wp3.2.2 gina trials execution trials execution status 8 th june 2010 brussels gnss for innovative...
TRANSCRIPT
WP3.2.2 GINA Trials execution
Trials execution Status
8th June 2010
Brussels
GNSS for INnovative Road Applications
GNSS for Innovative road Applications
Company’s
logo
Introduction
08/06/2010 Page 2PM#4 WP3.2.2 GINA Trials Execution
MAIN ITEMS:
WP3.2.2 trials execution currently ongoing
Exhaustive Trials Campaing concluded (both GMV & Navteq vehicles)
Exhaustive Trials analysis phase ongoing
GMV vehicle data preliminary results
Navteq vehicle data ready for analysis
End2End trials SW development and integration concluded
End2End trials OBEs production & installation currently ongoing after initial delays
Enforcement trials expected to be carried out once end2end trials are running
AENOR trials arrangments to be finished, final dates for the test (Summer 2010) to be concluded soon
GNSS for Innovative road Applications
Company’s
logo
Exhaustive Trials definition
08/06/2010 Page 3PM#4 WP3.2.2 GINA Trials Execution
1. GNSS OBU 2. GNSS Reference System 4. Geobjects Definition
GINA EXHAUSTIVE TRIALS: Evaluation of GNSS system peformance in terms of Position performance, Distance calculation performance, geo-objects detection performance and charging performance
Different configurations to be tested for results comparison GNSS GNSS + EGNOS (SISNET) GNSS + CANBUS GNSS + CANBUS + EGNOS (SISNET)
Two different vehicles operated by different Companies (GMV & Navteq)
Use of different defined geobjects with different definitions to test OBU performance
One vehicle subject to pre planned challenging routes (GMV) and other vehicle following its daily routes (Navteq)
3. Evaluation Routes
Exhaustive Trials ConceptExhaustive Trials Concept
GNSS for Innovative road Applications
Company’s
logo11/05/2010 Page 4
GINA: Evaluacion de Sistemas GNSS/GALILEO en el marco de aplicaciones EFC/RUC. Procedimiento, Metodologia y Resultados
Exhaustive Trials Status
GMV VehicleGMV Vehicle Navteq VehicleNavteq Vehicle
Navteq Trial campaing succesfully concluded June 2010
OBU and Reference system Data to be handed out by Navteq
OBU and Reference data to be processed as in GMV vehicle
Analysis phase for Navteq Data to take place after GMV analysis ends
Trial campaign succesfully concluded in April 2010
Data from the OBU and reference system collected and processed
Processed Data analysed and first set of results evaluated
Second analysis phase to introduce corrections and fine tunning
Evaluation Report and related results deliverable expected to start after 2nd
evaluation
Navteq results to be included together with GMV vehicle in the
evaluation Report
GNSS for Innovative road Applications
Company’s
logo
End2End Trials definition
08/06/2010 Page 5PM#4 WP3.2.2 GINA Trials Execution
1 EFC System Architecture 2 GINA end2end Trials Architecture
GNSS for Innovative road Applications
Company’s
logo
End2End Trials RUC Centre
08/06/2010 Page 6PM#4 WP3.2.2 GINA Trials Execution
FEATURES: User Interface & services communications through web applications
Billing Generator Module
Compliant with Netherlands EFC scheme requiriments (i.e privacy)
Report and charges generation
user profiles information and modification
GNSS for Innovative road Applications
Company’s
logo
RUC Service Centre Status
21/04/23 Page 7GINA Trials Execution
Billing Module fully operative
End user interface operative
Additional functionalities may be developed to provide additional information, e.g.
Geographical objects map
Publish table of tariffs
Users log into the system anonymously with the device number of their vehicle
Definition of charging schemes and tariffs ongoing
Integration test with VAS Module ready
GNSS for Innovative road Applications
Company’s
logo
End2End trials VAS Platform
08/06/2010 Page 8PM#4 WP3.2.2 GINA Trials Execution
RITA Reports online with test data at:
http://194.79.89.182/Gina/
The following features already functional and integrated
– General Traffic Information• Displays the zones, total Kms and average speed for all OBU IDs between a
given time interval
– Total vehicles by speed interval• Displays the vehicle count across a series of speed intervals for a given time
interval
– Traffic statistics by date• Displays the total amount of
– Traffic statistics by zone
GNSS for Innovative road Applications
Company’s
logo
End2End trials VAS Platform Status
08/06/2010 Page 9PM#4 WP3.2.2 GINA Trials Execution
General Traffic Information Total Vehicles per speed interval
Traffic Statistics By Date Traffic Statistics By Zone
GNSS for Innovative road Applications
Company’s
logo21/04/23 Page 10PRESENTATION TITLE VERDANA (9)
RITA providing PAYD per vehicle details in central system.
E2E trials VAS Platform
GNSS for Innovative road Applications
Company’s
logo
End2End Trials OBUs
08/06/2010 Page 11PM#4 WP3.2.2 GINA Trials Execution
EVENTS: OBEs materials provision delays and uncompliant materials produced a big delay in the process start
Installations appointments and material shipments had to be rescheduled thus increasing the final delay
Process already started and expected to be finished without any more setbacks
GNSS for Innovative road Applications
Company’s
logo
Geo-Objects Definition
08/06/2010 Page 12PM#4 WP3.2.2 GINA Trials Execution
GINA GEOBJECTS: Use of different geobjects classes in order to check OBU geobject recognition performance
Different classes Different geobjects definition methodology Different sizes for same geobjects
Different sub sets of geobjects for the different trials End2end trials geobjects GMV exhaustive trials geobjects Navteq exhaustive trials geobjects
GP0
GP1GP2
GP3
GP4
GP5
GNSS for Innovative road Applications
Company’s
logo08/06/2010 Page 13PM#4 WP3.2.2 GINA Trials Execution
Geo-Objects Definition Status
Exhaustive Trials GeobjectsExhaustive Trials Geobjects End2End Trials GeobjectsEnd2End Trials Geobjects
Status: Exhaustive geobjects definition closed
GMV exhaustive trial geobjects Navteq exhaustive trials geobjects
GMV exhaustive geobjects defined 51 different geobjects
Entry/Exit points Segments (Higway and urban) Cordon / Charging areas
3 locations Amsterdam The Hague Rotterdam
Different legal definitions and methodologies Geobjects x1, x2, x4
Navteq exhaustive Geobjects defined Cordons & entry/exit points (crossings) Adapted to navteq vehicle routes X geobjects defined
Status: End2End geobjects definition closed
End2end geobjects placed around strategic locations
volunteers likely routes
main roads
Postal codes areas
20+ geobjects defined
Segments (Higways)
Charging Areas
Nijmegen
Utrecht
Rotterdam
The Hague
GNSS for Innovative road Applications
Company’s
logo21/04/23 Page 14PRESENTATION TITLE VERDANA (9)
Enforcement trials status
ITEMS:
Enforcement Trials expected to take place after end2end trials kickoff
Date: July 2010
Place: not decided yet
Enforcement Trials will be split in two different phases
OBU – Enforcement Platform communication testing (Remote)
Enforcement live trials involving OBU & ANPR systems
1 OBU will be installed in a test vehicle
Test vehicle will drive around the area of the ANPR system
ANPR will trigger the central system into asking the OBU
GNSS for Innovative road Applications
Company’s
logo04/21/23 Page 15PRESENTATION TITLE VERDANA (9)
Specification and development in progress
1. Fleet Management• GIS Map with real-time vehicle positioning• Ready for test
2. Incident Management• Automatic detection of time taken from incident detection to arrival on site.• Under development
3. Contract obligations enforcement• Provide reports with information regarding specific sites and times
monitored per day• Under development
4. Reports• Current version under review by ASCENDI
Specification details under discussion with ASCENDI for 2 and 3¿? Date and location ¿?
ASCENDI (AENOR) trials status
GNSS for Innovative road Applications
Company’s
logo
ASCENDI (AENOR) Trials
08/06/2010 Page 16PM#4 WP3.2.2 GINA Trials Execution
VEHICLE TRACKING
GNSS for Innovative road Applications
Company’s
logo
ASCENDI (AENOR) trials
08/06/2010 Page 17PM#4 WP3.2.2 GINA Trials Execution
Fleet Management Report Incident Management Report
GNSS for Innovative road Applications
Company’s
logo
ASCENDI (AENOR) trials
08/06/2010 Page 18PM#4 WP3.2.2 GINA Trials Execution
Contract Obligations Enforcement Reports
GNSS for Innovative road Applications
Company’s
logo
Next Steps & Open Points
08/06/2010 Page 19PM#4 WP3.2.2 GINA Trials Execution
Open Points Actions Needed
- GMV Exhaustive trials results analysis
Review 1st analysis results (DATE) Fine Tune results (DATE) Prepare evaluation Report (DATE)
- Navteq Exhaustive trials results analysis
Collect Navteq vehicle data (DATE) Process data results (DATE) Evaluate and compare results (DATE)
- End2End Trials Campaign Start Ship all the remaining OBUs (DATE) Finish installations for the 100 OBUs (DATE) Start data collection process
- End2End Trials Platform Introduce charging schemes & tariffs (DATE) Feed real data into the platform
- Enforcement Trial definition Carry out Enforcement Communication Trials (DATE) Carry out Enforcement Live Trials (DATE)
- AENOR Trials End definition phase together with ASCENDI (DATE) Carry out defined tests (DATE)
Thank you