Overview
WASHINGTON STREET “COMPLETE STREET” REDESIGN 3 Public Meeting #3| 9.23.2014
Where Are We Now?
WASHINGTON STREET “COMPLETE STREET” REDESIGN 4 Public Meeting #3| 9.23.2014
Tonight’s Focus
• Final Concept Plan
• Design Details
• Implementation, Phasing & Costs
WASHINGTON STREET “COMPLETE STREET” REDESIGN 5 Public Meeting #3| 9.23.2014
PREFERRED ALTERNATIVE
WASHINGTON STREET “COMPLETE STREET” REDESIGN 6 Public Meeting #3| 9.23.2014
WASHINGTON STREET “COMPLETE STREET” REDESIGN 7 Public Meeting #3| 9.23.2014
Thank you! Questions or Comments?
WASHINGTON STREET “COMPLETE STREET” REDESIGN 8 Public Meeting #3| 9.23.2014
- New traffic signals - Pedestrian countdown signal
heads - Signal heads over protected
bicycle lane - IMPROVED VISIBILITY &
TRAFFIC FLOW - INCREASED PEDESTRIAN SAFETY
WASHINGTON STREET “COMPLETE STREET” REDESIGN 9 Public Meeting #3| 9.23.2014
- New street trees
- New benches
- Updated street lighting
- New solar / smart trash receptacles
- “Better Streets mean Better Business”
- INCREASED AESTHETICS & GREEN INFRASTRUCTURE
- IMPROVED MAINTENANCE
WASHINGTON STREET “COMPLETE STREET” REDESIGN 10 Public Meeting #3| 9.23.2014
- Designated loading zones & times - Numbered parking spaces - IMPROVED OPERATIONS &
CIRCULATION
WASHINGTON STREET “COMPLETE STREET” REDESIGN 11 Public Meeting #3| 9.23.2014
- Protected bicycle lanes (cycle track)
- New customized bicycle racks - Bicycle parking facilities - INCREASED MOBILITY &
ACCESS
WASHINGTON STREET “COMPLETE STREET” REDESIGN 12 Public Meeting #3| 9.23.2014
- New high visibility crosswalks - New gray concrete sidewalks - Roadway resurfacing - IMPROVED VISIBILITY - INCREASED PEDESTRIAN SAFETY - IMPROVED PAVEMENT
CONDITIONS
WASHINGTON STREET “COMPLETE STREET” REDESIGN 13 Public Meeting #3| 9.23.2014
- Redesigned bus shelters - IMPROVED TRANSIT ACCESS
& ECONOMIC BENEFIT
WASHINGTON STREET “COMPLETE STREET” REDESIGN 14 Public Meeting #3| 9.23.2014
Purpose / Goals - Why Are We Here?
Make Washington Street into a
COMPLETE, GREEN &
SMART Street
WASHINGTON STREET “COMPLETE STREET” REDESIGN 15 Public Meeting #3| 9.23.2014
Recap Benefits
of Complete
Streets
Safety, Access & Mobility And beyond…. Public Health Environmental Quality & Sustainability Aesthetics & Livability Economic Vitality &Prosperity
WASHINGTON STREET “COMPLETE STREET” REDESIGN 16 Public Meeting #3| 9.23.2014
Purpose / Goals - Why Are We Here?
“Better Streets Mean Better Business”
(Economic Benefits of Sustainable Streets, NYCDOT)
• Higher Retail Sales • 49% increase in retail sales
on 9th Avenue vs. 3% increase on all of NYC – after installation of bike lanes and trees
• Other Economic Outcomes • Retail/office rents • Increased property values
WASHINGTON STREET “COMPLETE STREET” REDESIGN 17 Public Meeting #3| 9.23.2014
Related Projects
• Frank Sinatra Drive Redesign • Parking & Mobility Master Plan • Observer Highway Resurfacing Project • Redevelopment plans • Utility & Infrastructure Upgrades
WASHINGTON STREET “COMPLETE STREET” REDESIGN 18 Public Meeting #3| 9.23.2014
COMMERCIAL CHARACTER
(Downtown)
WASHINGTON STREET “COMPLETE STREET” REDESIGN 19 Public Meeting #3| 9.23.2014
RESIDENTIAL CHARACTER
(Uptown)
WASHINGTON STREET “COMPLETE STREET” REDESIGN 20 Public Meeting #3| 9.23.2014
Outreach Activities- Who Was Involved?
• Stakeholder Interviews
• Project Website http://www.hobokennj.org/washingtonstreet
• Online Community Survey
• Stakeholder Meetings
• Public Workshops
WASHINGTON STREET “COMPLETE STREET” REDESIGN 21 Public Meeting #3| 9.23.2014
Insert outreach photos Public meeting #1
WASHINGTON STREET “COMPLETE STREET” REDESIGN 22 Public Meeting #3| 9.23.2014
Insert outreach photos Public meeting #2
WASHINGTON STREET “COMPLETE STREET” REDESIGN 23 Public Meeting #3| 9.23.2014
Seniors meeting
WASHINGTON STREET “COMPLETE STREET” REDESIGN 24 Public Meeting #3| 9.23.2014
Survey Findings
24
WASHINGTON STREET “COMPLETE STREET” REDESIGN 25 Public Meeting #3| 9.23.2014
Final Concept Plan DESIGN ELEMENTS:
• Traffic Signals
• Crosswalks
• Protected bicycle lane
• Streetscape Elements
– Sidewalks
– Benches
– Bike Racks
– Bus Shelters
– Trash Receptacles
– Tree Pits
– Street Lights
• Curb Extensions
• Parking & loading
• Green Infrastructure & Stormwater Management
WASHINGTON STREET “COMPLETE STREET” REDESIGN 26 Public Meeting #3| 9.23.2014
Street Design Assumptions
• Curb line to remain in place
• Curbside and angled parking to be retained (minimal impact only)
• Costs will be a consideration
• Proposed facilities to comply with current Federal and State standards
WASHINGTON STREET “COMPLETE STREET” REDESIGN 27 Public Meeting #3| 9.23.2014
Final Concept Plan
Traffic Signals
Crosswalks
Cycle Track (Protected Bicycle Lane)
Sidewalks
Loading Parking
Tree Pits
Bus Shelters
Trash Receptacles Curb Extensions
Roadway Resurfacing & Restriping
WASHINGTON STREET “COMPLETE STREET” REDESIGN 28 Public Meeting #3| 9.23.2014
Final Concept Plan DOWNTOWN
UPTOWN
WASHINGTON STREET “COMPLETE STREET” REDESIGN 29 Public Meeting #3| 9.23.2014
Typical Block Downtown
WASHINGTON STREET “COMPLETE STREET” REDESIGN 30 Public Meeting #3| 9.23.2014
Typical Block Uptown
WASHINGTON STREET “COMPLETE STREET” REDESIGN 31 Public Meeting #3| 9.23.2014
Renderings
WASHINGTON STREET “COMPLETE STREET” REDESIGN 32 Public Meeting #3| 9.23.2014
DESIGN DETAILS
WASHINGTON STREET “COMPLETE STREET” REDESIGN 33 Public Meeting #3| 9.23.2014
New & Improved Traffic Signals
New Traffic Signals
Pedestrian Signal Heads
New Light Poles & Fixtures
WASHINGTON STREET “COMPLETE STREET” REDESIGN 34 Public Meeting #3| 9.23.2014
Redesigned Bus Shelters
WASHINGTON STREET “COMPLETE STREET” REDESIGN 35 Public Meeting #3| 9.23.2014
Reconfigured Parking & Loading
Back-in Angle
Parking
Designated Loading Spaces
w/ time restrictions
Parking - Value Pricing
WASHINGTON STREET “COMPLETE STREET” REDESIGN 36 Public Meeting #3| 9.23.2014
Designated Loading Zones and times
- 2 commercial loading zones per block - Loading zone timing: 6am to 2pm - After 2pm open for 30 minute
metered parking - 32 designated loading zones
WASHINGTON STREET “COMPLETE STREET” REDESIGN 37 Public Meeting #3| 9.23.2014
Concrete Curb Extensions
• Improve pedestrian visibility
• Reduce crossing distance
• Provide additional space for pedestrian amenities
• Concrete
26
’
WASHINGTON STREET “COMPLETE STREET” REDESIGN 38 Public Meeting #3| 9.23.2014
Concrete curb extensions
WASHINGTON STREET “COMPLETE STREET” REDESIGN 39 Public Meeting #3| 9.23.2014
Street Level Cycle Track also known as a
(Two-way Protected Bicycle Lane)
• at street level • physically separated from
motor vehicle traffic through a variety of methods including: • parked vehicles, • pavement markings, • flexposts, bollards, • curbs, plantings, etc.
WASHINGTON STREET “COMPLETE STREET” REDESIGN 40 Public Meeting #3| 9.23.2014
Downtown Bike Facility Two-way Protected Bicycle Lane
(2-Way Cycle Track)
WASHINGTON STREET “COMPLETE STREET” REDESIGN 41 Public Meeting #3| 9.23.2014
Downtown Bike Facility Two-way Protected Bicycle Lane
(2-Way Cycle Track)
N
WASHINGTON STREET “COMPLETE STREET” REDESIGN 42 Public Meeting #3| 9.23.2014
Uptown Bike Facility Protected Bicycle Lane
(1-Way Cycle Track and Shared Lane)
WASHINGTON STREET “COMPLETE STREET” REDESIGN 43 Public Meeting #3| 9.23.2014
Uptown Bike Facility Protected Bicycle Lane
(One-Way Cycle Track & Shared Lane)
N
WASHINGTON STREET “COMPLETE STREET” REDESIGN 44 Public Meeting #3| 9.23.2014
Transit Stop Bike Racks
WASHINGTON STREET “COMPLETE STREET” REDESIGN 45 Public Meeting #3| 9.23.2014
Customized Bike Racks
Custom Bike Hitch by DERO
- Encourage bicycling - Better for business - Preserves pedestrian right-of-way - 90 individual bike racks proposed - 180 bicycle parking spots - Opportunities for multi-bike parking / bicycling corrals
Multi-Bike Parking dimensions
WASHINGTON STREET “COMPLETE STREET” REDESIGN 46 Public Meeting #3| 9.23.2014
New Bike Racks Custom to Hoboken
WASHINGTON STREET “COMPLETE STREET” REDESIGN 47 Public Meeting #3| 9.23.2014
Streetscape Elements
• Curb Extensions
• Sidewalks
• Benches
• Bus Shelters
• Trash Receptacles
• Street Lights
• Street Trees
WASHINGTON STREET “COMPLETE STREET” REDESIGN 48 Public Meeting #3| 9.23.2014
Concrete Curb Extensions
Standard Green
Enhanced Seating Green + Enhanced Seating
Downtown
WASHINGTON STREET “COMPLETE STREET” REDESIGN 49 Public Meeting #3| 9.23.2014
Concrete Curb Extensions
Standard Green
Enhanced Seating Green + Enhanced Seating
Uptown
WASHINGTON STREET “COMPLETE STREET” REDESIGN 50 Public Meeting #3| 9.23.2014
New Sidewalks & Crosswalks
New Sidewalks - Gray concrete
- Replace old, worn and inconsistent sidewalks
- 5’ x 5’ squares grid - Reconstruct curb ramps
High Visibility Striped Crosswalks
- high skid-resistant - retroreflective
- preformed - white thermoplastic
WASHINGTON STREET “COMPLETE STREET” REDESIGN 51 Public Meeting #3| 9.23.2014
Sleek/Modern Benches
Powder coated aluminum
Backless
Shown: MultipliCITY by Landscape Forms ®
- Face sidewalks instead of the existing street-facing benches
- Multiple bench configuration options - Wood is elastic, soft and durable/replaceable
& available domestically - 8-16 per block
Shown: MultipliCITY by Landscape Forms ®
Black Locust
WASHINGTON STREET “COMPLETE STREET” REDESIGN 52 Public Meeting #3| 9.23.2014
Portal Style Bus Shelters
52
- Allows pedestrians to pass through - Opportunities for advertising, wi-fi,
wayfinding maps, etc. - Black powder coated steel /
aluminum frame - Opaque structural glass canopy
WASHINGTON STREET “COMPLETE STREET” REDESIGN 53 Public Meeting #3| 9.23.2014
Smart / Solar Trash Receptacles
WASHINGTON STREET “COMPLETE STREET” REDESIGN 54 Public Meeting #3| 9.23.2014
Updated & New Street Lights
- Maintain and reuse existing lighting poles - Integrate new 25’ arm-mounted fixtures - New pole top fixtures
WASHINGTON STREET “COMPLETE STREET” REDESIGN 55 Public Meeting #3| 9.23.2014
New Street Trees - Hoboken Shade Tree Commission
specifications - 4’ x 10’ tree pits - Iron tree pit guards
Photo: City of Hoboken Facebook
WASHINGTON STREET “COMPLETE STREET” REDESIGN 56 Public Meeting #3| 9.23.2014
Green Infrastructure Stormwater Delay Tree Pit
Curb Extension Planter
WASHINGTON STREET “COMPLETE STREET” REDESIGN 57 Public Meeting #3| 9.23.2014
Wayfinding
WASHINGTON STREET “COMPLETE STREET” REDESIGN 58 Public Meeting #3| 9.23.2014
Implementation & Phasing
• Pre-Design Phase
(3-4 months)
• Coordination with utility upgrades • PSE&G lighting coordination • Geotechnical Investigations • Stormwater / Drainage Analysis
• Final Survey / Preliminary & Final Engineering Design & Construction Plans
(6-8 months)
• Construction (12 months)
WASHINGTON STREET “COMPLETE STREET” REDESIGN 59 Public Meeting #3| 9.23.2014
Cost Estimate
TOTAL COST: Approx. $ 14 million
WASHINGTON STREET “COMPLETE STREET” REDESIGN 60 Public Meeting #3| 9.23.2014
Next Steps - Moving Forward • Evaluation of tonight’s feedback
• Present Final Concept Plan to Council
WASHINGTON STREET “COMPLETE STREET” REDESIGN 61 Public Meeting #3| 9.23.2014
Thank you!