www.QinetiQ-NA.com© QinetiQ North America Operations LLC 2009
QinetiQ North America Operations LLC Proprietary
Technology Solutions Group
0000-1
PADS Provisioning Effort Kick OFF File Location:
Presenter: Paul Paolillo
1pm-3pmJanuary 12, 2012
www.QinetiQ-NA.com© QinetiQ North America Operations LLC 2009
QinetiQ North America Operations LLC Proprietary
Technology Solutions Group
Contents• Welcome to the Kick off• Introductions• Program Description
Overview SOW Schedule
• PADS Provisioning IPT Structure Defined• PADS Provisioning Explained• Roles and Responsibilities• Charters
Integrated Management Team Systems Engineering Hardware Engineering Logistics Engineering Product Assurance
- CM- DM- Quality
www.QinetiQ-NA.com© QinetiQ North America Operations LLC 2009
QinetiQ North America Operations LLC Proprietary
Technology Solutions Group
What is PADS? (Precision Airdrop System)
• Overall, PADS uses Global Positioning System (GPS) technology that permits Air Force aircrews to literally steer and fly a cargo pallet to the desired location, increasing the margin of safety for the aircrews. They can also land the cargo in a way that keeps the troops from having to scatter over a wide area and potentially making them vulnerable to hostile fire, when retrieving needed supplies. PSI has been working on the PADS system with the US Air Force and US Army since 1999.
• http://www.spacewar.com/reports/Qinetiq_Subsidiarys_Precision_Airdrop_System_Used_By_USAF_In_Afghanistan_999.html
www.QinetiQ-NA.com© QinetiQ North America Operations LLC 2009
QinetiQ North America Operations LLC Proprietary
Technology Solutions Group
4733-4
Airborne sensor, comms, and processing system for precision aerial delivery from high altitude
High-Res Atmospheric Forecast Model
Precision Airdrop System | PADS™
www.QinetiQ-NA.com© QinetiQ North America Operations LLC 2009
QinetiQ North America Operations LLC Proprietary
Technology Solutions Group
4733-5
2,000 Meters MSL
2,500 Meters MSL
PADS Simulates all Airdrop Components
www.QinetiQ-NA.com© QinetiQ North America Operations LLC 2009
QinetiQ North America Operations LLC Proprietary
Technology Solutions Group
PADs Provisioning Product Team (IPT) Structure
QNA TSG
www.QinetiQ-NA.com© QinetiQ North America Operations LLC 2009
QinetiQ North America Operations LLC Proprietary
Technology Solutions Group
Contract: Statement of WorkSUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE
1 Each $1,453,675.77
Production Technical Data PackageFFPContractor shall provide a Level 3 Production Technical Data Package (TDP) to the Government, which includes applicable parts list, detail and assembly drawings, schematics, interface control data, diagrams, performance characteristics, critical manufacturing limits and details of new materials and processes and any other information necessary to enable a competent manufacturer to produce and maintain quality control for the JPADS BLK 4UHF-DRS and GPS-RTS. The contractor shall provide all data, to include data that is currently claimed as contractor intellectual property, as Government Purpose Rights consistent with that prescribed in DFARS 252.227-7013 and/or DFARS 252.227-7014. Additionally, any data rights provided to the Government shall be documented consistent with that prescribed in DFARS 252.227-7017. In the event that the Government does not agree with any data rightsposition proposed by the Contractor, the Government may require substantiation of said data rights position by following the procedure prescribed in DFARS 252.227-7019 and/or DFARS 252.227-7037.
Delivery Schedule/Cost/Deliverable31 Dec 2011 $143,367.58 Guidance Conference31 Mar 2012 $436,102.73 Long Lead Item List31 Jul 2012 $290,735.15 Provisioning Conference31 Aug 2012 $145,367.58 Submission of SDFP/LMI31 Oct 2012 $145,367.58 Submission of PTD30 Nov 2012 $218,051.37 Spares Conference20 Dec 2012 $72,683.79 PTD/SDFP/LMI Deliveries
www.QinetiQ-NA.com© QinetiQ North America Operations LLC 2009
QinetiQ North America Operations LLC Proprietary
Technology Solutions Group
SOW: Attachments
Attachments:AFMC Form 718 – Provisioning Performance ScheduleCDRL A017 – Logistics Management Information (LMI) Data Products(S)CDRL A018 – Supplemental Data for Provisioning (SDFP)CDRL A019 – Logistics Management Information (LMI) Summaries
www.QinetiQ-NA.com© QinetiQ North America Operations LLC 2009
QinetiQ North America Operations LLC Proprietary
Technology Solutions Group
Key Points of Contact
Contracting OfficerName: Anne HellmanOrganization/Office Symbol: DITCO/PL8322Phone No.: 628-229-9596E-Mail Address: [email protected] Contract SpecialistName: Danette WesselmannOrganization/Office Symbol: DITCO/PL8322Phone No.: 618-229-9273E-Mail Address: [email protected] Customer/COR Point of ContactName: Kristin Dole-MitchellOrganization/Office Symbol: 951ELSG/OC(JPADS)Phone No.: 781-225-9317E-Mail Address: [email protected] Contractor Point of ContactContractor Legal Business Name: Planning Systems IncDUNS: 072651391CAGE CODE: 1K736Contractor POC: Quinn Smith E-Mail Address: [email protected] Number: 703-480-0749
www.QinetiQ-NA.com© QinetiQ North America Operations LLC 2009
QinetiQ North America Operations LLC Proprietary
Technology Solutions Group
0000-10
1. Start date slippage beyond 1 October 2011 will result in a high level of riskin achieving the goal of an accelerated nine (09) month delivery schedule forthis effort.2. QNA TSG is concerned with rejection rates of stock listing datasubmissions. To mitigate this risk, we will develop a random sample selectionof data early in the effort for review and comment by the Government.3. An unforeseen elongated contract definition period.4. QNA TSG believes that not having an updated Provisioning GuidanceConference may affect the critical path for completion of this effort in amanner that could impact the ability of the Air Force to utilize the PTD datafor input into the logistics system.5. QNA TSG understands the requirements as set forth in the CDRLs andSOWs. We reserve the right to equitable adjustment to our price andschedule based on additional requirements that may arise from theProvisioning Guidance Conference, Provisioning Conference, or otherformally communicated requirements that may arise during the period ofperformance of this effort.6. That the Legacy Drawings are in a non-combatable format, and may need to be re-created in a new tool.
Risks
www.QinetiQ-NA.com© QinetiQ North America Operations LLC 2009
QinetiQ North America Operations LLC Proprietary
Technology Solutions Group
PADS Provisioning IPT Structure
Paul Paolillo (PM)
SystemsBob Holmes (CAM)
SE Role (TBD)
Company Name:sdsdsd(Air force)
Quinn Smith (QNA TSG)
Product AssuranceFran Rush (CAM)CM Role (TBD)DM Role (TBD)Mike Waxman
LogisticsMichelle Sullivan (CAM)
Sr. Provisioner (TBD)Deanna Dysert
Steve SpongbergTom Karol
Ed Humbarger
Drafting Fran Rush (CAM)
Drafting/Eng (TBD)
HardwareBob Holme (CAM)
Wheaton(ME)Pratt (EE)
www.QinetiQ-NA.com© QinetiQ North America Operations LLC 2009
QinetiQ North America Operations LLC Proprietary
Technology Solutions Group
Integrated Management Team Integrated Product Team (IPT) Charter
Membership, Roles, Responsibilities, and Work Products
www.QinetiQ-NA.com© QinetiQ North America Operations LLC 2009
QinetiQ North America Operations LLC Proprietary
Technology Solutions Group
Integrated Management Team IPT Charter
Charter The charter of the Integrated Management Team IPT is to transform
customer’s needs, expectations, and constraints into provisioned product solutions and support those product solutions throughout the product’s development lifecycle. The IMT IPT is an overarching IPT primarily concerned with management and oversight of PADS Provisioning program execution.
www.QinetiQ-NA.com© QinetiQ North America Operations LLC 2009
QinetiQ North America Operations LLC Proprietary
Technology Solutions Group
Integrated Management Team IPT Work Products
Integrated Baseline Reviews Program Issue Resolution IPT Management and Conflict Resolution Risk Assessment and Mitigation Cost and Schedule Control Workload Management Life Cycle/Total Ownership Cost Analysis
www.QinetiQ-NA.com© QinetiQ North America Operations LLC 2009
QinetiQ North America Operations LLC Proprietary
Technology Solutions Group
Integrated Management Team IPT Roles & Responsibilities
Roles: IPT Lead
Responsible for technical quality, cost and schedule performance for all activity within the Integrated Management Team IPT.
Overarching responsibility for Hardware, Systems Engineering, Product Assurance, and Logistics
Serves as the primary customer interface. Applies risk and opportunity management throughout the product contract
cycle. Identifies and establishes any corrective actions necessary to ensure IPT
objectives are achieved. Coordinates IPT staffing requirements with the Skillset Directors. Supports the metrics coordinator(s) in the collection and reporting of metrics
as they pertain to working group activity for the program.
IPT Member Fully understand the scope and impact of technical, cost, and schedule
issues confronting the team, so that they can communicate, to the other team members, the impact those issues have with respect to their particular area of expertise.
www.QinetiQ-NA.com© QinetiQ North America Operations LLC 2009
QinetiQ North America Operations LLC Proprietary
Technology Solutions Group
Integrated Management Team IPT Roles & Responsibilities
Responsibilities of IPT: Cost account management Contracts Finance Planning (IMS) Subcontracts Management Sourcing Support CAIV activities as required
www.QinetiQ-NA.com© QinetiQ North America Operations LLC 2009
QinetiQ North America Operations LLC Proprietary
Technology Solutions Group
Integrated Management Team IPT Membership List
www.QinetiQ-NA.com© QinetiQ North America Operations LLC 2009
QinetiQ North America Operations LLC Proprietary
Technology Solutions Group
Integrated Management Team IPT
Integrated Management Team IPT Authority/Accountability Authority/Accountability
Cost, Schedule and Technical Performance authority and accountability is held by the Integrated Management Team Control Account Manager (CAM).
Integrated Management Team IPT Metrics IPT Metrics
EV lite Cost & Schedule, IMS Critical Path, Stop light charts (Hardware/deliveries) Workload burn down for key functional areas as needed (Requirements, part research, drawing and Provisioning Card creation etc.). Also, overall technical performance authority and accountability is held by the Integrated Management Team Control Account Manager (CAM).
www.QinetiQ-NA.com© QinetiQ North America Operations LLC 2009
QinetiQ North America Operations LLC Proprietary
Technology Solutions Group
Engineering Integrated Product Team (IPT) Charter
Membership, Roles, Responsibilities, and Work Products
www.QinetiQ-NA.com© QinetiQ North America Operations LLC 2009
QinetiQ North America Operations LLC Proprietary
Technology Solutions Group
Systems Engineering IPT Charter
Charter The charter of the Engineering IPT is to transform customer’s needs,
expectations, and constraints into product solutions and support those product solutions throughout the product’s development lifecycle.
www.QinetiQ-NA.com© QinetiQ North America Operations LLC 2009
QinetiQ North America Operations LLC Proprietary
Technology Solutions Group
Systems Engineering IPT Work Products
Requirements Database Systems Documentation
Example: Technical Data Package Supporting research for Provisioning CARDs Supporting research for Drawing creation Requirements Traceability Matrix
Drafting Drawing modifications, update and creation
As needed or requested Trade Studies White Papers
Review Delivery Packages
www.QinetiQ-NA.com© QinetiQ North America Operations LLC 2009
QinetiQ North America Operations LLC Proprietary
Technology Solutions Group
Engineering IPT Roles & Responsibilities
Roles: IPT Lead
Responsible for technical quality, cost and schedule performance for all engineering activity within a IPT.
Serves as the primary customer technical interface for the respective IPT product.
Serves as IPT Control Account Manager (CAM). Applies risk and opportunity management throughout the product life cycle. Identifies and establishes any corrective actions necessary to ensure IPT
objectives are achieved. Technical process discipline within the IPT. Coordinates IPT staffing requirements with the Program Office, Skillset
Manager, and Chief Technology Officer. Supports the metrics coordinator(s) in the collection and reporting of technical
metrics as they pertain to IPT activity.
IPT Member Fully understands the scope and impact of technical, cost, and schedule
issues confronting the team, so that they can communicate, to the other team members, the impact those issues have with respect to their particular area of expertise.
www.QinetiQ-NA.com© QinetiQ North America Operations LLC 2009
QinetiQ North America Operations LLC Proprietary
Technology Solutions Group
Engineering IPT Roles & Responsibilities
Responsibilities of IPT: Accept top-level requirements and allocate to subsystems Systems Integration, assessments of derivation of lower-level
requirements, systems design decisions, and compliance with top-level requirements
Manage and approve allocation of system-level functions to subsystems and components
Lead and approve design trade studies Oversee engineering analysis in support of subsystem, component,
hardware and software design Review Verification Requirements, Risk Assessment and Mitigation and
Traceability of Requirements As needed update and review applicable sections of technical
operations and functionality within the IDE customer database environment
Support CAIV activities as required
www.QinetiQ-NA.com© QinetiQ North America Operations LLC 2009
QinetiQ North America Operations LLC Proprietary
Technology Solutions Group
Engineering IPT
Engineering IPT Authority/Accountability Authority/Accountability
Cost, Schedule and Technical Performance authority and accountability is held by the Systems Engineering Control Account Manager (CAM).
Systems Engineering IPT Metrics IPT Metrics are such things as:
EV Cost & Schedule, IMS Critical Path, Stop light charts (Hardware/deliveries) Workload burn down for key functional areas as needed (Requirements, PADS research of development, etc.). Also, overall technical performance authority and accountability is held by the Integrated Management Team Control Account Manager (CAM).
www.QinetiQ-NA.com© QinetiQ North America Operations LLC 2009
QinetiQ North America Operations LLC Proprietary
Technology Solutions Group
Hardware Engineering Integrated Product Team (IPT) Charter
Membership, Roles, Responsibilities, and Work Products
www.QinetiQ-NA.com© QinetiQ North America Operations LLC 2009
QinetiQ North America Operations LLC Proprietary
Technology Solutions Group
Hardware Engineering IPT Charter
Charter The charter of the Hardware Engineering IPT is to provide engineering
support to provision the PADS design (electrical and mechanical) that directly implements all system and hardware requirements, helps understand the hardware architecture so that flexibly supports future expansion while ensuring reliability, maintainability, and long term support throughout the contract life-cycle.
www.QinetiQ-NA.com© QinetiQ North America Operations LLC 2009
QinetiQ North America Operations LLC Proprietary
Technology Solutions Group
Hardware Engineering IPT Work Products
The PADS hardware design Technical Data Package
Detail Drawings Assembly Drawings Specification Control Drawings Vendor Item Drawings
Peer Review Packages of Drawings and Provisioning Cards
www.QinetiQ-NA.com© QinetiQ North America Operations LLC 2009
QinetiQ North America Operations LLC Proprietary
Technology Solutions Group
Hardware Engineering IPT Roles & Responsibilities
Roles: IPT Lead
Responsible for technical quality, cost and schedule performance for all engineering activity within a IPT.
Serves as the primary customer technical interface for the respective IPT product.
Applies risk and opportunity management throughout the product life cycle. Serves as IPT Control Account Manager (CAM). Identifies and establishes any corrective actions necessary to ensure IPT
objectives are achieved. Technical process discipline within the IPT. Coordinates IPT staffing requirements with the Chief Technology Officer. Supports the metrics coordinator(s) in the collection and reporting of metrics as
they pertain to IPT activity. Also responsible understanding the metrics data and for making prudent technical management decisions based on the data.
IPT Member Fully understand the scope and impact of technical, cost, and schedule issues
confronting the team, so that they can communicate, to the other team members, the impact those issues have with respect to their particular area of expertise.
www.QinetiQ-NA.com© QinetiQ North America Operations LLC 2009
QinetiQ North America Operations LLC Proprietary
Technology Solutions Group
Hardware Engineering IPT Roles & Responsibilities
Responsibilities of IPT: Direct implementation of allocated hardware requirements Integration of mechanical and electrical design elements Participate in program and technical reviews Manage hardware design including schedule and approvals Review and resolve program problem reports Support CAIV Activities as required
www.QinetiQ-NA.com© QinetiQ North America Operations LLC 2009
QinetiQ North America Operations LLC Proprietary
Technology Solutions Group
Hardware Engineering IPT
Hardware Engineering IPT Authority/Accountability Authority/Accountability
Cost, Schedule and Technical Performance authority and accountability is held by the Hardware Engineering Control Account Manager (CAM).
Hardware Engineering IPT Metrics IPT Metrics are such things as:
EV Cost & Schedule, IMS Critical Path, Stop light charts (Hardware/deliveries) Workload burn down for key functional areas as needed (Requirements, Software Development, etc.). Also, overall technical performance authority and accountability is held by the Integrated Management Team Control Account Manager (CAM).
www.QinetiQ-NA.com© QinetiQ North America Operations LLC 2009
QinetiQ North America Operations LLC Proprietary
Technology Solutions Group
0000-31
Provisioning Overview
Michelle L. Sullivan
QinetiQ NA
ILS Manager
JANUARY 2012
www.QinetiQ-NA.com© QinetiQ North America Operations LLC 2009
QinetiQ North America Operations LLC Proprietary
Technology Solutions Group
Topics
0000-32
What is Provisioning?
Where Provisioning Fits in ILS
The Provisioning Process
Provisioning Schedule
Provisioning Technical Data (PTD)
JPADS Path Forward
www.QinetiQ-NA.com© QinetiQ North America Operations LLC 2009
QinetiQ North America Operations LLC Proprietary
Technology Solutions Group
What is Provisioning?
• Provisioning is the process of identifying and obtaining the initial stock of spare parts required to support fielded equipment.
• Part of the provisioning process is to obtain National Stock Numbers (NSN’s) for spare parts. Having an NSN allows the field to purchase the items through the DoD Requisitioning System. Additionally, it allows the DoD item manager to properly forecast requirements for the items and ensure items are stocked.
• NSN assignment is accomplished by generating provisioning lists containing Provisioning Technical Data (PTD). This data identifies the parts of an item of equipment and their application within the overall system.
• QNA’s role is to provide provisioning technical data regarding the items so they may obtain a National Stock Number (NSN).
0000-33
www.QinetiQ-NA.com© QinetiQ North America Operations LLC 2009
QinetiQ North America Operations LLC Proprietary
Technology Solutions Group
The ILS Equation
0000-34
Integrated Logistics Support (ILS) is the process that facilitates the
development and integration of all of the logistics support elements to acquire, test, field, and support a
weapons system
10 ILS Elements
Design Influence
Technical Data
Maintenance Planning
Manpower and Personnel
Supply SupportTraining and Training Support
Computer Resources Support
Facilities
Packaging, Handling, Storage and Transportation
Maintain Operational Readiness at system
fielding and throughout the systems lifecycle
Provisioning is part of Supply Support
www.QinetiQ-NA.com© QinetiQ North America Operations LLC 2009
QinetiQ North America Operations LLC Proprietary
Technology Solutions Group
Integrated Logistics Support – Supply Support
Objective:
Identify, plan, resource and implement management actions to acquire and support the product required to sustain the operation and maintenance of the system to ensure the product is available when needed.
0000-35
Description:Consists of all management actions, procedures, and techniques necessary to determine requirements to acquire, catalog, receive, store, transfer, issue, and dispose of spares, repair parts, and supplies.
Process includes provisioning for initial support as well as acquiring, distributing, and replenishing inventories.
Having the right items, in the right place, at the right time
www.QinetiQ-NA.com© QinetiQ North America Operations LLC 2009
QinetiQ North America Operations LLC Proprietary
Technology Solutions Group
Provisioning Process
0000-36
Engineering Drawings
Maintenance Task Analysis (MTA) Data
Prepare Initial Provisioning List
Obtain Application Information
Research Parts Information
Prepare Detailed Provisioning List
Application Data
Cataloging Data
Review/Verify List (may require
rework)
Submit List for NSN Screening
Prepare Final Provisioning List
Submit Provisioning
Technical Data to Government
Helpful Definitions
Provisioning Parts List (PPL): The PPL is a complete listing of all the parts that make up an item of equipment. This list is prepared by the contractor (us!) and submitted to the Government at or before the provisioning conference (not to be confused with the Provisioning Guidance Conference). Provisioning Screening: Screening of provisioning lists to identify parts that have already been assigned NSN’s.
Provisioning Submittal: Provisioning Lists are submitted to the Government for review prior to each conference
www.QinetiQ-NA.com© QinetiQ North America Operations LLC 2009
QinetiQ North America Operations LLC Proprietary
Technology Solutions Group
Common Provisioning Schedule
0000-37
Submission of Post Conference List
Provisioning Conference
Submission of PTD
DLIS screening*
Long Lead Time Items Provisioning Conference
Provisioning Guidance Conference
Contract Award
*The Defense Logistics Information Service (DLIS) is responsible for screening provisioning lists for existing NSN’s
www.QinetiQ-NA.com© QinetiQ North America Operations LLC 2009
QinetiQ North America Operations LLC Proprietary
Technology Solutions Group
Provisioning Technical Data (PTD)
• PTD is any data submitted to the Government as part of the provisioning Process
• There are several different types of PTD. The data reflected in them is generally the same. The difference in the lists is the type of items for which they are prepared and the intended use of the lists.
• Per the contract, QNA will be submitting a Provisioning Parts List (PPL) for items associated with JPAD’s.
Provisioning Parts List (PPL): The PPL is a complete listing of all the parts that make up an item of equipment. This list is prepared by the contractor (us!) and submitted to the Government at or before the provisioning conference (not to be confused with the Provisioning Guidance Conference).
Additionally, some of our items will be considered Common Bulk Items (CBI’s) and will fall under a CBI list.
0000-38
www.QinetiQ-NA.com© QinetiQ North America Operations LLC 2009
QinetiQ North America Operations LLC Proprietary
Technology Solutions Group
Data elements on the PPL
• PPL be divided into two categories Cataloging Data: describes the part without regard to its usage (Ex. Item Name, NSN,
Unit of Issue, etc.) Application Data: data that relates to the specific application of the part being reported on
the provisioning list (Ex. Quantity per assembly, maintenance task distribution, etc). Application data can be different for each use of a part in a system and tell how a part is used.
• PPL is generating using engineering drawings as a basis for data.
• Some elements will be provided by the Government at the Provisioning Guidance Conference
• Data elements commonly required:
0000-39
• Provisioning List Item Sequence Number (PLISN)• Manufacturer’s Part Number• Commercial and Government Entity Code (CAGE)• Source, Maintenance, and Recovery Code (SMR)• National Stock Number (NSN)• Quantity per End Item (QPEI)• Recommended Quantity• Production Lead Time (PLT)• Unit of Issue (UI)• Item Name
www.QinetiQ-NA.com© QinetiQ North America Operations LLC 2009
QinetiQ North America Operations LLC Proprietary
Technology Solutions Group
PTD 80 Card Column Format
0000-40
www.QinetiQ-NA.com© QinetiQ North America Operations LLC 2009
QinetiQ North America Operations LLC Proprietary
Technology Solutions Group
Sample 80CC Provisioning Parts List
0000-41
ABF888A0001XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX- - - - - - - - ABF888A0001 3023312345- 65 XXXXXXXXXXXXXXXXXX2X RADAR SYSTEM - XXA ABF888A0001- - - - XXXXXXXXXXXXXXXXX- - - - - - - - - - - - XXXXXXXXXXXX- - - - - XXXXXXXXXXXXXXXXXXB ABF888A0001- XXXXX- XXXXXXXXXXXXXXXXXXXX- - - - - - - - - - - - - - - XXXXXXXXXXXXXXXXXXXXXXXXXXC ABF888A0001- XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX- - - - - - - - - - - - - - - - - - - - XXD ABF888A0001- XXXXXXXXXXXXXX- - - - - - - - - - - - - - - XXX- - - - - - - - - - - - - - - - - - - - - - - - - - - XX- - - - XXE ABF888A0001- - - - - - - - - - - - - - - - XXXXXXXXXXXXXXXXXXXXXX- - XXXXX- XXXXXXXXXXXX- - - - - - - - XXF ABF888A0001- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - XXG ABF888A0001- - - - - - - - - - - - - - - - - - - - - XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX- - XXXXXXXXXXXXH ABF888A0001- - - - - - - - - - - - - - - - - - XXXXXXXXXXX- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - XXJ ABF888A0001- - - - - - - - - - - - - - - XX- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - XXL
www.QinetiQ-NA.com© QinetiQ North America Operations LLC 2009
QinetiQ North America Operations LLC Proprietary
Technology Solutions Group
Path Forward
0000-42
Near Term:• Provisioning Guidance Conference (to be scheduled in January 2012)• Development and Review of Engineering Drawings• Development of Data Entry Forms• Provisioning Parts Lists Data Research• Training of personnel on Data Entry• Data Entry
Long Term:• Data QA for content and formatting• Data Submittal (Initial)• Review and Revision of Data (from initial submittal)• Data Submittal (Final)
www.QinetiQ-NA.com© QinetiQ North America Operations LLC 2009
QinetiQ North America Operations LLC Proprietary
Technology Solutions Group
Program ScheduleID Task Name Start Duration Finish
0 PADs Provisioning Tue 12/27/11 199 d Thu 10/4/121 Program Milestones Tue 12/27/11 169 d Wed 8/22/12
2 Contract Award Tue 12/27/11 0 d Tue 12/27/11
3 Contract Ki ckoff Tue 1/3/12 0 d Tue 1/3/12
4 CDRL A017 – Logisti cs Management Information (LMI) Data Products(S) Wed 8/22/12 0 d Wed 8/22/12
5 CDRL A018 – Supplemental Data for Provi sioning (SDFP) Wed 7/18/12 0 d Wed 7/18/12
6 CDRL A019 – Logisti cs Management Information (LMI) Summari es Thu 7/19/12 0 d Thu 7/19/12
7 Billing Milestones Wed 1/18/12 153 d Wed 8/22/12
8 Guidance Conference Wed 1/18/12 0 d Wed 1/18/12
9 Submissi on of Stock Listing Data Tue 3/6/12 0 d Tue 3/6/12
10 Submissi on of PTD (A017) Wed 8/22/12 0 d Wed 8/22/12
11 Provi sioning Conference Wed 3/21/12 0 d Wed 3/21/12
12 Submissi on of SDFP/LMI (A018, A019) Thu 7/19/12 0 d Thu 7/19/12
13 Spares Conference Fri 7/6/12 0 d Fri 7/6/12
14 Program Management Tue 12/27/11 169 d Wed 8/22/12
15 Program Manager Tue 12/27/11 169 d Wed 8/22/12
16 Confi gurati on Manager Tue 12/27/11 169 d Wed 8/22/12
17 Conferences Wed 1/18/12 121 d Fri 7/6/12
18 Depot Provisi oning Conference Wed 1/18/12 1 d Wed 1/18/12
19 Spares Provisioning Conference Wed 3/21/12 1 d Wed 3/21/12
20 Extra Provisioning Conference (Cost Risk Miti gati on) Fri 7/6/12 1 d Fri 7/6/12
21 Pre-Prov isioning Data Wed 1/4/12 130 d Thu 7/5/12
22 Document Tree Wed 1/4/12 130 d Thu 7/5/12
23 Develop Ini tial Document Tree Wed 1/4/12 10 d Tue 1/17/12
24 Research Exi sti ng National Stock Listings Wed 1/18/12 10 d Tue 1/31/12
25 Research QNA parts for National Stock Li sti ng Wed 2/1/12 20 d Tue 2/28/12
26 Input Data D220 Format Wed 2/29/12 5 d Tue 3/6/12
27 Submit DLA Tue 3/6/12 0 d Tue 3/6/12
28 Receive from DLA Wed 6/27/12 0 d Wed 6/27/12
29 Update Document Tree Thu 6/28/12 5 d Thu 7/5/12
30 Mechanical Drawings Wed 1/4/12 45 d Tue 3/6/12
31 MBTF Analysis Wed 1/4/12 40 d Tue 2/28/12
32 MBTF Anal ysis - QNA Circuit Cards Wed 1/4/12 40 d Tue 2/28/12
33 MBTF Anal ysis - Manufactured Parts Wed 1/4/12 40 d Tue 2/28/12
34 Card Data Entry & Research Thu 6/21/12 37 d Mon 8/13/12
39 Design Change Notices Wed 1/4/12 100 d Tue 5/22/12
41 Long Lead Item List Wed 1/4/12 10 d Tue 1/17/12
43 Data Delivery Tue 8/14/12 7 d Wed 8/22/12
46 Data Rev ision Thu 8/23/12 30 d Thu 10/4/12
48 Supplemental Data for Prov isioning (DSFP) Fri 7/6/12 9 d Wed 7/18/12
53 Logistics Management Information Summaries Fri 7/6/12 10 d Thu 7/19/12
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov DecQtr 1, 2012 Qtr 2, 2012 Qtr 3, 2012 Qtr 4, 2012 Qtr 1, 2013
www.QinetiQ-NA.com© QinetiQ North America Operations LLC 2009
QinetiQ North America Operations LLC Proprietary
Technology Solutions Group
0000-44
Comments or
Questions?