© abb ptmv - 1, 2015-10-17 abb overhead distribution systems

12
© ABB PTMV - 1, 22-03-15 Overhead Distribution Systems

Upload: terence-anthony

Post on 01-Jan-2016

236 views

Category:

Documents


7 download

TRANSCRIPT

© A

BB

PT

MV

- 1

, 2

3-04

-20

Overhead Distribution Systems

© A

BB

PT

MV

-

2

ABB

Improving Distribution Reliability with Reclosers

The Example Distribution Circuit

Typical of suburban/rural circuits

10 miles of 3-Phase 13.8 kV Main Feeder

8 single-phase laterals, evenly distributed on the main feeder. Each lateral 3 miles long, and connected to the main feeder through a fuse

A total of 1800 customers (8 x 225 customers/lateral)

DistributionSubstation 10 miles

115 kV 13.8 kV3 miles

© A

BB

PT

MV

-

3

ABB

Basic Radial System

Substation 10 miles

Case 1

SAIFI: 1.6 int/cust/yrSAIDI: 3.3 hrs/yrMAIFI: 8.7 mom/yr

Recloser

R

Case 2

Substation 5 miles

Recloser

R

5 miles

R

SAIFI: 1.2 int/cust/yrSAIDI: 2.6 hrs/yrMAIFI: 6.5 mom/yr

Case 2 - with Single-Pole Reclosing

Substation 5 miles

Recloser

R

5 miles

R

SAIFI: 1.1 int/cust/yrSAIDI: 2.3 hrs/yrMAIFI: 5.4 mom/yr

Single phase

© A

BB

PT

MV

-

4

ABB

Loop Configuration with Manual Switch

Substation 1

SAIFI: 1.2 int/cust/yrSAIDI: 2.3 hrs/yrMAIFI: 6.5 mom/yr

5 miles

Case 3

R

5 miles

Substation 2

R

ManualTie

Switch

Assumptions•Circuit breakers have reclosing capability•Manual Tie Switch requires 1 hour to switch•Reclosers require 1 minute to switch

© A

BB

PT

MV

-

5

ABB

Loop Configuration with Manual Switch

Substation 1

SAIFI: 1.1 int/cust/yrSAIDI: 2.0 hrs/yrMAIFI: 5.4 mom/yr

5 miles

Case 3 - With Single-Pole Reclosing

R

5 miles

Substation 2

R

ManualTie

Switch

Assumptions•Circuit breakers have reclosing capability•Manual Tie Switch requires 1 hour to switch•Reclosers require 1 minute to switch and have single-pole capability

© A

BB

PT

MV

-

6

ABB

Automatic Loop Restoration - 3 Reclosers

Substation 1

SAIFI: 1.0 int/cust/yrSAIDI: 2.1 hrs/yrMAIFI: 6.8 mom/yr

5 miles

Case 4

R

5 miles

Substation 2

R

N.O.Recloser

Assumptions•Circuit breakers have reclosing capability•Reclosers require 1 minute to switch

R

N.C.Recloser

N.C.Recloser

N.C. - Normally-ClosedN.O. - Normally-Open

© A

BB

PT

MV

-

7

ABB

Automatic Loop Restoration - 3 Reclosers

Substation 1

SAIFI: 0.8 int/cust/yrSAIDI: 1.8 hrs/yrMAIFI: 3.1 mom/yr

5 miles

R

5 miles

Substation 2

R

N.O.Recloser

Assumptions•Circuit breakers have reclosing capability•Reclosers require 1 minute to switch

R

N.C.Recloser

N.C.Recloser

N.C. - Normally-ClosedN.O. - Normally-Open

Case 4 - With Single-Pole Reclosing

© A

BB

PT

MV

-

8

ABB

Automatic Loop Restoration - 5 Reclosers

Substation 1

SAIFI: 0.8 int/cust/yrSAIDI: 1.7 hrs/yrMAIFI: 6.5 mom/yr

3.3 miles

Case 5

R

3.3 miles

Substation 2

R

N.O.Recloser

Assumptions•Circuit breakers have reclosing capability•Reclosers require 1 minute to switch

R

N.C.Recloser

N.C.Recloser

N.C. - Normally-ClosedN.O. - Normally-Open

R

R

N.C.Recloser

N.C.Recloser

3.3 miles

© A

BB

PT

MV

-

9

ABB

Automatic Loop Restoration - 5 Reclosers

Substation 1

SAIFI: 0.6 int/cust/yrSAIDI: 1.4 hrs/yrMAIFI: 2.7 mom/yr

3.3 miles

R

3.3 miles

Substation 2

R

N.O.Recloser

Assumptions•Circuit breakers have reclosing capability•Reclosers require 1 minute to switch

R

N.C.Recloser

N.C.Recloser

N.C. - Normally-ClosedN.O. - Normally-Open

R

R

N.C.Recloser

N.C.Recloser

3.3 miles

Case 5 - With Single-Pole Reclosing

© A

BB

PT

MV

-

10

ABB

Benefits of Single-Pole Reclosing

SAIFI SAIDI MAIFI

3-Recloser Automatic Loop Restoration

3-PoleReclosing

1.0 2.1 6.8

Single-PoleReclosing

0.8 1.8 3.1

5-Recloser Automatic Loop Restoration

3-PoleReclosing

0.8 1.7 6.5

Single-PoleReclosing

0.6 1.4 2.7

© A

BB

PT

MV

-

11

ABB

Summary of Reclosing Benefits with Single Phase

R

R

R

R

R

R

R

R

R

R

R

RR

Case 1 - Substation reclosing 3 phase only

Case 3 - Loop with Manual Switch

Case 2 - Line Recloser

Case 5 - 5-Recloser Automatic Loop Restoration

Case 4 - 3-Recloser Automatic Loop Restoration

3.3 --- 3.3 ---

2.6 21% 2.3 30%

2.3 30% 2.0 39%

2.1 36% 1.8 45%

1.7 48% 1.4 58%

Hrs/Yr %* Hrs/Yr %*

*% Improvement as compared to Case 1

Single phase

© A

BB

PT

MV

-

12

ABB

Predictive Reliability Analysis

Useful for: Looking at system

configuration and design

Placement of protective devices

Impacts of changes in failure rates and restoration times

Analyzing system reliability

from a graphical perspective and determining the most cost-effective solutions

ABB Consulting’s Performance AdvantageTM Software