Web Enabled Vendor Data Collection on
BP Angola Block 18 Project
Howard Chipperfield, Information Manager BP
c o n t e n t e n g i n e e r i n g
3. Define/ReviewClass Requirement
Templates
3. Define/ReviewClass Requirement
Templates
Define and justify requirements
Develop collection templates
2. Define/ReviewStandards
2. Define/ReviewStandards
Upgrade standardsDevelop new standardsManage reference data
4. Develop/Improve Capture Process
& Tools
4. Develop/Improve Capture Process
& Tools
Implement best practice tools
Impose tools on information providers
Implement these processesNotify information providers
5. Define/Review Aggregation/
Validation Process
5. Define/Review Aggregation/
Validation Process
Engage an expert partnerMake IM Contractual
1. Establish/CoachInformation
Support Service
1. Establish/CoachInformation
Support Service
6. Review Lessons Learnt
6. Review Lessons Learnt
Modify processes for next time The Road Map
Block 31 Information Management Strategy
Data Validation/Aggregation
BP SYSTEMS
KBR Stolt/Technip/FMC HHI
Contract Responsibilities
EPC Data Management
3D Model 2D Docs DesignDocs
Information Collection Tool (Phantom)
SupplierData
SupplierDocs
PH CM Contract with EPC
PH CM Contract
with BP
$4 billion80,000 items
4-6 FPSOs4-6 x 80,000 items
ProjectInformation
Ori
gin
al Equip
ment
Manufa
cture
rs(O
EM
s)
Project Infra-structure
Rotork
Emerson
Weir
BrookCrompton
KBR
Engineering ProcurementContractors (EPC)
Caterpiller
Plenty Metrol
AtlasCopco
RollsRoyce
Package Vendors
BPAngola
GPP
BPBlock 31
Using the ICT to deliver the EIHS
Completion Analyser gives on line feedback.
Benefits for Suppliers
Supplier input minimised to ease completion.
Many copy features.
Enter data once and reports generated for delverables. i.e. Hazardous area schedule.
Web based shadowing to support users.
On line completion analyser lets the supplier know the shortfalls.
Early completion – early payment!
Benefits for BP
Data completion moved from 50% on last project to 95% on block 18.
Data available 18 months earlier than on last project.
Information organised to enable sharing with other BP projects.
BP has captured essential data and document relationships electronically.
Accuracy assured by validation process.