DESCRIPTION
Presentation of work on site of the construction of high level bridge over Sutlej river. most of the work is related to sinking of well foundation.TRANSCRIPT
![Page 1: well foundation](https://reader033.vdocuments.mx/reader033/viewer/2022061111/54546f36b1af9f1b348b48ac/html5/thumbnails/1.jpg)
WELL FOUNDATION
CONSTRUCTION OF HIGH LEVEL BRIDGE OVER SUTLEJ RIVER
![Page 2: well foundation](https://reader033.vdocuments.mx/reader033/viewer/2022061111/54546f36b1af9f1b348b48ac/html5/thumbnails/2.jpg)
PROJECT BREIFING
This bridge forms a part of a bye-pass project near Ropar The project is undertaken by B&R division of PWD. Total cost of the bridge over Sutlej is 63 crs. The contract is given to the company on the lump sum
basis.
Length 982 m
Lanes 4 lane
Spans 28
Length of span 36.5 m ( middle 23 spans)
24 m (end spans)
Formation level 273.5 m
High flood level 264.2 m
![Page 3: well foundation](https://reader033.vdocuments.mx/reader033/viewer/2022061111/54546f36b1af9f1b348b48ac/html5/thumbnails/3.jpg)
Alignment •Alignment of the bridge passes through :
New I.I.T. Road
Sutlej river
Nwansheher highway
•Alignment crosses river at an angle therefore it is a Skew alignment
![Page 4: well foundation](https://reader033.vdocuments.mx/reader033/viewer/2022061111/54546f36b1af9f1b348b48ac/html5/thumbnails/4.jpg)
Height of Bridge
Bridge is high level bridge i.e. formation level is above H.F.L.
Height if bridge is determined by examining the clearance of bridge over highway
As per IRC 5:1998 Min. clearance needed = 5 mRoad level =267Width of beam and slab =1.7 mReq. formation level= 273.7 mActual formation level=274.7 m
![Page 5: well foundation](https://reader033.vdocuments.mx/reader033/viewer/2022061111/54546f36b1af9f1b348b48ac/html5/thumbnails/5.jpg)
Extent of exploration
The exploration shall cover the entire length of the bridge and also extend at either side for a distance of about twice the depth below bed of the last main foundations i.e. if depth of foundation below bed is 24mts. then exploration will be done up to 48mts away from ends.
The depth of exploration should be at least 1 ½ times the minimum width of the foundation below the proposed foundation level in case of open foundations and deep well foundation
Where such investigation end in any unsuitable or questionable foundation material, the exploration shall be extended to a sufficient depth into firm and stable soil or rock but not less than four times the minimum depth of foundation below the earlier contemplated foundation level.
![Page 6: well foundation](https://reader033.vdocuments.mx/reader033/viewer/2022061111/54546f36b1af9f1b348b48ac/html5/thumbnails/6.jpg)
Scour depth
Depth of scour below the high flood level.Scour depth has important in determination
depth of foundation.DeterminationThe maximum depth of scour should be measured
with reference to existing structures near the proposed bridge site, if this is possible. Such soundings are best done during or immediately after a flood.
Mean scour depth (dsm )= 9.2 mMax. scour depth for piers = 2 dsm = 18.4 m
![Page 7: well foundation](https://reader033.vdocuments.mx/reader033/viewer/2022061111/54546f36b1af9f1b348b48ac/html5/thumbnails/7.jpg)
Depth of foundation
Well foundation are taken up to depth such that min. grip of foundation below max. scour depth is 1/3 rd of max. scour depth.
The max. Bearing pressure on the subsoil under the foundation resulting from any combination of the loads and forces except wind and seismic forces should not exceed the safe bearing capacity of the subsoil, after taking into account the effect of scour.
![Page 8: well foundation](https://reader033.vdocuments.mx/reader033/viewer/2022061111/54546f36b1af9f1b348b48ac/html5/thumbnails/8.jpg)
WELL FOUNDATION•Well foundation lies under the category of open caisson
•They are open at both ends
![Page 9: well foundation](https://reader033.vdocuments.mx/reader033/viewer/2022061111/54546f36b1af9f1b348b48ac/html5/thumbnails/9.jpg)
Well ComponentsCutting edge
Well curb
Well steining
Bottom plug
Sand fill
Top plug
Well cap
![Page 10: well foundation](https://reader033.vdocuments.mx/reader033/viewer/2022061111/54546f36b1af9f1b348b48ac/html5/thumbnails/10.jpg)
Cutting edge
•Cutting edge is the lowermost part of a well It is the part which cuts through the earth.•The mild steel cutting edge shall be made from structural steel sections.• The cutting edge shall weigh not less than 40 kg per metre length and be properly anchored into the well curb• sections are bent into shape by cold bended no heating is done.
The picture above shows a three 160mm MS
Sections curved and welded to form Cutting Edge.
![Page 11: well foundation](https://reader033.vdocuments.mx/reader033/viewer/2022061111/54546f36b1af9f1b348b48ac/html5/thumbnails/11.jpg)
Well curb
•Well curb is a structure with outer wall of curb being straight and inner at an appropriate angle which is fabricated over cutting edge.•The internal angle of curb can be kept between 30O to 37o .•It serves the purpose of transferring•Load from steining to bottom plug.•Thickness of well curb is 75mm more than that of steining to prevent tilts A fabricated well curb set atop wooden
planks
![Page 12: well foundation](https://reader033.vdocuments.mx/reader033/viewer/2022061111/54546f36b1af9f1b348b48ac/html5/thumbnails/12.jpg)
Well curb
Reinforcements in awell curb
Vertical bars -20 dia.
Triangular bars -20 dia.
![Page 13: well foundation](https://reader033.vdocuments.mx/reader033/viewer/2022061111/54546f36b1af9f1b348b48ac/html5/thumbnails/13.jpg)
Well steining
It is the longest part of well and it transfers load from well cap to the well curb at desired depth.
Track of length is taken by marking wells on 4 sides by gauges.
Steining is built in lifts of 2.15m and each lift is aligned with previous one.
As per IRC 78:2001. The amount of vertical reinforcement
provided should not be less than .2% of cross sectional area of steining.
2. At the inner face reinforcement must not be less than .06% of area.
3. Transverse reinforcement must not be less than .04% of volume/unit length of steining.
![Page 14: well foundation](https://reader033.vdocuments.mx/reader033/viewer/2022061111/54546f36b1af9f1b348b48ac/html5/thumbnails/14.jpg)
Reinforcements in steining
For wells 12 to 23Outer dia.= 5.35 m inner dia. = 3.4 mArea of steining= 13.394Min. reinforcement for steining (20 dia.
Bars)= .02*area/area of bar = 85.3 = 86 bars
Actual no. =62+26 =88 barsMin. reinforcements for inner wall(20
dia.)=.oo6*area/area of bar =25.59 = 26 bars
Actual no. =26 bars
![Page 15: well foundation](https://reader033.vdocuments.mx/reader033/viewer/2022061111/54546f36b1af9f1b348b48ac/html5/thumbnails/15.jpg)
Well steining
Determination of thickness of steining The min. thickness should not be less than 500mm and should be
according:
h=kd√l where : h- min. thickness in m
d=external dia. Of well
l=depth of well below well cap
k= a constant = 0.03
At the site: avg. depth of well = 25m
dia. = 5.2m
So Min. thickness required = .78 m
![Page 16: well foundation](https://reader033.vdocuments.mx/reader033/viewer/2022061111/54546f36b1af9f1b348b48ac/html5/thumbnails/16.jpg)
Well steining
But some adjustments are needed in thickness according to the strata as given by the table:
As the strata is sand with boulders final thickness is = .858 mOriginal thickness =.78 m (well no. 1-11 and 24
-29) = .88m (well no. 12-23)
Strata Adjustment
Very soft clay strata -10%
Hard clay strata +10%
Boulder strata or well resting on rock
+10%
![Page 17: well foundation](https://reader033.vdocuments.mx/reader033/viewer/2022061111/54546f36b1af9f1b348b48ac/html5/thumbnails/17.jpg)
Bottom plug- transfers the load of structure from well to the ground. It is cast under water after the final depth of well is reached. No reinforcement is provided. The mix should have min. cement content of 330Kg/m3
Sand filling : Sand filling shall commence after a period of 3 days of laying of bottom plug. It helps in increasing the weight of the foundation which provides more stability to the structure. It also counteract buoyant force of water.
Intermediate plug :The function of the plug is to keep the sand filling sandwiched & undisturbed. The concrete used for intermediate plugging is also M25.
Top plug :After filling sand up to the required level a plug of concrete is provided over it as shown on the drawing. It at least serves as a shuttering for laying well cap.
Well cap- It is needed to transfer the loads and moments from the pier to the well or wells below. It is designed as two way slab.
![Page 18: well foundation](https://reader033.vdocuments.mx/reader033/viewer/2022061111/54546f36b1af9f1b348b48ac/html5/thumbnails/18.jpg)
Well parameters
Parameters Data
1. Total no. of wells to be sunk59 n0.
2. Grade of concrete used for well curb and steinning: M 30
3. Grade of concrete used for bottom, intermediate and top plugging
M 25
4. Type of Cement usedOPC 43-G
5. Grade of steel used for reinforcement: FE 500
7. Scouring levels from previous years data: 9 m
9. Thickness of the cutting edge: 16 mm
![Page 19: well foundation](https://reader033.vdocuments.mx/reader033/viewer/2022061111/54546f36b1af9f1b348b48ac/html5/thumbnails/19.jpg)
Well parameters
Parameters Data
Depth of the wells below ground: Well no. 1 to 11:24.0 m
Well no. 12 to 23: 26.5 m
Well no. 24 to 29: 24.0 m
Height of well curb: well no. 1 to 11 and 24,25: 1.410 m
Well no. 12 to 25: 1.530
Thickness of the well steinning: Well no. 1 to 11: 780 mm
Well no. 12 to 23: 880 mm
Well no. 24 to 29: 780 mm
![Page 20: well foundation](https://reader033.vdocuments.mx/reader033/viewer/2022061111/54546f36b1af9f1b348b48ac/html5/thumbnails/20.jpg)
Construction of well
Setting of well curb
Sinking of well
Bottom plugging
Sand filling
Closing of top by well cap
![Page 21: well foundation](https://reader033.vdocuments.mx/reader033/viewer/2022061111/54546f36b1af9f1b348b48ac/html5/thumbnails/21.jpg)
Setting of well curb
The centre of the well is marked accurately with help of theodolite.
Cutting edge is placed on the wooden sleepers such that centre of cutting edge coincide with the marked centre.
Reinforcements and formwork for curb is fabricated on the cutting edge and concreting is done.
After curing of well curb is complete the wooden slippers below the curb are removed by making soil below them diluted by water and is allowed to sink under its own weight.
In this picture a well curb is resting on the wooden slippers
![Page 22: well foundation](https://reader033.vdocuments.mx/reader033/viewer/2022061111/54546f36b1af9f1b348b48ac/html5/thumbnails/22.jpg)
Sinking of well/Construction of steinning
1. Fabrication of formwork
and reinforcements
2. Concreting
3. Dredging of earth to
support sinking
![Page 23: well foundation](https://reader033.vdocuments.mx/reader033/viewer/2022061111/54546f36b1af9f1b348b48ac/html5/thumbnails/23.jpg)
Sinking of WellFabrication of Formwork
The formwork for casting are supported on the channels bolted with steining on both sides.
As per design lap is provided after every fourth reinforcement at same section.
Concreting is done by pumping the concrete to the mould by concrete pump.The concrete is placed in 400mm thick layers along with continues vibrations.On avg. about 23m3 of concrete is needed for casting of one lift.
Fabrication Concreting
![Page 24: well foundation](https://reader033.vdocuments.mx/reader033/viewer/2022061111/54546f36b1af9f1b348b48ac/html5/thumbnails/24.jpg)
Sinking of Well
Dredging In order to sink the well,
continuous dredging is done. Soil is excavated from the dredge hole inside the well.
The dredging operation is performed evenly along the hole circular hole
![Page 25: well foundation](https://reader033.vdocuments.mx/reader033/viewer/2022061111/54546f36b1af9f1b348b48ac/html5/thumbnails/25.jpg)
Construction of well
Bottom plugging : it is done after the well has reached the founding level. Concreting is done inside water. For this tremie pipe is used. A tremie is long funnel made of mild steel . A flap door is provided at its bottom.
Well cap:After water filling, a truss system consisting of three trusses supported in well steining and cribs welded with it in criss-cross manner are used for top plugging. This system is covered with strong plywood and sealed with concrete slurry so that nothing can enter inside the well. Hence preparing it for the casting of well cap.
![Page 26: well foundation](https://reader033.vdocuments.mx/reader033/viewer/2022061111/54546f36b1af9f1b348b48ac/html5/thumbnails/26.jpg)
Methods to promote sinking
Kentledge -Total of 125 concrete cubes of 1m3 in size are made for kentledge loading which is approximately equal to 25t × 125.
Chiseling- When the boulders are very firmly cemented then chiselling is done. In this soil is hit hard by sharp end chisel.
Dewatering- dewatering of dredge hole is done to reduce buyout force on well thus promoting sinking.
Flushing with jet of water on the outside face of well reducing skin friction
![Page 27: well foundation](https://reader033.vdocuments.mx/reader033/viewer/2022061111/54546f36b1af9f1b348b48ac/html5/thumbnails/27.jpg)
Tilt and shift
Tilt and shift are deviation of well from its proposed position and orientation.
Max. tilt allowed is 1/80Max. shift allowed is 150mmMeasures to avoid tilt and shiftThe outer surface of steining and curb should be kept as
smooth as possible.The radius of well curb should be kept more than the
steining.The dredging should be done on all sides of well uniformly.CausesEccentric dredgingCan be caused due to boulder under one side
![Page 28: well foundation](https://reader033.vdocuments.mx/reader033/viewer/2022061111/54546f36b1af9f1b348b48ac/html5/thumbnails/28.jpg)
Method of checking tilt and shift
Tilt and shift are calculated with the help of a level and total station.
MethodDifference between height of points (1&
3)= R.L.(1)-R.L.(3)Tilt = [ R.L.(1)-R.L.(3)]/diameter Shift at bottom from top position
= tilt/ lengthNote : this process is repeated on sides (2 &
4) and in similar manner tilt is obtained and then combined tilt and shift is reported.
Shift of well at top is measured by total station.
![Page 29: well foundation](https://reader033.vdocuments.mx/reader033/viewer/2022061111/54546f36b1af9f1b348b48ac/html5/thumbnails/29.jpg)
Correcting tilt and shift
Regulation of GrabbingEccentric LoadingStrutting The wellWater jetting or Digging Pit outside the
higher side of wellPulling the well or caisson Excavation on the higher side outside the
well
![Page 30: well foundation](https://reader033.vdocuments.mx/reader033/viewer/2022061111/54546f36b1af9f1b348b48ac/html5/thumbnails/30.jpg)
Problems
Sand blowing- This problem occurs when well bottom rests on sandy strata and dewatering is done below water table. In this sand from ground gushes into the well and there is sudden sinking of well. This sudden sinking is very dangerous and is very difficult to rectify.
Bridge scour -is the removal of sediment from bed such as sand and rocks from around bridge, abutments or piers. Scour, caused by swiftly moving water, can scoop out scour holes, compromising the integrity of a structure.
Sand heaving-When a well passes through soft strata over a considerable depth, the upward resistance acting on the outside surface of the well is less than the weight of the well. In that situation the well sinks down and quite often a heap is formed inside the dredge hole.
![Page 31: well foundation](https://reader033.vdocuments.mx/reader033/viewer/2022061111/54546f36b1af9f1b348b48ac/html5/thumbnails/31.jpg)
Bridge scour Sand heaving
Problems
![Page 32: well foundation](https://reader033.vdocuments.mx/reader033/viewer/2022061111/54546f36b1af9f1b348b48ac/html5/thumbnails/32.jpg)