Well Road Project – Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT’s) By: Mark Bucci, P.E.

Upload: others

Post on 13-Jul-2020

10 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Well Road Project – Accelerated Bridge Construction Using Self-Propelled

Modular Transporters (SPMT’s)

By: Mark Bucci, P.E.

Page 2: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Presentation Outline

Project History Project Scope Construction Alternatives Plan Development Contractor’s Methodology Current Project Status

Page 3: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Project History

Site Information◦ West Monroe, LA◦ LA 3249 (Well Road) over I-20

Well Road Overpass

Truck Stop

Page 4: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Project History

Site Information◦ High Average Daily Traffic (ADT) I-20 41,300 ADT LA 3249 (Well Road) 18,700 ADT

◦ High truck traffic

Page 5: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Project History

Existing Bridge◦ Built in 1963◦ 4 – Simple Span Composite Steel Plate Girder

Bridge (55 ft – 70 ft – 85 ft – 50 ft)◦ Lightweight concrete deck

Page 6: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Project History

Bridge Condition◦ Deck Deterioration

Page 7: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Project History◦ Deck Deterioration

Page 8: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Project History◦ Deck Deterioration

Page 9: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Project History Bridge Condition◦ Bearing Corrosion

Page 10: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Project History◦ Bearing Corrosion (Cont.)

Page 11: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Project History

Bridge Condition◦ Column Bent Spalling

Page 12: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Project History Bridge Load Testing (March 2008)◦ Bridge Diagnostics, Inc. (BDI) performed the

testing◦ Determine the structural capacity considering

deck deterioration◦ Review the load rating◦ Provide information to assist in determining

the best course of action for rehabilitation

Page 13: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Project History

Bridge Load Testing

Page 14: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Project History

Bridge Load Testing◦ Finite Element Model Calibrated to match the test results The structure was load rated

◦ Results The bridge did not need to be load posted An overlay could be applied

Page 15: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Project History

Temporary Repairs◦ Quick Set Concrete Patches

Page 16: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Project History

Temporary Repairs◦ Asphalt Overlay Recommended by the District to reduce

maintenance

Page 17: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Presentation Outline

Project History Project Scope Construction Alternatives Plan Development Contractor’s Methodology Current Project Status

Page 18: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Project Scope

Project created in mid 2008 to perform permanent repairs

Funded by State Surplus

Aggressive delivery schedule

Proposed July 2009 letting

Page 19: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Project Scope

Requirements◦ Replace the deck◦ Minimize impacts to

businesses and the traveling public◦ Maintain vertical

clearance◦ Strengthen

substructure if necessary

Considerations◦ High ADT◦ Heavy Truck Traffic◦ Future widening

Page 20: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Accelerated Construction

Page 21: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Presentation Outline

Project History Project Scope Construction Alternatives Plan Development Contractor’s Methodology Current Project Status

Page 22: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Construction Alternatives

Accelerated Construction◦ Precast Panel Units

Page 23: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Construction Alternatives

Accelerated Construction◦ Precast Panel Units

Page 24: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Construction Alternatives

Accelerated Construction◦ Span Replacement

Page 25: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Construction Alternatives

Accelerated Construction◦ Span Replacement Self-Propelled Modular Transporters (SPMT’s)

Page 26: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Construction Alternatives

Accelerated Construction◦ Span Replacement Self-Propelled Modular Transporters (SPMT’s)

Page 27: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Construction Alternatives

Accelerated Construction◦ Span Replacement Crane

Page 28: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Construction Alternatives

Accelerated Construction◦ Recommend span replacement Reduce traffic impacts

Limit overall closure period

Page 29: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Presentation Outline

Project History Project Scope Construction Alternatives Plan Development Contractor’s Methodology Current Project Status

Page 30: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Plan Development

Project Initiation◦ Task order was created with Modjeski and

Masters (NTP issued July 2008) Design and develop plans for the new steel girder

spans with a concrete deck Load rate the repaired bridge Develop plans to strengthen the substructure if

necessary Establish constructability Traffic control plan

Page 31: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Plan Development

Steel Girder Replacement Spans◦ 28’ clear roadway

◦ Weathering steel rolled W-shape girders

◦ Girders to be composite with deck

◦ 7 ½” thick concrete deck

◦ Epoxy coated deck steel

Page 32: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Plan Development

Steel Girder Spans

Page 33: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Plan Development

Bridge Load Rating◦ Existing bridge was designed using the HS-20

truck

◦ The rating showed that the substructure required strengthening using LRFR (HL-93 truck)

Page 34: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Plan Development

Substructure Strengthening◦ A spread footing was added between the

existing pile footings of column bents

◦ Drilled shafts were added to the existing end bents

Page 35: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Plan Development

Substructure Strengthening◦ Column Bent Spread Footing

Page 36: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Plan Development

Substructure Strengthening◦ End Bent Strengthening (Drilled Shafts)

Page 37: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Plan Development

Suggested Method of Construction◦ Construct spans in a staging area◦ Move the spans using SPMT’s Replace the spans over four consecutive nightly

closures from 7:00 PM to 7:00 AM Replace all four spans over a weekend closure

beginning at 7:00 PM Friday and re-opening the bridge at 7:00 AM the following Monday

Page 38: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Plan Development

Suggested Method of Construction

Page 39: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Plan Development

Suggested Method of Construction

Page 40: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Plan Development

Suggested Method of Construction

Page 41: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Plan Development

Prefabrication Plan◦ Geotechnical assessment◦ Design of temporary supports◦ Settlement analysis and monitoring

Page 42: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Plan Development

Movement Plan◦ As-built survey◦ Moving equipment◦ Path of movement◦ Lift point locations ◦ Analysis of temporary loads on spans◦ Geotechnical assessment◦ Span monitoring◦ Contingency planning

Page 43: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Plan Development

Span Monitoring◦ 10 – Elevation reference points per span◦ Monitoring Intervals Before Lift Immediately After Lift As needed through transport to maintain relative

elevations Final Position

Page 44: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Plan Development

Traffic Control Plan

Road Closed

Road Closed

Temporary Detour

Page 45: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Plan Development

Traffic Control Plan◦ Temporary Detour Road

Page 46: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Plan Development

Traffic Control Plan

Project Site

Page 47: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Plan Development

Project was let in December 2009◦ Engineer’s Estimate $3.95 Million

◦ Contractor’s Bid Price $ 3.17 Million

◦ Awarded to Gibson and Associates

◦ Work Order issued March 2010

Page 48: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Presentation Outline

Project History Project Scope Construction Alternatives Plan Development Contractor’s Methodology Current Project Status

Page 49: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Contractor’s Methodology

Staging area within the interchange

Temporary steel pipe trestle

SPMT’s to move the spans

Perform the moves over a weekend closure

Page 50: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Contractor’s Methodology

Staging Area and Movement Path

Staging Area

Page 51: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Contractor’s Methodology

Temporary Support

Page 52: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Contractor’s Methodology

Temporary Support

Page 53: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Contractor’s Methodology

Movement Method

Page 54: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Contractor’s Methodology

Movement Method

Page 55: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Presentation Outline

Project History Project Scope Construction Alternatives Plan Development Contractor’s Methodology Current Project Status

Page 56: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Current Project Status

Substructure Strengthening

Page 57: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Current Project Status

Substructure Strengthening

Page 58: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Current Project Status

Substructure Strengthening

Page 59: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Current Project Status

Span Construction

Page 60: Well Road Project - Florida International Universityutcdb.fiu.edu/LA 3249-Well Road Presentation.pdf · Presentation Outline Project History Project Scope Construction Alternatives

Current Project Status

Span Movement◦ Span movement plan is currently under

review

◦ Span movement is tentatively scheduled for early February 2011