Waterbury VT Downtown Planning Study Presentation 2009-10-29. Please note: This is a work in progress, posted for discussion purposes only. There is discussion in this presentation of how VT's tax increment finance and local option tax work that was included at the request of the committee, and no proposal or recommendation has been made - just a starting point for an important discussion of how these tools could work.TRANSCRIPT
![Page 1: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/1.jpg)
WATERBURY DOWNTOWN STUDY
Waterbury Downtown:
Present Future
Public Workshop
Thursday, October 29,
2009
7:00 PM
![Page 2: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/2.jpg)
WATERBURY DOWNTOWN STUDY
Waterbury Downtown:
Present FutureRevitalizing Waterbury
Waterbury Planning Commission
Waterbury Village/Town Staff
GMCR and Central Vermont Regional
Planning Commission
VHB Pioneer
Timothy Duff, Architect
![Page 3: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/3.jpg)
WATERBURY DOWNTOWN STUDY
Present Future
Completing the
Waterbury Downtown Study• Connector roadway and rail crossing, from
Demeritt Place to Pilgrim Park
• Options for infill development
• Evaluation of the Stone Shed
• Financial Analysis
• Downtown Master Plan
Tonight: • Financing Options & Ideas
• Downtown Master Plan “Action List”
![Page 4: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/4.jpg)
WATERBURY DOWNTOWN STUDY
Tonight’s Agenda:
1. The 3-D View: GMCR & CVRPC
Sketch-Up Team
2. Downtown Master Plan
3. The Stone Shed: Options & Ideas
4. Financing Options & Approaches
5. Group Discussion: Action List
![Page 5: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/5.jpg)
WATERBURY DOWNTOWN STUDY
SKETCH-UP MODEL
GMCR and Central VT Regional Planning Commission
![Page 6: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/6.jpg)
WATERBURY DOWNTOWN STUDY
Downtown Master Plan
Overview
![Page 7: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/7.jpg)
WATERBURY DOWNTOWN STUDY
Master Plan: Key Elements
Maintaining the residential, “leafy” character
of Main Street near Demeritt Place
Drainage issues if infill development occurs
![Page 8: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/8.jpg)
WATERBURY DOWNTOWN STUDY
Master Plan: Key Elements
•Connect Pilgrim Park to Demeritt Place with a new connector roadway
•Upgrade the railroad crossing and Demeritt Place to handle tractor-trailers
•Relieve Park Row/Main Street intersection
![Page 9: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/9.jpg)
WATERBURY DOWNTOWN STUDY
Master Plan: Key Elements
Consider infill
development on
Demeritt Place
site, behind
Batchelder Street
– Potential options for housing
![Page 10: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/10.jpg)
WATERBURY DOWNTOWN STUDY
Master Plan: Key Elements
Ways to make the
State offices more
of a community
amenity• River access
• Community garden on the horseshoe
• Art walk/solar installations along river path
![Page 11: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/11.jpg)
WATERBURY DOWNTOWN STUDY
Master Plan: Key Elements
Consider introducing some retail and service
uses into Pilgrim Park – potentially in Station
Lumber building (or on the site)
Enhance visibility, friendliness of parking
DRAW and LINK visitors to retail core
![Page 12: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/12.jpg)
WATERBURY DOWNTOWN STUDY
Master Plan: Key Elements
Focus on Waterbury‟s
retail core!
There is huge interest
in having more places
to shop locally
Restaurants are a
great anchor
Pursue
redevelopment
opportunities
![Page 13: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/13.jpg)
WATERBURY DOWNTOWN STUDY
Retail Core: CONTINUITY!
Ground-floor rrontage in this
section of Main from Park
Row to Stowe St. potentially
should be mandatory retail
or restaurant
Draw foot traffic through
Enhance sidewalks
Clean up & sign the parking!
No!
![Page 14: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/14.jpg)
WATERBURY DOWNTOWN STUDY
Retail Core: CONTINUITY!
Idea to “link and
draw” pedestrians
from Park Row
and train station
up in and through
the retail core
Untapped idea:
Sculpture contest
and art walk
![Page 15: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/15.jpg)
WATERBURY DOWNTOWN STUDY
Retail Core: Redevelopment
More of
this…
…less of
this.
![Page 16: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/16.jpg)
WATERBURY DOWNTOWN STUDY
Key Redevelopment Site:
Stone Shed & Bidwell Lane
Public meeting:
THEATER/ gathering
space
Support for Bidwell Ln.
Extension
![Page 17: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/17.jpg)
WATERBURY DOWNTOWN STUDY
STONE SHED – Existing Conditions
The Stone Shed was most
likely constructed in the 19th
century supporting several
uses and many alterations over
the years.
Former uses include
processing quarried stone and
as an iron foundry.
Currently used as a
warehouse.
The building is centrally
located within the village core
and adjacent to municipal
parking.
![Page 18: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/18.jpg)
WATERBURY DOWNTOWN STUDY
STONE SHED – Existing Conditions
![Page 19: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/19.jpg)
WATERBURY DOWNTOWN STUDY
STONE SHED – Existing Conditions
![Page 20: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/20.jpg)
WATERBURY DOWNTOWN STUDY
STONE SHED – Existing Conditions
![Page 21: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/21.jpg)
WATERBURY DOWNTOWN STUDY
STONE SHED – Existing Conditions
![Page 22: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/22.jpg)
WATERBURY DOWNTOWN STUDY
STONE SHED – Existing Conditions
![Page 23: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/23.jpg)
WATERBURY DOWNTOWN STUDY
STONE SHED – Existing Conditions
![Page 24: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/24.jpg)
WATERBURY DOWNTOWN STUDY
STONE SHED – Existing Conditions
The existing wood framed post and beam structure has numerous
alterations. Most likely much of the roof framing has been replaced
during the life of the structure.
![Page 25: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/25.jpg)
WATERBURY DOWNTOWN STUDY
STONE SHED – Existing Conditions
![Page 26: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/26.jpg)
WATERBURY DOWNTOWN STUDY
STONE SHED – Existing Conditions
The existing wood framed post and beam structure has numerous
alterations. Most likely much of the roof framing has been replaced
during the life of the structure.
There are original portions of the building throughout including:
![Page 27: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/27.jpg)
WATERBURY DOWNTOWN STUDY
STONE SHED – Existing Conditions
The existing wood framed post and beam structure has numerous
alterations. Most likely much of the roof framing has been replaced
during the life of the structure.
There are original portions of the building throughout including:
Clearstory wall framing
![Page 28: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/28.jpg)
WATERBURY DOWNTOWN STUDY
STONE SHED – Existing Conditions
![Page 29: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/29.jpg)
WATERBURY DOWNTOWN STUDY
STONE SHED – Existing Conditions
The existing wood framed post and beam structure has numerous
alterations. Most likely much of the roof framing has been replaced
during the life of the structure.
There are original portions of the building throughout including:• Clearstory wall framing
• Original wall framing and siding
![Page 30: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/30.jpg)
WATERBURY DOWNTOWN STUDY
STONE SHED – Existing Conditions
![Page 31: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/31.jpg)
WATERBURY DOWNTOWN STUDY
STONE SHED – Existing Conditions
The existing wood framed post and beam structure has numerous
alterations. Most likely much of the roof framing has been replaced
during the life of the structure.
There are original portions of the building throughout including:• Clearstory wall framing
• Original wall framing and siding
• Framed window openings in exterior walls
![Page 32: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/32.jpg)
WATERBURY DOWNTOWN STUDY
STONE SHED – Existing Conditions
![Page 33: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/33.jpg)
WATERBURY DOWNTOWN STUDY
STONE SHED –Potential for Reuse
![Page 34: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/34.jpg)
WATERBURY DOWNTOWN STUDY
STONE SHED – Potential for Reuse
The building will require substantial amounts of work in
order to adapt it for reuse.
Building Utilities:• Existing 6” water service should be adequate for any use, but the
fire protection system is antiquated and will have to be replaced.
![Page 35: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/35.jpg)
WATERBURY DOWNTOWN STUDY
STONE SHED –Potential for Reuse
![Page 36: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/36.jpg)
WATERBURY DOWNTOWN STUDY
STONE SHED – Potential for Reuse
The building will require substantial amounts of work in
order to adapt it for reuse.
Building Utilities:• Existing 6” water service should be adequate for any use, but the
fire protection system is antiquated and will have to be replaced.
• 4” sewer service should support a variety of potential uses.
![Page 37: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/37.jpg)
WATERBURY DOWNTOWN STUDY
STONE SHED – Potential for Reuse
The building will require substantial amounts of work in
order to adapt it for reuse.
Building Utilities:• Existing 6” water service should be adequate for any use, but the
fire protection system is antiquated and will have to be replaced.
• 4” sewer service should support a variety of potential uses.
• The existing electrical service is too small and will not support any adapted reuse.
![Page 38: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/38.jpg)
WATERBURY DOWNTOWN STUDY
STONE SHED –Potential for Reuse
![Page 39: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/39.jpg)
WATERBURY DOWNTOWN STUDY
STONE SHED –Potential for Reuse
![Page 40: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/40.jpg)
WATERBURY DOWNTOWN STUDY
STONE SHED – Potential for Reuse
The building will require substantial amounts of work in
order to adapt it for reuse.
Building Utilities:• Existing 6” water service should be adequate for any use, but the
fire protection system is antiquated and will have to be replaced.
• 4” sewer service should support a variety of potential uses.
• The existing electrical service is too small and will not support any adapted reuse.
Assembly uses will require a substantial upgrade to the
building structure.
New exterior finish, thermal envelope, HVAC, plumbing and
electrical systems will be required.
![Page 41: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/41.jpg)
WATERBURY DOWNTOWN STUDY
STONE SHED – Potential for Reuse
Lack of day lighting and egress access limits effective reuse
for residential uses.
It is recommended that additions be removed back to the
original building form to create more functional, usable space
and reduce the amount of building square footage required to
be upgraded.
![Page 42: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/42.jpg)
WATERBURY DOWNTOWN STUDY
STONE SHED – Potential for Reuse
![Page 43: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/43.jpg)
WATERBURY DOWNTOWN STUDY
STONE SHED –Potential for Reuse
![Page 44: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/44.jpg)
WATERBURY DOWNTOWN STUDY
STONE SHED –Potential for Reuse
![Page 45: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/45.jpg)
WATERBURY DOWNTOWN STUDY
STONE SHED –Potential for Reuse
![Page 46: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/46.jpg)
WATERBURY DOWNTOWN STUDY
STONE SHED – Potential for Reuse
![Page 47: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/47.jpg)
WATERBURY DOWNTOWN STUDY
![Page 48: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/48.jpg)
WATERBURY DOWNTOWN STUDY
![Page 49: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/49.jpg)
WATERBURY DOWNTOWN STUDY
![Page 50: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/50.jpg)
WATERBURY DOWNTOWN STUDY
STONE SHED – Potential for Reuse
Lack of day lighting and egress access limits effective reuse
for residential uses.
It is recommended that additions be removed back to the
original building form to create more functional, usable space
and reduce the amount of building square footage required to
be upgraded.
Current building footprint of over 12,000 square feet would
reduce to 8,200 square feet.
![Page 51: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/51.jpg)
WATERBURY DOWNTOWN STUDY
STONE SHED – Potential for Reuse
Previous group discussions have centered on community uses
such as theater/performing arts.
A potential for a 150 seat theater and adjacent multi-purpose
space.
![Page 52: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/52.jpg)
WATERBURY DOWNTOWN STUDY
![Page 53: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/53.jpg)
WATERBURY DOWNTOWN STUDY
![Page 54: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/54.jpg)
WATERBURY DOWNTOWN STUDY
COST ITEMS in the MASTER PLAN
Connector Road (@$1.3 million)
Drainage improvements behind Main St.
near Demeritt Place
Redevelopment sites esp. Stone Shed
Community garden initiation
Parking area spruce up and signage
Sidewalk improvements
“Art walk”/competition/installations
River access
$
![Page 55: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/55.jpg)
WATERBURY DOWNTOWN STUDY
Dear Santa Claus,
We have been a very good town and village this year.
Cost Items
INFRASTRUCTURE
PUBLIC FACILITY
ECONOMIC
ENHANCEMENTS
RECREATION
COMMUNITY
GARDEN
Avenues
CDBG, TIF, bonding
USDA-RD
BID, Local option
FISH „N CRITTER,
RECREATION
SOURCES
**ENERGY
![Page 56: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/56.jpg)
WATERBURY DOWNTOWN STUDY
Tax Increment Finance:
The Basics
Allows the municipality to capture some
or all of the incremental increase in
taxable value in a specific geographic
area, and pledge that future revenue
towards the payments on a municipal
bond for infrastructure improvements
that are DIRECTLY RELATED to
enabling the increase in taxable value.
(got that?)
![Page 57: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/57.jpg)
WATERBURY DOWNTOWN STUDY
Town Tax Rate2008 Grand List: $7,097,523
Taxes Necessary for General Fund & Highway: $1,853,455 Total Town & School Tax RateHomestead: 1.3674
Non-Residential: 1.5007
Village Tax Rate2008 Grand List: $1,976,734
Taxes Necessary for General Fund: $323,260
Total School, Town Village Tax RateHomestead: $1.5498
Non-Residential: $1.6831
![Page 58: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/58.jpg)
WATERBURY DOWNTOWN STUDY
Tax Increment Finance: Issues
Must apply to Vermont Economic Progress Council (VEPC) for TIF
approval
Requires formal authorization by the voters; not clear if Town or Village
or both would be bond issuing authority
Must demonstrate that the new increment of growth would not happen
BUT FOR the infrastructure investment
Must send 25% of the incremental tax revenue to Montpelier
**Must reserve as much or more of the MUNICIPAL increment towards
the TIF as you do the Statewide
Non-taxable properties don‟t pay their way (i.e. municipal buildings,
stone shed) unless space is leased from a taxable entity
Annual audit and compliance costs
![Page 59: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/59.jpg)
WATERBURY DOWNTOWN STUDY
WHAT’S THE POSSIBLE ‘I’?
Tax Increment Finance:
![Page 60: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/60.jpg)
WATERBURY DOWNTOWN STUDY
Pilgrim Park
Potentially 3 new
buildings
Not clear what
timing will be
Would be a
MAJOR
component of a
TIF.
![Page 61: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/61.jpg)
WATERBURY DOWNTOWN STUDY
Demeritt Place
Site plan done for @
20,000 SF office and
parking
Could also support office
with @ 14 units of housing
Neighborhood concerns
Drainage issues need to
be dealt with
![Page 62: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/62.jpg)
WATERBURY DOWNTOWN STUDY
Bidwell Lane/Stone Shed/Station
Lumber
Strong interest in redevelopment
that connects Waterbury Square to
the Stone Shed
All groups tended to have some
element of a gathering or
performance space/theater in this
area
Parking needs to be evaluated
carefully
Needs intensive economic
development plan/effort…but could
be worth it!
![Page 63: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/63.jpg)
WATERBURY DOWNTOWN STUDY
Mid-Downtown Site
Identified in public
workshop as good site
for offices, similar to
medical center
No discussion with
landowners
Access would need to be
worked out
![Page 64: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/64.jpg)
WATERBURY DOWNTOWN STUDY
Fire Station
ALL of the public meeting work
groups discussed redevelopment of
the Fire Station site; some included
land up to the Town Office.
Clearly, not consensus on this with
Village leadership.
Represents the “missing front tooth”
in the retail district from Park Row to
Stowe Street.
Stong case that this site needs to be
re-imagined as a key development
node.
![Page 65: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/65.jpg)
WATERBURY DOWNTOWN STUDY
Thoughts for Waterbury
Downtown:
Redevelopment initiatives will require multiple and developer-
driven funding sources.
Other projects are smaller, innovative…and more challenging to
fund through “regular” sources
**Ideal scenario is an annual “force account” for small projects
like the parking, art walk, river access, etc.
TIF is a possibility…but must be VERY SPECIFIC about what it‟s
for and the reasonable likelihood that the development will occur
Also must balance against the cost and complexity of approval
![Page 66: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/66.jpg)
WATERBURY DOWNTOWN STUDY
Other Financing Thoughts:
Where money is today
USDA Rural Development:• Can a local business or consortium be
created that can take on the Stone Shed and work with USDA through its implementation grants?
E N E R G Y:• The big money today is in ENERGY!
• What are the opportunities for Waterbury to make renewable energy part of the strategy for funding the art walk?
![Page 67: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/67.jpg)
WATERBURY DOWNTOWN STUDY
Other Financing Thoughts:
Where money is today
USDA Rural Development:• Can a local business or consortium be
created that can take on the Stone Shed and work with USDA through its implementation grants?
E N E R G Y:• The big money today is in ENERGY!
• What are the opportunities for Waterbury to make renewable energy part of the strategy for funding the art walk?
![Page 68: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/68.jpg)
WATERBURY DOWNTOWN STUDY
Other Financing Thoughts:
A local option (please put away the firearms)
would not be a bad way to develop a “force
account” for investments in the downtown,
which could be supplemented with grants.
Some of the key competitive retail markets to
Waterbury already have a local option tax:• Williston/Taft Corners but not Berlin
Question…how do you work with Waterbury
Center, Ben & Jerry‟s, and the Shaw‟s, where
a lot of the retail sales are generated
![Page 69: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/69.jpg)
WATERBURY DOWNTOWN STUDY
Current taxable retail receipts in
Waterbury:
2008 taxable
retail
receipts:
$30,488,168
2007 taxable
retail
receipts:
$30,506,338
![Page 70: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/70.jpg)
WATERBURY DOWNTOWN STUDY
What are the “launch pads”
and who can take them on?
![Page 71: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/71.jpg)
WATERBURY DOWNTOWN STUDY
For Discussion:
CONNECTOR ROADWAY
STONE SHED
BIDWELL LANE
PARKING IMPROVEMENTS
ART WALK
RIVER ACCESS/WALK
COMMUNITY GARDEN
FUTURE SITES
FINANCING STRATEGIES
RETAIL CONTINUITY/
RESIDENTIAL CHARACTER
![Page 72: Waterbury Downtown October 29 2009](https://reader031.vdocuments.mx/reader031/viewer/2022020207/54bb5d634a79590d668b4598/html5/thumbnails/72.jpg)
WATERBURY DOWNTOWN STUDY
Next Steps in the Study:
Finalizing report
Looking in detail and financing options
and how they would play out
Incorporating your comments and
feedback from tonight
Action items list for key initiatives