Our expertise in commissioning, commissioning management

and soft landings covers all aspects of building engineering

services and is based on experience gained working in this

challenging part of the industry.

From full commissioning management and HVAC

commissioning to system and plant validation, verification and

water treatment and testing, we can offer you a

comprehensive service.

Our clients include office land lords and tenants, design and

build contractors, developers and owner/occupiers.

Additionally, we have worked for mechanical and electrical

contractors and specialist suppliers across a number of

projects.

“We recognise the complexities of building services design and the importance of the need to support the operational aspects of any services project”

Commissioning is the process of ensuring that systems are designed, installed, tested, and capable

of being operated and maintained according to the owner’s operational requirements. It is a

continuous process that identifies, prevents, and resolves problems as early as possible, since

problems that are addressed early nearly always cost less to fix.

Our experienced commissioning managers specialise in ensuring M&E building services are

strategically planned, commissioned and signed off to ensure stringent compliance with the project

specification and the client’s requirements.

This involves managing, witnessing and verifying on and off site testing to ensure building/project

performance is compliant with the project requirements as well as CIBSE codes, BSRIA guidelines

and Part L building regulations and any specialist system requirements.

Our processes and systems are ISO 9001 and 14001 accredited and we are members of both

Constructionline and CHAS, in recognition of our commitment to ensuring we have robust levels of

heath and safety in place.

We are also a member of the Commissioning Specialists Association (CSA), the only body in the UK

aimed specifically at developing and improving the commissioning function to provide building

users, consultant engineers, main contractors and installation companies with a professional,

quality service carried out by trained and experienced staff.

COMMISSIONING MANAGEMENT

Planned refurbishments, change of use, fit out works and the purchase of property often results in

the requirement for existing plant and services to be validated. This provides assurance that the

plant and equipment is capable of achieving required performance criteria and establishes a

valuable ‘line in the sand’ between contractual responsibilities.

We can provide a full validation and verification service to ensure the appropriate checks and

reports are prepared, saving you from costly mistakes and potential disputes.

Our services include the preparation, processing and execution of validation plans, functional

specifications, installation qualifications and operational qualifications.

We can also provide specialist verification services for clean rooms, operating theatres, licensed

drug production facilities, data centres, cold stores, food production facilities and high care

environments.

VALIDATION AND VERIFICATION

Water Treatment and Legionella Risk Assessments

In conjunction with our specialist partners we can arrange, co-ordinate, witness and report on the

complete system. In addition, we can undertake legionella risk assessments and reviews for our

clients to ensure the requirement to comply with L8 is met.

Surveys

We carry out a bespoke survey service for clients on M & E systems. These vary from small

operational issues to the building-wide analysis of system design, previous commissioning and maintenance reviews.

Thermographic Surveys

We are equipped to undertake thermographic surveys of buildings, cold stores, electrical systems

and pipework systems for fault finding and validation.

Training Videos

We have an established working relationship with an experienced video production company to

offer a specialist training video service.

Fault Finding and Trouble Shooting

Along with our sister companies Silcock Leedham Consulting Engineers and Zero Energy Design,

we have many years experience of building construction and specialist systems and we offer a fault

finding service including ‘hands on’ testing, calculation verification and computer analysis.

OTHER SERVICES

We are a SLCE group company. Our group company model is based on offering a complete solution

to our clients.

All group companies are designed to allow full and transparent interoperability for our clients whilst

offering a mixed bag of specialisms to suit particular needs and requirements.

In addition to offering commissioning management services, through Silcock Leedham we have

access to the expertise of one of the country’s largest pool of highly skilled mechanical,

electrical and public health engineers,

Our other group company, Zero Energy Design (ZED), specialise in building physics, simulation and

sustainability. Working within the built environment ZED use thermal simulation and modelling

techniques to add value to your construction project. Their work covers the entire building

lifecycle, from the first drop of the architect's ink to maintaining buildings after decades of use.

We are also licensed BREEAM assessors and accredited professionals. We can deliver even the most

challenging schemes and have many years of experience hitting target ratings, time after time.

Our ‘end to end’ engineering service can be fully BIM integrated via our in house Autodesk certified

BIM and Revit team.

COLLABORATION

What Our customers say about us…

It really has been a pleasure to work with you and your team. All of your staff were very helpful

and nothing appeared to be a problem or issue despite the chaos that was going on around them.

Ian can’t speak highly enough of you and your team and wants to use you on all his future

projects.

Andy Taylor, Rotary, Yorkshire Ltd

Verisys have completed annual verification works of operating theatres and clean rooms at Derby

Hospital. This is an important exercise and requires a high level of detail and testing. Verisys

completed this task accurately and in a professional and timely manner and we will definitely use

them again to complete similar works.

Ivan Hodkinson, Skanska

NOVO Integration Ltd have worked with Verisys on many projects, including the commissioning of

B-Braun offices in Sheffield and Yorkshire Building Society Headquarters in Bradford. In all cases

works have met the programme requirements and issues have been dealt with clearly and

methodically to ensure the building services. I have nominated Verisys on various project and will

continue to do so in the future.

Ben Duckworth – Director, NOVO Integration

COMMISSIONS

Rol l s Royce Advanced Blade Cast ing Faci l i ty

Rolls Royce commissioned the

construction of a state of the art

advanced blade casting facility in

Rotherham.

Verisys was appointed to provide

commissioning management, hands on

commissioning and water treatment

testing.

In addit ion to completing full

commissioning management duties,

after the project had been handed over

and fitted out with the client’s specialist

equipment, we checked and verified

the previously commissioned plant.

We also produced training videos for

the staff to familiarise them with the

key systems and interfaces.

AIREDALE INTERNAL AIR CONDITIONING

This project consisted of the

construction of a new manufacturing

and production facility, built on the

footprint of the previous factory which was demolished following extensive fire

damage.

In addition to the new production shop

floor and office accommodation, the

proposed facility incorporated extensive

state of the art product testing facilities

and a research and development test

centre.

Airedale appointed the services of

Verisys as approved independent commissioning managers responsible

for developing and witnessing the

whole commissioning process on their

behalf prior to handover, including full

point to point and cause and effect

testing of the complete mechanical and

electrical services installations.

HARIBO

The c l ien t commiss ioned the

construction of a new 24,000m2

manufacturing and production facility,

including packing area and all central

plant and associated services. The

phase 1 development also included a

14,12m2 high bay (23m+) automated

storage and retrieval (ASR) warehouse.

Verisys was appointed to oversee all

aspects of commissioning and to verify

the commissioning results issued by

others.

We also completed snagging and

defects works and over saw the sign off

and completion of these works to

ensure the items were closed out

correctly.

HESLINGTON EAST CAMPUS, UNIVERISTY OF YORK

The award winning £55m Heslington

East Campus includes a new hub

building, theatre, film and television

building, law and commerce building

and computer sciences building.

Verisys provided a detailed study on

the supply air performance of fan coil

units relative to extract provision from

luminaires.

In the early stage of the appointment

we reviewed in detail the methodology

to be adopted during the water

treatment of the district heating system. This included advising the

designers on the valve separation and

by-pass arrangements so that the

system could be correctly flushed and

chemically cleaned.

Bradford Col lege David Hokney Campus

The city centre located David Hokney

campus was phase 2 of an ambitious

development strategy at Bradford

College.

The 23,000m2 new campus building is

an innovative and technology rich

learning environment spread over 6

storeys.

In addition to providing commissioning

management, hands on commissioning

and water treatment testing, Verisys

also provided load banks and thermal

mapping of the space in the data room

to enable testing of this area to be

completed.

DERBY HOSPITAL

Skanska appointed Verisys to complete

an annual review of operating theatres

(circa 20) and clean rooms at Derby

Hospital.

This required a high level of accuracy to

ensure strict standards were being

adhered to.

In addition, Verisys was asked to

validate verification defect reports

provided by external consultants.

Some of the reported defects were

found to be unsubstantiated and were

therefore disregarded, resulting in cost

savings for the client.

AXA INSURANCE,THE GHERKIN, LONDON

As part of AXA Insurance’s expansion

and rationalisation of their corporate

insurance and global identity, they took

a lease out on Level 20 of the landmark Gherkin building at 30 St Mary Axe,

London, to give them a city corporate

office of 2000m.

Verisys was appointed to complete a

pre-start survey prior to the fit-out, to

establish the condition of the existing

mechanical and electrical services.

Over a two week period we completed

a full chemical and micro-biological analysis of all water systems, reporting

against BSRIA Guidelines.