win-win cooperation for low carbon and sustainable future xiaohang... · win-win cooperation for...
TRANSCRIPT
©SPIC 2017. All Rights Reserved.
国家核电 www.snptc.com
2017.3
Win-Win Cooperation for
Low Carbon and Sustainable Future
©SPIC 2017. All Rights Reserved.
Intellectual Property Rights Statement
This document is the property of and contains proprietary information owned by SPIC and/or its related
proprietor. You agree to treat this document in strict accordance with the terms and conditions of the
agreement under which it was provided to you. No disclosure or copy of this document is permitted
without the prior written permission of SPIC.
©SPIC 2017. All Rights Reserved.
I. SPIC/SNPTC Profile
II. Introduction of CAP1400
III. Cooperation with Africa
©SPIC 2017. All Rights Reserved.
A Fortune Global 500 list corporation, with a revenue of USD 30 billion 2016
Total electric power installation capacity 117GW
The one and only integrated energy group with all types of electricity generation
in China
Overall power generation 2016: 500 billion kWh
(about 8% of China)
140,000 employees, two companies listed in Hongkong
and five A-share companies
Business covers power, coal, aluminum, logistics,
finance, environmental protection, high-tech industries,
etc.
Capable of R&D, planning, survey and design,
construction, investment, O&M in electricity generation,
power transmission and transformation
1
SPIC Overview
©SPIC 2017. All Rights Reserved.
China’s leading nuclear power company
One of three China’s authorized nuclear
power developers and operators
4,480 MWe nuclear power in operation
7,540 MWe under construction
more than 12 sites in preparation
By 2020: 14 GWs in operation,10 GWs
under construction
Leading technology of Gen 3 nuclear power,
CAP1000 , CAP1400, CAP1700
A complete NP supply chain, including R&D,
engineering, equipment, construction,
operation and maintenance, as well as life
cycle services
2
SPIC Overview
©SPIC 2017. All Rights Reserved.
China’s leading clean energy provider
Clean energy accounts for 43% of SPIC’s total installed
capacity with target of 50% by 2020
The world’s largest solar power provider as a single entity,
with capacity of 7,260 MWe
Hybrid energy system in development with renewable
energy
Integrated services to provide design, manufacturing,
installation, commissioning, O&M for ultra-low emission
coal-fired units
With smart energy technology to provide integrated energy
solution of power, heating, cooling, gas, water, etc.
3
SPIC Overview
©SPIC 2017. All Rights Reserved.
Overseas projects are distributed in 35 countries (regions)
3.5GW power plants in operation
EPC projects: 10 power plants, 12GW
Engineering and O&M services: 34 power projects
SPIC Overview
Dedication to world energy development 4
©SPIC 2017. All Rights Reserved.
SOUTH AFRICA
Nuclear
Power
Gas to
Power IPP
Clean Coal
Power IPP
9600MW 3600MW 2400 MW
TANZANIA
CCGT Thermal Plant IPP
300 MW
EGYPT
Coal-fired Thermal Plant
IPP
2*660MW
MOZAMBIQUE
Coal-fired Thermal Plant
IPP
2*150MW
ETHIOPIA
Hydro Power IPP
398MW
Ghana
Coal-fired plant
Consultancy
2×350 WM
SPIC Overview
©SPIC 2017. All Rights Reserved.
Nuclear power business platform of SPIC
To develop advanced NPP with independent IP-CAP1400/1700 by introducing
AP1000 technology and realizing localization
Be responsible for building the world’s first 4 AP1000 units, and CAP1400
project
Total asset over 15 billion USD ,with more than 13,000 employees in 30+
subsidiaries
SNPTC Overview
R&D Manufacturing EPC Operation Lifetime Service
©SPIC 2017. All Rights Reserved.
Sev
en B
ase System
s F
ive P
latform
s
R&D Engineering Design Construction Management Qualified Supplier
Plant Lifetime Service Plant Operation Nuclear Power Standard System
V&V Software EQ Fuel Elements Feasibility Study
SNPTC Overview- Business Scope
©SPIC 2017. All Rights Reserved.
CAP1000+ CAP1400
CAP-S onshore
GIV 4
2017 2019
2020
2030
CAP1000
CAP Passive Series
CAP-S offshore
Small Module Reactor
SNPTC Overview- Reactor Technology
©SPIC 2017. All Rights Reserved.
EPC
Integrated global supply chain for 6-8 sets a year
Standardized project management
Projects in Progress
4 AP1000 units in China
2 CAP1400 units
Engineering
Qinshan Phase-I 300MWe
Chashma 1#,2#,3#,4# (300MWe each)
CAP1000 (1250MWe) for six units
CAP1400(1500MWe) for 2 units
SNPTC Overview- Engineering & EPC
©SPIC 2017. All Rights Reserved.
SNPTC Overview- I&C System
NuPAC、 NuCON for Reactor
Protection and Control System Platform:
NNSA and NRC certified
I&C
DCS
Simulator
"Nu Series" NPP Digital I&C Product Line
©SPIC 2017. All Rights Reserved.
SNPTC Overview- Nuclear Fuel
Fuel R&D
Fuel design and fabrication
Manufacturing technology of fuel cladding
R&D of SiC and other nonmetallic materials for fuel
©SPIC 2017. All Rights Reserved.
Four AP1000 units on two sites in progress
Locations of Sanmen & Haiyang AP1000 Projects
15
SNPTC Overview- AP1000 Projects
©SPIC 2017. All Rights Reserved.
2014
2013
2012
2011
2010
2009
2008
2015
SNPTC Overview- Sanmen AP1000
Milestones of Sanmen AP1000 project
©SPIC 2017. All Rights Reserved.
SNPTC Overview- Sanmen AP1000
First AP1000 in the world: Unit 1 HFT Completed, fuel loading in June
2017.03
©SPIC 2017. All Rights Reserved.
I. SPIC/SNPTC Profile
II. Introduction of CAP1400 III. Cooperation with Africa
©SPIC 2017. All Rights Reserved.
Total electricity installation: 1650 GWe , Nuclear : 33.64GWe(~2%)
China’s Nuclear Power Program
By 2020:
58GWe in operation
30GWe under construction
TARGET
Xin Jiang
Tibet
Qing Hai
Gan Su Inner Mongolia
Si Chuan
Yun Nan
Gui Zhou
Shan
Xi
Chong
Qing
Shan Xi
Hu Bei
Hu
Nan
Guang Xi Guang
Dong
Jiang
Xi
An
Hui
He Nan
Shan
Dong
He
Bei
Bei
Jing
Liao
Ning
Ji Lin
Hei Longjiang
Jiang
Su
Zhe
Jiang
Fu
Jian
Tai Wan
Hai Nan
Shang
Hai
Tian
Jin Ning
Xia
Hongyanhe
Xudapu
Haiyang
Shidaowan
Tianwan
Qinshan & Fangjiashan
Qinshan 2
Qinshan 3
Sanmen
Ningde
Fuqing
Lufeng
DayaBay/LinAo
Taishan
Yangjiang
Fangchenggang
Changjiang
In operation: 35
Under construction:19
Planned: 40+
©SPIC 2017. All Rights Reserved.
1. General Pictures of CAP1400
Chinese Advanced passive
PWR
>1400MWe
CAP1400
Competitive GIII Tec with Own
Intellectual Property
Excellent safety/economy
environmental harmony
NNSA&GRSR Review finished
To be a World Brand
National key project
Led by Chinese government
(NEA), Performed by SNPTC
Supported and participated by
domestic and foreign entity
Fundamentals
40+ years of nuclear
industry experience
20+ years of NPP sound
operation
AP1000 technology
©SPIC 2017. All Rights Reserved.
Adoption of the Latest Nuclear Safety Requirement
Experiences Feedback From Fukushima Accident
Simplified System and Proven Components
Passive Safety Systems and Severe Accident Prevention and Mitigation Measures
Full Digital Reactor Protection System
Full Range Probabilistic Safety Analysis
Modularization Design and Construction Technology
1. General Pictures of CAP1400
©SPIC 2017. All Rights Reserved.
Parameters CAP1400
Core thermal power, MWt 4040
Electric power, MWe ~1500
RCS average temp, ℃ 304
RCS pressure, MPa(a) 15.5
Fuel assemblies 193
Average linear power, W/cm 181
SG type SNP140
CDF 4.0E-7
LRF 5.1E-8
DNBR margin >15%
1. General Pictures of CAP1400
©SPIC 2017. All Rights Reserved.
Safety
Passive SF & comprehensive SA prevention and mitigation
Low safety risk: CDF (Core Damage Freq.) : 4.02E-7/RY ; LRF (Large Release
Freq.) : 5.16E-8/RY
Enhanced margin for DBE: DNBR Margin > 15%; CV Pressure Margin > 10%;
SSE (Safety Shutdown Earthquake), 0.3 g
Sufficient margin against extreme external events: HCLPF for all safety-class
SSCs ≥0.5g, plus “Dry Site” (Fukushima feedback)
PXS PCS IVR
2. Design Features
©SPIC 2017. All Rights Reserved.
2. Design Features
Passive Core Cooling System (PXS)
Passive Residual Heat Removal Subsystem: PRHR-HX, IRWST
Passive Safety Injection Subsystem: CMT, ACC, IRWST
Automatic Depressurization Subsystem: ADS1-3, ADS4
Proven technology with verified capacity Maintain reactor core safety continuously
(verified by ACME test)
©SPIC 2017. All Rights Reserved.
2. Design Features
Passive Containment Cooling System (PCS) Design Remove the heat through the steel containment wall by water spraying and natural
air circulation
Water source: PCCWST for 72 hr, PCCAWST for next 4 days
Long-term cooling: Removable
pump & alternative water
source
Verification TEST: Phenomena
verified on PCS Test Facility
(CERT Facility)
Water film Cooling Long-term air Cooling
©SPIC 2017. All Rights Reserved.
Economic
Economy
~1500MWe(gross)
~Systematic optimization for efficiency
Self design with IPR 1
Key equipment and
material localized
2 Localization
Mature and competitive
equipment supply chain
3 Supply chain
Simplification and short construction period 4
2. Design Features
©SPIC 2017. All Rights Reserved.
Advantages
…
• Simplification: less welding seam,
less spare parts, less waste
generated
• MOX fuel capability
• RVI redesigned, the neutron shield
pad eliminated
• Enhanced design margin and
increased operation flexibility
• Design reliability assurance program
implemented
• Utilize the latest safety design standards,
As High As Reasonably Achievable
• Meet the most strict discharge standard, As
Low As Reasonably Achievable
• Integration of human factors balanced PSA
and D-RAP
2. Design Features
©SPIC 2017. All Rights Reserved.
3. Verification & Validation
Systematic Verification Tests Completed
Totally 887 cases performed for supporting the design, safety
review, and software V&V
ACME complex CERT Facility Facility for FIV Test IVR Test Facility
Facility for Hydro-
Simulation
Facility for SG Steam-Water
Separation Test
Tests for Passive Safety
Systems
• PXS performance test
• PCS performance test
• IVR test
Tests for Key Equipment
• SG hot-stage performance
test
• Core hydro-simulation test
• Reactor internal flow-
induced vibration test
©SPIC 2017. All Rights Reserved.
3. Verification &Validation
IVR- Metal Heat Transfer
PCS Water Distribution
PCS Heat Removal (LOCA)
0.0
1.2
2.4
3.6
4.8
0 600 1200 1800 2400 3000
时间(s)
水位(m)
NOTRUMP
堆芯活性区高度
试验
PXS – RPV Mixture Water Level
(CAP03 case)
Key verification tests result shows the feasibility of CAP1400
©SPIC 2017. All Rights Reserved.
3. Verification &Validation
Flow distribution of core inlet
SG Separator System
SG Tube Frictional Resistance
Key verification tests result shows the feasibility of CAP1400
©SPIC 2017. All Rights Reserved.
4. CAP1400 Project
Key Milestone
2010.6
Conceptual
Design
completed
2011.12
Basic Design
completed
2014.7
Feasibility
Report
approved
2016.04
~95% detailed
design
completed
2007
Proposal
prepared
2016.2
PSAR review
completed
All technical, manufacturing and
site preparations are ready, FCD
pending for government approval
1 2 3 4 5 6
©SPIC 2017. All Rights Reserved.
33
Shidao Bay
2 CAP1400 units in progress, site at Rongcheng, Shandong Province, China
4. CAP1400 Projects
©SPIC 2017. All Rights Reserved.
Contracts for all long lead equipments have been signed
Polar crane
Steam Generator
PRZ
Turbine
Generator
MSR
RCP
RPV ACCM CMT
CV
RCL
Key Equipments Procured
©SPIC 2017. All Rights Reserved.
Key Equipments Manufacturing
R
eact
or
Ves
sel
S
team
Gen
era
tor
Sq
uib
Va
lve
©SPIC 2017. All Rights Reserved.
Key Equipments Manufacturing C
an
ned
RC
P
R
UV
RC
P
R
eact
or
Inte
rna
l
Ma
in P
ipe
Fo
rgin
g
©SPIC 2017. All Rights Reserved.
Turbine
Generator
Condensate Water Pump
I & C
Key Equipments Manufacturing
©SPIC 2017. All Rights Reserved.
Rongcheng CAP1400 Project Site
Nuclear island 1
Conventional island 1
Nuclear island 2
Conventional island 2
CA assembly area
CV2 rings
CV1 rings
CV module assembly building
CR10
38
Bird View of Unit1&2 of Rongcheng CAP1400 Plant
©SPIC 2017. All Rights Reserved.
CAP1400’s follow-up projects are planned
Rongcheng CAP1400 project
Follow-up site
Shidao Bay
Liaoning
Guangdong
Guangxi
Shandong
Fujian
39
Follow-up CAP1400 Projects
©SPIC 2017. All Rights Reserved.
I. SPIC/SNPTC Profile
II. CAP1400 Technology
III. Cooperation with Africa
©SPIC 2017. All Rights Reserved.
Benefit from nuclear power project
Long-term clean and sustainable power
Job creation – thousands of technical positions, labour
Localization- major engine for economic and social
development
Promote overall industry through local participation
Building knowledge economy and low carbon economy
SNPTC is willing to support nuclear development in
Africa
All-round communication with African energy industry
to explore cooperation
To provide “Technology +Localization + Financing +
Training” one-stop solution to participate in nuclear
power projects with CAP1400 technology
Cooperation with Africa
President Zuma and President Xi Jinping
visiting SNPTC Stand
ANC Delegation Visiting
SNPTC Headquarter
©SPIC 2017. All Rights Reserved.
Cooperation with RSA for nuclear project
2014-02
Training agreement with NECSA
2014-04
SNPTC, ICBC and South Africa Standard
Bank: Financing Frame Agreement
2014-11
Inter-government framework for nuclear
project
2015-12, President Xi Jinping and President Jacob
Zuma Witness:
Signing of “CAP1400 Project Management
Cooperation Agreement” between SNPTC and
NECSA
2017
Respond to RFI in progress
DOE signed Agreement on Cooperation in the Field of
Civil Nuclear Energy Projects with NEA
SNPTC signed training cooperation Agreement with Necsa
Cooperation with Africa
©SPIC 2017. All Rights Reserved.
DTI delegation Visit SNPTC Headquarter
Eskom delegation Visit SNPTC Headquarter NNR delegation visit CAP1400 NPP
China-SA Nuclear Power Cooperation Seminar
Cooperation with Africa
©SPIC 2017. All Rights Reserved.
Training Program for SA
Initiated from Feb, 2014, by basic training, professional training and on-the-job training,
covering technologies and management of Gen III Nuclear Power Plant project design,
procurement, manufacturing, construction, commissioning, operation and maintenance
Training completed for more than 160 trainees from SA entities, including DOE, NNR,
Eskom, Necsa, etc.
An International Master Program in Nuclear Engineering and Management hosted by
Tsinghua University, supported by Chinese government and SNPTC started from 2017
Cooperation with Africa
©SPIC 2017. All Rights Reserved.
Localization Support
SNPTC has rich experiences of localization by introducing AP1000
Preliminary investigation to SA local manufacturer was conducted and
localization plan was drafted
Technology transfer can be realized by various way, such as cooperation,
investment and joint venture etc., as required
DTI delegation visited CAP1400 NPP and Chinese
Equipment Manufacturers
DOE delegation visited SNPEMC
(CAP1400 CV Module Manufacturer ) SNPTC delegation visit ed SA local manufacturers
Cooperation with Africa
©SPIC 2017. All Rights Reserved.
46
Consortium with local
Full scope EPC - Turnkey
NI EPC
NI/CI EPC
BOO with the vendor owning NPP asset
BOT based on concession
Full scope EPC - Turnkey □TT/Localization □ loan □ Joint venture IPP
□ G
lob
al e
xp
erie
nce
sh
arin
g
□ G
rid
□ I
nte
gra
ted
su
pp
ly c
hai
n
□ I
nfr
astr
uct
ure
dev
elo
pm
ent
□ F
uel
&sp
ent
fuel
□ H
R
dev
elo
pm
ent
1
2
3
4
5
6
7
Basic Value
CAP1400
Value-added
Local Industry Funding Reliable operation
Value-extended
Sustainability Leadership
□TT/Localization □ loan □O&M □ equity
□TT/Localization □ loan □O&M service
□TT/Localization □ loan □ O&M service
□TT/Localization □ loan □O&M □ equity
46
Options for Project Realization
Cooperation With Africa
©SPIC 2017. All Rights Reserved.
SNPTC is willing, and fully capable and confident to be the all-weather reliable
partner with Africa’s nuclear industry
To support the safe development of Africa’s nuclear power program based on the-
state-of-art passive NP technology
To support localization for realizing nuclear power industrial supply chain
To provide comprehensive training covering engineering, construction,
commissioning and O&M etc.
To be ready for technology transfer as required
SNPTC is looking forward to enhancing win-win cooperation and to making greater
contribution to Africa nuclear industry for the beautiful, low carbon and sustainable
future
Summary