xayaburi hydroelectric project - kmutt · hydroelectric power plant run-of-river concrete barrage...
TRANSCRIPT
![Page 1: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/1.jpg)
CH. Karnchang (Lao) Company LimitedBy Mr. Thamnoon Surarat & Mr. Weerayot Chalermnon
Xayaburi Hydroelectric project
How The Design
Implement to The Construction
![Page 2: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/2.jpg)
Objective:
•To exchange on “How to make Project Planning?”
•To exchange on “Design Phylosophy of the Xayaburi HPP”
•To exchange on “Construction of Xayaburi HPP”
![Page 3: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/3.jpg)
Content:
• Introduction to the Project: • The Potential on Lower Mekong
• Project configuration
• Project Time line
•Project Planning:• Construction Sequences
• Quantities of works
• Sources of Materials
• Construction Facilities
• Project Design Philosophy:• Key hydraulic information• Seismic design• Geology and Geotechnical• Physical Model test
• Construction of XHPP:• First phase construction• Intermediate block• First Stage Cofferdam• Spillway• Navigation Locks• River Closure and Diversion
• Conclusion
![Page 4: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/4.jpg)
Introduction to the Project: Mekong Basin
CountryCatchment area
(Km2)%
China 165,000 21
Myanmar 24,000 3
Laos 202,000 25
Thailand 184,000 23
Cambodia 155,000 20
Vietnam 65,000 8
Total 795,000 100
Source* : MRC
![Page 5: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/5.jpg)
Potential on Lower Mekong Basin and Xayaburi HPP
1 2
3
4
5
6
7
8
9
10
11
Project
Capacity (MW.)
Constructi
onPlanned
1. Pak Beng 1,230
2. Luang
Prabang1,410
3. Xayaburi 1,285
4. Pak Lay 1,320
5. Sanakham 570
6. Pak Chom 1,079
7. Ban Khoum 2,000
8. Lat Sua 800
9. Don Sahong 360
10. Stung Treng 980
11. Sambor 460
Total 1,285 10,209
XHPP locates at 1931 km upstream from Mekong River delta and 103 km downstream of Luang Prabang
![Page 6: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/6.jpg)
Upper Mekong Development
MengSong
600 MW
Ganlanba
150 MW
JingHong 1500 MW
Nuozhadu 5500 MW
DaChaoShan1350 MW
ManWan 1500 MW
Xiaowan 4200 MW
GongGuoQiao 750 MW
China
Viet nam
Lao PDR
Myanmar
Thailand
8 Dams in China
- Completed (6) 14,800 MW.
- Planned (2) 750 MW.
- Total 15,550 MW.
Hydropower development in China
Completed
Planned
Canceled
![Page 7: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/7.jpg)
Project timeline and cost
A. EPC 1. Civil Works 63%
2. Hydro-Mechanical Works 14%
3. Electro-Mechanical Works 18%
4. Transmission 5%
76,000 MB
2012 2013 2014 2015 2016 2017 2018
EPC Contract Signed 29 Oct 2011
2019
COD Oct 2019
1st stage Construction 2nd stage Construction
![Page 8: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/8.jpg)
Project Configuration
![Page 9: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/9.jpg)
Project General InformationHydroelectric power plant run-of-river concrete barrage
Installed Generating CapacityAnnual Production
1,285 MW (7x175 and 1x60 )7,370 GWh. (4.5%)
Average Flow (46 year record 1952-2007)
3,971 cms
Normal Operating Water Level 275 m.asl
River Pondage Area 49 sq.km
Barrage height 80 m.
Total Barrage Length 820 m.
Design Flood (PMF) 47,500 cms
Design Flow through Turbine 4,900 + 242 cms
Rated Net Head 28.5 m9
![Page 10: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/10.jpg)
10
Type 2-steps NLs, with u/s and d/s approach channels for accommodating boats up to 2X 500 DTW.
Head Water Levels for navigation
265.90 – 275.00 m asl
Tailwater Level for Navigation
236.00 -260.00 m asl
Length 144 m for upper lock)154 m for lower lockTotal length: 724.5 m
Width 12 m
Min Water Depth
4 m
Navigation Locks
![Page 12: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/12.jpg)
Spillways
12
![Page 13: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/13.jpg)
Spillways
13
![Page 14: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/14.jpg)
Spillway surface gate
![Page 15: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/15.jpg)
•A structure where separating the spillway from the power intake - powerhouse complex ; and housing the powerhouse
• It is composed with unloading - erection bay, the diesel building, and part of the fish passing facilities.
Intermediate Block
![Page 16: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/16.jpg)
Fish Passing Facilities
Facilities for upstream migration
•Fish collection gallery at powerhouse tailrace, auxiliary collection point at the spillway , The fish passing facilities situated on the left river bank is a pool type fish ladder, 800 m long and 10 m wide , pumping facilities for water supply in dry season , gravity water supply in wet season.
Facilities for downstream migration
•Fish collection gallery at the power intakes, fish delivery channel and chute in the spillway – powerhouse separating block.
![Page 17: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/17.jpg)
![Page 18: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/18.jpg)
Powerhouse
18
![Page 19: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/19.jpg)
19
EGAT EdL
No. of Generating Units 7 1
Turbine• Type• Rated Output• Rated Discharge (per unit)• Governor
Vertical axis Kaplan175 MW700 m3/s
Digital & Hydraulic
Vertical axis Kaplan60 MW
242 m3/sDigital & Hydraulic
Generators• Type• Rated Apparent Power• Power Factor
• Rated Frequency
3-phase synchronous220 MVA0.85 lagging and 0.95 lagging according to EGAT Grid Code50 Hz
Powerhouse
![Page 20: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/20.jpg)
Transmission System
20
EGAT EdL
Transformer• Capacity• Phase• Location
7 x 220 MVA3
Outdoor
1 x 72 MWA3
Outdoor
Transmission Line• Destination
• Length• Voltage• Tower• Conductor
Switchyard to Thali Substation
200 km500 kV
Steel TowerAluminum Conductor Steel
Reinforce
Switchyard to XayaburiSubstation
16.4 km115 kV
Steel TowerAluminum Conductor Steel
Reinforce
![Page 21: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/21.jpg)
Intermediate Block
Left Bank U/S Migration Fish
Passage
Fish Friendly TurbinesD/S Fish PassageD/S Fish Migration
U/S Fish Passage U/S Fish Passage
Original Design of Fish Passing Systems
![Page 22: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/22.jpg)
![Page 23: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/23.jpg)
ค ำถำมประเทศสมำชกิ MRC จำกกำรประชุม PNPCAProcedures for Notification, Prior Consultation and AgreementPrior Consultation for the Proposed Xayaburi Dam Project24th March 2011
1. เรอืเดนิขึน้และลงอยา่งไร
2. ตะกอนเกดิผลกระทบและแกไ้ขอยา่งไร
3. ปลาอพยพขึน้และลงอยา่งใร
4. ผลกระทบตอ่คณุภาพน ้าระหวา่งกอ่สรา้งและหลังการกอ่สรา้ง
5. ผลกระทบดา้นสงัคม
![Page 24: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/24.jpg)
Modify Design by Government of Laos Engineers.August 2011
There are 3-Majors issues have to consider and modified as following;
1.Spillway: Replaced ogee type radial gate to bottom outlet for sediment flushing.
2.Navigation Lock: Modify and add fish passage into Navigation lock.
3.Fish Passing Facilities: Additional study on local fish behavior, swimming performance resulted to Lowering gradient in fish passing facilities.
![Page 25: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/25.jpg)
Replace 3 radial gates with 4 low level outlet gates.
![Page 26: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/26.jpg)
Modified design for sediment flushing
![Page 27: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/27.jpg)
Modified design for fish passage during construction• Additional feeding system in Navigation Locks for attract the fish
Section
![Page 28: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/28.jpg)
Additional feeding system in Navigation Locks for attract the fish
Modified design for fish passage during construction
![Page 29: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/29.jpg)
Fish Lock
D/S Fish Passage
Pump 2 for D/S Fish
Migration
Pump 1 and Gravity pond
for U/S Fish Passage
U/S Fish Passage
U/S Fish Passage
Upper channel
Fish Ladder
D/S Exit
Switchyard AreaUpstream Reservoir
Modified Design of Fish passing facilities.
![Page 30: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/30.jpg)
Introduced fish lock to fish ladder
![Page 31: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/31.jpg)
Social Arrangement
RS 1
RS 2
RS 3
RS 4
RS 5
RS 6
RS-7RS-8
RSH-3
RSH-4
RSH-1
RSH-2
Project
CITY
Resettlement Site
Relocation Site
HouaySouy
93
98
164
55
68
24
3
3
4955
66
3
12
Paknoen
KhokYai
HouayDeua
Talan
76
62
Completed
Thadeua
PakkhonPakphai
Houaykheua
Pakhao
Khoktom
Hatxaykham
Pakmon
Paklan
Phonsavanh
Ongoing
• 612 household in 15 affected villages6 villages in Xayaburi side9 villages in Luang Prabang side
• Total 2,986 pp affected
• Social ArrangementSIA, RAP - Approved by GOL7 villages - Resettlement8 villages - Relocation684 new houses with InfrastructureCompensationCommunity Development ProgramLivelihoods Restoration ProgramIncome Generation Monitoring
![Page 32: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/32.jpg)
How to design? How to build?
• We are not the first one who design and construct.
• We make technical visit to the on going project and successful project to overview what is the difficulty, problem, constraint, etcand adopt to our XHPP.
![Page 33: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/33.jpg)
Technical Visit Xiangjaiba Dam, China.
![Page 34: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/34.jpg)
Technical Visit Wulong Dam, China.
![Page 35: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/35.jpg)
Technical Visit Tongzhilin HPP, China
![Page 36: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/36.jpg)
Technical Visit St Stephen, SC, USA.
![Page 37: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/37.jpg)
Technical Visit, Vattenfall - Geesthacht, Germany
![Page 38: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/38.jpg)
Technical Visit, E.ON – Kachlet, Germany
![Page 39: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/39.jpg)
Project Organization structure rev 01
Project Director Project Manager
Axillaries section support to the Project Manager
High Level Manager
FrontLinestaffs
Financial and Administration
ConstructionEngineering
Project control
ler
![Page 40: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/40.jpg)
Construction Planning:
![Page 41: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/41.jpg)
Project Planning
![Page 42: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/42.jpg)
![Page 43: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/43.jpg)
![Page 44: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/44.jpg)
Rainy Season 2011July 11 – Oct 11
Qty = 1,010,000 m3
252,500 m3 /month
Rainy Season 2011July 11 – Oct 11
Qty = 1,034,000 m3Aug 11 = 318,000 m3
Sep 11 = 350,000 m3
Oct 11 = 366,000 m3
![Page 45: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/45.jpg)
Dry Season 2012Nov 11 – May 12
Qty = 3,447,00 m3
NL = 32,600 m3
Nov 11 = 446,000 m3
Dec 11 = 566,000 m3
Jan 12 = 645,000 m3
Feb 12 = 653,000 m3
Mar 12 = 481,000 m3
Apr 12 = 316,000 m3
May 12 = 340,000 m3
![Page 46: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/46.jpg)
Rainy Season 2012June 12 – Oct 12
Qty = 630,000 m3
June 12 = 104,000 m3
July 12 = 99,000 m3
Aug 12 = 141,000 m3
Sep 12 = 130,000 m3
Oct 12 = 156,000 m3
![Page 47: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/47.jpg)
Dry Season 2013Nov 12 – May 13
Qty = 2,286,000 m3
IB = 360,000 m3
SW = 100,000 m3
NV = 143,000 m3
Nov 12 = 305,000 m3
Dec 12 = 440,000 m3
Jan 13 = 434,000 m3
Feb 13 = 414,000 m3
Mar 13 = 320,000 m3
Apr 13 = 210,000 m3
May 13 = 163,000 m3
![Page 48: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/48.jpg)
Rainy Season 2013June 13 – Oct 13
SW = 173,000 m3
NV = 165,000 m3
![Page 49: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/49.jpg)
Dry Season 2014Nov 13 – May 14
NV = 169,000 m3
SW = 158,000 m3
IB = 752,000 m3
Nov 13 = 10,000 m3
Dec 13 = 60,000 m3
Jan 14 = 60,000 m3
Feb 14 = 30,000 m3
Mar 14 = 14,000 m3
Qty = 174,000 m3
![Page 50: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/50.jpg)
Rainy Season 2014June 14 – Oct 14
IB = 516,000 m3
Oct 14 = 100,000 m3
![Page 51: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/51.jpg)
Dry Season 2015Nov 14 – May 15
![Page 52: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/52.jpg)
Rainy Season 2015June 15 – Oct 15
June 15 = 150,000 m3
July 15 = 120,000 m3
Aug 15 = 100,000 m3
Sep 15 = 54,000 m3
Qty = 424,000 m3
![Page 53: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/53.jpg)
Season 2016 ~ 2018
![Page 54: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/54.jpg)
![Page 55: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/55.jpg)
![Page 56: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/56.jpg)
Excavation Schedule
![Page 57: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/57.jpg)
Excavation Planning
![Page 58: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/58.jpg)
Excavation Planning
![Page 59: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/59.jpg)
Excavation Planning
![Page 60: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/60.jpg)
Excavation Planning
![Page 61: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/61.jpg)
Spoil area planning
![Page 62: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/62.jpg)
Equipment planning
![Page 63: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/63.jpg)
Construction Schedule
Navigation locks
(Sample)
![Page 64: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/64.jpg)
Navigation Locks Construction
![Page 65: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/65.jpg)
Working Group Arrangement
![Page 66: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/66.jpg)
![Page 67: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/67.jpg)
![Page 68: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/68.jpg)
![Page 69: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/69.jpg)
Manpower planning
![Page 70: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/70.jpg)
Manpower Planning
![Page 71: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/71.jpg)
Material planning•Concrete Peak Production = 170,000 cu.m. per month
•Aggregate Peak Production = 230,000 tons per month
•Crush sand production = 112,000 tons per month
•Cement delivery = 33,000 tons per month
•Fly ash delivery = 13,500 tons per month
![Page 72: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/72.jpg)
Material planning
• Aggregate demand = 230,000 tons per month = Crushing plant capacity = 660 tons per hours (26 working day per month, production 8 hours per day, night shift for maintenance).
• Concrete demand = 170,000 cu.m. per month, = batching capacity = 330 cu.m. per hour (26 working day per month, operate 20 hours per day) plus peak variable 20% = 396 cu.m. per hour => select 120x4 cu.m. per hour. (1-mixer under maintenance).
• Peak period maintained 1-year.
![Page 73: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/73.jpg)
Material planning
• Water usage for concrete at dry season = 92,000 cu.m. (5 month dry season).
• Aggregate Shade stockpile = 12 days at peak month.
• Cement Silo = 6000 tons = 8 days at peak month.
• Fly ash Silo = 3200 tons = 10 days at peak month.
![Page 74: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/74.jpg)
EPC Cost Estimateand
Financial planning
![Page 75: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/75.jpg)
Cost Estimate Structure:
• SA1
• SA2
• SA3
• E&M
• Process Material plants
• Engineering
• Indirect cost, Admin cost
![Page 76: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/76.jpg)
Cost Estimate assumption
• Working time = 26 days per month and 2-shifts of 8+3 hours.
• E&M provide equipments, machine, etc with rental rate as shown in attached rental fee with condition.
• The Site Agent who use equipment must pay the rental fee to E&M. The fuel shall pay by Site Agent who use the equipments or machine.
• Fuel cost exclude tax 34 THB/liter.
• Reinforcement steel include transport 25,180 THB/ton.
• Rental fee ,operator ,maintenance ,workshop operation is include rental rate. (exception hydraulic crawler drill and vehicles )
![Page 77: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/77.jpg)
Cost Estimate assumption (con.)
•Equipment rental rate ,transportation ,aggregate ,plant operation ,admixture ,cement is include concrete unit rate .
•Equipment rental rate ,plant operation is include aggregate unit rate .
•Development cost is not consider.
•Escalation Factor is not consider.
•Permanent Camp is exclude.
•Hauling distance consider as same as Nam Ngum 2.
•Staff compensation is exclude.
![Page 78: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/78.jpg)
Scope of Works
•SA1 Scope of works:- Construction Facilities (Earth Work)
- Access, Hauling, Permanent Road
- Quarry works
- Common and Rock Excavation
- Slope Stabilization works
- Embankment, Rock backfill works
- Concrete leveling, Dental concrete, anchoring works
- Foundation treatment works (Sub-contractor)
- Grouting works (Sub-contractor)
- Instrumentation works (Sub-contractor)
![Page 79: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/79.jpg)
Scope of Works
•SA2 Scope of works:- Temporary works; i.e. construction camp, workshop,
plants foundation, Yards construction, etc. (Structure Work)
- Concrete works, reinforcements, form works, water stop,
and others incidental works.
- Concrete back fill works.
- RCC
- Concrete works associated with the equipment and
system works. Installation of 1st stage embedded in
the first stage concrete. All second stage concrete.
- All required ladder, hand rail, fences, gate, all
architectural works.
![Page 80: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/80.jpg)
Scope of Works
•SA3 Scope of works:- Supervision on Packages contractors.
- Supply and installation of cable duct, conduits, all
piping required, all pipes conveying from the different
powerhouse floors toward the drainage pits or to the
sewage treatment plant.
- Water supply, Water maker, waste water treatment
and its system
- Dewatering
- Construction area lighting service.
- All supply and installation on Electrical & Mechanical works
which not in scope of Packages contractors.
![Page 81: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/81.jpg)
Scope of Works
•E&M Scope of works:- Supply and maintenance for all heavy equipments,machinery
(except batching plants, crushing plants, conveyor belts).
- Supply and maintenance for all light vehicles.
- Manage and control CSA contract i.e. Metro, Altas copco,
Italthai.
- Manage control use of spare part, lubricant, etc.
- Supply all equipments, machinery, vehicles, operators.
- Manage and control all heavy equipments, vehicles
investment.
- Transportation all equipments and production plant from NN2
![Page 82: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/82.jpg)
Scope of Works
•Process Material Scope of works:- Process and supply concrete and shotcrete
aggregates.
- Process and supply nature sand.
- Transport concrete to pouring location by transit truck
mixer, conveyor belt, 10-wheel trucks, tower crane
use for concrete pouring, etc.
- Control quality of concrete, shotcrete.
- Operate and maintenance crushing plants, batching
plant, wet belt, ice plant, conveyor belt, truck mixer,sand dragging, etc.
![Page 83: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/83.jpg)
Scope of Works
•Engineering:- Development on civil works design, drawings, shop drawings, as-built drawings, bar-bending, etc.
- Development and supervision on packages contractor design, drawings, shop drawings, as-built drawing, testing certificate,installation drawings, etc.
- Civil & Packages design interfaces works, interface drawings, combine drawings.
- Geological and geotechnical works.
- Survey works.
- Laboratory and material testing works, material submission.
- Information and Technology service., ERP, License
- Develop and Supervision on concrete mix design
![Page 84: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/84.jpg)
Scope of Works
•Indirect cost, Admin cost- All staff salary (range higher than headman).
- All office expenses.
- All temporary construction expenses.
- All utilities expenses (not include IT expenses).
- All premium and tax expenses.
- Manage control use of fuel.
- Etc.
![Page 85: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/85.jpg)
Preliminary cost estimate
![Page 86: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/86.jpg)
Interim payment
![Page 87: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/87.jpg)
Design Philosophy:
![Page 88: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/88.jpg)
General Design Code:
• The most commonly referenced guidelines include those published by the following United States agencies:• US Army Corps of Engineers (USACE): Engineering Manuals, Engineering Pamphlets,
Regulations, Engineering Technical Letters.• US Bureau of Reclamation (USBR): Design of Gravity Dams, other publications.• Federal Energy Regulatory Commission (FERC): Engineering Guidelines for the Evaluation
of Hydropower Projects, other publications.
• In addition, other general design codes, design manuals and specifications to be considered will include as applicable:• Canadian Dam Association: Dam Safety Guidelines• American Concrete Institute (ACI)
• Recommended Practices.• American Society for Testing and Materials (ASTM): testing specifications.• International Committee on Large Dams (ICOLD): guidelines and recommendations.
![Page 89: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/89.jpg)
Hydrology:
River Runoff recorded 46 years 1960-2006
![Page 90: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/90.jpg)
Frequency of Flood Recurrences:
![Page 91: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/91.jpg)
Tail water Rating Curve
![Page 92: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/92.jpg)
Seismic Design Parameter (Original)
• Seismic Design Parameters
• Based on the seismic hazard map in the Feasibility Study Report, the Peak Ground Acceleration (PGA) at the project site is adopted as follows:
• The seismic loadings are calculated using the seismic coefficient method(pseudo static method) with the following seismic coefficients being applied:
• OBE, kh = 2/3 x 0.16 = 0.11 for unusual loading condition
• MCE, kh =2/3x 0.31 = 0.21 for extreme loading condition
Seismic EventRecurrence
Earthquake Designation Horizontal
PGA
500-Year Operation Basis Earthquake (OBE)
0.16 g
10,000-Year Maximum Credible Earthquake
0.31 g
![Page 93: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/93.jpg)
Seismic Design Criteria:
• Xayaburi dam and reservoir are classified as large project with large damage potential, the dam and safety-relevant elements are designed for the worst earthquake ground motion to be expected at the dam site.
• Safety Evaluation Earthquake (SEE) ground motion have employed to the project.
![Page 94: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/94.jpg)
Seismic Hazard Risk Assessment:
• Dr. Pennung Warnitchai has been studied PROBABILISTIC SEISMIC HAZARD ASSESSMENT • 29th October 2010
• Dr. Noppadol, Dr. Panya, Dr. Supot as Seismic Hazard Risk Assessment Expert Team, have been reviewed and interpretation of aerial photos, satellite images, reports and papers with respect to crustal faults and active faults around Xayaburi dam site
• Field geologic and paleo-seismic investigation of the area and site verification of active faults by trenching and dating of young sediments around fault planes.
• Update deterministic seismic hazard analysis include hazard curves showing contributions of various earthquake sources and various periods, horizontal and vertical uniform hazard response spectra for various return periods such as 145, 475, 2475, and 10,000 years, and Acceleration Response Spectra with acceleration time histories• 30th Sep 2011/18th Oct 2012
![Page 95: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/95.jpg)
Seismic Hazard Risk Assessment:
• Comparison between the DBP fault segments (red lines) delineated by the SHRA team and the modeled fault lines of DBP North, Central, and South sections (pink, green, and black lines, respectively). The Xayaburi project site is illustrated by a yellow pin.
• Based on Geographical Hazard Deaggregation(Harmsen and Frankel, 2001) for the project site, the earthquake scenario selected for Deterministic Seismic Hazard Analysis (DSHA) is set to an Mw 6.8 earthquake with a focal depth of 5 km at Nam Huang segment (about 8 km from the project siteใ
![Page 96: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/96.jpg)
Comparison Seismic design Parameter.
Deterministic
Return Period PGA (g)
145 0.060
475 0.110
2475 0.240
10000 0.440
Deterministic (84th
percentile)
0.440
Original (Probabilistic)
Seismic EventRecurrence
Earthquake Designation Horizontal
PGA
500-Year Operation Basis Earthquake (OBE)
0.16 g
10,000-Year Maximum Credible Earthquake
0.31 g
![Page 97: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/97.jpg)
Plant Safety Concept against Seismic
• Establish priorities structure taking into account the impact of failures during and after quaking events on the plant itself and on the public safety / environment, particularly downstream of the plant; and the possibility, difficulty and cost of damage, repair of structures and hydro/electro-mechanical components. • First Priority: Mainly to the Upstream part of structures.
• Upstream part of Navigation lock
• Spillway
• Power Intake structure
• Second Priority: Mainly to the downstream part of structures
• Third Priority: Mainly to the equipment unlikely to be in use during an earthquake.
![Page 98: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/98.jpg)
Geology and Geological condition.
• Geotechnical design of the Xayaburi Hydropower Project, the geology has been divided into several rock mass classes and assigned geotechnical parameters. This classification is based on the classification by Marinos and Hoek (2000).
• Due to the high variability of each rock mass on site and for a simplified presentation of the geology, the rock masses are divided as follows: • Carbonate rock mass (muddy limestone, and crystalline Limestone )
• Coarse grain clastic dominated rock mass (Meta-sandstone)
• Fine grained dominant rock mass (Phyllite)
• Sheared rock-mass (Graphitic Phyllite)
![Page 99: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/99.jpg)
Original exploratory holes
![Page 100: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/100.jpg)
Geological Map of the Project
![Page 101: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/101.jpg)
Geological Map of the Project
• Plan view Quartzite, Meta Siltstone, Meta Sandstone
Phylite and graphitic sheared
Volcanic rock
Phyllite schist
Crystalize limestone
![Page 102: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/102.jpg)
Physical Model Test
![Page 103: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/103.jpg)
Sample of tests.
Navigation Lock flow pattern LLO: Negative and flow condition test
![Page 104: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/104.jpg)
Construction of XHPPFirst Stage Construction
![Page 105: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/105.jpg)
Construction Schedule
1. Preparation phase2. 1st stage construction phase (complete in Jan 2015)3. 2nd stage construction phase (complete by end October 2019)
![Page 106: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/106.jpg)
Preparation Phase.
Key Project Quantities
• Construction of access road 25 km.• 115kV transmission line and site
substation.• Camps, utilities, and community
facilities, • Procurement and installation of
Crushing Plant.• Procurement and installation of
Batching Plant.• Installation of plants and yards.
• Prepare lifting device; Tower crane
• Quarry Development
![Page 107: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/107.jpg)
Access road 25 km
Previous DBST
![Page 108: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/108.jpg)
Crushing Plant
Previous
2 Plants design capacity 660 tons/hr. each aggregate 63, 38, 19, 9.5 and artificial sand.
![Page 109: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/109.jpg)
Batching Plants
Previous
Batching Plant equipped with wet belt aggregate cooling system, and ice/ ice water plant (2 plants/4 mixers, capacity of 240m3/h each)
![Page 110: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/110.jpg)
Quarry Development and Operation
![Page 111: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/111.jpg)
Construction Facilities
Rebar yard (Total area 18,950 sq.m)Carpenter yard (Total area 21,920 sq.m)
![Page 112: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/112.jpg)
Construction Facilities
Equipment maintenance Workshop Precast yard
![Page 113: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/113.jpg)
Camps and Facilities
Previous Camps for 11,000 persons.
![Page 114: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/114.jpg)
Camps and Facilities
Emergency Medical Facility – 24 hour servicing first aid, stand-up ambulance Main Office
![Page 115: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/115.jpg)
First Construction PhaseNovember 2012-January 2015
• Construction of the upstream and downstream first stage cofferdam , of the navigation facility , of the spillway , and of the part of the intermediate block on the right bank while the river will keep flowing in its natural dry season channel
![Page 116: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/116.jpg)
Official Construction in the Mekong River
Ground Breaking ceremony 7th November 2012
![Page 117: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/117.jpg)
Navigation Lock
![Page 118: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/118.jpg)
Spillway
![Page 119: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/119.jpg)
Spillway
![Page 120: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/120.jpg)
Trouble and Solution:
• Late Start Construction resulted from Revised Design.• Acceleration plan, increase manpower and equipment
• Unforeseen Geological condition at Navigation lock excavation • Flatten excavation slope resulted to more excavation quantities.
• Dry Season Flood with more than 200 years recurrences' period on 17th
December 2013• Flood to Construction site resulted to pending on construction for 4 weeks.
• Unforeseen underwater Mekong Geology• Prepare alternative design and implement immediately.
• Difficulty on River Closure.• Prepare adequate stockpile for Big Riprap for River Closure.
![Page 121: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/121.jpg)
Conclusion:
•The Project is able to modified the design to meet all requirements of the Owner.
•The Construction able to made accelerate to meet key date with short noticed.
![Page 122: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/122.jpg)
Completion of the First Stage ConstructionRiver Diversion ceremony 26th January 2015
Conclusion:
![Page 123: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/123.jpg)
2nd Construction Phase.
The 2nd stage will consist of completion of the intermediate block construction of the intake powerhouse complex, fish passing facilities and 500kV transmission line. This stage will start with the construction of upstream and downstream embankment cofferdam across the river once the navigation facilities and the spillway are ready for operation.
![Page 124: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/124.jpg)
Construction Activities 2nd Stage Construction-initialJune 2015
![Page 125: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/125.jpg)
Construction Activities 2nd Stage Construction before impoundingOctober 2018
![Page 126: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/126.jpg)
Construction Activities Operation stageOctober 2019
![Page 127: Xayaburi Hydroelectric project - KMUTT · Hydroelectric power plant run-of-river concrete barrage Installed Generating Capacity Annual Production 1,285 MW (7x175 and 1x60 ) 7,370](https://reader034.vdocuments.mx/reader034/viewer/2022043009/5f9dc0b3aa40386808611291/html5/thumbnails/127.jpg)
Question?