Status of Wetland Permitting in Washington State:
An Applicant’s Perspective
Francis Naglich, Principal
Ecological Land Services, Inc.
![Page 2: Wetland Permitting in WA by Francis Naglich](https://reader033.vdocuments.mx/reader033/viewer/2022061222/54c23b864a79596e448b456b/html5/thumbnails/2.jpg)
Permitting in Washington State Permitting in Washington State BackgroundBackground
Wetlands Regulatory Framework: Wetlands Regulatory Framework: ● Federal – USACE and EPAFederal – USACE and EPA● State – Department of EcologyState – Department of Ecology● Local – County or CityLocal – County or City● Other – Shorelines, Hydraulic Permits, Other – Shorelines, Hydraulic Permits,
FEMA Floodplain FEMA Floodplain
![Page 3: Wetland Permitting in WA by Francis Naglich](https://reader033.vdocuments.mx/reader033/viewer/2022061222/54c23b864a79596e448b456b/html5/thumbnails/3.jpg)
![Page 4: Wetland Permitting in WA by Francis Naglich](https://reader033.vdocuments.mx/reader033/viewer/2022061222/54c23b864a79596e448b456b/html5/thumbnails/4.jpg)
Permitting in Washington State Permitting in Washington State BackgroundBackground
● Status of the Science:Status of the Science:● Wetland Categories I - IV Wetland Categories I - IV ● Best Available Science (BAS)Best Available Science (BAS)● Wetland BuffersWetland Buffers● Replacement RatiosReplacement Ratios
* Category and Land Use Intensity and * Category and Land Use Intensity and Mitigation Approach = Ratio Mitigation Approach = Ratio* Washington functional Assessment * Washington functional Assessment
Methodology Methodology* Credit – Debit Method (Focus on * Credit – Debit Method (Focus on Function) Function)
![Page 5: Wetland Permitting in WA by Francis Naglich](https://reader033.vdocuments.mx/reader033/viewer/2022061222/54c23b864a79596e448b456b/html5/thumbnails/5.jpg)
Permitting in Washington State Permitting in Washington State BackgroundBackground
● Mitigation ApproachesMitigation Approaches● Sequencing – Avoidance, Minimization…Sequencing – Avoidance, Minimization…● Applicant Sponsored: Concurrent – In-KindApplicant Sponsored: Concurrent – In-Kind● Third Party Provider: Mitigation Bank, In-lieu Third Party Provider: Mitigation Bank, In-lieu
Fee Fee ● Consolidated Mitigation SiteConsolidated Mitigation Site● Advanced MitigationAdvanced Mitigation● Maintenance/MonitoringMaintenance/Monitoring● Long Term Site ProtectionLong Term Site Protection
![Page 6: Wetland Permitting in WA by Francis Naglich](https://reader033.vdocuments.mx/reader033/viewer/2022061222/54c23b864a79596e448b456b/html5/thumbnails/6.jpg)
ChallengesChallenges
![Page 7: Wetland Permitting in WA by Francis Naglich](https://reader033.vdocuments.mx/reader033/viewer/2022061222/54c23b864a79596e448b456b/html5/thumbnails/7.jpg)
Challenges: Inconsistency Between Regulations and Challenges: Inconsistency Between Regulations and Agencies Agencies
1.1. JurisdictionJurisdiction
Some Wetlands are “isolated” per Corps, but Some Wetlands are “isolated” per Corps, but the process for determinations is unpredictablethe process for determinations is unpredictable
EPA has veto/challenge authority on such callsEPA has veto/challenge authority on such calls
Department of Ecology and local agencies still Department of Ecology and local agencies still have jurisdiction over isolated wetlandshave jurisdiction over isolated wetlands
![Page 8: Wetland Permitting in WA by Francis Naglich](https://reader033.vdocuments.mx/reader033/viewer/2022061222/54c23b864a79596e448b456b/html5/thumbnails/8.jpg)
Challenges: Inconsistency Between Regulations Challenges: Inconsistency Between Regulations and Agencies and Agencies
2.2. Avoidance CriteriaAvoidance Criteria
Non water-dependant projects may require Non water-dependant projects may require rigorous alternatives analysis to acquire Corps rigorous alternatives analysis to acquire Corps permitpermit
Criteria more relaxed at local and state levelCriteria more relaxed at local and state level
![Page 9: Wetland Permitting in WA by Francis Naglich](https://reader033.vdocuments.mx/reader033/viewer/2022061222/54c23b864a79596e448b456b/html5/thumbnails/9.jpg)
Challenges: Inconsistency Between Challenges: Inconsistency Between Regulations and Agencies Regulations and Agencies
3.3. Buffer WidthsBuffer Widths Example: Recent ELS projectExample: Recent ELS project
City of Camas buffer requirementsCity of Camas buffer requirements for a Category 2 for a Category 2 wetland with low habitat function and proposed high-wetland with low habitat function and proposed high-intensity land-use: intensity land-use: Original buffer width: 100 feetOriginal buffer width: 100 feet Allowed reduction of buffer width to 56.25 feetAllowed reduction of buffer width to 56.25 feet
DOE / USACE buffer requirementsDOE / USACE buffer requirements for a Category 2 for a Category 2 wetland with low habitat function and proposed high-wetland with low habitat function and proposed high-intensity land-use: intensity land-use: Required a buffer of 100 feetRequired a buffer of 100 feet Allowed reduction of buffer width to 75 feetAllowed reduction of buffer width to 75 feet
![Page 10: Wetland Permitting in WA by Francis Naglich](https://reader033.vdocuments.mx/reader033/viewer/2022061222/54c23b864a79596e448b456b/html5/thumbnails/10.jpg)
ESA & Cultural ResourcesESA & Cultural Resources
Issues must be resolved for any federal Issues must be resolved for any federal actionaction
Example: Corps permit, FEMA project, or Example: Corps permit, FEMA project, or any project with federal funds attachedany project with federal funds attached
![Page 11: Wetland Permitting in WA by Francis Naglich](https://reader033.vdocuments.mx/reader033/viewer/2022061222/54c23b864a79596e448b456b/html5/thumbnails/11.jpg)
Don’t Forget…Don’t Forget…
Washington Department of Fish & Wildlife,Washington Department of Fish & Wildlife,
through Hydraulic Project Application (HPA),through Hydraulic Project Application (HPA),
may take the same or additional jurisdictionmay take the same or additional jurisdiction
depending on the impact.depending on the impact.
![Page 12: Wetland Permitting in WA by Francis Naglich](https://reader033.vdocuments.mx/reader033/viewer/2022061222/54c23b864a79596e448b456b/html5/thumbnails/12.jpg)
OtherOther Buyer Beware! Buyer Beware!
Cumulative ImpactsCumulative Impacts
Permit Timing Permit Timing Section 404 Section 404
Nationwide Permit = 3-9 monthsNationwide Permit = 3-9 monthsIndividual Permit = 1-2 years or moreIndividual Permit = 1-2 years or more
Shorelines, Floodplain, NPDES, SWPPPShorelines, Floodplain, NPDES, SWPPP May be additional, overlapping, or even conflicting May be additional, overlapping, or even conflicting
regulationsregulations
High Mitigation Ratios for Wetland PreservationHigh Mitigation Ratios for Wetland Preservation
![Page 13: Wetland Permitting in WA by Francis Naglich](https://reader033.vdocuments.mx/reader033/viewer/2022061222/54c23b864a79596e448b456b/html5/thumbnails/13.jpg)
Permitting Hill Climb
![Page 14: Wetland Permitting in WA by Francis Naglich](https://reader033.vdocuments.mx/reader033/viewer/2022061222/54c23b864a79596e448b456b/html5/thumbnails/14.jpg)
Permitting Hill Climb
![Page 15: Wetland Permitting in WA by Francis Naglich](https://reader033.vdocuments.mx/reader033/viewer/2022061222/54c23b864a79596e448b456b/html5/thumbnails/15.jpg)
Permitting Hill Climb
![Page 16: Wetland Permitting in WA by Francis Naglich](https://reader033.vdocuments.mx/reader033/viewer/2022061222/54c23b864a79596e448b456b/html5/thumbnails/16.jpg)
Permitting Hill Climb
![Page 17: Wetland Permitting in WA by Francis Naglich](https://reader033.vdocuments.mx/reader033/viewer/2022061222/54c23b864a79596e448b456b/html5/thumbnails/17.jpg)
Solutions/OpportunitiesSolutions/Opportunities
![Page 18: Wetland Permitting in WA by Francis Naglich](https://reader033.vdocuments.mx/reader033/viewer/2022061222/54c23b864a79596e448b456b/html5/thumbnails/18.jpg)
1. 1. Early Agency InvolvementEarly Agency Involvement Pre-Application Meeting – On-site if possible, at a minimum by Pre-Application Meeting – On-site if possible, at a minimum by
conference callconference call
Applicant: Have a good plan, be flexible, know your bottom lineApplicant: Have a good plan, be flexible, know your bottom line
Agency: Identify impacts and mitigation, chart the path to the permitAgency: Identify impacts and mitigation, chart the path to the permit
Invite and include, where possible all stakeholders. Invite and include, where possible all stakeholders. Example: Tribes, Watershed Councils, Community GroupsExample: Tribes, Watershed Councils, Community Groups
Avoid: The “US and Them” SyndromeAvoid: The “US and Them” Syndrome
![Page 19: Wetland Permitting in WA by Francis Naglich](https://reader033.vdocuments.mx/reader033/viewer/2022061222/54c23b864a79596e448b456b/html5/thumbnails/19.jpg)
2.2. Realistic Expectations for Applicants/AgenciesRealistic Expectations for Applicants/Agencies
Understanding where the project crosses the Understanding where the project crosses the “point of fill / no-fill”“point of fill / no-fill”
Wetland Fill site Wetland Fill site Avoidance - No Fill Avoidance - No Fill
What information is needed? Once submitted, how long to review and make a What information is needed? Once submitted, how long to review and make a decision? Avoid “moving targets”.decision? Avoid “moving targets”.
Identify acceptable mitigation options. Avoid “back and forth, and crapshoot Identify acceptable mitigation options. Avoid “back and forth, and crapshoot approaches”approaches”
Beware of on-site mitigation limitations.Beware of on-site mitigation limitations. Beware of unintended consequences. Beware of unintended consequences.
Example: The disappearing oaks of Clark CountyExample: The disappearing oaks of Clark County
![Page 20: Wetland Permitting in WA by Francis Naglich](https://reader033.vdocuments.mx/reader033/viewer/2022061222/54c23b864a79596e448b456b/html5/thumbnails/20.jpg)
![Page 21: Wetland Permitting in WA by Francis Naglich](https://reader033.vdocuments.mx/reader033/viewer/2022061222/54c23b864a79596e448b456b/html5/thumbnails/21.jpg)
3. 3. Mitigation StrategiesMitigation Strategies
Wetland Mitigation BankingWetland Mitigation Banking In-Lieu FeesIn-Lieu Fees Applicant-Sponsored MitigationApplicant-Sponsored Mitigation Other Mitigation StrategiesOther Mitigation Strategies
* * Consolidated MitigationConsolidated Mitigation
* Advanced Mitigation* Advanced Mitigation
* Programmatic Mitigation* Programmatic Mitigation
Example: Regional General Permit Example: Regional General Permit (RGP)(RGP)
![Page 22: Wetland Permitting in WA by Francis Naglich](https://reader033.vdocuments.mx/reader033/viewer/2022061222/54c23b864a79596e448b456b/html5/thumbnails/22.jpg)
On-Going Dialogue with Corps, Department On-Going Dialogue with Corps, Department of Ecology, and Local Agencyof Ecology, and Local Agency
Alternatives Analysis ProcessAlternatives Analysis Process Identifying Impacts and Potential for Advanced Identifying Impacts and Potential for Advanced
Mitigation Strategies, Banking, and In-lieu Fees, Mitigation Strategies, Banking, and In-lieu Fees, Consolidated and ProgrammaticConsolidated and Programmatic
Creating Incentives for Wetland PreservationCreating Incentives for Wetland Preservation
Example: “String of Pearls”Example: “String of Pearls”
![Page 23: Wetland Permitting in WA by Francis Naglich](https://reader033.vdocuments.mx/reader033/viewer/2022061222/54c23b864a79596e448b456b/html5/thumbnails/23.jpg)
Integrating Stormwater Integrating Stormwater Management with Enhancement of Management with Enhancement of
Low-Quality WetlandsLow-Quality Wetlands
Low-quality Pasture WetlandLow-quality Pasture Wetland Enhanced WetlandEnhanced Wetland
![Page 24: Wetland Permitting in WA by Francis Naglich](https://reader033.vdocuments.mx/reader033/viewer/2022061222/54c23b864a79596e448b456b/html5/thumbnails/24.jpg)
Programmatic and Advance MitigationProgrammatic and Advance Mitigation
Port of Chehalis Port of Chehalis A Groundbreaking OpportunityA Groundbreaking Opportunity
![Page 25: Wetland Permitting in WA by Francis Naglich](https://reader033.vdocuments.mx/reader033/viewer/2022061222/54c23b864a79596e448b456b/html5/thumbnails/25.jpg)
Traditional Piece-Meal PermittingTraditional Piece-Meal Permitting
TimeTimeProject UncertaintyProject Uncertainty
Client Perceives Increased RiskClient Perceives Increased Risk
Client Loses Time and ProfitsClient Loses Time and Profits
Client is Distracted by Other OptionsClient is Distracted by Other Options
Port Loses Interested Port Loses Interested ClientClient
START
Client Client isis
ReadyReady
Local Permitting Process
State & Federal
Permitting
Process
Land Land
is is
ReadyReady
FINISH
![Page 26: Wetland Permitting in WA by Francis Naglich](https://reader033.vdocuments.mx/reader033/viewer/2022061222/54c23b864a79596e448b456b/html5/thumbnails/26.jpg)
Advance Advance MITIGATIONMITIGATION Round Table Round Table DiscussionDiscussion
WDFW
Senator Dan Swecker
![Page 27: Wetland Permitting in WA by Francis Naglich](https://reader033.vdocuments.mx/reader033/viewer/2022061222/54c23b864a79596e448b456b/html5/thumbnails/27.jpg)
Provide Certainty to ClientsProvide Certainty to Clients Address Permitting Issues with ConsistencyAddress Permitting Issues with Consistency Invite Regulators to RegulateInvite Regulators to Regulate
Discussion: Port’s ConcernsDiscussion: Port’s Concerns
![Page 28: Wetland Permitting in WA by Francis Naglich](https://reader033.vdocuments.mx/reader033/viewer/2022061222/54c23b864a79596e448b456b/html5/thumbnails/28.jpg)
Permitting Without a Specific ProjectPermitting Without a Specific Project Zero Net-Loss of WetlandsZero Net-Loss of Wetlands Agreeing to a Development without Agreeing to a Development without
Advanced Certainty of ReplacementAdvanced Certainty of Replacement
Wetland QualityWetland Quality
Discussion: Agency ConcernsDiscussion: Agency Concerns
![Page 29: Wetland Permitting in WA by Francis Naglich](https://reader033.vdocuments.mx/reader033/viewer/2022061222/54c23b864a79596e448b456b/html5/thumbnails/29.jpg)
Opens 125 AcresOpens 125 Acres for Developmentfor Development
Expect 750 New JobsExpect 750 New Jobs at at Complete Build-OutComplete Build-Out
Certainty for ClientsCertainty for Clients Looking for Timely DevelopmentLooking for Timely Development
Advance Mitigation Advance Mitigation Benefits to PortBenefits to Port
![Page 30: Wetland Permitting in WA by Francis Naglich](https://reader033.vdocuments.mx/reader033/viewer/2022061222/54c23b864a79596e448b456b/html5/thumbnails/30.jpg)
One Mitigation Site One Mitigation Site for Multiple Projectsfor Multiple Projects
Improved Survival Improved Survival of the Mitigation of the Mitigation
ProjectProject
Agency Access Agency Access for Monitoringfor Monitoring
Advance Mitigation Advance Mitigation Benefits to AgenciesBenefits to Agencies
![Page 31: Wetland Permitting in WA by Francis Naglich](https://reader033.vdocuments.mx/reader033/viewer/2022061222/54c23b864a79596e448b456b/html5/thumbnails/31.jpg)
One Mitigation ProjectOne Mitigation Project IIncreased Survival Ratencreased Survival Rate
Groundbreaking ProcessGroundbreaking Process that Could be Used as a Standard that Could be Used as a Standard Mitigation Approach for PortsMitigation Approach for Ports
True Symbiotic PartnershipTrue Symbiotic Partnership of Government Agenciesof Government Agencies
Timely Economic Boost Timely Economic Boost to a Struggling Areato a Struggling Area
Advance Mitigation Advance Mitigation Benefits to AllBenefits to All
![Page 32: Wetland Permitting in WA by Francis Naglich](https://reader033.vdocuments.mx/reader033/viewer/2022061222/54c23b864a79596e448b456b/html5/thumbnails/32.jpg)
Advanced Programmatic Advanced Programmatic MitigationMitigation
Impact AreaImpact Area Proposed Mitigation AreaProposed Mitigation Area
Port of Chehalis ExamplePort of Chehalis Example
![Page 33: Wetland Permitting in WA by Francis Naglich](https://reader033.vdocuments.mx/reader033/viewer/2022061222/54c23b864a79596e448b456b/html5/thumbnails/33.jpg)
Wetland Creation SiteWetland Creation Site
![Page 34: Wetland Permitting in WA by Francis Naglich](https://reader033.vdocuments.mx/reader033/viewer/2022061222/54c23b864a79596e448b456b/html5/thumbnails/34.jpg)
Project UnderwayProject Underway
![Page 35: Wetland Permitting in WA by Francis Naglich](https://reader033.vdocuments.mx/reader033/viewer/2022061222/54c23b864a79596e448b456b/html5/thumbnails/35.jpg)
![Page 36: Wetland Permitting in WA by Francis Naglich](https://reader033.vdocuments.mx/reader033/viewer/2022061222/54c23b864a79596e448b456b/html5/thumbnails/36.jpg)
![Page 37: Wetland Permitting in WA by Francis Naglich](https://reader033.vdocuments.mx/reader033/viewer/2022061222/54c23b864a79596e448b456b/html5/thumbnails/37.jpg)
Contact InfoContact Info