HAYS CISD TRANSPORTATION (PROJECT 162090)
WEEKLY PROGRESS REPORT: FEBRUARY 22, 2019
ANTICIPATED DATE OF SUBSTANTIAL COMPLETION: APRIL 23, 2019
Fuel Depot Canopies
Bus Wash area graded.
This Week’s Activities:
• Area B canopy erection
• Fuel Depot canopy erection
• Ceiling grid dropped throughout Area A
• PEMB trim, ridge cap, wall panels.
• Area B Mechanical and Electrical overhead.
• Overhead MEP devices in progress Area A
• Forming and reinforcement for 2nd to last
paving pour, grading in bus wash.
Forming and reinforcing 2nd to last paving pour.
Area B canopy erection
Upcoming Activities:
• Final 2 paving pours
• Flatwork
• Perimeter fencing
• Complete PEMB
• Area B mechanical and electrical
• Aluminum canopy installation
• Lighting and AV installation.