Strictly Confidential 2016-03-09 Page 1 Robbins / ESOL RNA Strictly Confidential dresser-rand.com March 9, 2016 WRBA Annual Meeting Steam Turbine Overhaul

Upload: others

Post on 15-Oct-2021

14 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: WRBA 2016 Steam Turbine Overhaul

Strictly Confidential

2016-03-09Page 1 Robbins / ESOL RNA

Strictly Confidential dresser-rand.com

March 9, 2016

WRBA Annual MeetingSteam Turbine Overhaul

Page 2: WRBA 2016 Steam Turbine Overhaul

Strictly Confidential

2016-03-09Page 2 Robbins / ESOL RNA

• Project Overview 3

• Disassembly Inspection 4

• Repair 5

• Final Report 6

• Reference 7

• VIP Parts Program 8

• Damaged Parts 10

• New Equipment 13

• Catastrophic Failures 16

• Contact Page 18

Table of content

Page 3: WRBA 2016 Steam Turbine Overhaul

Strictly Confidential

2016-03-09Page 3 Robbins / ESOL RNA

Project Overview

• Project Overview

• Receiving Report

• Inspection Scope

1. Complete Turbine

2. Multi-Stage Turbine Rotor

• Turbine Pre-Inspection

• Project Data Management Team Form

Page 4: WRBA 2016 Steam Turbine Overhaul

Strictly Confidential

2016-03-09Page 4 Robbins / ESOL RNA

Disassembly Inspection

• Inspection Report

• Inspection Forms – Disassembly

1. Multi-Stage Turbine (MST) Visual Inspection Report

2. Turbine Dimensional Inspection Report

3. MST Stationary Assembly Clearances

4. Trip & Throttle (T&T) Valve Disassembly Report

5. Control Valve Assembly Inspection

6. Misc. Turbine Dimensional Inspection Forms (Supplied by Supervisor)

7. Non-Destructive Test (NDT) Report

Page 5: WRBA 2016 Steam Turbine Overhaul

Strictly Confidential

2016-03-09Page 5 Robbins / ESOL RNA

Repair

• Repair Scope

• Additional Work

• Parts List Request

1. Parts Quote

2. Factory Packing List

• Inspection Forms - Assembly

1. Turbine Dimensional Inspection Report

2. MST Stationary Assembly Clearances

3. Control Valve Assembly Inspection

4. Checklist for Turbine Assembly

5. Misc. Turbine Dimensional Inspection Forms (Supplied by Supervisor)

Page 6: WRBA 2016 Steam Turbine Overhaul

Strictly Confidential

2016-03-09Page 6 Robbins / ESOL RNA

Final Report

• Job History

• Final Release

• Shipping

• Packing Slip

Page 7: WRBA 2016 Steam Turbine Overhaul

Strictly Confidential

2016-03-09Page 7 Robbins / ESOL RNA

Reference

• Job Safety Environmental Analysis (JSEA) / Safety

• Standard Work Instructions (SWI)

• Non-Conformance Report (NCR) Forms

• Bill of Material (BOM)

• Drawings

• Photos

• Correspondence

Page 8: WRBA 2016 Steam Turbine Overhaul

Strictly Confidential

2016-03-09Page 8 Robbins / ESOL RNA

VIP Parts Program

• The VIP Parts Program provides the Client with an easier way to identify

and order parts for D-R SSTs by using reference numbers/catalog

numbers vs. actual part numbers. The parts are also categorized by

three different levels:

• V = Vital parts (1-year/start-up spares)

• I = Ideal parts (2-year spares)

• P = Preventative parts (major components)

Page 9: WRBA 2016 Steam Turbine Overhaul

Strictly Confidential

2016-03-09Page 9 Robbins / ESOL RNA

VIP Turbine Program – illustration

Page 10: WRBA 2016 Steam Turbine Overhaul

Strictly Confidential

2016-03-09Page 10 Robbins / ESOL RNA

Rotor Damage

This turbine shaft is beyond repair

Page 11: WRBA 2016 Steam Turbine Overhaul

Strictly Confidential

2016-03-09Page 11 Robbins / ESOL RNA

Turbine Blade Damage

Foreign Material and Chemical

Page 12: WRBA 2016 Steam Turbine Overhaul

Strictly Confidential

2016-03-09Page 12 Robbins / ESOL RNA

Nozzle Block Damage

Steam Cuts and Chemical/Heat

Page 13: WRBA 2016 Steam Turbine Overhaul

Strictly Confidential

2016-03-09Page 13 Robbins / ESOL RNA

Turbine Interstage Section

Page 14: WRBA 2016 Steam Turbine Overhaul

Strictly Confidential

2016-03-09Page 14 Robbins / ESOL RNA

New MST Case

Page 15: WRBA 2016 Steam Turbine Overhaul

Strictly Confidential

2016-03-09Page 15 Robbins / ESOL RNA

Typical New MST Rotor

Page 16: WRBA 2016 Steam Turbine Overhaul

Strictly Confidential

2016-03-09Page 16 Robbins / ESOL RNA

8” Shaft Sheared and Last Row of Blades Flung

Page 17: WRBA 2016 Steam Turbine Overhaul

Strictly Confidential

2016-03-09Page 17 Robbins / ESOL RNA

Catastrophic Turbine Failure

Page 18: WRBA 2016 Steam Turbine Overhaul

Strictly Confidential

2016-03-09Page 18 Robbins / ESOL RNA

Mario Polselli

Account Manager

Sales / PNW Region / Department PG DR SE NAM AC3

1016 38th Street

Bellingham, WA 98229 USA

Phone: +1 (360) 778-1184

Fax: +1 (360) 778 1215

Mobile: +1 (360) 961-59680

E-mail:

[email protected]

Contact page

dresser-rand.com