HWY 169/ HWY 282/ CR 9 INTERCHANGE PROJECT PRELIMINARY DESIGN AND ENVIRONMENTAL DOCUMENTATION
What is the Status of the Hwy 169/ Hwy 282/ CR 9 Interchange Project?
The City of Jordan has been working with Scott County and MnDOT to study potential alternatives for the construction of an interchange at the Hwy 169/ Hwy 282/ CR 9 intersection. Improvements are needed to address safety and operational concerns in the area, and a long-term solution is needed.
In 2018, a conceptual design was developed for an interchange that was supported by all three agencies (see map below). More information on the concept design process can be found at http://tinyurl.com/hwy169-hwy282-cr9. The City is now moving forward with more detailed engineering design and environmental review.
Survey crews and soil boring equipment will be working in the project area over the next few months to collect field data in support of the preliminary design efforts.
City of Jordan
HWY 1
69
HW
Y 21
HWY 282
CR
9
Project Area
Agency Supported Vision
APRIL 2019
7TH STREET
VALL
EY VIEW
DRIVE
SYNDICATE STREET
CREEK LANE
PROPOSED ROADWAYPROPOSED BRIDGEPROPOSED TRAILSPROPOSED TRAFFIC SIGNAL
LEGEND
TRAFFIC SIGNAL
BRIDGE OVER RAILROAD TRACKS
TRAFFIC SIGNAL
ROUNDABOUT
ROUNDABOUT
BRIDGE OVER HIGHWAY 169
What is the current project schedule?
2019Apr May June July Aug Sept Oct Nov Dec
Surveying and Soil BoringsPreliminary Design & Environmental Review
Public Open House *
HWY 169/ HWY 282/ CR 9 INTERCHANGE PROJECT PRELIMINARY DESIGN AND ENVIRONMENTAL DOCUMENTATION
Who can I contact with questions?
Tom Nikunen, Jordan City [email protected](952) 492-2535
City of Jordan210 EAST 1ST STREETJORDAN, MN 55352
HWY 169/ HWY 282/ CR 9INTERCHANGE PROJECT
More details on the date and time of the October public open house will be provided at a later date.