, etc.) you can manage finances (both cost and income) by selecting either the Finance View through the implementation arrow or clicking the Finances button via the button bar
• The Finance module provides four tabs for entry of finance data:
1. Overall Budget
2. Baseline Plan
3. Actuals (includes budget variances) and
4. Forecast• As data is entered, a graph showing
the overall picture of finance builds up
• You can always choose to list all data entered so far by clicking the “Show Progress” arrow. This lists each record by type and date. The set of records can be exported to Excel.
• Finance data can be imported by using the ‘Import from Excel’ option in the progress section
• NB: The currency of the project you’re in is always shown here.• The finance type titles shown are examples. Your administrator
sets these for your organisation as a whole (see previous slide)• A comment can be stored for each and every item of finance data
Drop-down to choose between cost and income
48
a. Entering Finance Data
Back to contents
© Execview 2011Execview Portfolio Management Training
• The first thing to enter is an Overall Budget. This is simply the total amount of expenditure signed off for the project, and will be presented as a flat, top line on the cost/income graph.
• You can enter this overall budget broken down into the number of cost/income types set up for your Execview service.
• The finance record created is shown at the bottom of the screen.
• The records displayed will be for either costs or income depending on the type chosen in the drop-down.
1. Select the Overall Budget tab2. Enter values3. Enter a comment, if desired4. Click Update
49
b. Entering an Overall Budget
Back to contents
© Execview 2011Execview Portfolio Management Training
• The second thing to do is create a Baseline Plan of how your project is expected to spend money.
• You do this by entering successive amounts of expected spend for any number of dates (broken down by cost type).
• As you enter each date and set of amounts a record is added (see the Show Progress section).
• Dates do not have to be at regular intervals. There can be as many as you like.
1. Select the Baseline Plan tab2. Enter a date3. Enter values for the spend just in this period4. Enter a comment, if desired5. Click Update6. Repeat steps 2 to 5 to build up your plan
50
c. Entering a Baseline Plan
Back to contents
© Execview 2011Execview Portfolio Management Training
• The third thing to set up is your Forecast. This is your current view of how your project is going to spend money, which may vary from the original intended spend (the Baseline Plan).
• At the start of your project, the Forecast will be the same as your Baseline Plan.
• Execview makes it easy to set this up, by providing a button to create a copy of all Baseline Plan records to make equivalent Forecast ones.
• The graph shows the forecast as a dotted red line, which at first will lie directly on top of your blue Baseline Plan.
51
d. Creating a Forecast
Back to contents
© Execview 2011Execview Portfolio Management Training
• The previous slides covered things to set up at the start of a project.
• The data you need to enter during the life of a project are actual costs, any changes to the agreed budget and your expected future costs (i.e. your updated forecast).
• Use the Actuals tab to record actual spend each period and also any budget changes.
• NB: Amounts you enter are what you have spent since the last data entry, NOT your total spend to date.
1. Select the Actuals tab2. Enter a date3. Enter values for the spend just in this period4. Enter a comment, if desired5. Enter values for any changes to the overall
budget (prefix with a minus sign for a reduction)
6. Click Update7. Typically, you do this once each reporting
period8. A solid red line indicates Actuals entered so
far, with a dotted red line for any Forecast data beyond the date of the latest Actual.
52
e. Entering Actuals and Budget Variances
Back to contents
© Execview 2011Execview Portfolio Management Training
• To let people know your current expected spend from now until project completion, you have already set up Forecast records.
• However, as things change, they may need adjustment.
• Either change existing data by using the Edit button in “Show Progress” for dates already entered,
OR
• Enter new Forecast records for new dates using the Forecast tab
• Click the Edit icon to edit any existing Forecast data• Click the delete icon to delete an individual record• NB: Any Forecast records for dates earlier than the latest Actual
data are ignored by Execview
53
f. Show Progress / Updating your Forecast
Back to contents
© Execview 2011Execview Portfolio Management Training
Progress Reporting
© Execview 2011Execview Portfolio Management Training
• The Progress View automatically picks up latest status data for:• Milestones• Deliverables and Tasks• RAID items• Finance info
• For your report to be up to date when you produce it, you need to have first updated the above items.
• It is a good idea to use the Progress View to review how a report looks prior to ‘producing’ the report. Producing the report ‘locks’ it and stores a PDF version in your project’s archive. You’ll need to unlock it again if further editing is needed.
• Look at the format. Try to judge the amount of text to include. Our recommendation is that if you adhere to the overall format, and put status text in the right places, you can summarise most projects in two or three pages.
55
20. Progress Reporting
Back to contents
© Execview 2011Execview Portfolio Management Training
The progress report system generates a progress report in PDF format for distribution and printing.
Steps to create a full progress report:
• 1. From the left-hand buttons click the Progress Report button. This opens a new window.
• 2. Select the Create button (to create a new report) or, if greyed-out, the Edit button (to continue making a report previously started).
Now complete each tab (Edit, DAIs then Produce) to carry out each step needed – see the next few slides.
• The ‘Settings’ tab allows you to define: Report frequency (weekly is the default
and strongly recommended) Day of the week for reporting Previous period Status & Actions Various options, including display of costs,
a key to symbols and additional commentary fields
List of previous reports
If the create button is greyed out it means a report already exists in draft.
To access it press Edit instead.
Progress Report Window
Clicking the Progress Report button accesses
the set of screens for creating or editing the latest progress report.
56
a. Progress Reporting: Creating a Report
Back to contents
© Execview 2011Execview Portfolio Management Training
3. At the top of every progress report there are spaces for you to add comments about your activity. Use the Edit tab to record overall achievements so far and actions required in the future:
Say it as it is – use RAG statuses appropriately to focus attention
Relevance – focus on the areas of performance at risk and the main project roles who can endorse actions
Avoid surprises – progress reports should mostly reflect management actions already discussed.
4. Don’t forget to press Save!
Overall Status
Actions required (general)
GREEN – On track to complete in the agreed timescale and to the required output criteria.
AMBER – Some issues or risks may impact the activity, but it will be recovered through existing management action to meet required output criteria.
RED – The activity will be impacted in either output, quality, completion or timescale and cannot be recovered to the original intention.
Current expected completion date
A number of options exist to allow you to tailor your progress report. These are accessed via the Settings tab.
57
b. Progress Reporting: Adding Commentaries
Back to contents
© Execview 2011Execview Portfolio Management Training
• 5. Use the DAIs tab to enter each ‘Delivery Assurance Indicator’ (DAI) status and, if desired, some commentary.
• Each DAI has a RAG status to be selected and commentary text field. The screen also shows these values, for each DAI, for the last report produced.
• You can copy the previous text into that of the current progress report by pressing the Copy Last Comment button.
When finished, press Save at the bottom of the screen.
• 6. Producing a report is done via the Produce button on the Produce tab. This commits the current information into a final version of the report, which is then stored and accessible in the View Reports tab as part of the project’s archive of progress reports.
Previous reported RAG & commentary
Current report RAG & commentary
Report Produce button
If you want to edit a report even after it’s locked, then press the unlock button
58
c. Progress Reporting: Scoring Status using DAIs
Back to contents
© Execview 2011Execview Portfolio Management Training
Summary and Feedback
© Execview 2011Execview Portfolio Management Training
• This overview should enable you to produce reports.
• They will be produced on a regular basis. How frequently will be advised by the CPO.
• The circulation of the collected reports will cover many of the key stakeholders in the programme so please think about what you write and make it understandable by an audience not embedded in the workstreams.
• The reports will shape the conversations at review meetings, one-to-ones and project or programme boards.
• The reports should be straightforward to produce. If you spot errors or have suggestions for improvements please let us know – our aim is to facilitate delivery and to communicate the status of the projects.
• Q & A
60
Summary and Feedback