webinar 03 electrical installation of pv system
DESCRIPTION
Dr. Jeffery Lee Johnson's #SolarMOOC slide set on the electrical installation of a typical pv systemTRANSCRIPT
Email: [email protected] Tele: (+52) 871 722 9522 www.todo-solar.com.mx
Electrical Installation of a PV SystemMaking the Right Connections…
Dr. Jeffery Lee JohnsonCTO Todo-Solar
Coahuila, Mexico
Agenda
• Resources• Assumptions and Background
• The DC side of things – Choosing and Connecting the Panels in Series– Proper grounding– String combiners
• Meeting in the Middle– DC connection to the Inverter– DC Disconnects, fusing and loading
• The AC side of things– AC Connection to the Inverter– AC Disconnects, fusing and safety– Connecting to the grid
• Summary and questions
Resources
Doc Solstice’s Seasoned Sentiments
Facts about Global PV installations
http://www.pv-tech.org/news/global_pv_installations_reached_27.7gw_in_2011_industry_at_crossroads_says
Global PV installations reached 27.7GW in 2011
That comes to 0.87 KW per second or 3 to 4 panels every second of the year
Global PV Installations to Grow by up to 21 Percent in 2012 Predicts IMS Research
http://www.pvmarketresearch.com/press-release/Global_PV_Installations_to_Grow_by_up_to_21_Percent_in_2012_Predicts_IMS_Research/5
For comparison , the entire grid capacity of the country of Mexico is 53 GW
INTRODUCTION, BACKGROUND AND ASSUMPTIONS ABOUT THE SYSTEM
Key Concepts and Assumptions
• Follow the typical systematic Installation Procedures– Assemble and place racks– Mount and connect panels (DC)– Install combiner box (DC)– Connect DC disconnect (may be integrated) (DC)– Connect DC to inverter (DC)– Mount and configure inverter (AC/DC)– Install AC Disconnect (AC)– Connect inverter to grid via electrical center (AC)– Commission and test (AC/DC– Install or activate Monitoring system
• You have an approved wiring diagram meeting specifications and needs of Locations
– Routing, cable lengths, junction locations, fusing etc a
• You have a complete parts list with prepared components
Electrical diagram: Generic System
General Schematic
One-line diagram
Sample SMA Wiring Diagram with external DC Disconnect
Combiner Box
Sample SMA Wiring Diagram with integrated DC Disconnect
Combiner Box
Sample System
3 strings of 10 panels 250W Siliken
SMA sunny Boy SB7000US
THE DC SIDE OF THINGS
Always use components rate for UL 1703 and IEC standards
Panel Characteristics
Must know VOC, ISC, Vmp Imp Pmp, tolerances under STC and NOTC (preferably)
Characteristics of Panels in Series
String is a series of panels with predetermined current and voltage outputV = V1 + V2 + …Vn = ∑ Vi
I = I1 = I2 = …In
Choosing Panels for Series layout
Issue Voltages for Panels in Series add linearly
Ideally, every series has the same voltage output – but generally not true
When combining series into Parallel Arrays at a combination node (such as a combiner box or Inverter input), the voltage at that node is the weighted average of the series voltages favoring the lowest voltage present
Important to balance your strings by equalizing the string voltages as best as possible !
Balancing String Voltage
Layout your panels in a similar environment of illumination & temperature
Measure and Record VOC for each panel – assign a numbering system
WHY measure VOC? Safer and varies little with changes in illumination
WHEN? Measure during peak hours near solar noon when solar radiation is changing slowly
With knowledge of panel characteristics, group them as best you can so each series will have equal or similar voltage – mix and match high /low performers
Installing panels – measure as you go!
RETURN LINE
Using return line measure VOC as you connect panels
Why? To ensure each connection is secure and voltage sums as you go! Panel interconnect issues are difficult to find after the fact
Make Sure panel connectors and cables are secured to rack
Physical Ground
All panels must have common physical ground and be grounded to racks
Aluminum frames are anodized (resistive)
Most panels provide a ground connection hole
Other technique is to use WEEBs or lugs – electrically connect panel frames to rack and then ground rack
Combiner boxes – adding the current of strings
PV COMBINER BOXES ARE CURRENT ADDERS FOR STRINGS IN PARALLEL
Common buss bar • DC positive inputs• DC Negative inputs• Ground
• Single outputs for Positive, Negative & ground
Each DC positive input (string) is fused before common output
Fuse: 600 VDC with amp rating > 1.45 operating amps
Acts as string switch
Recommendation:Pre-wire the box with negative/ positive cables with mated connectors
DC routing
• Have a DC cable routing plan– DC is on the roof or remote from inverter
• Best solar cables do not need conduit but bundle them nicely using UV resistant cable ties
• For esthetics and some codes, use metal conduit to distribute DC cables
MEETING IN THE MIDDLECONNECTING DC TO THE INVERTER
DC Disconnects
Integrated DC Disconnect Switch(Typically fused inside the inverter)
Stand-alone DC Disconnect Switch
• Fuse: 600 VDC with Amp rating > 1.45 x operating amps for each positive lead
Connecting DC to Inverter
Disconnect all DC power
Follow Inverter manual to connect positive, negative and ground cables*
*Note: some panels are positively grounded … so pay attention
Turn on DC and measure voltage at all outputs and inputs
Turn off DC
THE AC SIDE OF THINGS
Know your Grid
Know which type of grid you are connecting to
Most inverters are reconfigurable by dip switches or programming
Line voltages vary so choose the operating output range that fits your grid conditions
Inverter must be equipped with anti-islanding and must shutdown upon loss of grid power(grid connected systems)
The AC connection
AC Disconnect
Main Panel connection
AC Outputs
AC Disconnect
• Locate AC disconnect near the inverter -- must be accessible
• Fuses or Breakers must be compatible with grid voltage (240 VAC)
• Amp repeating should be 1.45 x the output current under operating conditions
Fused style
Breaker Style
Connecting to the Grid
L1
Phase 2
L2
Phase 1
Typical 240 VAC Connection
Outputs from Inverter are: L1, L2 are positive feed lines Neutral Physical Ground
Shut off AC power at main switchShut off all DC inputs to inverter
Connect Neutral and Physical Ground
Connect L1 to Phase 1 using breakerConnect L2 to Phase 2 using breaker or use two pole breakers
** Phase numbering is for convenience
Commissioning
• Check all connections• Follow manual for startup• Usual procedure is
– For Startup: Turn on AC First then DC– For Shutdown: Turn off DC first then AC
• After shutdown, ALWAYS wait 5 to 10 minutes before opening or working on inverter !!!
• Capacitive load needs to discharge
SYSTEM MONITORING
30
Monitoreo de Bluetooth para Internet o iPhone, iPad
(Solar Energy made available to Everyone)
http://www.todo-solar.com.mx
Twitter: @TodoSolarKidsTwitter: @TodoSolar