yerba buena island (ybi) westside bridges project …...2017/05/19  · westside bridges project...

40
Yerba Buena Island (YBI) Westside Bridges Project and YBI Southgate Road Realignment Improvements Construction Management Services Pre-Proposal Conference SAN FRANCISCO COUNTY TRANSPORTATION AUTHORITY May 22, 2017

Upload: others

Post on 19-Aug-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Yerba Buena Island (YBI) Westside Bridges Project …...2017/05/19  · Westside Bridges Project Project Setting 5 Seismic Strategy –Retrofit and Replacement 6 Structure No. 1 (Retrofit)

Yerba Buena Island (YBI) Westside Bridges Project and YBI Southgate Road Realignment Improvements

Construction Management Services

Pre-Proposal Conference

SAN FRANCISCO COUNTY TRANSPORTATION AUTHORITY

May 22, 2017

Page 2: Yerba Buena Island (YBI) Westside Bridges Project …...2017/05/19  · Westside Bridges Project Project Setting 5 Seismic Strategy –Retrofit and Replacement 6 Structure No. 1 (Retrofit)

► Introductions

► Scope of Services

► DBE requirements

► Schedule

► Q & A

Agenda

2

Page 3: Yerba Buena Island (YBI) Westside Bridges Project …...2017/05/19  · Westside Bridges Project Project Setting 5 Seismic Strategy –Retrofit and Replacement 6 Structure No. 1 (Retrofit)

Scope of RFP

► Purpose: To retain two qualified construction management

firms to provide construction management services, one for

each of the following projects:

YBI Southgate Road Realignment Improvements

Design-Bid-Build Project Delivery Method

Yerba Buena Island (YBI) Westside Bridges Project

Construction Manager/General Contractor Project Delivery

Method

3

Page 4: Yerba Buena Island (YBI) Westside Bridges Project …...2017/05/19  · Westside Bridges Project Project Setting 5 Seismic Strategy –Retrofit and Replacement 6 Structure No. 1 (Retrofit)

SAN FRANCISCO COUNTY TRANSPORTATION AUTHORITY

Yerba Buena Island Westside Bridges Project

Page 5: Yerba Buena Island (YBI) Westside Bridges Project …...2017/05/19  · Westside Bridges Project Project Setting 5 Seismic Strategy –Retrofit and Replacement 6 Structure No. 1 (Retrofit)

Project Setting

5

Page 6: Yerba Buena Island (YBI) Westside Bridges Project …...2017/05/19  · Westside Bridges Project Project Setting 5 Seismic Strategy –Retrofit and Replacement 6 Structure No. 1 (Retrofit)

Seismic Strategy – Retrofit and Replacement

6

Page 7: Yerba Buena Island (YBI) Westside Bridges Project …...2017/05/19  · Westside Bridges Project Project Setting 5 Seismic Strategy –Retrofit and Replacement 6 Structure No. 1 (Retrofit)

Structure No. 1 (Retrofit)

7

Page 8: Yerba Buena Island (YBI) Westside Bridges Project …...2017/05/19  · Westside Bridges Project Project Setting 5 Seismic Strategy –Retrofit and Replacement 6 Structure No. 1 (Retrofit)

Structure No. 4 (Retrofit)

Page 9: Yerba Buena Island (YBI) Westside Bridges Project …...2017/05/19  · Westside Bridges Project Project Setting 5 Seismic Strategy –Retrofit and Replacement 6 Structure No. 1 (Retrofit)

Structure No. 7A / 7B (Retrofit)

Page 10: Yerba Buena Island (YBI) Westside Bridges Project …...2017/05/19  · Westside Bridges Project Project Setting 5 Seismic Strategy –Retrofit and Replacement 6 Structure No. 1 (Retrofit)

Structure No. 8 (Retrofit)

Page 11: Yerba Buena Island (YBI) Westside Bridges Project …...2017/05/19  · Westside Bridges Project Project Setting 5 Seismic Strategy –Retrofit and Replacement 6 Structure No. 1 (Retrofit)

Replacement Structures 2, 3 and 6

11

Page 12: Yerba Buena Island (YBI) Westside Bridges Project …...2017/05/19  · Westside Bridges Project Project Setting 5 Seismic Strategy –Retrofit and Replacement 6 Structure No. 1 (Retrofit)

Replacement Structures 2, 3 and 6

12

Page 13: Yerba Buena Island (YBI) Westside Bridges Project …...2017/05/19  · Westside Bridges Project Project Setting 5 Seismic Strategy –Retrofit and Replacement 6 Structure No. 1 (Retrofit)

Replacement Structures – Unstable Soil Swale

CABLE HOUSE

13

Page 14: Yerba Buena Island (YBI) Westside Bridges Project …...2017/05/19  · Westside Bridges Project Project Setting 5 Seismic Strategy –Retrofit and Replacement 6 Structure No. 1 (Retrofit)

Replacement Structure 2

Page 15: Yerba Buena Island (YBI) Westside Bridges Project …...2017/05/19  · Westside Bridges Project Project Setting 5 Seismic Strategy –Retrofit and Replacement 6 Structure No. 1 (Retrofit)

Replacement Structure 3

Page 16: Yerba Buena Island (YBI) Westside Bridges Project …...2017/05/19  · Westside Bridges Project Project Setting 5 Seismic Strategy –Retrofit and Replacement 6 Structure No. 1 (Retrofit)

Replacement Structure 6

Page 17: Yerba Buena Island (YBI) Westside Bridges Project …...2017/05/19  · Westside Bridges Project Project Setting 5 Seismic Strategy –Retrofit and Replacement 6 Structure No. 1 (Retrofit)

Replacement Project

17

Page 18: Yerba Buena Island (YBI) Westside Bridges Project …...2017/05/19  · Westside Bridges Project Project Setting 5 Seismic Strategy –Retrofit and Replacement 6 Structure No. 1 (Retrofit)

Replacement Project

18

Page 19: Yerba Buena Island (YBI) Westside Bridges Project …...2017/05/19  · Westside Bridges Project Project Setting 5 Seismic Strategy –Retrofit and Replacement 6 Structure No. 1 (Retrofit)

Replacement Project

19

Page 20: Yerba Buena Island (YBI) Westside Bridges Project …...2017/05/19  · Westside Bridges Project Project Setting 5 Seismic Strategy –Retrofit and Replacement 6 Structure No. 1 (Retrofit)

TIMMA Tolling

20

Page 21: Yerba Buena Island (YBI) Westside Bridges Project …...2017/05/19  · Westside Bridges Project Project Setting 5 Seismic Strategy –Retrofit and Replacement 6 Structure No. 1 (Retrofit)

Traffic Handling

21

Page 22: Yerba Buena Island (YBI) Westside Bridges Project …...2017/05/19  · Westside Bridges Project Project Setting 5 Seismic Strategy –Retrofit and Replacement 6 Structure No. 1 (Retrofit)

Project Challenges

► Steep terrain, unstable soils

► Environmental constraints

Birds

Plants

► Storm water

► Coordination with Caltrans – SFOBB Ramps

► Coordination with TICD

Construction Detour

Construction Traffic

22

Page 23: Yerba Buena Island (YBI) Westside Bridges Project …...2017/05/19  · Westside Bridges Project Project Setting 5 Seismic Strategy –Retrofit and Replacement 6 Structure No. 1 (Retrofit)

Project Status

► Retrofit Bridges

Environmental Approval Complete

Design is 35% Complete

► Replacement

Environmental Approval – Fall 2017

Design is at Preliminary Conceptual

23

Page 24: Yerba Buena Island (YBI) Westside Bridges Project …...2017/05/19  · Westside Bridges Project Project Setting 5 Seismic Strategy –Retrofit and Replacement 6 Structure No. 1 (Retrofit)

Project Delivery

► Schedule

NTP Pre-Construction Services : August/September 2017

NTP Construction Services: January 2019

Construction Complete: December 2020

► Estimated construction cost

$48 Million

► Delivery method

CM/GC

24

Page 25: Yerba Buena Island (YBI) Westside Bridges Project …...2017/05/19  · Westside Bridges Project Project Setting 5 Seismic Strategy –Retrofit and Replacement 6 Structure No. 1 (Retrofit)

SAN FRANCISCO COUNTY TRANSPORTATION AUTHORITY

Yerba Buena Island Southgate Road

Realignment Improvements

Page 26: Yerba Buena Island (YBI) Westside Bridges Project …...2017/05/19  · Westside Bridges Project Project Setting 5 Seismic Strategy –Retrofit and Replacement 6 Structure No. 1 (Retrofit)

Project Setting

26

Page 27: Yerba Buena Island (YBI) Westside Bridges Project …...2017/05/19  · Westside Bridges Project Project Setting 5 Seismic Strategy –Retrofit and Replacement 6 Structure No. 1 (Retrofit)

Project Timing

• Macalla Construction

spring 2018

• Southgate

Construction Spring

2018

• Treasure Island Road

(West Side Bridges)

Construction Spring

2019

27

Page 28: Yerba Buena Island (YBI) Westside Bridges Project …...2017/05/19  · Westside Bridges Project Project Setting 5 Seismic Strategy –Retrofit and Replacement 6 Structure No. 1 (Retrofit)

Southgate Project Elements

28

Page 29: Yerba Buena Island (YBI) Westside Bridges Project …...2017/05/19  · Westside Bridges Project Project Setting 5 Seismic Strategy –Retrofit and Replacement 6 Structure No. 1 (Retrofit)

Project Elements- Structure Components

29

Page 30: Yerba Buena Island (YBI) Westside Bridges Project …...2017/05/19  · Westside Bridges Project Project Setting 5 Seismic Strategy –Retrofit and Replacement 6 Structure No. 1 (Retrofit)

Access Control

30

Page 31: Yerba Buena Island (YBI) Westside Bridges Project …...2017/05/19  · Westside Bridges Project Project Setting 5 Seismic Strategy –Retrofit and Replacement 6 Structure No. 1 (Retrofit)

Quarters 8 Building

31

Page 32: Yerba Buena Island (YBI) Westside Bridges Project …...2017/05/19  · Westside Bridges Project Project Setting 5 Seismic Strategy –Retrofit and Replacement 6 Structure No. 1 (Retrofit)

Preliminary Cost EstimateCosts in ($ Millions)

Roadway – $9.0

Utility Relocation – 0.5

Structures – 9.7

Landscaping – 0.4

S. Bridgehead Foundation – 1.5

Mobilization – 2.0

Contingency (15%) – 3.4

Subtotal Construction Cost - $26.5M

32

Page 33: Yerba Buena Island (YBI) Westside Bridges Project …...2017/05/19  · Westside Bridges Project Project Setting 5 Seismic Strategy –Retrofit and Replacement 6 Structure No. 1 (Retrofit)

Advance Components

33

Page 34: Yerba Buena Island (YBI) Westside Bridges Project …...2017/05/19  · Westside Bridges Project Project Setting 5 Seismic Strategy –Retrofit and Replacement 6 Structure No. 1 (Retrofit)

Schedule

NTP Pre-construction Services : August/September 2017

NTP Construction Services: April 2018

Construction Complete: June 2019

34

Page 35: Yerba Buena Island (YBI) Westside Bridges Project …...2017/05/19  · Westside Bridges Project Project Setting 5 Seismic Strategy –Retrofit and Replacement 6 Structure No. 1 (Retrofit)

Response Requirements

35

RFP > SECTION VI > Pages 18-24

► Technical Proposal

Limited to 40 pages

Excluded from page limitations

Cover Letter

Table of contents

Résumés

DBE certificates

Exhibits

Cost Proposal

Separate submission in sealed envelope

Refer to page 23 for requirements

Page 36: Yerba Buena Island (YBI) Westside Bridges Project …...2017/05/19  · Westside Bridges Project Project Setting 5 Seismic Strategy –Retrofit and Replacement 6 Structure No. 1 (Retrofit)

Evaluation Criteria

36

RFQ > SECTION VI > Pages 24-25

► Proposal

1. Proposer Information and Understanding of Project

Objectives (15 points)

2. Technical and Management Approach (50 points)

3. Capabilities and Experience (35 points)

Page 37: Yerba Buena Island (YBI) Westside Bridges Project …...2017/05/19  · Westside Bridges Project Project Setting 5 Seismic Strategy –Retrofit and Replacement 6 Structure No. 1 (Retrofit)

DBE Requirements

37

RFP > Section VII > Pages 25-26

DBE Goal: 10.2%

By the proposal due date, firms must:

Be certified by the California Unified Certification Program

(DBE certification)

Submit:

Exhibit 10-O1 – Local Agency Consultant Proposal DBE

Commitment

Exhibit 10-O2 – Local Agency Consultant Contract DBE

Commitment

Exhibit 15-H – DBE Information – Good Faith Efforts

Page 38: Yerba Buena Island (YBI) Westside Bridges Project …...2017/05/19  · Westside Bridges Project Project Setting 5 Seismic Strategy –Retrofit and Replacement 6 Structure No. 1 (Retrofit)

Proposal Schedule

38

RFP > Pages 1-2

DUE DATE SELECTION PROCESS

May 23 5:00 PM deadline for proposers to submit written questions to [email protected].

May 26 Written responses to questions issued; addenda if necessary (via www.sfcta.org)

June 122:00 PM deadline for proposals and sealed cost proposals. Late submissions not

accepted.

June 16 Invitation to Interview issued to short list of proposers (if necessary)

June 22 Interviews (scheduled if necessary)

June 28 Recommendation to Citizens Advisory Committee for award (subject to change)

July 11 Recommendation to Transportation Authority Board for award (subject to change)

Questions are due by 5pm on Tuesday, May 23rd to [email protected].

July 25 Transportation Authority Board awards contract (subject to change)

Page 39: Yerba Buena Island (YBI) Westside Bridges Project …...2017/05/19  · Westside Bridges Project Project Setting 5 Seismic Strategy –Retrofit and Replacement 6 Structure No. 1 (Retrofit)

SAN FRANCISCO COUNTY TRANSPORTATION AUTHORITY

Questions and Answers

Page 40: Yerba Buena Island (YBI) Westside Bridges Project …...2017/05/19  · Westside Bridges Project Project Setting 5 Seismic Strategy –Retrofit and Replacement 6 Structure No. 1 (Retrofit)

Southgate Schedule

Final Design start – June 2017

Advance Construction Elements – through Dec. 2017

Environmental Revalidation – Spring 2018

Permits – Spring 2018

Advertise Bid Package – Spring 2018

Construction Start – Summer 2018

Construction complete - Summer 2019

40