![Page 1: Whittier Bridge Project Briefing 5-8-17 - Mass.Gov · Issue MassDOT found with Pier 1 Cap • On February 23, 2017, contractor placed 260 cubic yards for the pier 1 southbound cap](https://reader031.vdocuments.mx/reader031/viewer/2022040912/5e87db4430199e52985818fd/html5/thumbnails/1.jpg)
Project Briefing:
Whittier Bridge
MassDOT Highway Division
District 4 Highway Director Paul Stedman
![Page 2: Whittier Bridge Project Briefing 5-8-17 - Mass.Gov · Issue MassDOT found with Pier 1 Cap • On February 23, 2017, contractor placed 260 cubic yards for the pier 1 southbound cap](https://reader031.vdocuments.mx/reader031/viewer/2022040912/5e87db4430199e52985818fd/html5/thumbnails/2.jpg)
Issue Overview
2
• In March, MassDOT inspectors discovered deficiencies in pier cap 1 of
the southbound portion of the I-95 bridge now under construction.
• After careful review, MassDOT notified the Joint Venture Walsh/McCourt
that they must reconstruct the pier cap in accordance with MassDOT’s
standards.
• While MassDOT is working to fully assess the schedule impacts
associated with this matter:
• There will be no cost impacts to MassDOT
• This work will not change the existing configuration of 3 lanes of traffic
in each direction on the bridge
![Page 3: Whittier Bridge Project Briefing 5-8-17 - Mass.Gov · Issue MassDOT found with Pier 1 Cap • On February 23, 2017, contractor placed 260 cubic yards for the pier 1 southbound cap](https://reader031.vdocuments.mx/reader031/viewer/2022040912/5e87db4430199e52985818fd/html5/thumbnails/3.jpg)
Project Background
3
• Full replacement of the bridge that carries I-95 over the Merrimack River
between Amesbury and Newburyport.
• Includes 4 miles of I-95 roadway reconstruction/widening and 3
additional bridge replacements and 1 rehabilitation.
• Expands from a 6 lane bridge to 8 lanes to match the cross sections to
the north and south
• Budget: $328M | Project is 85% complete
![Page 4: Whittier Bridge Project Briefing 5-8-17 - Mass.Gov · Issue MassDOT found with Pier 1 Cap • On February 23, 2017, contractor placed 260 cubic yards for the pier 1 southbound cap](https://reader031.vdocuments.mx/reader031/viewer/2022040912/5e87db4430199e52985818fd/html5/thumbnails/4.jpg)
Work Completed to Date
• Joint Venture of Walsh/McCourt was issued Notice to Proceed in
Spring 2013; construction began in Summer 2013
• Northbound traffic was shifted onto the new bridge in November
2015; southbound traffic was shifted onto the new bridge in
December 2015
• Demolition of the old bridge
began in late 2015
• As of today, all substructure elements
for new southbound bridge
completed with the exception
of pier 1
4
![Page 5: Whittier Bridge Project Briefing 5-8-17 - Mass.Gov · Issue MassDOT found with Pier 1 Cap • On February 23, 2017, contractor placed 260 cubic yards for the pier 1 southbound cap](https://reader031.vdocuments.mx/reader031/viewer/2022040912/5e87db4430199e52985818fd/html5/thumbnails/5.jpg)
5
Whittier Bridge (looking east)
• The bridge is currently open to 3 lanes of traffic in each direction on
the existing northbound bridge.
![Page 6: Whittier Bridge Project Briefing 5-8-17 - Mass.Gov · Issue MassDOT found with Pier 1 Cap • On February 23, 2017, contractor placed 260 cubic yards for the pier 1 southbound cap](https://reader031.vdocuments.mx/reader031/viewer/2022040912/5e87db4430199e52985818fd/html5/thumbnails/6.jpg)
Whittier Bridge - Traffic
• There are currently 3 lanes of traffic on I-95 NB and SB
from Route 113 in Newburyport to Route 110 in
Amesbury. This includes 3 lanes of traffic on the bridge
itself (the pre-project traffic alignment).
• This roadway opens up to 4 lanes of traffic from Route
110 in Amesbury to the New Hampshire state line.
6
![Page 7: Whittier Bridge Project Briefing 5-8-17 - Mass.Gov · Issue MassDOT found with Pier 1 Cap • On February 23, 2017, contractor placed 260 cubic yards for the pier 1 southbound cap](https://reader031.vdocuments.mx/reader031/viewer/2022040912/5e87db4430199e52985818fd/html5/thumbnails/7.jpg)
Issue MassDOT found with Pier 1 Cap
• On February 23, 2017, contractor placed 260 cubic yards for the pier 1 southbound cap.
• On March 6, MassDOT observed deficiencies in the pier cap and reported these to the contractor. The pier cap exhibited extensive honeycombing due to improper consolidation (see slide 8).
• On March 8, MassDOT issued a Deficiency Report to the contractor and withheld $827K until the deficiency is corrected.
• The Deficiency Report requires the contractor to examine the work further and suggest possible repair procedures
7
![Page 8: Whittier Bridge Project Briefing 5-8-17 - Mass.Gov · Issue MassDOT found with Pier 1 Cap • On February 23, 2017, contractor placed 260 cubic yards for the pier 1 southbound cap](https://reader031.vdocuments.mx/reader031/viewer/2022040912/5e87db4430199e52985818fd/html5/thumbnails/8.jpg)
8
Example Defects MassDOT found
in Pier 1 Cap
![Page 9: Whittier Bridge Project Briefing 5-8-17 - Mass.Gov · Issue MassDOT found with Pier 1 Cap • On February 23, 2017, contractor placed 260 cubic yards for the pier 1 southbound cap](https://reader031.vdocuments.mx/reader031/viewer/2022040912/5e87db4430199e52985818fd/html5/thumbnails/9.jpg)
9
Example Pier with NO Defects
![Page 10: Whittier Bridge Project Briefing 5-8-17 - Mass.Gov · Issue MassDOT found with Pier 1 Cap • On February 23, 2017, contractor placed 260 cubic yards for the pier 1 southbound cap](https://reader031.vdocuments.mx/reader031/viewer/2022040912/5e87db4430199e52985818fd/html5/thumbnails/10.jpg)
10
Pier 1 Southbound
![Page 11: Whittier Bridge Project Briefing 5-8-17 - Mass.Gov · Issue MassDOT found with Pier 1 Cap • On February 23, 2017, contractor placed 260 cubic yards for the pier 1 southbound cap](https://reader031.vdocuments.mx/reader031/viewer/2022040912/5e87db4430199e52985818fd/html5/thumbnails/11.jpg)
11
Resolution
• On April 20, the contractor submitted three alternative concept repairs for review of varying scope and impact.
• After careful review, MassDOT notified the contractor that the proposed repair procedures were rejected and the contractor would need to reconstruct the pier cap in accordance with MassDOT’s standards.
• This will ensure that MassDOT is not compromising on the quality of the contractor’s work to ensure the tax payers are receiving what they ordered.
• MassDOT has met with senior leadership at the company to discuss this poor performance on the job and to ensure a strong working relationship going forward.
![Page 12: Whittier Bridge Project Briefing 5-8-17 - Mass.Gov · Issue MassDOT found with Pier 1 Cap • On February 23, 2017, contractor placed 260 cubic yards for the pier 1 southbound cap](https://reader031.vdocuments.mx/reader031/viewer/2022040912/5e87db4430199e52985818fd/html5/thumbnails/12.jpg)
12
Impacts: Schedule and Traffic
A preliminary meeting was held with the contractor on May 3rd to discuss the schedule impacts of this work.
• Gantry system installed to support remaining bridge construction operations (May)
• Demolition of existing pier cap 1 (late May - late June)
• Reinstallation of the new pier cap (July - August)
• At this point, work will resume on “pre-pier cap” operations, including installing structural steel, precast bridge deck panels, and ultimately paving of the new SB bridge
• MassDOT is working to fully assess the schedule impacts associated with this matter; however, there will be no cost impacts to MassDOT or change in the existing traffic configuration.
![Page 13: Whittier Bridge Project Briefing 5-8-17 - Mass.Gov · Issue MassDOT found with Pier 1 Cap • On February 23, 2017, contractor placed 260 cubic yards for the pier 1 southbound cap](https://reader031.vdocuments.mx/reader031/viewer/2022040912/5e87db4430199e52985818fd/html5/thumbnails/13.jpg)
Project Briefing:
Whittier Bridge
MassDOT Highway Division
District 4 Highway Director Paul Stedman
![Page 14: Whittier Bridge Project Briefing 5-8-17 - Mass.Gov · Issue MassDOT found with Pier 1 Cap • On February 23, 2017, contractor placed 260 cubic yards for the pier 1 southbound cap](https://reader031.vdocuments.mx/reader031/viewer/2022040912/5e87db4430199e52985818fd/html5/thumbnails/14.jpg)
Appendix