PROJECT: HIGH LEVEL WATER TANK BILLS OF QUANTITIES PROJECT: BILL OF QUANTITY FOR 15M HIGH TOWER Item Item DESCRIPTION UNIT QTY RATE No. KShs 1.0 Safety requirements 1.1 Allow for safety requirements including safety wear,scaffolding,wcp documentation site signage and safety officer on site during the period of project ITEM SUM 2.0 Preminary & General 2.1 Provide for insurance cover and performance bond ITEM SUM 3.0 15.0 m Tower 3.10 Foundation 3.11 Excavate in soft material to remove all top soil maximum depth n.e. 1.5 m in preparation to lay foundation store material on site or cartaway as directed by the engineer CM 4 3.12 Supply lay,and compact approved stone hardcore in layers not exceeding 250mm,to achieve 100% MDD compaction and blinding with approved stone dust to receive disturbed concrete blocks.Allow for watering as necessary during compaction CM 1 3.13 Supply,bend and position high yield steel bars for reinforcing base slab . Y10 bars KG 90 3.14 Supply ,lay compact and vibrate as necessary class 20 concrete for 400mm thick concrete slab for columns . Allow for watering as necessary during compaction. CM 2 4.0 Steel structure 4.10 Supply and install the following steel members complete with all necessary protective painting, welding fixing provissions & accessories like welds, bolts washers,nuts etc. A 100 x 100 x 4 mm angles main columns complete with gusset plates Kg 119 B 50 x 50 x 4 mm Angles as diagonal braces Kg 184 C 50 x 50 x 4mm Angle for horinzontal braces Kg 25 D 65 x 8 mm flat bars for ladders (vertical) complete with base plates Kg 90 E 20 mm dia x 400 long mild steel ladder rungs welded to legs No. 28 F 50 x 6 mm mm flat bar for ladder fall protection (circular around ladder) Kg 67 G 25 x 3mm CHS balustrade verticals at 1000 c/c Kg 47 H 3mm chequered plate for working platform SM 20 I 25 x 3mm CHS hand rail Kg 70 J 350 x 350 x 10 mm base and cap plates complete with gussets and bolt holes No. 8 K 600 long x 20 mm dia. achorage bolts complete with welded anchor rods No. 16 L 152 x 89 x 16 Kg/M UB complete with gusset plates and bolt holes Kg. 85 M 127 x 76 x 13 Kg/M UB complete with gusset plates and bolt holes Kg. 160 N No. 1 Total COST FOR TANK AND TOWER Add 16% VAT Grand Total Supply and install 100000 litre pressed steel tank in 6 mm thick panels complete with internal diagonal and horizontal bacings as necessary all boted with 16mm diameter bolts including provision for testing and disinfecting to approval

Upload: isaac-mureithi-maina

Post on 27-Oct-2015

15 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: Water Tower Bq

PROJECT: HIGH LEVEL WATER TANK

BILLS OF QUANTITIES

PROJECT: BILL OF QUANTITY FOR 15M HIGH TOWERItem Item DESCRIPTION UNIT QTY RATE AMOUNT No. KShs KShs cts

- 1.0 Safety requirements

1.1 Allow for safety requirements including safety wear,scaffolding,wcp documentation site signage and safety officer on site during the period of project ITEM SUM

2.0 Preminary & General2.1 Provide for insurance cover and performance bond

ITEM SUM3.0 15.0 m Tower

3.10 Foundation3.11 Excavate in soft material to remove all top soil maximum

depth n.e. 1.5 m in preparation to lay foundation store material on site or cartaway as directed by the engineer CM 4

3.12 Supply lay,and compact approved stone hardcore in layers not exceeding 250mm,to achieve 100% MDD compaction and blinding with approved stone dust to receivedisturbed concrete blocks.Allow for watering as necessary during compaction CM 1

3.13 Supply,bend and position high yield steel bars for reinforcing base slab . Y10 bars KG 90

3.14 Supply ,lay compact and vibrate as necessary class 20 concrete for 400mm thickconcrete slab for columns . Allow for watering as necessary during compaction. CM 2

4.0 Steel structure4.10 Supply and install the following steel members complete with all necessary protective

painting, welding fixing provissions & accessories like welds, bolts washers,nuts etc.A 100 x 100 x 4 mm angles main columns complete with gusset plates Kg 119

B 50 x 50 x 4 mm Angles as diagonal braces Kg 184

C 50 x 50 x 4mm Angle for horinzontal braces Kg 25

D 65 x 8 mm flat bars for ladders (vertical) complete with base plates Kg 90

E 20 mm dia x 400 long mild steel ladder rungs welded to legs No. 28

F 50 x 6 mm mm flat bar for ladder fall protection (circular around ladder) Kg 67

G 25 x 3mm CHS balustrade verticals at 1000 c/c Kg 47

H 3mm chequered plate for working platform SM 20

I 25 x 3mm CHS hand rail Kg 70

J 350 x 350 x 10 mm base and cap plates complete with gussets and bolt holes No. 8

K 600 long x 20 mm dia. achorage bolts complete with welded anchor rods No. 16

L 152 x 89 x 16 Kg/M UB complete with gusset plates and bolt holes Kg. 85

M 127 x 76 x 13 Kg/M UB complete with gusset plates and bolt holes Kg. 160

N No. 1

Total

COST FOR TANK AND TOWER

Add 16% VAT

Grand Total

Supply and install 100000 litre pressed steel tank in 6 mm thick panels complete with internal diagonal and horizontal bacings as necessary all boted with 16mm diameter bolts including provision for testing and disinfecting to approval