Résumé NAME Wallace Darryl Forsyth (Wal) ADDRESS 10 Maidenhair Place CALAMVALE QLD 4116 TELEPHONE Mobile: +61 419 208 982 E-Mail: [email protected] CAREER SUMMARY 24 years in the Construction industry – 12 years of Infrastructure projects Extensive experience in modular building installation and complexing of multi-floor buildings Construction of Central Facilities – Kitchen-Diner complex, cold stores, gymnasium, storage facilities, etc In-ground services installation – Plumbing, Pit & Pipe work, Earthworks, Civil, Structural & Building fit-out Experience in rail formation, bridgeworks, concrete works Project Management from break ground to Handover Strong Project Planning and Supervision experience Emphasis on safety and Zero Harm culture Broad supervisory experience on mine site construction projects Significant experience in business management and construction project administration Accustomed to living and working in remote and isolated areas CORE COMPETENCIES Design Analysis and implementation Subcontractor management Zero Harm focused Progress tracking and reporting Operational Health and Safety Procedures Risk Assessment and Mitigation Client Relationship Management Regulatory Compliance Team Management Mentoring junior team members Site Operations Management Manpower Planning Construction Planning and Control Contract negotiations Inventory Control KEY DELIVERABLES Participates in all phases of project life cycle management including planning, execution and successful handover/close-out.

Upload: wallace-forsyth

Post on 16-Apr-2017

53 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: WDF Resume Sept 2016

Résumé

NAME Wallace Darryl Forsyth (Wal)

ADDRESS 10 Maidenhair PlaceCALAMVALE QLD 4116

TELEPHONE Mobile: +61 419 208 982E-Mail: [email protected]

CAREER SUMMARY

24 years in the Construction industry – 12 years of Infrastructure projects Extensive experience in modular building installation and complexing of multi-floor

buildings Construction of Central Facilities – Kitchen-Diner complex, cold stores, gymnasium,

storage facilities, etc In-ground services installation – Plumbing, Pit & Pipe work, Earthworks, Civil,

Structural & Building fit-out Experience in rail formation, bridgeworks, concrete works Project Management from break ground to Handover Strong Project Planning and Supervision experience Emphasis on safety and Zero Harm culture Broad supervisory experience on mine site construction projects Significant experience in business management and construction project

administration Accustomed to living and working in remote and isolated areas

CORE COMPETENCIES Design Analysis and implementation Subcontractor management Zero Harm focused Progress tracking and reporting Operational Health and Safety Procedures Risk Assessment and Mitigation Client Relationship Management Regulatory Compliance Team Management Mentoring junior team members Site Operations Management Manpower Planning Construction Planning and Control Contract negotiations Inventory Control

KEY DELIVERABLES Participates in all phases of project life cycle management including planning, execution and successful handover/close-out. Manages on-site operations, conduct Pre-Start meetings, Safety focused, monitoring site labour force and Sub-contractor work, monitoring and organising site facilities to meet agreed deadlines. Contributes to design changes, problem solving, constructability issues. Oversees project progress, design implementation, cost variation tracking, budget adherence and control and quality assurance for finished work. Manages client interaction on assigned projects and develop professional relations with internal and external clients/stakeholders, understanding requirements and presenting correct solutions within a given framework. Motivates workforce to achieve their full potential safely, while focusing on

Page 2: WDF Resume Sept 2016

developing strategies to ensure sustainable business success. Conducts regular safety interactions with workforce to measure safety compliance, improving safety culture and increased safety awareness through performance management/feedback system to indicate service strengths and weaknesses.

RECENT KEY ACHIEVEMENTS

Ranbury / Queensland Sugar Ltd

Re-roofing 23,000m2 Mourilyan Sugar storage terminal -

Ranbury / Queensland Rail Completion of Robina NGR Stabling Yard – construction of rail formation, OHLE,

track laying, plumbing and drainage, modular building installation, electrical and communications

Decmil Australia, Rio Tinto, Cape Lambert WA - May 2015 – Aug 2015 Deconstruction of a construction water system – 3 x water storage tanks, 11km of

HDPE pipeline, management of demolition without incident Completion of a heavy vehicle wash facilityJacobs - Rio Tinto, Cape Lambert Port Upgrade, WA - Feb 2011 to May 2015 Supervised 400 room Expansion of Accommodation Village and Central Facilities -

$15.5M Managed construction of a New 1200 room Accommodation Village – ground up –

all in ground services, piping, Civils, Structural, Mechanical, tilt panel concrete structures, concrete paths, lighting, Kitchen Diner Crib fit-out – all infrastructure - $44M

EPCM Complex – modular construction, internal fit-out Construction of 3 x Waste Water Treatment facilities – tanks, pipework, pumps Supply Hub - ground up construction of 1700 pallet Warehouse, Gas Store,

Dangerous Goods Store, Transformer Bund - $8.5M Production Administration building –ground up – all in-ground services, piping –

(welded HDPE, steel), Civils, Structural, Mechanical, concrete paths, asphalt, area lighting - high standard fit-out, $8.7M

Non Process Infrastructure site upgrades and maintenance – concrete, steelwork Bulk and Detailed Project Earthworks Construction of Site roads, car park areas, Asphalt laying Site Signage, road furniture, line marking.

FAST JV/BHPBIO, Yandi, WA – 2009 – 2011 ‘Spinifex’1200 room Accommodation village construction including all services

- trenching, electrical, comms, water, sewer, detailed earthworks, roads, paths and all associated infrastructure

Bulk earthworks including new rail formation, rail crossings, ore handling plant, Rail bridge construction, pile driving, bridge abutments, concrete and earthworks Rail formation earthworks Concrete ‘Techspan’ pinned arch Rail Tunnel MSE Walls for new crushing plant Mine access road construction/widening

Fluor/OZ Minerals, Prominent Hill, SA 2007 – 2009 Construction of modular 1000 man accommodation village Modification of SPQs to upgrade to en-suite facilities Roads, Infrastructure earthworks, Civil/Structural works for a heavy truck maintenance depot Civil/Structural/Mechanical works for new RO Plant at Prominent Hill Civil/Structural works for upgrade of BHPB Olympic Dam HV Sub-Station Civil/Structural/Mechanical works for raw water bore field and pumping station Civil/Structural/Mechanical works for Diesel Fuel storage facility Construction of Accommodation village including kitchen and mess facilities

Page 3: WDF Resume Sept 2016

Installation of Containerised 180kl RO Plants Construction of Waste Water Treatment plant including HDPE lined evap pond Infrastructure early works - site access roads, temporary camp, bore field, comms

POSITIONS HELD in past 14 years Senior Inspector, Ranbury Construction Supervisor, Greentree Bithuwarnda Fencing & Civil Construction Supervisor, Decmil Australia Infrastructure Supervisor, SKM Cape Lambert (Rio Tinto Iron Ore Port Upgrade) Construction Supervisor, Projects - OZ Minerals, Prominent Hill Civil Supervisor, FAST JV (Fluor, SKM) Yandi BHPB Iron Ore, WA Construction Supervisor, Fluor Australia, Oxiana Prominent Hill Project. Construction Supervisor, Parsons Brinckerhoff, Oxiana Prominent Hill Project. Construction Supervisor, KBR – Evap Pond construction, BHPB Olympic Dam, SA Construction Supervisor, Maunsell (AECOM) - BHP Billiton Project Delivery Group

Olympic Dam Construction Supervisor, Thiess – Olympic Dam Extraction Plant Enhancement

WMC/BHPB

REFERENCESBusiness:Paul Redwood

Project Manager – CLB Infrastructure Rio Tinto Projects, Technology & Innovation Ph: 0403 606 934

Peter PrestageSenior Site Civil EngineerRio Tinto Cape Lambert W.A Ph: 0477 310 121

Russell Ford Deputy Construction Manager, Jacobs Ph: 0437 194 705

Personal:

Alan Joice Project Engineer

Rio Tinto Cape Lambert W.A Ph: 0405 748 381

Bimal Mahendroo Senior Project Manager Ph: 0412 134 155