Fire Paging
Role of Workgroup• The workgroup’s responsibilities are to educate
and inform the interoperability board: To propose a pager implementation plan to guide agencies in the transition from analog to P25 paging. Develop user training guidelines, and pre-deployment testing best practices. Address in-building coverage issues by educating users on building properties that block public safety radio transmissions and develop mitigation techniques to facilitate in-building public safety communications.
February 11-14, 2020 2
Members• Chair Greg Janik Fire Chief / Fire Marshal Saugatuck Township Fire
District• Vice Chair Al Mellon MPSCS TDU/RPU • Chris Mantel – Saugatuck TFD• Lisa Hall – Midland County• Jason Torrey – Grand Traverse• Kurt Fechter – Digi-Com Global (Dealer)• Adam Carrol – Fire Chief Hartland Deerfield Fire Authority• Kent County
– Matt Grosser– Eric Hutchinson– Jerry Yntema
• Kate Jannereth MPSCS
February 11-14, 2020 3
Tasks, Activities & Deliverables
• Address in-building coverage issues
– Educate users on building properties that block public safety radio transmissions
– Develop mitigation techniques to facilitate in-building public safety communications.
February 11-14, 2020 4
Meeting/Schedule
• Meeting Bi-Monthly via Telephone Conference
• Working independently between meetings
– Pager Firmware / Software Tests
– Building Code Education
– Micro-Site Development
– Documentation
February 11-14, 2020 5
2020 Strategic Efforts
• MPSCS Fire Paging Work Group webpage
February 11-14, 2020 6
Work Group recommendations• Software / firmware• Antenna Version
• Manufacturer Reference Page With Programming Training
2020 Strategic Efforts
• MPSCS Fire Paging Work Group webpage
February 11-14, 2020 7
Work Group future recommendations
• Building & Fire Codes Enforcement Education
• RFP Coverage Language• Grid Test Checklist
• Vendor Best Practices• Operator Training
2020 Strategic Efforts
• Develop mitigation techniques to facilitate in-building public safety communications.
– Generate an Extremely Strong Signal Nearby to penetrate building construction
- OR -
– Make a Path Into Building
February 11-14, 2020 8
2020 Strategic Efforts
• Develop mitigation techniques to facilitate in-building public safety communications.
– MPSCS Mini Site Two Way
• MPSCS engineering Eric Holmer & Greg Farrer
• Full Power Site
• Up to 6 voice channels
• Network Connected Point to Point or Fiber
• Monitored with alarms
• DC Backup
February 11-14, 2020 9
5
10
15
20
25
30
35
40RFI MC
Combiner
-48V Batteries
GTR DC PDU
ELTEK Flatpack S
PTP
Duplexer
2020 Strategic Efforts
• Develop mitigation techniques to facilitate in-building public safety communications.
– MPSCS Micro-Site One Way
• Retransmits Host MPSCS Site
• Full Power Site
• DC Backup
• Capacity Determined by Channel Count
• Now Field Testing
• Upgradeable / Developing Two Way
February 11-14, 2020 10
2020 Strategic Efforts
• Develop mitigation techniques to facilitate in-building public safety communications.
• Uni-Directional Amplifiers / Bi-Directional
• Create a path into building for pager coverage
• Create a path out to network for two-way
coverage
February 11-14, 2020 11
2020 Strategic Efforts• Pager implementation plan to guide agencies in the
transition from analog to P25 paging.
• Develop user training guidelines
• Pre-deployment testing best practices– No Surprises
– Test Pager Everywhere a user will go !!!
• In Building Coverage MBC 916 and IFC 510 – Education and Communication
February 11-14, 2020 12
- Building Officials -Fire Code Officials- Plan Reviewers - Architects- Designers - Engineers
Why did building and fire codes change to ensure coverage inside buildings?
• Following the tragic events of September 11, 2001, national, state (including Michigan), building and fire codes were revised to ensure that first responders would have access to reliable radio communications.
February 11-14, 2020 13
The Problem
❖ Critical information is not well understood
❖ Officials do not seem aware of the MBC 916 and IFC 510 application:
- Building Officials- Fire Code Officials- Plan Reviewers- Architects- Designers- Engineers
February 11-14, 2020 14
Better Pager Performance
• Reliable two-way radio coverage inside a building will enhance the level of performance of pager reception inside the building as well.
February 11-14, 2020 15
Educational Outreach Plan
❖ International Association of Fire Chiefs
❖ Bureau of Construction Code, Director Keith Lambert
❖ Bureau of Fire Services, Director Kevin Sehlmeyer
❖ Michigan Fire Inspectors Society
❖ Michigan Association of Fire Chiefs – Sent to hundreds fire service leadership around the state of Michigan.
❖ Tri-County Fire Inspectors Society
❖ Allegan County Sheriff’s Office
February 11-14, 2020 16
The following organizations and entities have received the MPSCIB communication recommendation on Emergency Responder Coverage:
Questions
Chair Greg Janik Fire Chief Contact # (269) 857-3000Contact email [email protected]
Vice Chair Al Mellon Contact # (517) 284-4072Contact email [email protected]
17February 11-14, 2020