In this presentation, Dragon Innovation will provide an overview to working with oversea contract manufacturers. This presentation was given at the Las Vegas Hardware Meetup in My 2014. Topics will include: - Dragon Innovation Introduction - Product Development: The Old Way & The New Way - Decide Where to Build - Request for Quote / Contract Manufacturer Selection - Schedule - The Road to Production - Quality Share the presentation here: http://bit.ly/Overseas-Contract-Manufacturers About Dragon Innovation Dragon Innovation works with entrepreneurs to launch hardware products and scale companies. Founded by a team of hardware experts, Dragon provides a clear path from prototype through production with unmatched manufacturing expertise and trusted connections. Dragon's client roster includes Coin, MakerBot, LIFX, Scout, Romotive, Sifteo, Orbotix, FormLabs and over 100 more companies paving the road for how new technology gets made. Connect with Dragon Innovation Website: http://www.dragoninnovation.com Blog: http://blog.dragoninnovation.com Twitter: http://twitter.com/dragoninnovate Slideshare: http://www.slideshare.net/dragoninnovation/TRANSCRIPT
![Page 1: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/1.jpg)
DRAGON INNOVATION, INC. !
WORKING WITH OVERSEAS CONTRACT MANUFACTURES
!MAY 19, 2014
LV HARDWARE STARTUPS MEETUP| LAS VEGAS !!!!!
SCOTT N. MILLER | CEO | @DRAGONINNOVATE | WWW.DRAGONINNOVATION.COM
![Page 2: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/2.jpg)
No Need To Take Notes
http://bit.ly/Overseas-Contract-Manufacturers
![Page 3: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/3.jpg)
MIT RoboTuna
3
![Page 4: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/4.jpg)
Disney Dino
4
![Page 5: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/5.jpg)
My Real Baby
5
![Page 6: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/6.jpg)
Product Development !
The Old Way
6
![Page 7: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/7.jpg)
Build then Sell
7
![Page 8: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/8.jpg)
Agenda
8
Arrgh!
![Page 9: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/9.jpg)
9
![Page 10: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/10.jpg)
Agenda
10
![Page 11: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/11.jpg)
HARDWARE IS EXPLODING
Unprecedented periods of growth come with lots of chaos.
![Page 12: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/12.jpg)
DRAGON INNOVATION HAS HELPED LAUNCH AND SCALE OVER 100 COMPANIES SINCE 2009
![Page 13: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/13.jpg)
HARDWARE INNOVATION NOW COMES FROM THE LITTLE GUY Prototyping has never been easier thanks to 3D printing, Arduino, the Maker Movement
(all of these guys are Dragon clients)
![Page 14: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/14.jpg)
Product Development !
The New Way
14
![Page 15: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/15.jpg)
CROWDFUNDING IS FUEL ON THE FIRE
•Raise capital upfront •Validate product / market fit •Create engaged & passionate community early •Get the attention of media and investors •Understand build volumes
New transactional model is perfect for hardware
![Page 16: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/16.jpg)
But the promise of the hardware revolution faces an existential
threat.
75% OF CROWDFUNDED HARDWARE PROJECTS
DELIVER LATE OR NOT AT ALL
!!
PROF. ETHAN MOLLICK, UNIVERSITY OF PENNSYLVANIA / WHARTON
![Page 17: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/17.jpg)
17
•COGS & Tooling Estimation •DFMA •Funding Threshold Calculation •Production Strategy & Scheduling •Marketing Strategy •Connections
![Page 18: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/18.jpg)
STEP 1: DECIDE WHERE TO BUILD
![Page 19: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/19.jpg)
Examples to Talk Through
![Page 20: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/20.jpg)
China?
![Page 21: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/21.jpg)
21
Yes! Manufacture in China If Your Product... Is COGS (Cost of Goods Sold) sensitive
![Page 22: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/22.jpg)
22
Yes! Manufacture in China If Your Product... Requires higher production volumes (>10k units)
![Page 23: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/23.jpg)
23
Yes! Manufacture in China If Your Product... Requires significant manual labor to manufacture and assemble
![Page 24: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/24.jpg)
24
Yes! Manufacture in China If Your Product... Uses existing manufacturing technology (i.e. injection molding, etc)
http://berkeleysg.com
![Page 25: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/25.jpg)
25
Yes! Manufacture in China If Your Product... Is tolerant of variations in supply chain and logistics
http://berkeleysg.comhttp://kilterpulse.com
![Page 26: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/26.jpg)
26
Yes! Manufacture in China If Your Product... Can benefit from low cost Design for Manufacturing (DFM) Non-recurring Engineering (NRE)
http://berkeleysg.comhttp://kilterpulse.com
http://plasticstoday.com
![Page 27: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/27.jpg)
27
Yes! Manufacture in China If Your Product... Has “physically” protectable IP
http://berkeleysg.comhttp://kilterpulse.com
![Page 28: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/28.jpg)
China Drawbacks for Manufacturing
![Page 29: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/29.jpg)
29
China Drawback Significant Distance from USA
http://supplychaindigital.com
http://skeptically.orghttp://studentuniverse.com
![Page 30: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/30.jpg)
30
China Drawback Significant Language Barrier
http://supplychaindigital.com
http://skeptically.orghttp://studentuniverse.com
http://asiasociety.org
![Page 32: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/32.jpg)
32
China Concern Rising Exchange Rate
http://en.wikipedia.org
![Page 33: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/33.jpg)
USA?
![Page 34: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/34.jpg)
34
Yes! Manufacture in the US If Your Product... Requires low volumes
http://berkeleysg.comhttp://kilterpulse.com
http://www.theguardian.com
![Page 35: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/35.jpg)
35
Yes! Manufacture in the US If Your Product... Can be manufactured and assembled through automation
http://berkeleysg.comhttp://kilterpulse.com
![Page 36: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/36.jpg)
36
Yes! Manufacture in the US If Your Product... Is sensitive to shipping time and expense
http://berkeleysg.comhttp://kilterpulse.com
![Page 37: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/37.jpg)
37
Yes! Manufacture in the US If Your Product... Has difficult-to-protect IP
http://berkeleysg.comhttp://kilterpulse.com
http://www.independent.co.uk
![Page 38: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/38.jpg)
38
Yes! Manufacture in the US If Your Product... Requires non-standard capital equipment
http://scientificmachining.com
![Page 39: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/39.jpg)
39
Yes! Manufacture in the US If Your Product... Is part of a government contract
http://en.wikipedia.org
![Page 40: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/40.jpg)
STEP 2: REQUEST FOR QUOTE / CM SELECTION*
!
!
!*THE MOST IMPORTANT MANUFACTURING DECISION YOU’LL MAKE
![Page 41: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/41.jpg)
41
Overview of the CM Selection Process
http://en.wikipedia.org
1. Talk with trusted network connections who have manufacturing experience. 2. Create a differentiated list of 5 - 10 CMs. 3. Down select to 3 - 5 factories based on your product category (why?) 4. Create a Request for Quote (RFQ) Package. 5. Visit! 6. Analyze Results. 7. Negotiate Big Items. 8. Talk with the CM’s customers. 9. Select the winner, and leave the others on good terms.
![Page 42: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/42.jpg)
42
RFQ Package
http://en.wikipedia.org
•Company Overview -Team overview -Funding -Product -What’s done -What needs to be done -Factory Criteria
•BOM -Canonical format (A2A) in Excel -Transparent and Formula Driven -Separate Std, Special and Consigned Margins/Markups -Include all costs to Ex-Factory -Fill in the blanks
•Schedule -Gantt chart (Cloud) -Fill in the blanks
![Page 43: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/43.jpg)
43
Factory Visit Checklist
http://en.wikipedia.org
Do you like the team? Are they experienced and friendly? Do they have the right manufacturing capabilities? Does your intended volume match their volume capabilities? Are they financially stable? Do they have enough working capital to get going? Do they have favorable payment terms? Are they transparent in their costing? Do they take IP seriously? Did they show you something they shouldn’t have? Are they ethical in their treatment of their workers and otherwise? Do you have access to upper management? Are they excited about working on your product?
![Page 44: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/44.jpg)
44
CM Comparison (A2A Decision Matrix)
http://en.wikipedia.org
•Total Material Costs •Labor •Margins/Markup (Std, Special, Consigned) •Pareto of Top 5 Most Expensive Components •Fixed Costs (tooling, fixtures, NRE) •Schedule •Fit Criteria
![Page 45: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/45.jpg)
POP QUIZ
• Question: What is the biggest challenge in manufacturing ?
![Page 46: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/46.jpg)
Hint
![Page 47: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/47.jpg)
POP QUIZ
• Question: What is the biggest challenge in manufacturing?
• Answer: Communication! • You cannot design in a vacuum (even if you design
vacuums). Strong communication and teamwork skills are critical to success. Engineering is team sport. It’s all about the people. “Us” and “Them” won’t work.
![Page 48: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/48.jpg)
Communication At Work
Bi-Directional Knowledge Flow
Product Designed In U.S.A. Database Sent To Cm Tooling Manufactured
Parts Molded Product Assembled Final Inspection & Shipping
![Page 49: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/49.jpg)
Manufacturing Management Triangle
Quality
Cost
Schedule
![Page 50: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/50.jpg)
Cost of Goods Sold
(COGS)
• Direct costs for goods produced. • Does NOT include Tooling. • Actual price depends on where a
company takes ownership: - Ex-Factory (XF) - FOB (add overland transport to
XF) - Landed (add shipping to FOB) - Inventory (add warehousing)
• Price will vary by date depending on running changes, transportation costs, currency exchange, commodity costs, etc.
![Page 51: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/51.jpg)
Very Simple Retail Costing Model
$
Sell-Through Price (Retail Price)
Sell-In Price (Wholesale Price)
COGS
Retailer Gross Profit
Company Gross Profit
COGS
![Page 52: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/52.jpg)
COGS YOUR DESIGN
• Material and Component Selection
• Fabrication Method • Manufacturing Efficiency
(First Time Yield, machine tonnage, assembly labor, number of operations, etc.)
• Quality Requirements (driven by requirements / Voice of Customer)
• Packout (replaceable vs. rechargeable batteries; packaging; spares, etc.)
MANUFACTURING PARTNER • BOM Transparency • Profit Margin • Labor Rate • Currency • Geographic Location
(shipping, tariffs, etc.) • Capability (in-house vs.
outsourced) • Supply Chain (Purchasing
Power, volume (piggy back), Consigned vs Purchased, etc).
![Page 53: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/53.jpg)
Controlling Costs
1.Deconstruct the BOM. 2.Separate special components. 3.Transparency 4.Compare to standards. 5.NegoAate Inclusions
![Page 54: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/54.jpg)
Additional COGS Strategies
Cost
•Bill of Material Transparency: Require factories to provide an item by item costed BOM. No mysteries or hidden formulas.
•Calculate labor rates. Pop Quiz – How???
•Build a “Standard Cost” database. Price out cost reducJons.
•If Jme permits, develop relaJonships with mulJple vendors to avoid single source suppliers. Leverage is a beauJful word.
•When manufacturing in volume for a CE product, it is criJcal to understand and control COGS. Focus here! Because of the volume, every penny counts ($10k @ 1M units)
![Page 55: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/55.jpg)
1
19
34
14
11
1328
20
221721
36
30
37
10
24
1812 23
5
25
2915
166
897
2
35
34
13
26
33
31
ITEM NO. PART NUMBER DESCRIPTION QTY.
1 100132 Heatsink, Aavid 60520 12 PCB 1
100104 Circuit board blank 1 100015 LED, Luxeon LXHL-LW6C 1
3 GATE 1 100110 Film Gate 1 100011 Backgate 1 100024 Film Spacer 1
4 Bottom 1 100144 Bottom Plate 1 100029 Leaf Spring 2
5 Knobreel 2 100106 Cover Bush 1 100151 Dowel .125 dia 2.000 long 1 100009 Driver 1 100153 Gripring .125 dia 1 100149 Knob bush 1 100007 Clutch, one-way, Torrington RC-02 1 100152 Washer, ss .125 id, McMaster 98019A310 1 100017 Knob, plastic McMaster 7354K15 1 100045 Felt washer 1
6 Reel 27 condentube 1
100031 Condenser lens, small Fisher Price 1 100105 Condenser Tube 1 100154 O-ring Buna -120 1 100035 Retaining ring, internal 1.062 dia 1 100031b Condenser lens, large, Fisher-Price 2
8 100162 Spacer, condenser lens, short 19 100136 Spacer, condenser lens, long 1
10 100163 Spacer, projector, short 111 FHMS Phillips M4x20 812 PHMS Phillips M4x8 613 PHMS Phillips M4x6 514 PHMS Phillips M5x16 815 FHMS Phillips M4x12 616 PHMS Phillips M4x12 117 PHMS M4x8 618 100150 Endplate, Right 119 100160 Endplate, Left 120 100100 Front Plate 121 100138 Projector Lens Housing 122 100148 End Spacer 223 100145 Top Plate 124 100158 Window Edmund R39-773 125 100146 Handle 126 100161 M5 Acorn Nut 127 100147 Half Bridge 128 100012 Focus Screw McMaster 92558A170 129 100143 Spacer, .25 dia, .19 long 430 100156 Spacer, projector, long 131 FHMS Phillips M4x8 232 100150 Washer, Nylon, MSC 05401757 133 100159 Detent 134 100101 Bumper, rubber McMaster 9540K35 835 100039 Switch, SPST rocker Carlingswitch 136 100155 Projector lens, concave 137 100157 Projector lens, plano 1
D
C
B
AA
B
C
D
12345678
8 7 6 5 4 3 2 1
APPLICATION
DIMENSIONS ARE IN MILLIMETERSTOLERANCES: 0,1MM ANGULAR: 0 30'
MATERIAL
FINISH
DRAWN
APPROVED
DATENAME
TITLE:
SIZE
BDWG. NO. REV
SCALE 2:5
UNLESS OTHERWISE SPECIFIED:
KINKAJOU DELTA100141
DO NOT SCALE DRAWING
REMOVE ALL BURRS AND SHARP EDGES
allen 21july04
Anatomy of a BOM• Plastic • Purchased Parts • Electrical Components • Consigned Components • Deco • Packaging • Assembly Labor • CM Profit, Overhead and Scrap • Overland Transportation
![Page 56: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/56.jpg)
• Does it matter that it is a gear???
• Components (3) 1.Material Cost = Part Weight * Resin Cost 2.Machine Overhead: = Hourly Cost * Cycle Time (sec) / (3,600 sec / hr) 3.Factory Mark-up, Scrap and Overhead (%)
• Total Part Cost: = (Material Cost + Overhead Cost) * (1+Factory M/U)
How to Calculate Plastic
![Page 57: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/57.jpg)
HK Resin Prices (USD/Ton)
Reference: http://www.nhh.com.hk/eng/trading/price_trend.asp (you will need to create a login)
![Page 58: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/58.jpg)
Item Cost (USD)
280 Ton / hr $15.48
220 Ton / hr $10.96
180 Ton / hr $8.38
140 Ton / hr $7.09
100 Ton / hr $5.80
80 Ton / hr $5.16
Example PRC
![Page 59: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/59.jpg)
How to Calculate EE Costs
• Cost = Component * Usage • Separate high cost components over a certain
threshold. Apply a lower mark-up. • Apply Factory M/U
![Page 60: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/60.jpg)
Typical PRC CM Margins (Profit, Scrap, Overhead)
PCBA 6–8%
Toys 12%
Consumer 15%
Medical >40%
![Page 61: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/61.jpg)
Other BOM Costs
• Deco (Tampo, Paint, etc.) • Labor (PRC $2 – 6 / hr) • Packaging (Gift + Master)
![Page 62: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/62.jpg)
Schedule
![Page 63: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/63.jpg)
Schedule
•Many consumer products are driven by the Christmas (which has a fixed date). Plan conJngency in your schedule. Things never go according to plan.
Have an onsite presence. Track schedule carefully and take correcJve acJons early. Avoid: “There is never Jme to do it right the first Jme, but there is always Jme to do it again. ”
![Page 64: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/64.jpg)
The Road to Production
![Page 65: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/65.jpg)
Detailed Milestones‣Hand Over / Kick-‐Off
Form CM Team Contact Lists / Roles and ResponsibiliJes
ME and EE File transfer Works Like / Looks Like Samples CM trip to the US if possible (access to models and team, relaJonship building).
Factory Input Components
Engineering Quality ProducJon Planning (interface with Sales)
Sourcing / MA / CosJng LogisJcs Process / Procedure Financial (modeling and payments)
Pre-‐ProducJon Milestones Tool Release
Tool Start (TS) First Shots (FS) Engineering Pilot 1 (EP1) EP2 EP3 Final Engineering Pilot (FEP) ProducJon Pilot (PP)
ProducJon ProducJon Start (PS) Ramp
Engineering Change NoJce (ECN) Sustaining (Quality Up / Cost Down) Sunset
![Page 66: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/66.jpg)
Quality
![Page 67: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/67.jpg)
Quality•DefiniJons:
•Quality = Customer SaJsfacJon = Performance – ExpectaJons •“Fitness for Use” Incoming Quality Control: Use good ingredients. Build and test along the way. Use sub-‐components. StaJsJcal Process Control (SPC) / Yield. Find out now, not later. Sample TesJng: Temp/Humidity; TransportaJon; Drop; T/T; Small Parts; Heavy Metals;
Compliance; FuncJonal; Life. How do tests match reality? ISTA-‐3A. Final InspecJon / Acceptable Quality Levels (AQL) Walk the line. Get your hands dirty. It is much easier (and less expensive) to make changes before ProducJon Start. What happens if something fails? Will make or break a product … and a Company! Quality is rarely considered in the engineering phase by startups due to schedule, cost and
technical pressures. Watch out for the Unknown Unknowns. Strong indicator of long term success, etc. Can you answer the quesAon “How do you know the product is good”?
![Page 68: Working with Oversea Contract Manufacturers - Las Vegas Hardware Meetup - May 19, 2014](https://reader034.vdocuments.mx/reader034/viewer/2022051612/54bbf8b64a7959e3458b45f2/html5/thumbnails/68.jpg)
Recommended Reading
"Factory Girls", Leslie Chang: W.S.J. Reporter Who Lived In China Interviewing Migrant Factory Workers In The Pearl River Delta. Great Insight Into The Workforce.
"Poorly Made In China", Paul Midler: Light, Humorous,
"Mr. China", Tim Clissold: Older Humorous Memoir Of One Of The First Westerners