zorlu pakistan -08sept2013

19
ZORLU ENERJI PAKISTAN 56.4 MW WIND POWER PLANT September 2013

Upload: ashfaque-hussain

Post on 27-Dec-2015

24 views

Category:

Documents


0 download

DESCRIPTION

Zulu project

TRANSCRIPT

Page 1: Zorlu Pakistan -08Sept2013

ZORLU ENERJI PAKISTAN

56.4 MW

WIND POWER PLANT September 2013

Page 2: Zorlu Pakistan -08Sept2013

ZORLU ENERGY

GROUP

ZORLU INDUSTRIAL PAKISTAN

Engineering,Design, Construction

Services for Power Plants

ZORLU ENERJI PAKISTAN

•56.4 MW WPP under

construction

•Up to 300 MW Expansion

ZORLU O&M PAKISTAN

Operation and Maintenance

Services for Power Plants

ZORLU ENERGY IN PAKISTAN

Page 3: Zorlu Pakistan -08Sept2013

WF ZORLU

ZORLU PAKISTAN WPP PROJECT LOCATION

Page 4: Zorlu Pakistan -08Sept2013

HISTORY OF ZORLU ENERGY WIND POWER PROJECT

2007

• First Wind Mast of 85 m height in Pakistan

• Approvals from Authorities and arrangements for Phase I (6 MW) and Phase II (43.5 MW)

2008 • Construction works starts (Phase I – 6 MW) 5 Vensys 1.2 MW

2009

• Despite the economical crisis, Zorlu Energy completed Phase-I with %100 Equity.

• 6 MW Phase I starts to generate electricity.

2010 • New financing opportunities are arisen.

2011

• Vestas V90 1.8 MW for Phase II and the total capacity increased to 56.4 MW. All approval are renewed. Financial arrangements are done.

2012

• Energy Purchase Agreement and Implementation Agreement signed with Goverrnment of Pakistan. EPC and O&M agreements are signed. The construction is started. Financial Close is done.

2013 • 25th July 2013, COD Achieved (3 months before Required COD)

Page 5: Zorlu Pakistan -08Sept2013

HISTORY – PHASE I CONSTRUCTION

2007

2009

2008

Page 6: Zorlu Pakistan -08Sept2013

HISTORY – PHASE I INAGURATION (19th April 2009)

Page 7: Zorlu Pakistan -08Sept2013

HISTORY – PHASE II CONSTRUCTION

2013

Page 8: Zorlu Pakistan -08Sept2013

HISTORY 2008 - 2013

2008 2013

Page 9: Zorlu Pakistan -08Sept2013

PROJECT MILESTONES

2013

Civil Works Jan ‘12 Dec `12 Turbines Deliveries Apr’12 July`12

Mechanical Works Jul’ 12 Nov`12

Electrical Works Sep’ 12 Dec`12 Pre-commissionning Jan’ 13 May`13

Energisation of the Complex May`13 Hot-commissionning and Run Tests May 2013 July 2013

COD 25.07.2013 25.07.2013

Page 10: Zorlu Pakistan -08Sept2013

PAKISTAN WIND POWER PROJECT DETAILS

Project: Pioneer in Wind Sector (Zorlu Enerji)

Location: Jhimphir, District Thatta

Installed Capacity: 56.4 MW

Expected Generation: 159.010 GWh

Number of Turbines: 5*Vensys 62 1.2 MW (Phase I)

28*VestasV90 1.8 MW (Phase II)

Project Area: 1,148 acres

Project Cost*: 143.7 M $

Debt/Equity: 70:30

Loan Amount: 100.2 M $

Foreign Lenders : IFC / ADB / ETDB

Local Lender : HBL

COD Achieved: July’13

Required COD Date: November 2013

Page 11: Zorlu Pakistan -08Sept2013

DEVELOPMENT STAGE

ALTERNATIVE ENERGY DEVELOPMENT BOARD (AEDB)

Letter of Intent (LOI) 01 Month

Allocation of Land 3 Months

Feasibility Study

Wind Assessment

Soil Investigation

Environmental Study

Selection of Technology

6 Months

National Electric Power Regulatory Authority (NEPRA)

1. Tariff Determination 03 Months

CENTRAL POWER PURCHASING AGENCY (CPPA)

EPA Negotiations 6 Months

IA Agreement 01 Month

Financial Closure 01 Month

Page 12: Zorlu Pakistan -08Sept2013

Issues

• Lengthy Procedure

• Lack of Wind

Knowledge

• Communication

Page 13: Zorlu Pakistan -08Sept2013

Execution

1. Local Issues

2. Security Issues

3. Transport & Logistics Problems

4. Land Issues

Page 14: Zorlu Pakistan -08Sept2013

Protest at ZEPL Site

2008 2013

Page 15: Zorlu Pakistan -08Sept2013

BLADE DAMAGE

Page 16: Zorlu Pakistan -08Sept2013

ILLEGAL SETTLEMENTS

Page 17: Zorlu Pakistan -08Sept2013

OPERATION PHASE

• EPA COMPLIANCE:

• BILLING

Page 18: Zorlu Pakistan -08Sept2013

FUTURE DEVELOPMENTS

• LAND ACQUISATION

• SLOW TRANSMISSION

INFRASTRUCTURE

• BAD ROAD INFRASTRUCTURE

• SECURITY ISSUES

Page 19: Zorlu Pakistan -08Sept2013