when a dream becomes realitythost-iabse-elearning.org/l37/data/downloads/handouts_combault.pdf ·...
TRANSCRIPT
IABSE Conference – Shanghai 2009
When a Dream becomes RealityThe Rion-Antirion Bridge
y
Jacques Combault (France)
Second Severn Crossing(UK)
Confederation Bridge(Canada)
Vasco de Gama Bridge(Portugal)
5 km 13 kmRion‐Antirion Bridge
(Greece)
5 cable‐stayed spans
16.5 kmOresund Bridge
(Denmark – Sweden)
13 km
Millau Viaduct(France)
8 cable‐stayed spansSutong Bridge
(China)
1088 m long main span
Hangzhou Bridge(China)
36 km2
15 yearsof
Major Achievements
Gulf of Corinth
1/26
MAIN BRIDGE
Site CharacteristicsSite Characteristics
DEEP WATER
65 mRION ANTIRION
SAND AND GRAVELCLAY
WEAK ALLUVIUMS
65 m.
RION ANTIRION
CLAYSILT
SEISMIC and TECTONIC ACTIVITY
1 2
1.3
0.5
0.6
0.7
0.8
0.9
1
1.1
1.2
Acc
eler
atio
n
•Pic Ground Acceleration : 0.48 g•Maximum Acceleration : 1.20 g•Tectonic Drift : 8 mm / year
0
0.1
0.2
0.3
0.4
0 1 2 3 4 5 6 7 8
Vibration Period of the Structure (s)2/26
TECTONIC MOVEMENTS
ELEVATION
PIER BASE
VERTICAL SLIP : 2 m
PLAN HORIZONTAL OPENING : 2 m
SHIP IMPACT
RION ANTIRION
16 knots
180 000 t
65 m WATER DEPTH
WEAK ALLUVIUMS
NO UNUSUAL PROBLEM
WEAK ALLUVIUMS
SEISMIC INTENSITY
TECTONIC ACTIVITY
SHIP IMPACT
TECTONIC ACTIVITY
SEISMIC and TECTONIC ACTIVITY
+DEEP WATER
+
HUGE INTERACTION FORCES
3/26
HUGE INTERACTION FORCES
+WEAK ALLUVIUMS
+
WHAT ABOUT FOUNDATION ?The Akashi Kaikio Bridge - Kobe (Japan)
MAIN BRIDGE
Initial ConceptInitial Concept
4/26
Pylon Base
Spreading walls
Large diameter footing
Shallow pad foundation
Spreading walls+
Supporting Soil
Soil improvement
Poor quality soil
Shallow pad foundation
Soil improvement
+
5/26
Pylon Deck Connection
Energy dissipation
Displacement capacity
Seismic hazard
Energy dissipation+
6/26
Tectonic Movement
Deck Concept
Drop in section
Expansion joints
Drop-in section+
Pylon HeadConcrete pylon head
Transverse PT
Weight+
7/26
MAIN BRIDGE
Final ConceptFinal Concept
Pylon
• Made Monolithic
• Base re-designed and Simplified
• Head made Composite and Light
230 m
65 m
8/26
Pylons Concept
Seabed
• Deposits Removedp
• Reinforced with Steel Pipes
• Gravel Soil – Pylon Interface
9/26
Deck
• Made Continuous
• Fully Suspended
• Made Slender
10/26
Deck
The Rion - Antirion Bridge
Deck
and
Cables
• Composite steel-concrete deck• Steel I girders 2.20 m high• Concrete top slab 25 cm thick
• 5 continuous spans
• Composite steel-concrete deck• Steel I girders 2.20 m high• Concrete top slab 25 cm thick
• 5 continuous spans• Rion side span 286 m long• 3 typical spans 560 m long• Antirion side span 286 m long
• Fully suspended• 2*23 pairs of cable-stays• Uniformly distributed
• Rion side span 286 m long• 3 typical spans 560 m long• Antirion side span 286 m long
• Fully suspended• 2*23 pairs of cable-stays• Uniformly distributed• Regular spacing 12.15m
• Simply supported at both ends• Regular spacing 12.15 m
• Simply supported at both ends
CONTINUOUS DECK
Stay-Cables•spacing: 12.174 m
•strands: 43 - 55 - 61 - 73Top Flange•width: 0.80 - 1.00 m
•thickness: 40 - 80 mm
Bottom Flange•width: 1.00 - 1.35 - 1.70 m
•thickness: 80 - 90 mm
• Composite steel-concrete deck• Steel I girders 2.20 m high• Concrete top slab 25 cm thick
• 5 continuous spans
• Composite steel-concrete deck• Steel I girders 2.20 m high• Concrete top slab 25 cm thick
• 5 continuous spans• Rion side span 286 m long• 3 typical spans 560 m long• Antirion side span 286 m long
• Fully suspended• 2*23 pairs of cable-stays• Uniformly distributed
• Rion side span 286 m long• 3 typical spans 560 m long• Antirion side span 286 m long
• Fully suspended• 2*23 pairs of cable-stays• Uniformly distributed• Regular spacing 12.15m
• Simply supported at both ends• Regular spacing 12.15m
• Simply supported at both ends
CONTINUOUS DECK11/26
Final Characteristics of the Bridge
286 560 560 560 2862252
• Composite steel-concrete deck• Steel I girders 2.20 m high• Concrete top slab 25 cm thick
• 5 continuous spans
• Composite steel-concrete deck• Steel I girders 2.20 m high• Concrete top slab 25 cm thick
• 5 continuous spans• Rion side span 286 m long• 3 typical spans 560 m long• Antirion side span 286 m long
• Fully suspended• 2*23 pairs of cable-stays• Uniformly distributed
• Rion side span 286 m long• 3 typical spans 560 m long• Antirion side span 286 m long
• Fully suspended• 2*23 pairs of cable-stays• Uniformly distributed• Regular spacing 12.15m
• Simply supported at both ends• Regular spacing 12.15m
• Simply supported at both ends
CONTINUOUS DECK
FUSE
DAMPERS
12/26
• Composite steel-concrete deck• Steel I girders 2.20 m high• Concrete top slab 25 cm thick
• 5 continuous spans
• Composite steel-concrete deck• Steel I girders 2.20 m high• Concrete top slab 25 cm thick
• 5 continuous spans• Rion side span 286 m long• 3 typical spans 560 m long• Antirion side span 286 m long
• Fully suspended• 2*23 pairs of cable-stays• Uniformly distributed
• Rion side span 286 m long• 3 typical spans 560 m long• Antirion side span 286 m long
• Fully suspended• 2*23 pairs of cable-stays• Uniformly distributed• Regular spacing 12.15m
• Simply supported at both ends• Regular spacing 12.15m
• Simply supported at both ends
CONTINUOUS DECK
RION-ANTIRION Bridge (Greece)
286 560 560 560 2862252
2701480890 320
TATARA Bridge (Japan)
127 448 475 1271177
TING KAU Bridge (Hong Kong)
13/26
St t l St bilit
ADVANTAGES
• Structural Stability• Natural Seimic Isolation• Structural Flexibility
• For linear variations (shrinkage, creep, temperature)
• For tectonic displacementsp• For gravity loads (traffic)
• Structural Lightness• Better seismic behaviour• Better aerodynamic behaviour
14/26
MAIN BRIDGE
Final DesignFinal DesignReinforced Soil
CapacityCapac ty
THEORETICAL ANALYSESGlobal Soil Bearing Capacity
THEORETICAL ANALYSESKinematic Approach of the Yield Design Theory
15/26
m)
THEORETICAL ANALYSESInclusion Spacing Effect
10000
20000
30000
ng M
omen
t (M
N-m
9m x 9m
7m x 7m
M0
10000
0 200 400 600 800
Horizontal Shear Force (MN)
Ove
rtur
ni
WH
M
Centrifuge Test in a Laboratory EXPERIMENTAL VALIDATION
EXPERIMENTAL VALIDATION
Centrifuge Test : Reinforced Soil Model
EXPERIMENTAL VALIDATION
Centrifuge Test : Before Installation of the Foundation Model
16/26
EXPERIMENTAL VALIDATION
Centrifuge Test : Ultimate Capacity Test
120
MN
)
Monotonic Failure Load EXPERIMENTAL VALIDATION
40
60
80
100
uted
failu
re lo
ad (M
0
20
0 20 40 60 80 100 120
Measured failure load (MN)
Com
pu
50
Cyclic Load (75% Failure Load) EXPERIMENTAL VALIDATION
-10
10
30
zont
al fo
rce
(MN
)
1
10
-50
-30
-0.50 -0.30 -0.10 0.10 0.30 0.50
Horizontal displacement (m)
Hor
iz
MAIN BRIDGE
ConstructionConstruction
17/26
18/26
19/26
20/26
REINFORCINGSOILSOIL
G idi E i tHydraulic Hammer
Tremie Pipe
Guiding Equipment
INCLUSIONDRIVINGDRIVING
Hydraulic Hammer Base(View from Below)
21/26
22/26
23/26
24/26
MAIN BRIDGE
ConclusionConclusion
25/26
When a Dream has become RealityThe Rion-Antirion Bridge
Jacques Combault (France)
26/26