guelph.caguelph.ca/wp-content/uploads/contract_12-117_description.pdf · and waterproofing system...

73

Upload: hanhan

Post on 29-Jun-2018

213 views

Category:

Documents


0 download

TRANSCRIPT

PAGES DIVISION 0 BIDDING DOCUMENTS Section 00100 Information For Bidders 1 - 4 Section 00800 Supplementary Conditions 1 - 5 DIVISION 1 GENERAL REQUIREMENTS Section 01000 General Requirements 1 - 17 DIVISION 3 CONCRETE Section 03500 Concrete Repairs 1 - 8 DIVISION 5 METALS Section 05720 Aluminum Railings 1 - 7 DIVISION 7 THERMAL & MOISTURE PROTECTION Section 07100 Hot-Applied Waterproofing 1 – 6 Section 07150 Asphaltic Traffic Deck Waterproofing 1 - 5 Section 07570 Elastomeric Waterproofing 1 - 4 Section 07950 Expansion Joint Seals 1 - 3 DIVISION 15 MECHANICAL Section 15420 Garage Roof Drains 1 - 3 Section 15430 Garage Floor Drains 1 - 3 TYPICAL DETAILS SK3-01 Through Slab Concrete Repair Detail SK3-02 Top Surface Concrete Repair Detail SK3-03 Underside Concrete Repair Detail SK3-04 Vertical Surface Concrete Repair Detail SK7-03 Hot-Applied Waterproofing - Up-Turn Detail – Pavement

Guelph Parkades, Guelph SECTION 00100 Page 1 Parking Garage Repairs April 2012 INFORMATION FOR BIDDERS

PART 1: GENERAL 1.1 DESCRIPTION OF THE WORK

.1 The intent of the work is to remove and replace the asphalt traffic topping and waterproofing system at the East Parkade roof deck and repair the concrete roof deck with allowances for localized concrete and waterproofing repairs at the ‘East’ and ‘West’ Parkades in downtown Guelph (off Macdonnell Street).

The Owner reserves the right to limit the extent of the Work actually carried out to any part of that described below. All work must be carried out in accordance with the attached specifications, Building Code requirements, and manufacturer’s recommendations as directed by the Engineer.

.2 The proposed work includes the following:

West Parkade (Predominantly Pre-Cast Concrete):

i. Provide any and all access equipment, hoarding, shoring, and bracing necessary to both safely complete and inspect the work.

ii. Supply and install heavy duty elastomeric waterproofing system on the

cast-in-place concrete ramp assembly at the P2 level, including fully encapsulating all related curb assemblies and onto surrounding slab surfaces by a minimum of 400mm. (It may be assumed that all traffic will be diverted around this ramp for the duration, provided the installation is completed without undue delay in the sole discretion of the Engineer).

Identify all delaminated concrete within designated work areas and repair as specified where authorized by the Engineer and in accordance with suitable Unit Rates using prepackaged repair material (FA-S10 by King Packaged Materials Company or approved equal).

Guelph Parkades, Guelph SECTION 00100 Page 2 Parking Garage Repairs April 2012 INFORMATION FOR BIDDERS

Re-apply affected traffic markings and curb-paint to match existing.

East Parkade (Cast-In-Place Concrete):

iii. Provide any and all access equipment, hoarding, shoring, and bracing necessary to both safely complete and inspect the work.

iv. Remove the existing asphalt traffic topping and related waterproofing at

the East Parkade roof slab and dispose of off site. Identify all delaminated concrete within designated work areas and repair as specified where authorized by the Engineer and in accordance with suitable Unit Rates. Supply and install new 2 ply fully reinforced hot-applied rubberized asphalt waterproofing system and butt-jointed asphalt protection boards (including related “upturns” and “downturns”), “bonded” asphalt surfacing (2 min. 40mm layers and sloped to drains). Reinstate traffic markings to match existing layout.

v. Remove and replace mastic asphalt traffic topping and waterproofing

system at intermediate suspended slab locations authorized by the Engineer. It can be assumed that waterproofing and topping repairs will be confined to one area of the parking garage and will not be scattered throughout. Identify all delaminated concrete within designated work areas and repair as specified where authorized by the Engineer and in accordance with suitable Unit Rates.

vi. Remove and replace existing ‘catch-basin’ drain assemblies with new

assembly PROVIDED BY THE OWNER (or reuse existing assemblies if deemed appropriate) as specified below.

Guelph Parkades, Guelph SECTION 00100 Page 3 Parking Garage Repairs April 2012 INFORMATION FOR BIDDERS

If authorized, remove and replace existing drain assemblies in conjunction with surrounding waterproofing replacements. Re-locate or supply and install new 4” epoxy coated drains with hinged grates and sediment bucket assemblies as specified and directed. Carry concrete repairs not associated with drain replacements in Unit Rates.

vii. At top deck level, supply and install dowelled-in 4” by 4” concrete curb assembly along edge of slab along length of slab and waterproof in conjunction with other waterproofing as necessary to avoid water running over the slab edge, including ‘tying into’ existing curb.

Elevated Walkway (Optional):

viii. Provide any and all access equipment, hoarding, shoring, and bracing necessary to both safely complete and inspect the work.

ix. Identify all delaminated concrete on the elevated

walkway and repair as specified where authorized by the Engineer.

x. Supply and install drains as directed by the Engineer, including related

above-grade drainpipes.

Guelph Parkades, Guelph SECTION 00100 Page 4 Parking Garage Repairs April 2012 INFORMATION FOR BIDDERS

xi. Supply and install new elastomeric

waterproofing system and gland type expansion joint sealant system on all horizontal topside walkway surfaces as well as ‘downturns’ to soffit drips. Include area over the loading dock, but not step assembly closest to the street. Incorporate ‘gland’ type expansion joint seal into top of the slab at the construction joint where these sections meet.

xii. Remove and replace the railings with new

prefinished aluminum assembly that meets current Code as specified.

.3 The Owner reserves the right to enter into a

contract for all or part of the Work. 1.5 SCHEDULE

.1 Time is of the essence for this project. .2 All work shall be completed by August 30, 2012. Traffic disrupting work

must be done between July 1st and August 25th

2012.

End of Section 00100

Guelph Parkades SECTION 00800 Page 1 Parking Garage Repairs April, 2012 SUPPLEMENTARY CONDITIONS

GENERAL The Standard Construction Document CCDC4, 1994, Unit Price Contract as amended and supplemented as set forth herein after, governs the Work and applies to every trade, division and section of the Work. REVISIONS TO THE CONTRACT ARTICLES Article A-5 Payment, clause 5.1.2; replace the words “Substantial Performance of the Work” with the following: “45 days after publication of Substantial Performance of the Work and the expiry of all liens under applicable legislation”. DEFINITIONS Definition of Contract Documents; add the words “in writing” after “agreed upon”. REVISIONS TO THE GENERAL CONDITIONS GC 1.1 CONTRACT DOCUMENTS

Add the following paragraph to GC 1.1: “If the Contractor believes that there is some discrepancy, omission, error or departure from the applicable regulations in the Contract Documents or Consultant’s instructions, he shall immediately cease work on the portion affected until resolved with the Consultant and instructed to proceed.” Replace paragraph 1.1.8 with the following: “The Contractor will be provided with up to two (2) sets of the Contract Documents. Additional sets will be provided at the Contractor’s expense.”

GC 3.5 CONSTRUCTION SCHEDULE

In paragraph 3.5.1.1, replace “prior to the first application for payment” with “prior to the start of the Work”.

GC 3.10 SHOP DRAWINGS

Add the following paragraph to GC 3.10: “The Contractor shall make all required submissions of shop drawings to the Consultant in sets of three.”

Guelph Parkades SECTION 00800 Page 2 Parking Garage Repairs April, 2012 SUPPLEMENTARY CONDITIONS

GC 5.2 APPLICATIONS FOR PROGRESS PAYMENT

Add the following paragraph to GC 5.2: “The Contractor shall submit an application for each payment of an acceptable form, complete with a breakdown of the unit rates and quantities

showing work performed to date, HST, holdback and if requested, receipts or other vouchers showing his payments for labour and materials, and payments to Subcontractors and Testing Companies.

The Contractor shall submit with each application a current Certificate of Clearance from the Workplace Safety & Insurance Board and a current Certificate of Insurance. The Contractor shall submit with each application, after the first, a Statutory Declaration in a form satisfactory to the Consultant that all accounts for labour, subcontracts, products, construction, machinery and equipment and other indebtedness incurred by the Contractor to the last day of the agreed monthly payment period have been paid in full, excepting only holdbacks. The Contractor shall submit with each application, after the first, an updated work schedule.” Replace paragraph 5.2.7 with the following: “No application for payment will be approved for materials delivered to the site but not yet incorporated into the Work.”

GC 5.3 PROGRESS PAYMENT

Replace paragraph 5.3.1.3 with the following: “the Owner shall make payment on account as provided in Article A-5 of the Agreement – PAYMENT no later than thirty (30) days after receipt of the certificate for payment issued by the Consultant.”

GC 5.5 PAYMENT OF HOLDBACK UPON SUBSTANTIAL PERFORMANCE OF THE WORK

Add the following to paragraph 5.5.1: “The Contractor shall submit with the application for payment of the holdback all specified warrantees, records, maintenance manuals, a Certificate of Clearance from the Workplace Safety & Insurance Board and proof of publication of Substantial Performance.”

Guelph Parkades SECTION 00800 Page 3 Parking Garage Repairs April, 2012 SUPPLEMENTARY CONDITIONS

Add to the end of the first sentence of paragraph 5.5.4; “or 45 days following publication of substantial performance by the Contractor, whichever is the later date.”

GC 5.7 FINAL PAYMENT

Add the following to paragraph 5.7.1. “The Contractor shall submit a current Certificate of Clearance from the Workplace Safety & Insurance Board and a current Certificate of Insurance with the application for final payment.”

In paragraph 5.7.4 replace the words “5 calendar days” with “30 calendar days”.

GC 6.2 CHANGE ORDER

Add the following to paragraph 6.2.2: “The Contractor shall comply with the following procedures when submitting a change in the Contract Price and, if applicable, a change in the Contract Time: (a) The claim must set out the value of the changes (referred to in the notice of contemplated change) in sufficient detail for a proper assessment to be made including breakdowns of labour and materials for the Contractor and each Subcontractor. The valuations must indicate that additional sums for overhead and profit are included as set out herein. (b) The claim must indicate that the total value of the changes (referred to in the notice of contemplated change) is the product of the quantity of work involved and of the applicable unit price as set out in the Schedule of Contract Unit Prices or such other unit price as may be agreed upon. Unit prices include all additional sums for overhead and profit. No additional mark-ups are permitted for valuations submitted under this method. (c) The claim must set out the value of the changes (referred to in the notice of contemplated change) and be accompanied by signed time sheets, invoices and vouchers to enable a proper assessment to be made. The valuation must indicate that additional sums for overhead and profit are included as set out herein. The valuation for each and every change under methods (a) and (c) is to include additional sums for overhead and profit based of the actual cost of work as follows: Extras and Credits - Up to $10,000

Guelph Parkades SECTION 00800 Page 4 Parking Garage Repairs April, 2012 SUPPLEMENTARY CONDITIONS

For Subcontractors: 10 % for overhead and 5 % for profit on the actual cost of their work.

For Contractor: 10 % total for overhead and profit on the valuation of Subcontractor’s work.

For Contractor: 10 % for overhead and 5 % for profit on the actual cost of his work.

Extras and Credits - Over $10,000 For Subcontractors: 10 % total for overhead and profit on the actual cost of their

work. For Contractor: 10 % total for overhead and profit on the actual cost of his

work, or on the valuation of Subcontractor’s work.”

GC 6.7 QUANTITY VARIATIONS In paragraphs 6.7.2, 6.7.3 and 6.7.4 replace “15%” with “30%”. In paragraph 6.7.3 replace “115%” with “130%”.

GC 8.2 NEGOTIATION, MEDIATION AND ARBITRATION

Add the following paragraph to GC 8.2: “The Project Mediator and Arbitrator shall in no way be financially connected with the Work or the business affairs of either party.”

GC 9.1 PROTECTION OF WORK AND PROPERTY

Add the following paragraph to GC 9.1: “Should construction be closed down for any cause, the Contractor shall assume all responsibility for protecting the Work during such period.”

GC 10.2 LAWS, NOTICES, PERMITS, AND FEES

In paragraph 10.2.2 remove the words “building permit”. Add the following paragraph to 10.2: “The Contractor will apply and pay for the Building Permit, if required. The Owner will reimburse the Contractor for the Building Permit fee from the contingency allowance of the Contract.”

Guelph Parkades SECTION 00800 Page 5 Parking Garage Repairs April, 2012 SUPPLEMENTARY CONDITIONS

GC 12.3 WARRANTY

In paragraph 12.3.1 replace the words “one year” with “two years unless specified otherwise within the Contract Documents” In paragraphs 12.3.2, 12.3.3., remove the words “one year”. Add the following paragraph to GC 12.3: “.1 The Contractor shall obtain and submit all manufacturer product

warranties in excess of two years to the Owner. .2 The warranty shall include all work related to Change Orders. .3 Submit each warranty in the Contractor’s and Owner’s names and

identifying the Contractor as the warrantor/guarantor. .4 The warranty shall include all labour and materials for the replacement or

repair of the defective work and associated work as the result of faulty materials and/or workmanship.

.5 Promptly correct, at no expense to the Owner, any defects or deficiencies

which become apparent within the warranty period.”

End of Section 00800

00800ccdc4(2011).doc

Guelph Parkades SECTION 01000 Page 1 Parking Garage Repairs April, 2012 GENERAL REQUIREMENTS

PART 1: GENERAL 1.1 SCOPE OF WORK

.1 The work consists of the repair and waterproofing of the P2 cast-in-place concrete ramp at the West Parkade, and localized repair and waterproofing of the East Parkade suspended slabs, with an option to repair and waterproof the elevated walkway at the Guelph Parkades, Downtown Guelph.

.2 The Scope of Work is summarized in Section 00100, Instructions to

Bidders, and detailed in each respective section, the typical details and drawings.

1.2 MOBILIZATION / DEMOBILIZATION / SITE SAFETY / ADMINISTRATION

.1 Mobilize and demobilize all forces including labour, materials, equipment,

site office and safety hoarding / fencing necessary to carry out all of the work.

.2 Mobilization also includes all insurance, permits and schedules.

.3 This item includes all site safety and project administration.

.4 Payment for this item will be 50% upon full mobilization and the remaining

in increments equivalent to the portion of the work completed, except the final 20% that will not be released until Substantial Performance has been achieved and final clean-up is completed.

.5 Should this item exceed 10% of the total contract price, a detailed breakdown may be required prior to reviewing further the Bidder’s tender.

1.3 SUBMITTALS

.1 Provide an emergency phone number and contact for use by the Engineer or Owner outside of normal business hours.

.2 Submit to the Engineer, if requested, all submittals listed for review.

Follow-up fax submissions with originals. Make submissions two weeks prior to requiring a response unless notified otherwise and in an orderly sequence so as not to cause any delay in the Work.

.3 Prior to the start of the Work, submit the following documents for review.

.1 Insurance Certificates.

Guelph Parkades SECTION 01000 Page 2 Parking Garage Repairs April, 2012 GENERAL REQUIREMENTS

.2 Bonds.

.3 Clearance Certificate from the Workplace Safety and Insurance

Board.

.4 Construction Schedule. .4 During the course of the Work, submit the following documents for review.

.1 Shop drawings. .2 Product literature and samples.

.3 Material Safety Data Sheets (MSDS).

.4 Colour samples.

.5 Upon completion of the Work, submit the following documents for review.

.1 Statutory Declaration. .2 Clearance Certificate from the Workplace Safety and Insurance

Board.

.3 Warranty Documentation.

.4 Equipment Manuals. .6 The issuing of a Statutory Declaration declares that all Subcontractors

and Suppliers have been paid what is rightfully owed to them, such that no liens can be legally registered against the property, regardless of the wording of the Statutory Declaration.

1.4 LAYOUT

.1 Verify existing conditions on the site and dimensions shown on the drawings and report any errors or inconsistencies to Engineer before commencing work. Note all irregularities affecting the Work.

.2 Lay out work in accordance with lines and levels, as shown on the

drawings. When dimensions and levels are not shown on the drawings, determine site dimensions and levels so that all new work is installed to correct sizes.

Guelph Parkades SECTION 01000 Page 3 Parking Garage Repairs April, 2012 GENERAL REQUIREMENTS

.3 Arrange for utility locate services prior to any excavation or digging.

1.5 SITE CONDITIONS

.1 Report in writing to the Engineer, prior to commencing work, any conditions or defects encountered on the site upon which the work depends, and which may adversely affect the performance of the work. Do not commence work until such conditions or defects have been investigated and corrected.

.2 Have the manufacturers and suppliers of any materials and products to be

used on this project review the tender documents at the time of tendering and report any discrepancies or concerns to the Engineer before tender closing.

.3 Before commencing the Work, inspect all building components and property within the area of the Work. Report in writing, any damage or items not functioning. Pay to rectify all damage not reported in writing prior to the start of the work.

.4 Commencement of work implies acceptance of surfaces and conditions. No claim for damages or resulting extra work will be accepted except where such conditions cannot be determined prior to construction and brought to the Engineer’s attention prior to disturbance of conditions.

.5 Be responsible for making good, repair and restoration of existing conditions on public or private properties as part of the tendered prices. In all cases blend with existing conditions.

.6 Any item not specifically mentioned in the description of the Work or shown on the drawings but implied or required to complete the work, will be considered to be included in the total and/or unit price.

1.6 BUILDING AND BALCONY ACCESS

.1 Workers are not permitted access to the building interior without prior authorization from the Owner.

.2 Obtain access to balconies and exterior walls by means of swing stages

supplied by the Contractor. If requested, submit a swing stage rigging drawing designed and stamped by a Professional Engineer registered in the Province of Ontario.

Guelph Parkades SECTION 01000 Page 4 Parking Garage Repairs April, 2012 GENERAL REQUIREMENTS

.3 It will be the responsibility of the Owner to remove all personal effects including carpeting off balconies and away from exterior walls.

.4 Provide the Owner with a minimum of 7 days written notice to have unit owners clear personal effects from balconies and away from exterior walls.

.5 Secure balconies from the exterior to prevent access by occupants during

the Work. Method of securement shall not damage any part of the building.

1.7 PARKING

.1 Limited parking is available. Obtain the Owner’s approval for parking of the Contractor’s vehicles.

.2 Provide a minimum of 72 hours notice to the Owner for the temporary

removal of vehicles from parking areas affected by the Work.

1.8 SAFETY

.1 Comply with provisions of The Occupational Health and Safety Act and Regulations for Construction Projects, Workplace Hazardous Materials Information System (WHMIS) Regulations and Canadian Construction Safety Code. Follow the recommendations of The Construction Health & Safety Manual issued by the Construction Safety Association of Ontario.

.2 Register the project with The Ministry of Labour by providing them with

Form 1000 as required under the Occupational Health & Safety Act. Ensure all sub-trades register with The Minstry of Labour. If requested, provide the Engineer with a copy of the Registration Forms including those from the sub-contractors.

.3 Notify the The Ministry of Labour of the project by providing them with a Notice of Project as required under the Occupational Health & Safety Act. If requested, provide the Engineer with a copy of the Notice of Project.

.4 Work in conjunction with the proper safety associations operating under the authority of the Ontario Workers’ Compensation Act. Do not, in any manner, endanger the safety or unlawfully interfere with the convenience of the public. Be solely responsible for all safety related to the work at the site.

.5 Maintain on Site, readily accessible to those who may be exposed to hazardous materials, a list of all hazardous materials proposed for use together with current MSDS.

Guelph Parkades SECTION 01000 Page 5 Parking Garage Repairs April, 2012 GENERAL REQUIREMENTS

.6 Safety precautions are part of the construction techniques and processes for which the Contractor is solely responsible.

.7 Erect and maintain fencing, hoarding, barricades and signage in accordance with governing regulations and as required to ensure public safety or as requested by the Engineer.

.8 Maintain all public, fire and maintenance access to and from the building and parking garage. Where fire routes or fire exits to a building will be disrupted as a result of the work, notify the local Fire Department and implement any recommendations made by them.

.9 Burning of rubbish on site is not permitted.

.10 Conform to Construction Safety Association of Ontario`s manual on Propane in construction. Watch work area until all chance of danger has passed. Provide Site fire security when required by local building department and/or municipal fire department.

.11 The Engineer and the Owner have the right to stop the Work for reasons of safety. This in no way shall limit the Contractor’s sole responsibility for safety.

.12 The Contractor is solely responsibly for site safety and protection of property. No instructions from the Owner or the Engineer are to be taken as replacing the Contractor’s total responsibility for safety.

1.9 SCHEDULE

.1 The Contractor is solely responsible for the project schedule. Provide a suitable work schedule with sufficient detail, in the opinion of the Engineer, to facilitate tracking critical aspects of the Work towards a satisfactory completion date. Submit updated schedule with each application for payment.

.2 When progress of the Work falls behind the schedule submitted by the

Contractor, and upon the request of the Engineer, increase the forces on the site as well as hours worked each week in order to catch up to the schedule. This work shall be done without extra cost to the Owner.

.3 Do not unduly disrupt normal building and site operations during the Work. 1.10 WORKING TIMES

Guelph Parkades SECTION 01000 Page 6 Parking Garage Repairs April, 2012 GENERAL REQUIREMENTS

.1 Hours of work on the site shall be approved by the Owner. Weekend work will not be permitted without approval by the Owner.

.2 Work may only be carried out between 8:00 a.m. and 5:00 p.m., Monday to

Friday inclusive, except for statutory holidays.

.3 Seventy-two (72) hours notice is required for work to be performed outside the designated times, if permitted.

1.11 ADDITIONAL WORK

.1 Do not engage in any other work at the site without prior consent of the

Engineer and Owner. The consent may be withdrawn at any time should the additional work, in the opinion of the Engineer, jeopardize the Work.

1.12 QUALIFICATIONS OF WORKERS

.1 Provide a site superintendent who will oversee all work carried out at the site. The site superintendent shall be present during all times that work is being carried out.

.2 For operating equipment, use only thoroughly trained and experienced

operators.

.3 For installation of various items of work, or for finishing work of any trade, use only personnel thoroughly trained and experienced.

1.13 WORKMANSHIP

.1 Materials are to be applied or installed in accordance with the manufacturer’s written instructions.

.2 Should the manufacturer’s instructions differ from the specifications or

drawings, the more stringent, in the opinion of the Engineer, shall apply. 1.14 QUALITY ASSURANCE

.1 As requested by the Engineer, have material and component

manufacturers review the installation or application methods and procedures and comment in writing on their acceptability with respect to their requirements.

1.15 SUBCONTRACTORS

Guelph Parkades SECTION 01000 Page 7 Parking Garage Repairs April, 2012 GENERAL REQUIREMENTS

.1 Obtain current WSIB Clearance Certificates and Liability Insurance Certificates (minimum $1,000,000 coverage) from sub-contractors. Provide copies to the Engineer if requested.

.2 Ensure that Subcontractors examine the Drawings and Specifications

covering their work and the work of all other Subcontractors which may affect their work.

.3 Ensure that all work is carried out in compliance with the Contract

Documents and to accept responsibility for delays or costs arising from his failure to inspect or adequately co-ordinate a Subcontractor’s work.

.4 Ensure that Subcontractors and other trades cooperate with other Subcontractors whose work attaches to, or is affected by their own work, and ensure that all required adjustments are made to allow proper attachment of adjoining work.

.5 Ensure that subcontractors do not engage in any other work at the site without prior consent of the Engineer and Owner. The consent may be withdrawn at any time should the additional work, in the opinion of the Engineer, jeopardize the Work.

.6 Communications between the Contractor and the Owner shall be through the Engineer and vise versa. The Contractor shall be responsible for communications with the subcontractors.

1.16 MATERIALS STORAGE & HANDLING

.1 Do not order or store products and materials on site unless specified and samples have been approved by the Engineer.

.2 Deliver products and materials to the job site in good condition and

properly protect against damage of any kind, including vandalism.

.3 Store products and materials in a clean, dry location and in a manner to avoid damage. Where products or materials should be kept dry, cover with a waterproof tarpaulin or polyethylene sheeting in a manner that permits air circulation inside the covering.

.4 Store packaged materials in original, undamaged containers with manufacturer’s labels and seals intact. Handle and store materials in accordance with manufacturer’s and supplier’s recommendations. Prevent damage to materials during storage and handling, and replace any damaged materials.

Guelph Parkades SECTION 01000 Page 8 Parking Garage Repairs April, 2012 GENERAL REQUIREMENTS

.5 Follow precautionary statements on product labels and Material Safety Data Sheets for storage and handling before use.

.6 Store materials away from open flame or ignition sources.

.7 Remove and replace any damaged materials.

.8 Obtain the Owner’s approval of the location and extent of all on-site storage areas. Do not transport materials through the buildings.

1.17 SITE OFFICE AND STORAGE SHEDS

.1 Provide a site office and storage sheds, if required, in approved locations, and maintain as necessary. Remove them when directed or when no longer required.

.2 The site office must be kept in a clean, presentable condition and remain

that way until completion of the Work. 1.18 PERMITS

.1 The Contractor will secure and pay for all permits (including the Building Permit if required), fees and inspections required by all authorities having jurisdiction.

.2 The Owner will reimburse the Contractor for the cost of the Building Permit

only. Attach a copy of the receipt for the Building Permit fee to the invoice.

.3 Forward a copy of the Building Permit to the Engineer.

.4 Keep a copy of all permits on site.

.5 Keep a copy of the specifications and drawings on site whether a permit has been issued or not. Ensure site supervisors are familiar with the specification and drawing requirements.

.6 If a Building Permit has been issued and significant changes in the scope of work have occurred during the Work, notify and file appropriate details with the local Building Department where the Permit was issued.

1.19 STANDARDS AND CODES

.1 Work shall conform to the 2006 Ontario Building Code and all referenced standards and codes therin.

Guelph Parkades SECTION 01000 Page 9 Parking Garage Repairs April, 2012 GENERAL REQUIREMENTS

.2 All Standards, Codes, Regulations, Contract Forms, Manuals, Installation, Application and Maintenance Instructions, referred to in this specification, shall be understood to be the latest published edition including all amendments.

1.20 ALTERNATES

.1 Items specified by trade name shall be used unless an approved equal is stipulated.

.2 Requests for substitution must be submitted with sufficient notice and

accompanied by sufficient technical data and testing information to substantiate the claim that the item is equal to that specified.

.3 Approval for the use of an alternate must be received in writing from the Engineer. Such approval may be refused without reason.

.4 The costs incurred by the Engineer to review proposed alternates in subcontractors, materials, procedures, methods, etc. after contract award shall be at the Contractor’s expense. Reimburse the Owner for the Engineer’s costs at the rate of 1.5 times billing. Notice of the invoking of this clause by the Engineer is not required.

.5 Any cost savings resulting from the use of an approved equal shall be passed on to the Owner.

.6 If no trade name is specified, the materials used shall conform to the specified standards and substantiation that the standards have been met must be provided if requested by the Engineer.

1.21 PROTECTION

.1 The building and parking areas not immediately affected by the Work, will remain occupied during the Work.

.2 Take all necessary precautions to adequately protect the building and

property from damage. Protect all trees and planting areas that are to remain. Make good all damage at no extra cost.

.3 Protect, relocate and maintain existing utilities and services wherever they are encountered.

.4 Erect suitable safety barriers and warning signs as required for security and to make the site safe for pedestrians.

Guelph Parkades SECTION 01000 Page 10 Parking Garage Repairs April, 2012 GENERAL REQUIREMENTS

.5 Construct and maintain hoardings, covered ways and protective canopies as required to maintain access to buildings and public safety. Erect hoarding around all work and storage areas.

.6 Take precautions to protect openings made in existing building from entry of elements and of persons during construction and to protect existing structure and finishes from damage.

.7 Provide suitable protection to prevent rain, ground water, frost, snow or wind damage to exposed sections of the building.

.8 Adequately protect the Work at all stages, and maintain the protection until the Work is completed. Remove and replace any work and materials damaged that can not be satisfactorily repaired at no extra cost.

.9 Damaged work shall be made good by the original trade, but at the expense of those causing damage.

.10 Protect floor and roof surfaces during the Work from all construction activities by using plywood sheathing panels.

.11 Do not load any part of the structure during the Work with loads greater than the design loads. Make all temporary supports as strong as permanent supports.

1.22 EMBEDDED SERVICES

.1 Consult with the Owner regarding the location of embedded conduit and other services prior chipping, drilling, coring, cutting and hydrodemolition into concrete or masonry. Use a metal detector to identify embedded services prior to chipping, drilling, coring, cutting and hydrodemolition.

.2 Examine electrical drawings (if available from the Owner) to determine the

potential for embedded conduit prior to chipping, drilling, coring, cutting and hydrodemolition.

.3 X-ray the area of the building prior to work if requested by the Owner. Owner to pay for the cost of such service from the contract contingency allowance.

.4 Do not chip, drill, core, cut or hydrodemolish within 1 metre of any known embedded conduits or services without the approval of the Owner.

.5 The Owner shall repair or replace embedded services damaged by corrosion.

Guelph Parkades SECTION 01000 Page 11 Parking Garage Repairs April, 2012 GENERAL REQUIREMENTS

.6 The Owner shall repair or replace embedded services and other related

damaged components provided the Contractor follows the above requirements of this section otherwise the Contractor shall be responsible for such damage.

1.23 SHORING AND FALSEWORK

.1 All shoring and falsework shall be designed and approved in the field by a suitably experienced Professional Engineer registered in the Province of Ontario.

.2 Design shoring so as not to block any parking areas or traffic flow in the

parking garage as outlined in the Contract.

.3 Arrange and pay for the design and preparation of all temporary shoring and falsework drawings. The shop drawings shall bear the stamp of a Professional Engineer. Submit the shop drawings to the Engineer for approval.

.4 Install shoring and falsework in accordance with the reviewed and approved shop drawings and as requested by the Engineer.

1.24 TEMPORARY ELECTRICAL SERVICE

.1 The existing electrical service may be used as a temporary service for lighting and the operation of electrical tools and motors during construction to the extent that there is sufficient capacity. Where capacity is insufficient, provide a temporary electrical service. Arrange with the Owner for use of existing services and avoid overloading of circuits.

.2 The Owner will pay for the cost of the power supply for the existing service

only.

.3 Where existing lighting fixtures and conduits require removal to complete the Work, provide temporary lighting service. Reinstall original lighting upon completion of the Work.

1.25 TEMPORARY WATER SUPPLY

.1 The existing water service may be used as a temporary water supply for construction purposes.

.2 The Owner will pay for the cost of the water supply for the existing service

only. Where existing service is not sufficient, provide for additional service.

Guelph Parkades SECTION 01000 Page 12 Parking Garage Repairs April, 2012 GENERAL REQUIREMENTS

.3 Hoses and water containers shall be supplied by the trade performing the

work.

.4 All temporary connections must provide a proper shut-off valve and backflow preventer between each existing and temporary service.

.5 Use of hydrants or fire hoses is not permitted without written consent from the Owner.

1.26 TEMPORARY TOILETS

.1 Provide and maintain sanitary temporary toilets and washbasins for the use of workers, in compliance with local by-laws and regulations. Toilets in the buildings shall not be used by anyone engaged in the work without the Owner’s written approval.

1.27 COLD WEATHER CONSTRUCTION

.1 It is the intention of this Contract to work on a continuous basis to complete the Work before cold weather conditions are encountered. Should work be required beyond the date that ambient air temperatures are prohibititive then it may be necessary to postpone the remaining work. If it is decided by the Owner or Contractor to continue, the Work must be carried out under strict cold weather construction criteria, to be established by the Engineer, which will include but not necessarily be restricted to, the provision of temporary heat and protection. Pay for all procedures necessary to either postpone or continue the Work.

.2 Comply with cold weather contruction requirements and guidelines in

related Codes and Standards.

.3 Some materials must be applied and cured at a minimum temperature. Provide temporary protection by means of enclosures, heat and ventilation as required to maintain proper temperatures for applying and curing materials.

.4 Protect all areas of the Work from cold, wind and rain by enclosing the area with tarps and heating the enclosure.

.5 Pay all costs relating to the provision of temporary heat and ventilation used during the Work, including the cost of installation, fuel, operation, maintenance and removal of equipment. Use of direct-fired heaters (propane heaters, etc.), discharging waste products into work area are not permitted.

Guelph Parkades SECTION 01000 Page 13 Parking Garage Repairs April, 2012 GENERAL REQUIREMENTS

.6 Furnish and install temporary heat and ventilation in enclosed areas as

required to:

.1 Facilitate progress of the Work. .2 Protect the Work and products against dampness and cold.

.3 Prevent moisture condensation on surfaces.

.4 Provide ambient temperatures and humidity levels for storage,

installations and curing of materials.

.5 Provide adequate ventilation to meet health regulations for safe working environment and prevent construction fumes from entering the building.

.7 Remove snow and ice affecting any part of the work as soon as possible so

that progress is not disrupted. Calcium chloride is not permitted on new concrete surfaces.

1.28 INSPECTION

.1 Provide free access to the Engineer and other authorized personnel to all areas of the Work at all times. Facilitate swing stage access as necessary for the Engineer to inspect the Work and administer the Contract.

.2 Give minimum notice of 36 hours when any phase of the work is ready for

inspection.

.3 As and where requested by the Engineer, dismantle portions of the Work completed in his absence should subsequent inspections identify issues of non-conformance.

.4 All materials are subject to inspection by the Engineer on arrival to the site. Any materials not meeting the specifications will be rejected and must be removed from the site immediately.

.5 Allow for the costs associated with providing facilities and access for inspection of the work, excluding the cost of the Engineer’s time which will be paid for by the Owner.

.6 The cost of re-inspection due to deficient work may be the Contractor’s responsibility, including the cost of the Engineer if deemed appropriate by

Guelph Parkades SECTION 01000 Page 14 Parking Garage Repairs April, 2012 GENERAL REQUIREMENTS

the Engineer. The Engineer’s costs related to disputes may be the Contractor’s responsibility if deemed appropriate by the Engineer.

.7 Inspection of the work by the Engineer does not relieve the Contractor of their responsibility to carry out the work in accordance with the Contract Documents.

.8 Immediately notify the Engineer of a quantity of work which is appreciably greater than that foreseen, as generally defined by the Contract.

.9 Where required, provide notice to the local municipal Building Department of the readiness of the Work for inspection in accordance with Part 2 of the Ontario Building Code.

1.29 MATERIALS TESTING

.1 Arrange and pay for all material testing services as required by the Engineer. The Testing Firm, and all Field Technicians of the firm, shall be CSA certified and must be acceptable to the Engineer.

.2 All testing shall be in accordance with CSA standards.

.3 The Materials Testing Allowance will be used to pay for the testing services

only. Submit invoices from the Testing Firm as back-up with corresponding progress claims. No additional charges other than the Testing Firm’s charges will be approved. Pay for costs related to re-testing of failed materials or faulty workmanship.

.4 Provide the Engineer with at least 48 hours notice of intended backfilling, asphalt paving and concrete placement or any other operation requiring testing. The Engineer will stipulate the number and types of tests required.

.5 Provide the Testing Firm with at least 24 hours notice of the required tests. Be responsible for delays associated with the Testing Firm.

1.30 ALLOWANCES

.1 Allowances shall be used to pay for those services as specified under the

allowance description. Submit invoices as back-up with corresponding progress claims. No additional charges or mark-up will be approved.

1.31 MAKE GOOD

.1 Make good all damage resulting from work carried out under this Contract. Restore and blend to match surrounding existing conditions.

Guelph Parkades SECTION 01000 Page 15 Parking Garage Repairs April, 2012 GENERAL REQUIREMENTS

.2 Unless otherwise specified or required by codes or by-laws to meet a

certain requirement or both, make good new work to match existing work. .3 Where existing work is to be made good, the new work shall match the old

work in material, construction and finish, unless otherwise noted or specified.

1.32 MEASUREMENT FOR PAYMENT

.1 Measurements for payment shall be carried out by the Engineer in the presence of the Contractor. Work carried out by swing stages shall be measured by the Contractor and recorded on forms provided by the Engineer if requested. Provide access to allow the Engineer to verify the Contractor’s measurements.

.2 There are no minimum measurements of work.

.3 The applicable Unit Price shall be applied to the measurements of each part

of the Work.

.4 Exceedence of the estimated tender quantities without prior written approval from the Engineer is done so at the Contractor’s risk.

.5 Final measurements for payment of all concrete repairs to be carried out shall be measured and agreed upon by the Engineer and the Contractor prior to commencing patching.

.6 Costs for containing dust within work areas and providing temporary heat will be considered to be included in the Work.

.7 Measurements for localized waterproofing repair shall be taken at the area of waterproofing (including minimum overlaps) only and not the excavation or overburden replaced.

.8 Balcony slab edge repair will be considered slab edge up until the depth repaired equals the slab thickness, unless otherwise noted.

1.33 CLEAN-UP

.1 Leave work areas in a tidy, safe and secure condition at the end of each work day.

Guelph Parkades SECTION 01000 Page 16 Parking Garage Repairs April, 2012 GENERAL REQUIREMENTS

.2 .2 Supply a disposal bin for temporary storage of debris at locations authorized by the Owner. Do not locate bins on a structural slab. Remove disposal bins promptly when full and upon completion of the work.

.3 As work proceeds and at the completion of the work each day collect all debris and garbage and store in the disposal bin.

.4 Storage of debris outside of the disposal bin will not be allowed overnight.

.5 Cleaning of the area of the work shall include, but not be limited to:

.1 The removal of rubbish and other unsightly material and/or debris from the building interior, face of the building, adjacent ground areas and from the roof and balcony surfaces.

.2 The removal of dust and other debris from pipes, window frames,

sills and other areas by brushing and/or other suitable methods.

.6 As work proceeds remove surplus materials and equipment from the site.

.7 Upon completion of the work, leave areas affected in a condition as close to, or better than the original.

.8 Power wash paved surfaces to remove earth contamination resulting from construction activities.

.9 Clean out all drains, catch basins and manholes within the construction area to maintain proper drainage and immediately before final acceptance. Remove all debris, surplus material, temporary facilities, temporary connections, etc.

.10 Power wash the interior surfaces of the parking garage upon completion of the work including but not limited to floors, soffits, walls, stairwells and pipes.

.11 Clean-up shall be to the complete satisfaction of the Owner and Engineer. 1.34 WARRANTY

.1 Warranty all work including that related to Change Orders, regardless of the extent, for the period specified, from the date of substantial performance. The warranty period shall be for two (2) years unless otherwise noted.

.2 Submit each warranty in the Contractor’s and Owner’s names and

identifying the Contractor as the warrantor/guarantor.

Guelph Parkades SECTION 01000 Page 17 Parking Garage Repairs April, 2012 GENERAL REQUIREMENTS

.3 The warranty shall include all labour and materials for the replacement or

repair of the defective work and associated work as the result of faulty materials and/or workmanship.

.4 Promptly correct, at no expense to the Owner, any defects or deficiencies which become apparent within the warranty period.

End of Section 01000 01000.doc

Guelph Parkades SECTION 03500 Page 1 Parking Garage Repairs April, 2012 CONCRETE REPAIRS

PART 1: GENERAL 1.1 GENERAL

.1 The General Instructions, Section 01000, is part of this section and shall apply as if repeated here.

1.2 DESCRIPTION

.1 This section specifies the repair of reinforced concrete. 1.3 SUBMITTALS

.1 Submit concrete and shotcrete mix designs for approval prior to placement. 1.4 TESTING

.1 Concrete

.1 Arrange for testing of concrete by the Testing Firm as directed by the Engineer.

.2 Testing shall be for each day of concrete placement unless

otherwise directed by the Engineer. .3 Tests shall include slump and air content of the plastic concrete. .4 Test cylinders shall be cast for evaluating the compressive strength

potential of the concrete. Additional cylinders may be cast to evaluate the insitu compressive strength.

.2 Shotcrete

.1 Construct one test panel 500 x 500 x 100 mm gunned in the same

direction as the work for each 200 m2

of shotcrete placed. Cure test panel with wet burlap continuously moist for 7 days.

.2 Cut three 75 mm diameter cores from the panel by core drilling 7 to 9 days after shotcreting.

.3 Arrange for compressive strength testing of cores by the Testing

Firm as directed by the Engineer.

.3 Polymer Modified Mortar

Guelph Parkades SECTION 03500 Page 2 Parking Garage Repairs April, 2012 CONCRETE REPAIRS

.1 Arrange for compressive strength testing of mortar by the Testing Firm as directed by the Engineer.

1.5 QUALITY ASSURANCE

.1 Take necessary measures to control cracking in new concrete and patching materials.

.2 Should, in the opinion of the Engineer, excessive cracking occur, repair

such cracks as required by the Engineer at no additional cost to the Owner. PART 2: PRODUCTS 2.1 EQUIPMENT

.1 Pneumatic Hammers:

.1 For removal of surface concrete to the first level of reinforcing steel: Maximum 14 kg. (30 lb.) for garages. Maximum 7 kg. (15 lb.) for all other concrete.

.2 For removal of concrete at and beyond the first level of reinforcing

steel: Maximum 7 kg. (15 lb.).

.2 High Pressure Water: Hydrodemolition equipment capable of directing water at an adequate pressure to remove surface concrete and concrete at and beyond the reinforcing steel while ensuring no damage to sound concrete that is to remain.

2.2 MATERIALS

.1 The concrete may be repaired using ready mix concrete, site mixed concrete, polymer modified mortar or shotcrete. Concrete pours of 3 m3

or more shall be from ready mixed concrete. Specified compressive strength for each repair material is 35 MPa. Admixtures containing chlorides are not permitted.

.2 Ready Mixed Concrete: Class C-1 conforming to CSA A23.1, supplied by a RMCAO company, with the following properties:

Course Aggregate: 10 mm maximum Air Content: 6-9% Slump: 80 mm without superplasticizer 150 mm after addition of superplasticizer Water/Cement Ratio: 0.40 maximum

Guelph Parkades SECTION 03500 Page 3 Parking Garage Repairs April, 2012 CONCRETE REPAIRS

.1 Maximum 25% cementitious hydraulic slag is permitted by weight of

total cementing materials. Fly ash is not permitted. Parking garage concrete pours of 3 m3

or more shall include a silica fume in the mix.

.2 Water reducing agent conforming to ASTM C494 Type A. .3 Air entraining agent conforming to ASTM 260. .4 Superplasticizer conforming to ASTM C494, Type F.

Superplasticizer shall be added to the ready mix truck at the site. .5 All admixtures shall be from the same manufacturer.

.3 Site Mixed Concrete: Conforming to the requirements of ready mixed

concrete above or 10-60 Rapid Mortar (with aggregate extension) and Masterpatch 240 CR by BASF, FA-S10 by King Packaged Materials Company or SikaQuick 1000 by Sika Canada Inc.

.4 Site Mix Concrete (for Vertical Surface Repair and Pumping Overhead):

LA40 PMAC Repair Mortar and Masterpatch 240 CR by BASF, MS Self-Consolidating Concrete by King Packaged Materials Company or Sikacrete SCC 08 by Sika Canada Inc.

.5 Shotcrete Mix: Prebagged with 8% silica fume by weight of total cementing

materials and a maximum water to cementitious ratio of 0.40, MS-S6 by King Packaged Materials Company, Eucoshot by Euclid Chemical or approved equal.

.6 Polymer Modified Mortar: SikaTop 122 and 123 Plus by Sika Canada Inc.,

HBA Repair Mortar by Thoroc or Gel Patch by BASF or approved equal. .7 Mixing Water: From municipal supply; clean, potable and free from

deleterious amounts of acids, alkalis and organic matter. .8 Reinforcing Steel: Epoxy coated deformed bars with 400 MPa yield

strength conforming to CSA G30.12-M1977. Minimum size 10M. .9 Reinforcing Steel Coating: Amerlock 400 High-Solids Epoxy by Amercoat

Canada Inc. Colour to sharply contrast with steel and rust. .10 Touch-up Coating for Epoxy Coated Reinforcing Steel: Epoxy compatible

with the existing, Tammsbar by Euclid Chemical or as acceptable to the manufacturer of the reinforcing steel.

Guelph Parkades SECTION 03500 Page 4 Parking Garage Repairs April, 2012 CONCRETE REPAIRS

.11 Reinforcing Steel Supports: Plastic, precast concrete or plastic coated steel conforming to the requirements of the Reinforcing Steel Institute of Ontario.

.12 Reinforcing Steel Tie Wire: Plastic coated wire conforming to the

requirements of the Reinforcing Steel Institute of Ontario. .13 Bonding Agent: Cement/sand slurry conforming to CSA A23.1. Minimum

bond strength 1.0 MPa. .14 Formwork: Plywood and timber conforming to CSA A23.1. .15 Bearing Pad: Paired rubber laminated plastic board by Good Co. or

approved equal. .16 Paint: Exterior latex paint. Colour to match existing.

PART 3: EXECUTION 3.1 GENERAL

.1 Carry out the work in accordance with CSA A23.1. 3.2 IDENTIFICATION OF REPAIR AREAS

.1 Remove and dispose of troughing from the soffit of suspended slabs. .2 Determine the extent of delaminated concrete by hammer tap and/or chain

drag. Repair areas shall also include spalled concrete. Mark all areas with spray paint and allow for verification by the Engineer.

.3 Include in the repair those areas of sound concrete adjacent to delaminated

concrete as directed by the Engineer. 3.3 PREPARATION

.1 Remove and store surface mounted electrical conduit, light fixtures, signs, drain pipes and other items as required to carry out the work.

.2 Take precuations to determine the location of embedded services and

avoid such damage in accordance with Section 01000. .3 Erect hoarding and dust barriers at the perimeter of the work area to protect

the areas of the building not being repaired.

Guelph Parkades SECTION 03500 Page 5 Parking Garage Repairs April, 2012 CONCRETE REPAIRS

.4 Erect shoring to support the weight of the slab and construction loads. Shoring shall be designed in accordance with Section 01000.

3.4 REMOVAL OF CONCRETE

.1 Remove concrete from the repair areas and continue removal to 20 mm around both layers of bars in the top mat of reinforcing. Should unsound concrete continue beyond this point continue removal until all defective concrete is removed. Avoid damage to embedded services.

.2 Do not damage reinforcing steel that is to remain and avoid damage to

sound concrete. Do not remove reinforcing steel without the approval of the Engineer.

.3 Where top and soffit delaminations coincide, repair the area as a through-

slab repair. .4 Remove obsolete chairs, ties and services. .5 Should unsound concrete continue beyond the limits marked, obtain the

Engineer’s approval prior to proceeding with the removal in these areas. .6 Provide a 12 mm vertical edge at the perimeter of the repair areas. Do not

cut reinforcing steel. .7 Do not stockpile concrete rubble on suspended slabs. Remove rubble from

the work area on a daily basis. 3.5 SURFACE PREPARATION

.1 Sound all areas to ensure all defective concrete has been removed. Obtain Engineer’s approval and remove any defective concrete identified as above.

.2 Obtain Engineer’s approval before proceeding with surface preparation. .3 Abrasive blast clean the concrete surface, exposed reinforcing steel and

embedded hardware within the repair areas to remove all materials that may impair the bond of the new concrete including defective concrete, rust, dirt, scale, etc. to the satisfaction of the Engineer and to the reinforcing steel coating manufacturer’s specifications. Wire brushing is not permitted.

.4 Allow for inspection by the Engineer. Repair defective concrete and provide

additional abrasive blast cleaning as directed by the Engineer.

Guelph Parkades SECTION 03500 Page 6 Parking Garage Repairs April, 2012 CONCRETE REPAIRS

.5 For steel joist balconies, abrasive blast clean or grind off excessive rust from joists as directed by the Engineer. Abrasive blast concrete surfaces within the repair area.

3.6 REINFORCING STEEL

.1 Replace severely corroded reinforcing steel as directed by the Engineer. Leave sufficient lap splice length when cutting existing reinforcing in accordance with CSA A23.3-94.

.2 Install additional reinforcing steel to compensate for corroded reinforcing as

directed by the Engineer. Replace existing wire mesh where directed by the Engineer.

.3 Apply reinforcing steel coating to the exposed original bars and embedded

hardware. Locally apply coating to new reinforcing where epoxy coating is damaged or bars cut. The coating shall be free of voids, holes and cracks after curing so as to completely encapsulate the exposed portion of the bars. Coating of joists, reinforcing steel or wire mesh in steel joist balconies is not required.

.4 Provide necessary support to reinforcing steel as required to ensure correct

location of bars. .5 Secure reinforcing steel to ensure no movement of the bars prior to and

during placement of concrete or other repair material. 3.7 FORMWORK

.1 Design falsework in accordance with Section 01000. .2 Design and erect formwork in accordance with CSA S269.3. .3 Make forms tight and flush to prevent the leakage of concrete materials. .4 Apply a form release agent to ensure the forms can be removed readily and

without damage to the concrete. .5 Form expansion joints at location and size as directed by the Engineer or

indicated on the drawings. .6 Install bearing pad above ledge beams. Pads shall cover the entire

exposed surface of the ledge and extend 25 mm beyond the face. .7 Locate construction joints as directed by the Engineer.

Guelph Parkades SECTION 03500 Page 7 Parking Garage Repairs April, 2012 CONCRETE REPAIRS

.8 Do not remove shoring, falsework or formwork unless directed by the

Engineer. 3.8 CONCRETE PLACEMENT

.1 Maintain concrete substrate continuously moist for 24 hours prior to placement of concrete.

.2 Immediately prior to placing concrete remove ponding water and scrub

bonding agent into concrete surfaces. .3 Place concrete while bonding agent is still damp. .4 Consolidate concrete thoroughly around all reinforcing and embedded

hardware using vibrators and other means as necessary. .5 Slope slabs towards drains and away from columns and walls.

3.9 SHOTCRETE PLACEMENT

.1 Place shotcrete in accordance with ACI 506R-85. .2 Dampen concrete substrate and maintain continuously moist for two hours

prior to shotcreting. .3 Remove rebound prior to application of successive layers.

3.10 POLYMER MODIFIED MORTAR PLACEMENT

.1 Apply a slurry coat to the concrete surface as required by the manufacturer. .2 Mix and apply mortar in accordance with the manufacturer’s instructions.

3.11 FINISHING AND CURING

.1 Finish surfaces to the lines and levels of adjacent concrete. .2 Provide a suitable finish for surfaces to be coated with protective membrane

or sealer. Provide a wood float finish for shotcrete. .3 Cure concrete and shotcrete with wet burlap or other suitable means and

keep continuously moist 7 days or as required by the manufacturer for polymer modified mortar. Commence curing immediately after finishing.

Guelph Parkades SECTION 03500 Page 8 Parking Garage Repairs April, 2012 CONCRETE REPAIRS

Do not use curing agents on surfaces to receive a protective membrane or sealer.

3.12 MAKE GOOD

.1 Upon removal of formwork remove concrete surface irregularities, particularly at the perimeter of through-slab repair areas. Make good by patching with polymer modified mortar at no additional cost.

.2 Paint wall, soffit and through-slab repair areas to match existing. .3 Reinstate surface mounted conduit, light fixtures, signs, drain pipes and

other items removed to facilitate the work.

End of Section 03500 03500.doc

Guelph Parkades SECTION 05720 Page 1 Parking Garage Repairs April, 2012 ALUMINUM BALCONY RAILINGS

PART 1: GENERAL 1.1 GENERAL

.1 The General Instructions, Section 01000, is part of this section and shall apply as if repeated here.

1.2 DESCRIPTION

.1 This section specifies the supply and installation of prefinished aluminum railings.

1.3 WARRANTY

.1 The warranty shall be as specified in Section 01000 except that there shall be 5 year warranty on finishes against fading, chalking, discolouration, peeling, blistering, etc.

1.4 SUBMITTALS

.1 Submit available layout, configuration and colour information with tender

.

.2 Submit detailed shop drawings to the Engineer for review.

.3 Shop drawings shall indicate all materials, dimensions, core thicknesses, finishes, connections, welds, fastenings, joints, methods of anchorage, number and type of anchors, supports, reinforcement, accessories, construction methods and relationship to adjacent work. Shop drawings shall indicate all details, connections, etc., whether shown on architectural drawings or not.

.4 No fabrication shall commence until shop drawings have been reviewed.

.5 Submitted shop drawings shall confirm the design meets the relevant

code requirements and bear the signature and seal of a qualified Professional Engineer licensed to practice in Ontario.

.6 Upon request, submit as requested independent test reports related to

submitted shop drawings that confirm that all relevant Codes have been met for the railing support and construction for this specific project.

Guelph Parkades SECTION 05720 Page 2 Parking Garage Repairs April, 2012 ALUMINUM BALCONY RAILINGS

1.5 MOCK-UP

.1 Upon request, provide a mock-up installation to serve as a model with respect to performance and aesthetic requirements for the general installation.

.2 Do not proceed with the general fabrication or installation until the mock-up

has been reviewed and accepted by the Engineer and Owner. .3 Pay for all costs related to the mock-up installation whether or not it is

accepted. 1.6 TESTING

.1 Upon request, arrange for testing of the mock-up railing by the Testing Firm. Tests shall inlude all those required to ensure compliance with Clause 4.1.10.1 of the Ontario Building Code.

1.7 QUALITY ASSURANCE

.1 Carry out work in accordance with CSA Standard CAN3-S157-M83. .2 All work shall be executed by skilled and competent workers. Installers

shall have minimum of five years experience in metal railing installations and shall be approved in writing by the manufacturer for this specific project.

.3 Install railings in strict accordance with the manufacturer’s written

instructions and shop drawings.

.4 Welders shall be qualified under CSA W47.2-M1987, “Certification of Companies for Fusion Welding of Aluminum”.

.5 Welding shall conform to CSA W59.2-M1991, “Welded Aluminum

Construction”. 1.8 DESIGN CRITERIA

.1 Supply and install a complete aluminum railing system to withstand loading requirements detailed in the Ontario Building Code, the National Building Code of Canada and all applicable local regulations. Specific provisions include the following.

Guelph Parkades SECTION 05720 Page 3 Parking Garage Repairs April, 2012 ALUMINUM BALCONY RAILINGS

.1 Minimum height of 1,070 mm in accordance with OBC clause 3.3.1.17 (1)(c).

.2 Maximum size of openings at any location within the guard (railing)

of 100 mm in accordance with OBC clause 3.3.1.17(2). .3 No climbable members shall be located between 140 mm and 900

mm above the top surface of the balcony in accordance with OBC clause 3.3.1.17(5).

.4 The railing shall be designed to resist the applied loads in OBC

clause 4.1.5.15.

.2 Retain a Professional Engineer licensed to practice in Ontario who shall be responsible for the complete design and preparation of shop drawings for the aluminum railing system. The Contractor shall include all related costs for retaining an engineer and preparation of shop drawings in the contract amount.

.3 Design anchors in accordance with CSA Standard CAN3-A23.3, Appendix

‘H’. Bolts and anchors shall conform to ASTM A32.74. Expansion anchors may not be used in masonry or near edges in concrete unless authorized by the Engineer.

.4 The railing system shall be top surface mounted and supported

independent of the masonry walls. Connection to the masonry is permitted for augmentative or redundancy purposes but the railing design must not rely on this support.

.5 Design railing to be picket type as specified. Railing shall match existing

layout. .6 The railing system shall be rattle-free.

.7 Make allowances in the design for thermal expansion and contraction of

component parts without causing buckling, undue stress on fasteners and other detrimental effects.

PART 2: PRODUCTS 2.1 MATERIALS

.1 Aluminum Railing System: Assemblies and components as manufactured by Greco Aluminum Inc., LSC Railings, Railcraft Aluminum Railing

Guelph Parkades SECTION 05720 Page 4 Parking Garage Repairs April, 2012 ALUMINUM BALCONY RAILINGS

Systems, Royalguard Industries Inc. or as approved by the Engineer, provided the system complies with the specifications herein

.

.2 Aluminum components shall be in perfect condition, free from defects which may impair the strength, durability, performance or appearance. Aluminum components shall be as follows.

.1 All custom extrusions including the corrugated panels shall be

aluminum alloy 6063-T6. .2 All structural shapes (plates, angles, base shoes, channels, pipes

and tubes) shall be aluminum alloy 6351-T6 or 6061-T6. .3 Extruded rail posts shall be aluminum alloy 6005-T6. .4 Top handrail shall be extruded aluminum channel. .5 Make drilled or punched holes accurately without deformation to

components. .6 Fittings shall be of wrought aluminum material. Mitre elbows shall

be of welded construction with no weld marks visible when the fittings are installed.

.7 Internal connector sleeves shall be of extruded aluminum.

.5 Screw fasteners shall be stainless steel, AISI 300 with neoprene washers.

No other ferrous metals shall be incorporated into the railing system. Coat exposed fasteners to match existing finish colour.

.6 Post Base Plate Anchors: Epoxy-grouted stainless steel, AISI 304,

threaded rods (complete with stainless steel washers and nuts), HVA Adhesive Anchor System by Hilti Canada Limited or approved equal. Size to accommodate anticiapted loads and forces as indicated on the shop drawings.

.7 Concrete Wall Plate Anchors: Stainless steel, AISI 304, expansion anchor

(complete with stainless steel washers and nuts), Kwik Bolt II by Hilti Canada Limited or approved equal. Size to accommodate anticpated loads and forces as indicated on the shop drawings. Use epoxy-grouted anchors when closer than 100 mm to edges.

.8 Masonry Wall Plate Anchors: Stainless steel, AISI 304, threaded rods

(complete with stainless steel washers and nuts), HIT System by Hilti

Guelph Parkades SECTION 05720 Page 5 Parking Garage Repairs April, 2012 ALUMINUM BALCONY RAILINGS

Canada Limited or approved equal. Size to accommodate anticpated loads and forces as indicated on the shop drawings.

2.2 FABRICATION

.1 Check all existing conditions and dimensions on site to avoid errors. Do all cutting, fitting and making good as required.

.2 Fabricate to reviewed and accepted shop drawings.

.3 Verify all dimensions on site prior to shop fabrication.

.4 Fabricate work square, true, straight and accurate to required size, with

joints closely fitted and properly secured. Tolerances not to exceed +/- 0.5%.

.5 Cut material square and remove burrs from all exposed edges, with no

chamfer.

.6 Make exposed joints butt tight, flush and fitted to a hairline crack.

.7 Close exposed ends of handrails and posts by use of appropriate end caps.

.8 Form rail to end post connections and all changes in rail direction by mitre

elbows.

.9 Fit rail posts into matching cast aluminum base plates and/or receptacle shoes secured to the concrete with the specified anchors. Base plates or shoes shall be able to accommodate any unevenness in the slab surface. Shims are not acceptable without the approval of the Engineer.

.10 Secure railing panels to prevent any lateral or vertical movement. .11 Use self-tapping, shake-proof round headed screws on items requiring

assembly by screws. Conceal fasteners where possible. Where concealed fasteners cannot be used, countersunk flathead screws. Use welded connections for exterior metal work unless otherwise approved.

.12 Where possible, fit and shop assemble work, ready for erection in

sections as large as practical. .13 All required welding of aluminum components shall be carried out by the

manufacturer under shop conditions. Ensure exposed welds are

Guelph Parkades SECTION 05720 Page 6 Parking Garage Repairs April, 2012 ALUMINUM BALCONY RAILINGS

continuous for length of each joint. File or grind exposed welds smooth and flush. No site welding is permitted.

.14 Welds shall develop full strength of section.

2.3 FINISHES

.1 Finishes shall be fluoropolymer liquid coating, Duranar by PPG Canada Inc. (Duracron and Acrynar are not acceptable) or polyester powder coating with clear coat (urethanes and epoxy hybrids are not acceptable) electrostatically applied and baked on. Coating shall comply with AAMA 605.

.2 Colour to be selected by the Owner from the manufacturer’s standard

range. .3 Finishes to be applied by the manufacturer under shop conditions. .4 All exposed surfaces of all components shall be finished. Surfaces in

contact with concrete shall also be finished.

.5 Finishes shall be free from streaks, blisters, runs and sags. PART 3: EXECUTION 3.1 REMOVALS

.1 Secure doors to prevent people from entering the walkway prior to the removal of the existing railing. Maintain emergency access at all times.

.2 Remove the existing railing including anchorages to a minimum of 50 mm

below the slab surface. Repair resulting openings or holes as specified elsewhere or as directed by the Engineer. The Contractor shall include all related costs for removal of the existing railing and anchorages and repairing openings or holes in the lump sum item for railing replacement.

3.2 PREPARATION

.1 Deliver items for casting into concrete or building into masonry to appropriate trades together with setting templates. Notify other trades of holes, chases or other preparations required by them for properly securing or anchoring the work of this trade. Where work is to be built in by others, furnish ample time to avoid delay.

Guelph Parkades SECTION 05720 Page 7 Parking Garage Repairs April, 2012 ALUMINUM BALCONY RAILINGS

3.3 ERECTION

.1 Install railings in accordance with reviewed and accepted shop drawings.

.2 Erect work square, level, plumb, straight and true, accurately fitted, with tight joints and intersections. The railing shall be free from distortion or defects detrimental to appearance or performance. Tolerances not to exceed +/- 0.5%.

.3 Anchor railing posts to slabs and top rail to walls as shown on shop

drawings. .4 If approved by the Engineer, use coated aluminium shims as required to

ensure railings are level. Maximum total shim height shall be 25 mm. .5 Field cutting and welding will not be permitted.

.6 Do not install aluminum components requiring bituminous paint coating

until examined and approved by the Engineer. .7 Deform / burr threads on the anchors to prevent nuts from being easily

removed. 3.4 CLEAN UP

.1 As installation is completed, wash the railing thoroughly using clean water and soap; rinse with clean water.

.2 Do not use acid solution, steel wool or other corrosives or abrasives.

.3 If stain remains after washing, remove finish and restore in accordance

with manufacturer’s written directions. 3.5 MAKE GOOD

.1 Remove permanently stained, marred, dented or otherwise defective work and replace with products and materials that meet specification requirements.

.2 Touch-up coating where damaged during transport or installation. Use

material approved by the manufacturer and Engineer. Where requested replace railing components with damaged coating.

End of Section 05720

Guelph Parkades SECTION 07100 Page 1 Parking Garage Repairs April, 2012 HOT-APPLIED WATERPROOFING

PART 1: GENERAL 1.1 GENERAL

.1 The General Instructions, Section 01000, is part of this section and shall apply as if repeated here.

1.2 DESCRIPTION

.1 This section specifies the application of multi-ply, fully reinforced and mechanically fastened, hot-applied rubberized asphalt waterproofing systems.

1.3 SUBMITTALS

.1 Submit a letter from the Manufacturer certifying that the surface preparation and installations are satisfactory.

1.4 TESTING

.1 Repair all test cuts made by the Engineer. .2 Establish that the surfaces are waterproof by water testing prior to

replacement of the overburden materials.

1.5 QUALITY ASSURANCE

.1 Waterproofing materials shall be applied by a Contractor approved by the Manufacturer and the Engineer. Provide written evidence of approval from the Manufacturer as requested.

PART 2: PRODUCTS 2.1 MATERIALS

.1 Membrane: Hot-applied fabric reinforced rubberized asphalt membrane system conforming to CGSB 37-GP-50M and OPSS 1213. One of the following double application, fully reinforced systems.

• Monolithic Membrane 6125 by Hydrotech Membrane Corporation • Hot Applied Rubberized Asphalt Waterproofing 790-11 by Bakor Inc. • Tremproof 6100 by Tremco Limited

.2 Primer: Asphalt based, conforming to CGSB 37-GP-9M as recommended

by the membrane manufacturer.

Guelph Parkades SECTION 07100 Page 2 Parking Garage Repairs April, 2012 HOT-APPLIED WATERPROOFING

.3 Fabric Reinforcement: Polyester spun-bonded sheet as recommended by

the membrane manufacturer.

.4 Elastomeric Reinforcing Sheet: Heavy duty, butyl sheet as recommended by the membrane manufacturer. Thickness; 63 mils.

.5 Modified Bitumen Reinforcing Sheet: Non-woven polyester reinforcing mat coated with SBS modified bitumen conforming to CGSB 37-GP-56M, NP180 S/S or P/P Base Sheet by Bakor Inc. or approved equal by Soprema Waterproofing Inc. or Tremco Limited.

.6 Mastic Asphalt Traffic Topping: Duromastic Traffic Topping by Duron Ontario Ltd. or Florastic Hot Applied Mastic by Vulcan Asphalt & Supply Ltd.

.7 Separation Sheet: Asphalt impregnated glass fibre sheet by CanRoof Corporation Inc. or approved equal.

.8 Protection Board: Against or under asphalt paving; asphalt impreganated solid core protection board as recommended by the membrane manufacturer. Thickness, 3 mm. Against backfill or under landscaping; Extruded flexible hollow core polypropylene protection board as recommended by the membrane manufacturer. All vertical surfaces shall have polypropalene boards. Vertical surfaces shall have an additional layer of asphalt board adjacent to asphalt paving materials.

.9 Backer Rod: Heat resistant; Cera-Rod by W.R. Meadows of Canada Limited or approved equal.

.10 Fastening Bar: 3 mm x 38 mm aluminum with pre-drilled holes at 150 mm o.c. secured with compatible expansion pin bolts.

.11 Hot Pour Sealant: Sealtight Hi-Spec by W.R. Meadows of Canada Ltd. or approved equal.

2.2 EQUIPMENT

.1 Heat the membrane material in a double-jacketed oil bath kettle with agitator. The kettle shall have calibrated thermometers for the oil and membrane.

PART 3: EXECUTION 3.1 PREPARATION

Guelph Parkades SECTION 07100 Page 3 Parking Garage Repairs April, 2012 HOT-APPLIED WATERPROOFING

.1 Remove existing waterproofing materials from surfaces to receive new waterproofing. Avoid damage to concrete.

.2 Repair the concrete substrate as directed elsewhere. .3 Prepare terminations at existing waterproofing that is to remain to ensure a

minimum 150 mm overlap. Remove the protection board from the existing waterpoofing for a distance of 150 mm, exposing the underlying existing membrane. Ensure the underlying membrane is clean and dry. Saw cut reglets into the concrete, 3 mm wide, at the edge of the new waterproofing.

Where the existing waterproofing is not bonded, prepare both the waterproofing and the concrete below as necessary to “sandwich” the existing between two layers of new waterproofing.

.4 At up-turns provide a saw cut reglet on the vertical surface for termination of

the top of the waterproofing. Ensure the reglet is free of dust and debris. .5 Abrasive blast clean surfaces to receive new waterproofing as necessary to

remove all materials that may hinder the adhesion of the new membrane. .6 Provide protection to adjacent surfaces.

3.2 EXAMINATION

.1 Examine all surfaces for suitability of the application of the waterproofing. Report any defects to the Engineer. Commencement of work implies acceptance of conditions by the Contractor.

.2 Have the membrane manufacturer’s representative examine the

preparation and verify the acceptability of the existing conditions and installations, specifically with respect to the substrate.

.3 Have the manuafacturer comment on the compatibility of the membrane

with the existing waterproofing that is to remain. .4 Have the manufacturer confirm that the joints in the protection board will not

result in cracking of the asphalt pavement when paving directly over top. 3.3 APPLICATION

1 Apply primer to the concrete surfaces to receive membrane and both sides of the elastomeric sheets and fastening bars at a rate recommended by the membrane manufacturer and allow to thoroughly dry.

Guelph Parkades SECTION 07100 Page 4 Parking Garage Repairs April, 2012 HOT-APPLIED WATERPROOFING

2 Pre-treat construction joints and cracks where directed by the Engineer by the application of 2 mm layer of membrane and embedding a 300 mm wide modified bitumen base sheet, torched in place.

3 Apply one layer of membrane to a minimum thickness of 3 mm. Place

fabric reinforcing in hot membrane. Lap adjacent sheets 50 mm. Apply a second layer of membrane to a minimum thickness of 3 mm over the fabric reinforcing. Apply additional layers of membrane over rough areas of concrete prior to the general waterproofing to ensure a minimum thickness of 6 mm. On sloped ramps the membrane shall consist of a single 3 mm layer with a separation sheet installed over top. Extend reinforced waterproofing at up-turns and down-turns as indicated on the details.

4 Reinforce the membrane at up-turns and down-turns with a continuous (no

laps on the vertical surface) modified bitumen base sheet as indicated on the details. Remove surface sand from the sheets. Lightly torch sheets to further embed sand immediately before all applications of hot membrane material. Apply modified bitumen while sheets are still warm and malable and embed them immediately following the application of the first layer of hot membrane to ensure complete adhesion of the sheet. Lap ends of adjacent sheets 300 mm.

Mechanically fasten the top of the base sheet with a metal fastening bar. Terminate waterproofing in the reglet above the fastening bar on up-turns and 150 mm below the fastening bar on down-turns.

5 At junctions between the new membrane and the existing waterproofing,

overlap the waterproofing 150 mm. Prior to application of the new membrane, heat the edge of the existing waterproofing to soften it. Allow material to cool and lay a polethylene separation sheet over the membrane prior to installation of protection boards.

6 Reinforce the membrane at expansion joints with an elastomeric sheet fully

adhered to the membrane as indicated on the details. Embed the sheet immediately following the application of the first layer of hot membrane to ensure complete adhesion of the sheet. Lap ends of adjacent sheets 300 mm. As and where directed by the Engineer, provide an external loop on the elastomeric sheet utilizing a backer rod.

Mechanically fasten the elastomeric sheet with a metal fastening bar as indicated on the details. Where expansion joints are located adjacent to up-turns terminate the waterproofing in the reglet above the fastening bar.

7 Reinforce the membrane at drains with an elastomeric sheet. The sheet

shall be minimum 450 mm square with holes for the clamping ring bolts.

Guelph Parkades SECTION 07100 Page 5 Parking Garage Repairs April, 2012 HOT-APPLIED WATERPROOFING

Embed the sheet immediately following the application of the first layer of hot membrane to ensure complete adhesion of the sheet. Place the sheet directly over the drain such that the clamping ring bolts pass through the holes in the sheet. Cut a 100 mm diameter hole in the elastomeric sheet upon application of the second layer of hot membrane. Secure clamping ring to drain body.

8 Apply protection boards immediately after initial cooling of the

waterproofing, but while still warm. Lap adjacent boards 25 mm.

3.4 MASTIC ASPHALT WATERPROOFING

.1 Apply one layer of membrane to a minimum thickness of 3 mm. Place a separation sheet installed over top and lap adjacent sheets 50 mm. Extend waterproofing 150 mm at up-turns and down-turns.

.2 Reinforce the membrane at expansion joints with an 300 mm wide

elastomeric sheet fully adhered to the membrane. Embed the sheet immediately following the application of the first layer of hot membrane to ensure complete adhesion of the sheet. Loop the sheet into the expansion joint to a minimum depth of 25 mm. Lap ends of adjacent sheets 300 mm.

Mechanically fasten the elastomeric sheet to adjacent walls and columns with a metal fastening bar. Apply a second layer of membrane to form a double reinforced layer of waterproofing. Fill the expansion joint loop with membrane material and completely cover the metal fastening bar.

.3 Prior to general application of the mastic asphalt traffic topping form mastic

asphalt cants at columns and walls. Build cants as necessary to slope the surface away and ensure the membrane on the columns and walls is completely covered after a general traffic topping installation.

.4 Apply mastic asphalt traffic topping over top of waterproofing to a thickness

of 20 mm. Dimple mastic surface on interior ramps for traction purposes. Form joints in the mastic asphalt at expansion joints and other locations as directed by the Engineer. Fill joints with hot pour sealant.

3.5 WATER TESTS

.1 Perform water tests as and where directed by the Engineer. .2 Pond water to a 50 mm depth for a minimum period of 24 hours.

Guelph Parkades SECTION 07100 Page 6 Parking Garage Repairs April, 2012 HOT-APPLIED WATERPROOFING

.3 Notify the Engineer of the start of the test and arrange for a review of the test in progress. Inspect the walls and soffit immediately below the test areas.

.4 Repair defects in the waterproofing to the satisfaction of the Engineer.

Repeat water test until the area is determined to be in a watertight condition.

.5 Remove water at the end of the test.

3.6 PROTECTION

.1 Cover the protection board within 48 hours with the overburden materials as

specified elsewhere.

End of Section 07100 07100.doc

Guelph Parkades SECTION 07150 Page 1 Parking Garage Repairs April, 2012 ASPHALTIC TRAFFIC DECK WATERPROOFING

PART 1: GENERAL 1.1 GENERAL

.1 The General Instructions, Section 01000, is part of this section and shall apply as if repeated here.

1.2 DESCRIPTION

.1 This section specifies the application of a hot-applied rubberized asphalt waterproofing and bonded asphalt traffic topping system.

1.3 SUBMITTALS

.1 Submit a letter from the Manufacturer certifying that the surface preparation and general application procedures are satisfactory.

1.4 TESTING

.1 Repair all test cuts made by the Engineer.

1.5 QUALITY ASSURANCE

.1 Waterproofing materials shall be applied by a Contractor approved by the Manufacturer. Provide written evidence of approval from the Manufacturer as requested.

PART 2: PRODUCTS 2.1 MATERIALS

.1 Traffic Deck Waterproofing System: Multiguard II by Multiseal, Bondeck Traffic Deck System by Bravo Cement Contracting Inc. or Permaphalt III by Permaquik Corporation. The system shall consist of individual components from the same manufacturer (where possible) and compatible with one another.

.2 Membrane: Hot-applied rubberized asphalt membrane conforming to

CGSB 37-GP-50M. .3 Primer: Asphalt based, conforming to CGSB 37-GP-9M as recommended

by the membrane manufacturer. .4 Fabric Reinforcement: Polyester spun-bonded sheet as recommended by

the membrane manufacturer.

Guelph Parkades SECTION 07150 Page 2 Parking Garage Repairs April, 2012 ASPHALTIC TRAFFIC DECK WATERPROOFING

.5 Elastomeric Reinforcement: Heavy duty, 450 mm wide butyl sheet as

recommended by the membrane manufacturer. Thickness; 63 mils. .6 Modified Bitumen Reinforcement: Non-woven polyester reinforcing mat

coated with SBS modified bitumen conforming to CGSB 37-GP-56M, NP180 P/P Base Sheet by Monsey Bakor or approved torch-applied equal by Soprema Waterproofing Inc.

.7 Backer Rod: Heat resistant; Cera-Rod by W.R. Meadows of Canada

Limited or approved equal. .8 Fastening Bar: 3 mm x 38 mm aluminum with pre-drilled holes at 150 mm

o.c. with compatible fasteners. .9 Base Sheet: Asphalt impregnated glass ply, PQ 2178 by Permaquik

Corporation or approved equal. .10 Protection Board: Polypropalene boards at vertical surfaces where

directed. .11 Traffic Topping: Hot laid, high-stability HL3 asphaltic concrete mix as

approved by the waterproofing manufacturer. .12 Hot Pour Sealant: Sealtight Hi-Spec by W.R. Meadows of Canada Ltd. or

approved equal.

.13 Traffic Marking Paint: White or yellow paint conforming to CGSB 1-GP-74M. Colour to be selected by Owner.

2.2 EQUIPMENT

.1 Heat the membrane material in a double-jacketed oil bath kettle with agitator. The kettle shall have calibrated thermometers for the oil and membrane.

.2 Asphalt spreader shall have rubber tire wheels that to not cause damage to

the waterproofing membrane.

PART 3: EXECUTION 3.1 PREPARATION

.1 Remove existing waterproofing materials from surfaces to receive new waterproofing. Avoid damage to concrete.

Guelph Parkades SECTION 07150 Page 3 Parking Garage Repairs April, 2012 ASPHALTIC TRAFFIC DECK WATERPROOFING

.2 Repair the concrete substrate as directed elsewhere. .3 Prepare terminations at existing waterproofing that is to remain to ensure a

minimum 150 mm overlap. Ensure the membrane is clean and dry. Saw cut reglets into the concrete, 3 mm wide, at the edge of the new waterproofing.

.4 Abrasive blast clean or blast-track surfaces to receive new waterproofing as

necessary to remove all materials that may hinder the adhesion of the new membrane.

.5 Provide protection to adjacent surfaces. .6 Set drains to the correct elevation to accommodate minimum required

asphalt thicknesses.

3.2 EXAMINATION

.1 Examine all surfaces for suitability of the application of the waterproofing. Report any defects to the Engineer. Commencement of work implies acceptance of conditions.

.2 Have the Manufacturer examine the preparation and verify the acceptability

of the existing conditions, specifically with respect to the substrate. .3 Have the Manuafacturer comment on the compatibility of the membrane

with the existing waterproofing that is to remain. 3.3 MEMBRANE

.1 Apply waterproofing only when the ambient temperature is above 0o

C.

.2 Apply primer to the concrete surfaces to receive membrane and both sides of the elastomeric sheets at a rate of 0.1 to 0.2 litres per 1.0 m2

and allow to thoroughly dry.

.3 Apply one layer of membrane to a minimum thickness of 2 mm and an average thickness of 3 mm. Extend the membrane 150 mm up vertical surfaces. Apply additional layers of membrane over rough areas of concrete prior to the general waterproofing to ensure a minimum thickness of 2 mm.

Guelph Parkades SECTION 07150 Page 4 Parking Garage Repairs April, 2012 ASPHALTIC TRAFFIC DECK WATERPROOFING

.4 Pre-treat construction joints and cracks where directed by the Engineer by a double application of membrane (each layer at least 1.5 mm) reinforced with a polyester sheet.

.5 At junctions between the new membrane and the existing waterproofing,

overlap the waterproofing 150 mm. Prior to application of the new membrane, heat the edge of the existing waterproofing to soften it.

.6 At upturns, apply a double application of membrane (each layer at least 1.5

mm) reinforced with a modified bitumen base sheet torched in place. Embed the base sheet immediately following the application of the first layer of hot membrane to ensure complete adhesion of the sheet. The base sheet shall extend 150 mm onto the deck and 100 mm up walls and columns. Lap ends of adjacent sheets 300 mm. Mechanically fasten the top of the base sheet with a metal fastening bar. Completely cover the metal fastening bar with a layer of membrane.

.7 Where directed by the Engineer install protection boards over the

membrane on vertical surfaces above grade. .8 At downturns, apply a double application of membrane (each layer at least

1.5 mm) reinforced with a modified bitumen base sheet torched in place. Embed the base sheet immediately following the application of the first layer of hot membrane to ensure complete adhesion of the sheet. The base sheet shall extend 150 mm onto the deck and 150 mm below the underside of the slab. Lap ends of adjacent sheets 300 mm. Mechanically fasten the top and bottom of the base sheet with a metal fastening bar. Completely cover the metal fastening bar with a layer of membrane.

.9 At expansion joints apply a double application of membrane (each layer at

least 1.5 mm) reinforced with an elastomeric sheet fully adhered to the membrane. Embed the sheet immediately following the application of the first layer of hot membrane to ensure complete adhesion of the sheet. Lap ends of adjacent sheets 300 mm. As and where directed by the Engineer, provide an external loop on the elastomeric sheet utilizing a backer rod.

.10 At drains apply a double application of membrane (each layer at least 1.5

mm) reinforced with an polyester sheet. The sheet shall be minimum 450 mm square with holes for the clamping ring bolts. Embed the sheet immediately following the application of the first layer of hot membrane to ensure complete adhesion of the sheet. Place the sheet directly over the drain such that the clamping ring bolts pass through the holes in the sheet. Cut a 100 mm diameter hole in the sheet upon application of the second layer of hot membrane. Secure clamping ring to drain body.

Guelph Parkades SECTION 07150 Page 5 Parking Garage Repairs April, 2012 ASPHALTIC TRAFFIC DECK WATERPROOFING

.11 Lay base sheet over entire area of membrane while it is still warm. Butt-joint adjacent sheets.

.12 Protect the membrane until application of the traffic topping.

3.4 TRAFFIC TOPPING

.1 Apply the asphalt traffic topping only when the ambient temperature is at

least 5o

C.

.2 Apply the asphaltic traffic topping to a final minimum compacted thickness of 80 mm (applied in 2 lifts) using a self-propelled, mechanical spreader. The asphalt shall be bonded to the underlying membrane. Cove the asphalt at walls and columns to cover the waterproofing. With the approval of the Engineer increase the asphalt thickness where necessary to provide 2% slope to drains and away from walls and columns. Allow for at least 20% additional asphalt material for “padding”.

.3 Where heating cables are to be installed, apply a 40 mm scratch course of

asphalt. Install heating cables as specified elsewhere. Apply a second 20 mm layer of asphalt by hand. Apply a final 25 mm layer of asphalt. Take care not to damage the heating cables during this work.

.4 Compact each layer of the asphalt with a smooth wheeled roller. In areas

not accessible to rolling equipment, use hand tampers or vibrating plate compaction equipment. Roller marks are not permitted.

.5 Form joints in the asphalt surface at expansion joints with steel angles in

accordance with detail SK7-05. Form 20 mm wides isolation joints between asphalt and building walls. Fill joints with hot pour sealant.

.6 Protect asphalt until acceptable for vehicular traffic (minimum 28 hours).

3.5 TRAFFIC MARKINGS

.1 Reinstate traffic markings to match original layout unless specified otherwise.

End of Section 07150

Guelph Parkades SECTION 07150 Page 6 Parking Garage Repairs April, 2012 ASPHALTIC TRAFFIC DECK WATERPROOFING

07150.doc

Guelph Parkades SECTION 07570 Page 1 Parking Garage Repairs April, 2012 ELASTOMERIC WATERPROOFING

PART 1: GENERAL 1.1 GENERAL

.1 The General Instructions, Section 01000, is part of this section and shall apply as if repeated here.

1.2 DESCRIPTION

.1 This section specifies the application of elastomeric waterproofing. 1.3 SUBMITTALS

.1 Submit a letter from the manufacturer certifying that the surface preparation is satisfactory.

1.4 TESTING

.1 Repair all test cuts made by the Engineer. .2 As directed by the engineer, establish that the surfaces are waterproof by

water testing.

1.5 QUALITY ASSURANCE

.1 Waterproofing materials shall be applied by a Contractor approved by the manufacturer. Provide written evidence of approval from the manufacturer as requested.

PART 2: PRODUCTS 2.1 MATERIALS

.1 Garage Waterproofing: Polyurethane membrane and wear course system conforming to ASTM C-957. Auto-Gard II by Neogard, Duodeck by Duochem Inc. or Vulkem 350/950 by Tremco. Colour to be selected by the Owner from the manufacturer’s standard range.

Auto-Gard II shall consist of base coat (20 mils dry), wear course (20 mils

dry in two applications with aggregate broadcast between) and top course in drive aisle (12 mils dry).

Duodeck shall consist of 390 membrane (20 mils dry), 391 wear course with

aggregate broadcast (25 mils dry, 36 mils at turns and ramps) and for exterior applications 394 top coat (5 mils dry).

Guelph Parkades SECTION 07570 Page 2 Parking Garage Repairs April, 2012 ELASTOMERIC WATERPROOFING

Vulkem shall consist of 350NF membrane (25 mils dry), 950 wear course (12 mils dry with aggregate broadcast, 18 mils at drive aisles and ramps) and 950 top coat (12 mils dry). Use 951 in lieu of 950 for exposed locations.

.2 Balcony and Podium Deck Waterproofing: Polyurethane membrane and

wear course system conforming to ASTM C-957. Peda-Gard II by Neogard, Duodeck by Duochem Inc., Sonoguard by BASF or Vulkem 350/351 by Tremco. Colour to be selected by the Owner.

Peda-gard II shall consist of base coat (18 mils dry) and wear course (16

mils dry in two applications with aggregate broadcast between). Duodeck shall consist of 390 membrane (25 mils dry), 391 wear course (18

mils dry with aggregate broadcast) and 394 top coat (5 mils dry). Sonoguard shall consist of base coat (25 mils wet, 21 mils dry) and top coat (25 mils wet, 19 mils dry with aggregate broadcast). Vulkem shall consist of 350NF membrane (25 mils dry), 351 wear course (10 mils dry with aggregate broadcast).

.3 Cant Bead Sealant: Urethane sealant, Neogard 70991 by Neogard,

Sonolastic NP 1 or NP 2 by BASF, Vulkem 116 by Tremco or as approved by the membrane manufacturer.

.4 Crack Repair Sealant: Urethane sealant, THC 901 by Tremco Ltd.,

Sikaflex 1CSL by Sika Canada Inc. and Sonolastic NP 2 and SL 2 by BASF.

PART 3: EXECUTION 3.1 PREPARATION

.1 Repair the concrete substrate as directed elsewhere. .2 Abrasive blast clean concrete surface to receive waterproofing including the

bottom 150 mm of columns and walls. .3 Sound the slab surface by chain dragging or other suitable means. Mark

and repair any unsound concrete as directed elsewhere. .4 Seal openings around pipes, conduits, etc. with non-shrink grout or polymer

modified mortar.

Guelph Parkades SECTION 07570 Page 3 Parking Garage Repairs April, 2012 ELASTOMERIC WATERPROOFING

.5 Where specified construct concrete curbs around mechanical equipment

and services. .6 Install expansion joint seals as specified elsewhere. .7 Apply a bead of sealant at all up-turns as required by the manufacturer. .8 Repair cracks (greater 1.5 mm wide) by routing out to 6 mm wide x 6 mm

deep as directed by the waterproofing manufacturer. Install suitable bond breaker and fill with sealant.

.9 Allow concrete repair materials to sufficiently cure prior to application of the

waterproofing materials. Do not apply waterproofing unless ambient and substrate temperature is at least 4o

C.

.10 Mask walls, columns and other surfaces to ensure clean finished edge to the waterproofing.

3.2 EXAMINATION

.1 Examine all surfaces for suitability of the application of the waterproofing. Report any defects to the Engineer. Commencement of work implies acceptance of conditions.

.2 Have the manufacturer examine the preparation and verify the acceptability

of the existing conditions, specifically with respect to the substrate. .3 Have the manuafacturer comment on the compatibility of the membrane

with any existing waterproofing that is to remain. 3.3 APPLICATION

.1 Blow surfaces clean with oil-free compressed air immediately prior to waterproofing.

.2 Apply primer to the concrete surfaces to receive membrane as required by

the manufacturer. .3 When tieing into existing waterproofing that is to remain, prepare surface

and apply primer as required by the manufacturer to provide a minimum overlap of 100 mm.

Guelph Parkades SECTION 07570 Page 4 Parking Garage Repairs April, 2012 ELASTOMERIC WATERPROOFING

.4 Pre-treat construction joints and cracks (up to 1.5 mm wide) with the application of a stretch coat of membrane (30 mils dry thickness) along the line of the crack or joint 100 mm wide.

.5 Apply one coat of membrane base coat over the entire surface. Extend

waterproofing 150 mm up walls, columns and penetrations. Tie in the membrane at drains.

.6 On balconies, extend the waterproofing down the outside vertical face and

into the drip slot on the underside. .7 Extend waterproofing minimum 25 mm onto elastomeric expansion joint

block-outs. .8 Allow the membrane to dry and apply wear course coat while broadcasting

in the aggregate and backroll as specified by the manufacturer. Remove excess aggregate.

.9 Apply an additional wear course layer in high traffic areas as specified. .10 Apply top coat as specified.

3.4 PROTECTION

.1 Protect the waterproofing during each stage of the application until suitable

for vehicular and pedestrian traffic.

3.5 TRAFFIC MARKINGS .1 Reinstate traffic markings to match original layout unless otherwise

specified.

3.6 MAKE GOOD

.1 Remove masking.

End of Section 07570 07570.doc

Guelph Parkades SECTION 07950 Page 1 Parking Garage Repairs April, 2012 EXPANSION JOINT SEALS

PART 1: GENERAL 1.1 GENERAL

.1 The General Instructions, Section 01000, is part of this section and shall apply as if repeated here.

1.2 DESCRIPTION

.1 This section specifies the installation of expansion joint seals for parking garage floor slabs.

1.3 SUBMITTALS

.1 Submit a letter from the manufacturer certifying that the gland size is suitable for the joint width and that the surface preparation is satisfactory.

1.4 TESTING

.1 Water test the repaired expansion joints prior to leaving the site. Repair areas not watertight as directed by the Engineer and the manufacturer.

1.5 QUALITY ASSURANCE

.1 Expansion joint materials shall be applied by a Contractor approved by the manufacturer. Provide written evidence of approval from the manufacturer as requested.

PART 2: PRODUCTS 2.1 MATERIALS

.1 Expansion Joint Seal: Neoprene gland with elastomeric concrete nosing. Permacrete WF Expansion Joint System by Permaquik Corporation, WaboCrete Membrane by Watson Bowman Acme (BASF) or Polycrete/WM-Series System by Erie Metal Specialties. Gland size to suit site conditions.

.2 Fastening Bar: 3 mm x 38 mm aluminum with pre-drilled holes complete

with compatible fasteners. PART 3: EXECUTION 3.1 FABRICATION

Guelph Parkades SECTION 07950 Page 2 Parking Garage Repairs April, 2012 EXPANSION JOINT SEALS

.1 Site measure expansion joint. Joint selant to extend 150 mm up walls. .2 Fabricate gland to suit site measurements and provide one conitnuous

piece where practical. Factory weld all joints. .3 Upon delivery to the job site allow the gland to relax. Clean gland surfaces

as required by the manufacturer. 3.2 PREPARATION

.1 Create a block-out (100 mm wide x 25 mm deep) on either side of the expansion joint by saw cutting and concrete removal. At joint terminations at columns or walls continue the block-out 150 mm up the vertical surface.

.2 Cut out slab edges as necessary to facilitate gland installation. .3 Remove existing expansion sealant. .4 Abrasive blast clean the concrete surfaces forming the block-out to ensure

proper adhesion of the elastomeric concrete. Blow surfaces clean. .5 Mask the edges of the block-out to ensure a clean finished product.

3.3 INSTALLATION

.1 Position the gland in joint block-out. Apply primer or tack coat as required by the manufacturer.

.2 Mix and apply elastomeric concrete in accordance with the manufacturer’s

instructions. Adhere the gland in position and fill the block-out. .3 Build up the slab level with the elastomeric concrete to provide a slope

away from either side of the joint. .4 Where expansion joints are parallel to walls or columns mechanically fasten

the adjacent gland flap to the wall using a continuous fastening bar secured at 450 mm spacing. Seal the fasteners and the top of the flap using a bituminous sealant.

.5 Protect the installation until suitable for vehicular traffic.

3.4 MAKE GOOD

.1 Remove masking.

Guelph Parkades SECTION 07950 Page 3 Parking Garage Repairs April, 2012 EXPANSION JOINT SEALS

.2 Paint the underside of the concrete slab along the length of the joint for a width of 600 mm.

End of Section 07950 07950.doc

Guelph Parkades SECTION 15420 Page 1 Parking Garage Repairs April, 2012 GARAGE ROOF DRAINS

PART 1: GENERAL 1.1 GENERAL

.1 The General Instructions, Section 01000, is part of this section and shall apply as if repeated here.

1.2 DESCRIPTION

.1 This section specifies the supply and installation of garage roof drains and related drain pipe.

1.3 SUBMITTALS

.1 Submit to the Engineer for review, shop drawings of each type of drain proposed. Do not commence installation until shop drawings have been accepted.

1.4 QUALITY ASSURANCE

.1 Work shall comply with applicable plumbing codes and standards.

1.5 PRODUCT DELIVERY, STORAGE AND HANDLING .1 Protect products during handling and storage to prevent rusting, staining,

abrasion of finish coatings and other damage. .2 Replace products deemed unacceptable by the Engineer.

PART 2: PRODUCTS 2.1 MATERIALS

.1 Drain for Asphalt and Concrete Paved Areas: Heavy duty, factory epoxy coated cast iron, bi-level drain with waterproofing clamp ring by Ancon, Watts Drainage or Zurn Industries Limited, complete with sediment bucket and hinged grate. Minimum 250 x 250 mm. All related componenets to be factory epoxy coated.

.2 Above-Grade Drain Pipe: Cast iron, minimum 100 mm diameter, complete

with a clean-out for each drain. .3 Below Grade Drain Pipe: Poly-vinyl chloride (PVC), minimum 100 mm

diameter.

Guelph Parkades SECTION 15420 Page 2 Parking Garage Repairs April, 2012 GARAGE ROOF DRAINS

.4 Pipe Hangers: Corrosion resistance steel such as galvanized or epoxy coated.

.5 Non-shrink Grout: SikaGrout 212 by Sika Canada Inc. or approved equal. .6 Heat-Tracing: Type EC Cable by Pyrotenax or approved equal.

PART 3: EXECUTION 3.1 PREPARATION

.1 Consult with the Engineer to determine locations for new drains. .2 Carry out a level survey to ensure the grades slope away from curbs and

towards drains. .3 Determine the interior building and/or garage conditions below each drain

location. .4 Remove existing drains and drain pipe as directed by the Engineer. Repair

existing drain openings not to be reused as specified elsewhere. 3.2 DRAIN INSTALLATION

.1 Install new roof drains at locations designated by the Engineer. .2 Do not install drains through beams or drop panels without prior approval of

the Engineer. .3 Use a core drill to cut drain openings. Cut holes no larger than required to

install drain. Avoid damage to existing reinforcing by using a metal detector. Take precuations to determine the location of embedded services and avoid such damage in accordance with Section 01000.

.4 Set drain at the appropriate level to prevent water from ponding on the roof

slab. .5 Use collars to raise drain grate only as authorized by the Engineer. Drains

grates are to be as low as possible to faciliate required slopes of surfacing. .6 Provide a clean-out with each drain installed. .7 Completely repair the space between the drain and core hole with non-

shrink grout.

Guelph Parkades SECTION 15420 Page 3 Parking Garage Repairs April, 2012 GARAGE ROOF DRAINS

3.3 ABOVE-GRADE DRAIN PIPE

.1 Install drain pipe and connect to existing storm sewer system. Ensure drain pipe has a minimum 2% slope.

.2 Supply and install all necessary elbows, T’s, Y’s, clamps and hangers, etc. .3 Install pipe hangers at appropriate spacing using suitable expansion

anchors. .4 If necessary, extend the drain pipe to the lower parking levels by core

drilling through the garage floor slabs. Repair the slabs with non-shrink grout and waterproofing, if present, to match existing.

.5 If specified, install heat tracing complete with thermostatic controls and

pipe-wrap insulation. Electric supply to within 1 metre of the piping by others.

3.4 BELOW-GRADE DRAIN PIPE

.1 Install drain pipe below slab on grade only where suitable connection cannot be made to the existing storm sewer system with above-grade drain pipe and where approved by the Engineer.

.2 Determine the location of new below-grade drain pipe, saw cut the slab on

grade and remove the concrete to the full depth of the slab. .3 Excavate subgrade material as necessary to install pipe. .4 Lay pipe to ensure positive drainage and connect to storm sewer system. .5 Backfill with existing material and lightly compact. .6 Reconstruct slab on grade using Class C-2 ready mixed concrete.

3.5 PROTECTION

.1 Protect drains and drain pipes until acceptance by the Engineer and Owner.

End of Section 15420 15420.doc

Guelph Parkades SECTION 15430 Page 1 Parking Garage Repairs April, 2012 GARAGE FLOOR DRAINS

PART 1: GENERAL 1.1 GENERAL

.1 The General Instructions, Section 01000, is part of this section and shall apply as if repeated here.

1.2 DESCRIPTION

.1 This section specifies the supply and installation of garage floor drains and related drain pipe.

1.3 SUBMITTALS

.1 Submit to the Engineer for review, shop drawings of each type of drain proposed. Do not commence installation until shop drawings have been accepted.

1.4 QUALITY ASSURANCE

.1 Work shall comply with applicable plumbing codes and standards.

1.5 PRODUCT DELIVERY, STORAGE AND HANDLING .1 Protect products during handling and storage to prevent rusting, staining,

abrasion of finish coatings and other damage. .2 Replace products deemed unacceptable by the Engineer.

PART 2: PRODUCTS 2.1 MATERIALS

.1 Drains: Medium duty, epoxy-coated cast iron drain with waterproofing clamp ring by Ancon, Watts Drainage or Zurn Industries Limited, complete with sediment bucket and hinged grate. Minimum 200 x 200 mm.

.2 Above-Grade Drain Pipe: Cast iron, minimum 100 mm diameter, complete

with a clean-out for each drain. .3 Below Grade Drain Pipe: Poly-vinyl chloride (PVC), minimum 100 mm

diameter.

.4 Non-shrink Grout: SikaGrout 212 by Sika Canada Inc. or approved equal.

Guelph Parkades SECTION 15430 Page 2 Parking Garage Repairs April, 2012 GARAGE FLOOR DRAINS

PART 3: EXECUTION 3.1 PREPARATION

.1 Consult with the Engineer to determine locations for new drains. .2 Determine the interior building and/or garage conditions below each drain

location. .3 Remove existing drains and drain pipe as directed by the Engineer. Repair

existing drain openings not to be reused as specified elsewhere. 3.2 DRAIN INSTALLATION

.1 Install new floor drains at locations designated by the Engineer. .2 Do not install drains through beams or drop panels without prior approval of

the Engineer. .3 Use a core drill to cut drain openings. Cut holes no larger than required to

install drain. Avoid damage to existing reinforcing by using a metal detector. Take precuations to determine the location of embedded services and avoid such damage in accordance with Section 01000.

.4 Set drain at the appropriate level to prevent water from ponding on the slab. .5 Provide a clean-out with each drain installed. .6 Completely repair the space between the drain and core hole with non-

shrink grout. 3.3 ABOVE-GRADE DRAIN PIPE

.1 Install drain pipe and connect to existing sanitary sewer system. Ensure drain pipe has a minimum 2% slope.

.2 Supply and install all necessary elbows, T’s, Y’s, clamps and hangers, etc. .3 Install pipe hangers at appropriate spacing using suitable expansion

anchors. .4 If necessary, extend the drain pipe to the lower parking levels by core

drilling through the garage floor slabs. Repair the slabs with non-shrink grout.

Guelph Parkades SECTION 15430 Page 3 Parking Garage Repairs April, 2012 GARAGE FLOOR DRAINS

3.4 BELOW-GRADE DRAIN PIPE

.1 Install drain pipe below slab on grade only where suitable connection cannot be made to the existing sanitary sewer system with above-grade drain pipe and where approved by the Engineer.

.2 Determine the location of new below-grade drain pipe, saw cut the slab on

grade and remove the concrete to the full depth of the slab. .3 Excavate subgrade material as necessary to install pipe. .4 Lay pipe to ensure positive drainage and connect to sanitary sewer system. .5 Backfill with existing material and lightly compact. .6 Reconstruct slab on grade using Class C-2 ready mixed concrete.

3.5 PROTECTION

.1 Protect drains and drain pipes until acceptance by the Engineer and Owner.

3.6 MAKE GOOD .1 Repair any garage floor slab waterproofing damaged during the installation

as specified elsewhere.

End of Section 15430 15430.doc

1

PARKING GARAGE REPAIRS AT THE CITY OF GUELPH PARKADES

Reference Number: 12-117

A D D E N D U M NO. 1

The following shall form part of the tender documents issued by the City of Guelph’s Purchasing Department, May 2012.

NOTE: the acknowledgement of this addendum must be indicated on FT2 NOTE: The form of tender is set up to allow you to enter your prices

and it will calculate the subtotals and the totals. ADD the Following to the specification

Section 07570 Elastomeric Waterproofing

Clause 2.1.1, Add Sikalastic 710/715 by Sika as an approved alternate product. Clause 2.1.2, Add Sikalastic 180/181 by Sika as an approved alternate product.

End of Addendum #1.