www.hertsdirect.org highway adoption implementation stage highway adoption implementation stage...

27
www.hertsdirect .org www.hertsdirect .org Highway Adoption Highway Adoption Implementation Stage Implementation Stage Steve Johnson Head of Network Management

Upload: jayce-vale

Post on 15-Dec-2015

216 views

Category:

Documents


0 download

TRANSCRIPT

  • Slide 1

www.hertsdirect.org Highway Adoption Implementation Stage Highway Adoption Implementation Stage Steve Johnson Head of Network Management Slide 2 www.hertsdirect.org Session will cover Background information Overview of implementation phase Legal agreement Section 38 How the process should work Delays to the process Case studies Summary of current agreements Highway Adoption - Implementation Slide 3 www.hertsdirect.org Background information Highways Maintainable at Public Expense Until 1835 Highways Act all highways maintainable by inhabitants of parish With 1835 Act all existing public highways remained publicly maintainable. Adoption procedure applies Publicly maintainable highways: Existed before 1835 Adopted since 1835 Constructed by Secretary of State for Transport or by the highway authority Slide 4 www.hertsdirect.org Background information Highways Maintainable at Public Expense HCC do not maintain all roads within the county Motorways and trunk roads Highways Agency Private Roads/Streets developers, residents, managing companies Statutory Duty - list of all roads maintainable at public expense Best practise record private roads/streets Gazetteer HCC as Highway Authority maintain approx 4,920km Further 1,091km recorded as private road Slide 5 www.hertsdirect.org DistrictPublicly maintainable [km] Private [km] Broxbourne27936 Dacorum681117 East Herts939311 Hertsmere37466 North Herts813187 St. Albans586118 Stevenage26028 Three Rivers33577 Watford21220 Welwyn and Hatfield439131 TOTAL4,918[km]1,091[km] Slide 6 www.hertsdirect.org Overview of Implementation Phase Section 38 of the Highways Act 1980 Power of highway authorities to adopt by agreement Sets out basis for adoption HCC recover their costs Requirements for bond Requirement for commuted sum future maintenance Slide 7 www.hertsdirect.org Overview of Implementation Phase Section 38 of the Highways Act 1980 Parties include HCC as Highway Authority, developer, land owner, and bank (bond) HCC standard template Highway authority has no power to force developer to put roads forward for adoption Relies on developer to progress Slide 8 www.hertsdirect.org Overview of Implementation Phase Herts Highways responsible for S38 in 8 out of 10 districts Dacorum, East Herts, Hertsmere, North Herts, St. Albans, Three Rivers, Watford, Welwyn & Hatfield Agency agreements in Broxbourne and Stevenage Carryout certain functions of Highway Authority including Section 38 agreements relating to residential roads Work to HCC standards and procedures Joint inspections with Borough and County officers prior to issue of certificates Slide 9 www.hertsdirect.org Slide 10 Slide 11 Overview of Implementation Phase How the process should work 1.Post planning developer approaches implementation team for application pack 2.Agree extent of adoption based on HCC policy and developer requirements (proposal to change TPP to identify) 3.Fee estimate provided 4.County Secretaries instructed 5.Designs prepared by developer Roads in Hertfordshire 6.Designs checked independent safety audit Slide 12 www.hertsdirect.org Overview of Implementation Phase How the process should work 7.Designs approved 8.Legal agreement signed bond in place 9.Construction HCC (Agent) supervise 10.Works completed including any remedial 11.Completion certificate issued bond reduced 12.12 month maintenance starts 13.Stage 3 safety audit carried out outlined in agreement Slide 13 www.hertsdirect.org Overview of Implementation Phase How the process should work 14.Sewers adopted 15.Final inspection and remedial carried out 16.Maintenance certificate issued 17.Commuted sums paid by develop 18.Bond released 19.Road becomes maintainable at public expense Slide 14 www.hertsdirect.org Delays to the process Developer doesnt enter into agreement at start of project Designs change, structures added, additional phases - Highway Authority withhold maintenance certificate No direct access onto public highway Sewers not adopted Land issues to be resolved Developers change Staff changes over period of time schemes inherited Design doesnt comply with HCC standards Protracted negotiations on agreement Remedial not completed Slide 15 www.hertsdirect.org Case Studies Silk Mill Road Draft agreement 2000 Wilcon Homes Couldnt adopt as no access onto public highway as Brook End not adopted. Brook End Initially dealing with Westbury Homes Taken over by Persimmon Sewers not adopted until 2008 Finally adopted June 2008 2 nd draft issued 2004 3 rd draft issued 2009 Restructure within Taylor Wimpey change of staff so little progress Remedial to be completed Current Status ongoing negotiation Slide 16 www.hertsdirect.org Case Studies Lilbourne Drive Works have been complete for a number of years. Developer had not conveyed the highway easements Deed of Easements needed with each of the frontages. Current Status easements resolved and scheme adopted 21 st January 2010 Slide 17 www.hertsdirect.org Lilbourne Drive Easements not secured Slide 18 www.hertsdirect.org Case Study - The Hedgerows Adoption delayed - layout did not conform to original agreement drawing. Current Status agreement in place, deed of variation required Case Study - Pixmore Avenue Works commenced without technical approval Installed proposed highway drainage system within footway without consent s278 Agreement had to be modified to include Section 50 clauses Awaiting clarification and confirmation of SUDS storage tanks suitability. Current status scheme still active Slide 19 www.hertsdirect.org The Brambles - Remedial Current Status agreement not in place, remedials to be completed, sewer adoption Slide 20 www.hertsdirect.org Yearling Close Non standard design Current Status agreement not in place, drainage issues and remedial works to be completed Slide 21 www.hertsdirect.org Summary of current agreements List of Section 38 agreements in pack Sites we are working on to adopt Historic schemes inherited by Herts Highways in 2002 - funding 48 sites agreements in place 76 sites agreement being prepared Approximately 200 roads Slide 22 www.hertsdirect.org Summary of HH Section Agreements DistrictSigned Agreement Agreement in Prep stage TotalNo. of roads affected Broxbournen/a Dacorum42611 East Herts7121934 Hertsmere2248 North Herts7142138 St. Albans10142434 Stevenagen/a Three Rivers14510 Watford36913 Welwyn and Hatfield 14223652 TOTAL4876124200 Slide 23 www.hertsdirect.org Improvements Guidance for developers Proactive stance Close working with developers cleared 36 sites in East Herts since 2004 Similar approach in South West and Mid Herts Restructure of team Investigation & developing process for calling in bond on one or two sites as a trial Standard report to members/JMPs - highway adoption Slide 24 www.hertsdirect.org Summary Key issues 1.Follow legislation 2.Need to work with developers to progress 3.Early involvement of Highway Authority 4.Land ownership and easements agreed 5.Designed and constructed to relevant standards departures agreed with Highway Authority 6.S 38 agreement in place. 7.Utility apparatus adopted by relevant authority (sewers) 8.Number of roads/streets are private Slide 25 www.hertsdirect.org Section 38 Agreements - Agency Broxbourne Roads under construction 7 Roads completed but S38 not signed 15 Roads completed S38 signed and in maintenance period 11 Roads completed S38 signed, maintenance period expired but remedial works 1 Total Unadopted roads - 34 Slide 26 www.hertsdirect.org Section 38 Agreements - Agency Stevenage Agreements in maintenance period 7 Agreements being progressed - 14 Slide 27 www.hertsdirect.org Highway Adoption - Implementation Questions?