WinTR-20 PS, SD, FB Hydrographs June 2015 1 WinTR-20 Principal Spillway, Stability Design, and Freeboard Hydrographs Presented by: WinTR-20 Development Team

Upload: francis-tucker

Post on 14-Dec-2015

215 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: WinTR-20 PS, SD, FB HydrographsJune 20151 WinTR-20 Principal Spillway, Stability Design, and Freeboard Hydrographs Presented by: WinTR-20 Development Team

June 2015 1WinTR-20 PS, SD, FB Hydrographs

WinTR-20 Principal Spillway, Stability Design, and Freeboard Hydrographs

Presented by: WinTR-20 Development Team

Page 2: WinTR-20 PS, SD, FB HydrographsJune 20151 WinTR-20 Principal Spillway, Stability Design, and Freeboard Hydrographs Presented by: WinTR-20 Development Team

June 2015 2WinTR-20 PS, SD, FB Hydrographs

Lesson Objectives

1. Introduce NRCS Technical Release 60 (TR-60) criteria for developing structure design hydrographs.

2. How to input data for Principal Spillway, Stability Design, and Freeboard storms to the Win-TR20 computer program.

3. How to develop PS, SD, and FB hydrographs for import to the WinDAM computer program.

Page 3: WinTR-20 PS, SD, FB HydrographsJune 20151 WinTR-20 Principal Spillway, Stability Design, and Freeboard Hydrographs Presented by: WinTR-20 Development Team

June 2015 3WinTR-20 PS, SD, FB Hydrographs

What is TR-60 ?

TR-60 includes criteria for designing dams.

The latest version is 2005.

Specifically of interest to hydrologists are criteria for selection of rainfall amount for the design storms.

Page 4: WinTR-20 PS, SD, FB HydrographsJune 20151 WinTR-20 Principal Spillway, Stability Design, and Freeboard Hydrographs Presented by: WinTR-20 Development Team

June 2015 4WinTR-20 PS, SD, FB Hydrographs

TR-60 Hazard Classification

Page 5: WinTR-20 PS, SD, FB HydrographsJune 20151 WinTR-20 Principal Spillway, Stability Design, and Freeboard Hydrographs Presented by: WinTR-20 Development Team

June 2015 5WinTR-20 PS, SD, FB Hydrographs

Principal Spillway Criteria

Typical data source is NOAA Atlas 14 if available.

Page 6: WinTR-20 PS, SD, FB HydrographsJune 20151 WinTR-20 Principal Spillway, Stability Design, and Freeboard Hydrographs Presented by: WinTR-20 Development Team

June 2015 6WinTR-20 PS, SD, FB Hydrographs

PS Criteria – Quick Return Flow

Page 7: WinTR-20 PS, SD, FB HydrographsJune 20151 WinTR-20 Principal Spillway, Stability Design, and Freeboard Hydrographs Presented by: WinTR-20 Development Team

June 2015 7WinTR-20 PS, SD, FB Hydrographs

PS Criteria – Runoff Volume

Page 8: WinTR-20 PS, SD, FB HydrographsJune 20151 WinTR-20 Principal Spillway, Stability Design, and Freeboard Hydrographs Presented by: WinTR-20 Development Team

June 2015 8WinTR-20 PS, SD, FB Hydrographs

PS Criteria – Ratio 1-day/10-day Q

Page 9: WinTR-20 PS, SD, FB HydrographsJune 20151 WinTR-20 Principal Spillway, Stability Design, and Freeboard Hydrographs Presented by: WinTR-20 Development Team

June 2015 9WinTR-20 PS, SD, FB Hydrographs

Stability Design and Freeboard Criteria

Auxiliary spillway hydrograph is the same as Stability Design terminology used in WinTR-20.

Page 10: WinTR-20 PS, SD, FB HydrographsJune 20151 WinTR-20 Principal Spillway, Stability Design, and Freeboard Hydrographs Presented by: WinTR-20 Development Team

June 2015 10WinTR-20 PS, SD, FB Hydrographs

Stability Design and Freeboard Criteria

TR-60 includes a detailed list of data sources for locations in the United States.

NOAA Atlas 14 is typical data source for 100-year precipitation if available.

NOAA Hydrometeorological Series Reports (HMR) are typical data sources for probable maximum precipitation (PMP) if available.

Page 11: WinTR-20 PS, SD, FB HydrographsJune 20151 WinTR-20 Principal Spillway, Stability Design, and Freeboard Hydrographs Presented by: WinTR-20 Development Team

June 2015 11WinTR-20 PS, SD, FB Hydrographs

SD and FB criteria – areal reduction

Page 12: WinTR-20 PS, SD, FB HydrographsJune 20151 WinTR-20 Principal Spillway, Stability Design, and Freeboard Hydrographs Presented by: WinTR-20 Development Team

June 2015 12WinTR-20 PS, SD, FB Hydrographs

Principal Spillway Data Window

Page 13: WinTR-20 PS, SD, FB HydrographsJune 20151 WinTR-20 Principal Spillway, Stability Design, and Freeboard Hydrographs Presented by: WinTR-20 Development Team

June 2015 13WinTR-20 PS, SD, FB Hydrographs

Principal Spillway Data Help

Page 14: WinTR-20 PS, SD, FB HydrographsJune 20151 WinTR-20 Principal Spillway, Stability Design, and Freeboard Hydrographs Presented by: WinTR-20 Development Team

June 2015 14WinTR-20 PS, SD, FB Hydrographs

Stability Design Freeboard Data Window

Page 15: WinTR-20 PS, SD, FB HydrographsJune 20151 WinTR-20 Principal Spillway, Stability Design, and Freeboard Hydrographs Presented by: WinTR-20 Development Team

June 2015 15WinTR-20 PS, SD, FB Hydrographs

Stability Design Freeboard Data Help

Page 16: WinTR-20 PS, SD, FB HydrographsJune 20151 WinTR-20 Principal Spillway, Stability Design, and Freeboard Hydrographs Presented by: WinTR-20 Development Team

June 2015 16WinTR-20 PS, SD, FB Hydrographs

Principal Spillway, Stability Design, and Freeboard Hydrographs

WinTR-20 Demo Example

Page 17: WinTR-20 PS, SD, FB HydrographsJune 20151 WinTR-20 Principal Spillway, Stability Design, and Freeboard Hydrographs Presented by: WinTR-20 Development Team

June 2015 17WinTR-20 PS, SD, FB Hydrographs

Principal Spillway, Stability Design, and Freeboard Hydrographs

Watershed near Harrison, Boone County, Arkansas

o Drainage Area 8.0 square mileso Curve Number 78o Time of Concentration 2.3 hourso Hazard Classification “Significant”

Page 18: WinTR-20 PS, SD, FB HydrographsJune 20151 WinTR-20 Principal Spillway, Stability Design, and Freeboard Hydrographs Presented by: WinTR-20 Development Team

June 2015 18WinTR-20 PS, SD, FB Hydrographs

Open WinTR-20, Open new input file

Click WinTR-20 icon from desktop

Click File and New WinTR-20

File

Page 19: WinTR-20 PS, SD, FB HydrographsJune 20151 WinTR-20 Principal Spillway, Stability Design, and Freeboard Hydrographs Presented by: WinTR-20 Development Team

June 2015 19WinTR-20 PS, SD, FB Hydrographs

Enter Watershed Description, Open Principal Spillway Data

Enter Watershed Description

Click Accept Changes (Close)

Click Principal Spillway Data

Page 20: WinTR-20 PS, SD, FB HydrographsJune 20151 WinTR-20 Principal Spillway, Stability Design, and Freeboard Hydrographs Presented by: WinTR-20 Development Team

June 2015 20WinTR-20 PS, SD, FB Hydrographs

Enter Principal Spillway Data

Enter Description Click Look Up for

Climatic Index Click OK button Enter PS

Precipitation Click Accept

Changes (Close)

Page 21: WinTR-20 PS, SD, FB HydrographsJune 20151 WinTR-20 Principal Spillway, Stability Design, and Freeboard Hydrographs Presented by: WinTR-20 Development Team

June 2015 21WinTR-20 PS, SD, FB Hydrographs

WinTR-20 Main Window

Click File and Save As

Select directory and enter file name, Save

Click Stability Freeboard Data

Page 22: WinTR-20 PS, SD, FB HydrographsJune 20151 WinTR-20 Principal Spillway, Stability Design, and Freeboard Hydrographs Presented by: WinTR-20 Development Team

June 2015 22WinTR-20 PS, SD, FB Hydrographs

Enter Stability Freeboard Data

Enter Stability Freeboard Data

Click Accept Changes (Close)

Click Sub-area:

Page 23: WinTR-20 PS, SD, FB HydrographsJune 20151 WinTR-20 Principal Spillway, Stability Design, and Freeboard Hydrographs Presented by: WinTR-20 Development Team

June 2015 23WinTR-20 PS, SD, FB Hydrographs

Enter Sub-area Data

Enter Sub-area Data

Click Accept Changes (Close)

Click Global Output:

Page 24: WinTR-20 PS, SD, FB HydrographsJune 20151 WinTR-20 Principal Spillway, Stability Design, and Freeboard Hydrographs Presented by: WinTR-20 Development Team

June 2015 24WinTR-20 PS, SD, FB Hydrographs

Enter Global Output Data

Enter Global Output Data

Click Accept Changes (Close)

Page 25: WinTR-20 PS, SD, FB HydrographsJune 20151 WinTR-20 Principal Spillway, Stability Design, and Freeboard Hydrographs Presented by: WinTR-20 Development Team

June 2015 25WinTR-20 PS, SD, FB Hydrographs

Save data and run WinTR-20

Click File and Save

Click Run

Page 26: WinTR-20 PS, SD, FB HydrographsJune 20151 WinTR-20 Principal Spillway, Stability Design, and Freeboard Hydrographs Presented by: WinTR-20 Development Team

June 2015 26WinTR-20 PS, SD, FB Hydrographs

WinTR-20 Printed Page Output

Scroll to end of file for summary

Page 27: WinTR-20 PS, SD, FB HydrographsJune 20151 WinTR-20 Principal Spillway, Stability Design, and Freeboard Hydrographs Presented by: WinTR-20 Development Team

June 2015 27WinTR-20 PS, SD, FB Hydrographs

View Debug Output File

Click View and Debug FilePS Data PrepSD FB Data PrepClose

Page 28: WinTR-20 PS, SD, FB HydrographsJune 20151 WinTR-20 Principal Spillway, Stability Design, and Freeboard Hydrographs Presented by: WinTR-20 Development Team

June 2015 28WinTR-20 PS, SD, FB Hydrographs

WinTR-20 Hydrograph Output File

Click View and Hydrograph FileScroll to SDH and FBH hydrographs

Page 29: WinTR-20 PS, SD, FB HydrographsJune 20151 WinTR-20 Principal Spillway, Stability Design, and Freeboard Hydrographs Presented by: WinTR-20 Development Team

June 2015 29WinTR-20 PS, SD, FB Hydrographs

WinTR-20 hydrograph plots

Click PlotsSelect Storms and LocationClose

Page 30: WinTR-20 PS, SD, FB HydrographsJune 20151 WinTR-20 Principal Spillway, Stability Design, and Freeboard Hydrographs Presented by: WinTR-20 Development Team

June 2015 30WinTR-20 PS, SD, FB Hydrographs

Isabel - 2003

Page 31: WinTR-20 PS, SD, FB HydrographsJune 20151 WinTR-20 Principal Spillway, Stability Design, and Freeboard Hydrographs Presented by: WinTR-20 Development Team

June 2015 31WinTR-20 PS, SD, FB Hydrographs

QUESTIONS???