WP12 Management Report & EuCARD-2 Updates. [email protected] [email protected] [email protected] 16- 17 th April 2014 WP12 First Annual Review Meeting, CEA Saclay. WP12 Innovative RF Technologies. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: WP12  Management Report  &  EuCARD-2 Updates

EuCARD-2 is co-funded by the partners and the European Commission under Capacities 7th Framework Programme, Grant Agreement 312453

WP12 Management Report & EuCARD-2 Updates

[email protected]@cea.fr

[email protected]

16- 17th April 2014WP12 First Annual Review Meeting, CEA Saclay

Page 2: WP12  Management Report  &  EuCARD-2 Updates

WP12Innovative RF Technologies

• This JRA focuses on the development of a range of technical solutions that has the potential to achieve significant performance increases in gradient, efficiency and beam quality of RF-based accelerator systems.

• Several novel techniques in the field of normal and superconducting RF technology have been selected, presenting the highest impact potential and with the additional benefit of profiting from exchanges and communication between these two distinct communities.

• Main R&D areas encompass: – SRF Thin Films – C Antoine (CEA Saclay); – High Gradient NC Cavities – W Wuensch (CERN)– SRF HOM Beam Diagnostics – R Jones (Manchester University)– RF Photocathodes – R Nietubyc (NCBJ)

Reducing the footprint, machine energy consumption and overall cost of linear accelerators are of

primary importance for all accelerators being developed today.

High Risk High Win!

Page 4: WP12  Management Report  &  EuCARD-2 Updates

WP12 Pushing the Envelope

• Beam Generation:– New photocathodes providing

demonstration of highest beam intensities and smallest beam emittances.

• Acceleration:– Demonstration of the highest level of

acceleration performance.

• Beam Diagnostics/Control:– Demonstration of high performance and

low cost beam position diagnostic.

Integrated and balanced programme encompassing high performance

capabilities across both SC and NC technologies.

Page 5: WP12  Management Report  &  EuCARD-2 Updates

Fundamental Objectives

12.2 Thin FilmsExploitation of new superconducting materials, such as Nb3Sn and the development of new nano and multi-layer thin films, each anticipated to break new ground in the performance of SC accelerator cavities, with the potential of achieving gradients well beyond present Nb technology.

12.3 High Gradient NC CavitiesDevelopment of an efficient NC structure capable of high gradient operation (Eacc > 100 MV/m) but free from dangerous wakefield contributions.

12.4 SRF HOM Beam DiagnosticsDevelopment of electronics for utilising Higher Order Mode (HOM) signals from accelerating cavities for precision beam position diagnostics in high-energy electron linear accelerators, with the goal of reducing accelerator cost and length.

12.5 RF PhotocathodesDevelopment of next generation advanced RF photocathodes, exploring revolutionary production techniques as lead deposition, diamond amplifier cathode and metallic photocathodes, enhancing the ability to reach fs response time, for more effective electron beam generation, capture and transport with high brightness and low intrinsic emittance.

Page 6: WP12  Management Report  &  EuCARD-2 Updates

Task 12.1 Management & Coordination

• The WP12 Task 12.1 management team:– Nicoleta Baboi (DESY)– Juliette Plouin (CEA) – Peter McIntosh (STFC)

• WP12 Steering Committee comprises above plus the 4 Task Leaders.

• Annual WP12 review meetings:– Alternating venues; CEA, DESY, STFC & CERN.– Each including a Task Leader SC meeting. – Approximately 1 month before each EUCARD-2 Annual Review.

Page 7: WP12  Management Report  &  EuCARD-2 Updates

WP12 Milestones

Milestone Title Beneficiary Date Comments

MS87 Fundamental SRF Thin Film physics report CEA M48 Final Activity Report

MS84 Deposition test facility designed at CEA. CEA M40 Facility designed and validated

MS78 Characterisation test facility implemented at HZB HZB M30 Facility implemented and validated

MS88Report summarising the results obtained in characterising the various new thin film technologies developed, which include both multilayer and monolayer techniques

CEA M48 Final Activity Report

MS81 RF design CLIC_DDS_B UNIMAN M36 Activity Report.

MS86 RF design of fully interleaved structure and CLIC SW study. UNIMAN M45 Activity Report. Concluding final report

MS76 High power RF components fabricated and tested at low level CEA M24 Prototype completed and validated

MS74 Design concept RF front end PSI M12 Activity Report

MS77 Phase stabilisation experiment design ULANC M24 Activity Report

MS79 Crab cavity electromagnetic design ULANC M30 Activity Report

MS82 Completed coupled cavity simulations of 8-cavity module UNIMAN M36 Activity Report

MS80 Demonstrated operation of improved deposition system, Pb layers of 1 μm in thickness. NCBJ M30 Report on sample characterisation

MS73 Commissioning of the SAPI for operation with metal photocathodes STFC M8 Publication report

MS75 Investigation of quantum yield and energy spectrum of the electrons, emitted from the metal photocathode surface in SAPI STFC M18 Intermediate scientific report

MS83 Manufacturing and commissioning of the photocathode transport system STFC M36 Technical design report

MS85 Investigation of the brightness of different metal photocathodes in a S-band NCRF gun STFC M42 Scientific report

Task 12.2

Task 12.3

Task 12.4

Task 12.5

Page 8: WP12  Management Report  &  EuCARD-2 Updates

WP12 Deliverables

Deliverable Title Beneficiary Date Comments

D12.1 Deposition test facilities implemented and verified at CERN and INPG. CERN M18 Report

D12.5 First resonator deposited and qualified at CERN. CERN M36 ReportD12.10 Cavity deposited and qualified at CEA. CEA M48 ReportD12.2 Initial progress report of task 12.3. CERN M18 ReportD12.6 Intermediate progress report of task 12.3. CERN M36 Report

D12.11 Final report of task 12.3. CERN M48 ReportD12.3 Design of electronics for XFEL HOM diagnostics. DESY M18 Report

D12.7 Completed characterisation of HOMs in the 8-cavity XFEL 3HC module. UNIMAN M36 Report

D12.12 Report on characterisation of HOMs in XFEL coupled 3HC cryomodule. UNIMAN M48 Report

D12.4 Scientific report on photocathode R&D. STFC M18 Report

D12.8 Optimised procedure for microdorplets flattening with an UV laser. NCBJ M36 Report

D12.9 Pb/Nb plug photocathodes measurements and characterization. HZDR M42 Report

D12.13 Results of DAC implementation in SRF guns. HZB M48 Report

Task 12.2

Task 12.3

Task 12.4

Task 12.5

Page 9: WP12  Management Report  &  EuCARD-2 Updates

Deliverable Approval Process

• EuCARD-2: 62 deliverables and 94 milestones to review and approve.• Huge task, needs to be well organised.• Milestones: approved by WP Coordinator and Coordinator• Deliverables: approved by Steering Committee and Coordinator after a

WP review process.2 months before deadline Project Assistant send reminder to Responsible (with copy to WP

Coordinator and Project Coordinator)1 month before deadline Report sent to WP Coordinator for comments.

Between 30 and 20 days before deadlineStart Review phase

WP Coordinator or Author send Report to Project Assistant who enters report in EDMS and notifies the Reviewers: Coordinator, WP Coordinator, one selected member of SC. Comments entered in EDMS

10 days before deadlineStart Approval phase

Author enters comments and corrections and submits a final version. All SC is notified and can give comments or approve/reject the report. The Coordinator gives final approval

At deadline The Deliverable Report is sent to EU Project Officer.

Page 10: WP12  Management Report  &  EuCARD-2 Updates

1st Annual Report -URGENT

Deadlines:Advised start of writing 1 April 2014Advised input from Task Leaders to WP Coordinators ~ 1 May 2014 Input from WP Coordinators to Project Coordinator Sunday 18 May 2014Draft completed, submitted to Steering Committee Y+30 30 May 2014Draft approved and available on web site Y+60 30 June 2014 Size:Inputs from Task Leaders: 1 or 2 pages, including 1 or 2 pictures, graphs, tables.Inputs from WP coordinators: input from Tasks (between 8 and 12 pages) plus an introductory summary.

Templates available at: https://espace.cern.ch/eucard2-intranet/Annual%20Reporting/Forms/AllItems.aspx

Page 11: WP12  Management Report  &  EuCARD-2 Updates

EUCARD-2 Annual Review

• 19-22 May 2014 @ DESY• Encourage all WP12 collaborators to

attend.

• On Tuesday 20th May:– WP12 Report by P McIntosh.– WP12 Highlight talk on:

• HOM-based Beam Diagnostics: from FLASH to the European XFEL, by N Baboi (DESY).

• On Wednesday 21st May:– Parallel WP12 session (3-hour).– Utilisation to be determined with SC

this week.https://indico.cern.ch/event/302074/overview

Page 12: WP12  Management Report  &  EuCARD-2 Updates

WP12 Publications

Author Title Link

C.B. Baumier (IPNO)Task 12.2

Multilayers Activities at Saclay / Orsay SRF 2013 http://ipnweb.in2p3.fr/srf2013/papers/weioc02.pdf

M Dehler (PSI)Task 12.3

Wake field monitors in a multi purpose X Band accelerating structure

IBIC13: http://accelconf.web.cern.ch/AccelConf/IBIC2013/papers/webl3.pdf

T Flisgen (UROS)Task 12.4

Scattering parameters of the 3.9 GHz accelerating module in a free-electron laser linac: A rigorous comparison between simulations and measurements

Phys. Rev. ST Accel. Beams 17, 022003 (2014)

R. Barday (HZB)Task 12.5

Characterization of a superconducting Pb photocathode in a superconducting rf photoinjector cavity

Phys. Rev. ST Accel. Beams 16, 123402 – Published 6 December 2013

Every publication needs to be uploaded into CDMS (@ CERN) by the management team.

Please ensure we’re informed of all WP12 publications generated!

Page 13: WP12  Management Report  &  EuCARD-2 Updates

SharePoint Pages

• Contact lists

• Document sharing (templates, drafts, presentations, project documents, meeting minutes)

• List of actions / to do lists / prepare events

• Collaborative calendar (synchronised with Outlook calendar)

• Image/photo libraries

• Discussion forums SharePoint Workspacehttps://espace.cern.ch/eucard2-intranet/

Page 14: WP12  Management Report  &  EuCARD-2 Updates

WP12 Sharepoint Site

https://espace.cern.ch/eucard2-intranet/WP12/default.aspx

Note: Need to have a CERN NICE account – follow instructions!

Page 15: WP12  Management Report  &  EuCARD-2 Updates

Accelerating News Newsletter• Issue 9 published www.acceleratingnews.eu• EuCARD-2 related stories in this issue:

– Launching video– Explore accelerator applications (WP4)– FCC kick-off (sponsored by WP5)– A step towards Next Generation Magnets (WP10)

• 1315 subscribers! • Survey results (overall rating 4.6/5)• Planned stories for June 2014

– Report on Annual event– WP12 suggestions?

In past issues:• WP3• WP5• WP12• WP13

Task 12.2 Performance breakthrough for SRF thin film, utilising multi-layer, high Tc technologies.

Task 12.3 Breakdown free performance capability demonstrated for >100MV/m NC RF structures.

Task 12.4 High performance beam position diagnostic demonstrated for XFEL.

Task 12.5 High performance (intensity, emittance) photocathodes demonstrated for SRF and NC applications.

Page 16: WP12  Management Report  &  EuCARD-2 Updates

Monographs

• 6 published so far, incl. EuCARD final report:

WP12 Topics?!?!?

Page 17: WP12  Management Report  &  EuCARD-2 Updates

WP12 Website

WP12 website can be found here: http://www.cockcroft.ac.uk/events/WP12/

Page 18: WP12  Management Report  &  EuCARD-2 Updates

WP12 Annual Review

Organisation:• Review hosted at: https://indico.cern.ch/event/301619/• Group photograph during morning coffee break today.• Review dinner this evening at ‘Au port du salut’ at 19:30• Laboratory tour: 09:00 – 10:30 tomorrow.

Many thanks:• To the CEA organising committee:

– particularly Juliette Plouin and Catherine Desailly-Guyard• To all WP12 task leaders