Presentation and boards developed by Stantec
Waterbury, Vermont 2014-2018 Construction Projects
![Page 2: Waterbury, Vermontwatp.vtransprojects.vermont.gov/...VTrans_Waterbury_v2_PRESENTA… · 14/7/2014 · Other Projects Presentation and boards developed by Stantec • Smart Work Zone](https://reader034.vdocuments.mx/reader034/viewer/2022052008/601d757e92733b4d797fabad/html5/thumbnails/2.jpg)
Presentation and boards developed by Stantec
I-89 to Montpelier
I-89 to Burlington
VT Route
100 t
o Stowe
North
VT Rou
te 1
00
to W
aitsfi
eld
Spring 2014 Fall 2014 Fall 2015Spring 2015 Spring 2016 Fall 2016 Spring 2017 Fall 2017 Spring 2018 Fall 2018
![Page 3: Waterbury, Vermontwatp.vtransprojects.vermont.gov/...VTrans_Waterbury_v2_PRESENTA… · 14/7/2014 · Other Projects Presentation and boards developed by Stantec • Smart Work Zone](https://reader034.vdocuments.mx/reader034/viewer/2022052008/601d757e92733b4d797fabad/html5/thumbnails/3.jpg)
Presentation and boards developed by Stantec
State Project: 6 Miles of Highway Rehabilitation along US Route 2Construction: September 2013 – August 2014Cost: $7.1 million
Bolton-Waterbury
Spring 2014 Fall 2014 Fall 2015Spring 2015 Spring 2016 Fall 2016 Spring 2017 Fall 2017 Spring 2018 Fall 2018
![Page 4: Waterbury, Vermontwatp.vtransprojects.vermont.gov/...VTrans_Waterbury_v2_PRESENTA… · 14/7/2014 · Other Projects Presentation and boards developed by Stantec • Smart Work Zone](https://reader034.vdocuments.mx/reader034/viewer/2022052008/601d757e92733b4d797fabad/html5/thumbnails/4.jpg)
Presentation and boards developed by Stantec
State Project: Reconstruction of Flood Damaged PropertyConstruction: January 2014 – January 2016Cost: $125 million
State Office Complex
Spring 2014 Fall 2014 Fall 2015Spring 2015 Spring 2016 Fall 2016 Spring 2017 Fall 2017 Spring 2018 Fall 2018
![Page 5: Waterbury, Vermontwatp.vtransprojects.vermont.gov/...VTrans_Waterbury_v2_PRESENTA… · 14/7/2014 · Other Projects Presentation and boards developed by Stantec • Smart Work Zone](https://reader034.vdocuments.mx/reader034/viewer/2022052008/601d757e92733b4d797fabad/html5/thumbnails/5.jpg)
Presentation and boards developed by Stantec
State Project: Installation of a New Traffic Signal at Route 100/Interstate 89, Exit 10 Northbound Off-RampConstruction: June 2014 – August 2014Cost: $250,000
Signal at I-89 and VT-100 Intersection
Spring 2014 Fall 2014 Fall 2015Spring 2015 Spring 2016 Fall 2016 Spring 2017 Fall 2017 Spring 2018 Fall 2018
![Page 6: Waterbury, Vermontwatp.vtransprojects.vermont.gov/...VTrans_Waterbury_v2_PRESENTA… · 14/7/2014 · Other Projects Presentation and boards developed by Stantec • Smart Work Zone](https://reader034.vdocuments.mx/reader034/viewer/2022052008/601d757e92733b4d797fabad/html5/thumbnails/6.jpg)
Presentation and boards developed by Stantec
State Project: 12 Miles of Pavement Resurfacing along VT Route 100Construction: July 2014 – October 2014Cost: $2.1 million
Waitsfield-Moretown-Duxbury
Spring 2014 Fall 2014 Fall 2015Spring 2015 Spring 2016 Fall 2016 Spring 2017 Fall 2017 Spring 2018 Fall 2018
![Page 7: Waterbury, Vermontwatp.vtransprojects.vermont.gov/...VTrans_Waterbury_v2_PRESENTA… · 14/7/2014 · Other Projects Presentation and boards developed by Stantec • Smart Work Zone](https://reader034.vdocuments.mx/reader034/viewer/2022052008/601d757e92733b4d797fabad/html5/thumbnails/7.jpg)
Presentation and boards developed by Stantec
Municipal Project: Reconstruction of US Route 2/VT Route 100 North T-Intersection with a Modern RoundaboutConstruction: July 2014 – June 2015 (substantial completion November 2014)Cost: $3.9 million
Waterbury Roundabout
Spring 2014 Fall 2014 Fall 2015Spring 2015 Spring 2016 Fall 2016 Spring 2017 Fall 2017 Spring 2018 Fall 2018
![Page 8: Waterbury, Vermontwatp.vtransprojects.vermont.gov/...VTrans_Waterbury_v2_PRESENTA… · 14/7/2014 · Other Projects Presentation and boards developed by Stantec • Smart Work Zone](https://reader034.vdocuments.mx/reader034/viewer/2022052008/601d757e92733b4d797fabad/html5/thumbnails/8.jpg)
Presentation and boards developed by Stantec
Municipal Project: 0.5 Miles of Sidewalk ImprovementsConstruction: August 2014 – October 2014Cost: $410,000
Stowe Street Sidewalk
Spring 2014 Fall 2014 Fall 2015Spring 2015 Spring 2016 Fall 2016 Spring 2017 Fall 2017 Spring 2018 Fall 2018
![Page 9: Waterbury, Vermontwatp.vtransprojects.vermont.gov/...VTrans_Waterbury_v2_PRESENTA… · 14/7/2014 · Other Projects Presentation and boards developed by Stantec • Smart Work Zone](https://reader034.vdocuments.mx/reader034/viewer/2022052008/601d757e92733b4d797fabad/html5/thumbnails/9.jpg)
Presentation and boards developed by Stantec
State Project: Rehabilitation of Interstate 89 Mainline Bridges and Replacement of Exit 10 Northbound Off-Ramp BridgeConstruction: August 2014 – November 2016Phase 1: August 2014 – November 2014Cost: $11 million
I-89 Bridge Reconstruction
Spring 2014 Fall 2014 Fall 2015Spring 2015 Spring 2016 Fall 2016 Spring 2017 Fall 2017 Spring 2018 Fall 2018
![Page 10: Waterbury, Vermontwatp.vtransprojects.vermont.gov/...VTrans_Waterbury_v2_PRESENTA… · 14/7/2014 · Other Projects Presentation and boards developed by Stantec • Smart Work Zone](https://reader034.vdocuments.mx/reader034/viewer/2022052008/601d757e92733b4d797fabad/html5/thumbnails/10.jpg)
Presentation and boards developed by Stantec
State Project: 8 Miles of Highway Rehabilitation along VT Route 100Construction: April 2016 – October 2017Cost: $10 million
Waterbury-Stowe
Spring 2014 Fall 2014 Fall 2015Spring 2015 Spring 2016 Fall 2016 Spring 2017 Fall 2017 Spring 2018 Fall 2018
![Page 11: Waterbury, Vermontwatp.vtransprojects.vermont.gov/...VTrans_Waterbury_v2_PRESENTA… · 14/7/2014 · Other Projects Presentation and boards developed by Stantec • Smart Work Zone](https://reader034.vdocuments.mx/reader034/viewer/2022052008/601d757e92733b4d797fabad/html5/thumbnails/11.jpg)
Presentation and boards developed by Stantec
State Project: 1 Mile of Highway Reconstruction along US Route 2 (Main Street)Construction: April 2016 – October 2018Cost: $15 million
Waterbury Main Street
Spring 2014 Fall 2014 Fall 2015Spring 2015 Spring 2016 Fall 2016 Spring 2017 Fall 2017 Spring 2018 Fall 2018
![Page 12: Waterbury, Vermontwatp.vtransprojects.vermont.gov/...VTrans_Waterbury_v2_PRESENTA… · 14/7/2014 · Other Projects Presentation and boards developed by Stantec • Smart Work Zone](https://reader034.vdocuments.mx/reader034/viewer/2022052008/601d757e92733b4d797fabad/html5/thumbnails/12.jpg)
Presentation and boards developed by Stantec
Other Projects
• Smart Work Zone Summer 2014 implementation
• Southbound On-Ramp Closure Trial period, 2015 – 2016
• Stowe VT-100 Bridge Reconstruction April 2014 – September 2014
• Stowe VT-108 Bridge Reconstruction Spring 2015
Spring 2014 Fall 2014 Fall 2015Spring 2015 Spring 2016 Fall 2016 Spring 2017 Fall 2017 Spring 2018 Fall 2018